  • provisions of the Electricity Act, 2003 namely Section 42(5)
  • Electricity Act, a specific provision namely Section 145
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • provisions of the Electricity Act, 2003 namely Section 42(5)
  • Electricity Act, a specific provision namely Section 145

    M/S. Darpan Multi Polypack [India] Pvt. Ltd., Nagpur v. The Electricity Ombudsman, Maharashtra Electricity Regulatory Commission, Nagpur And Others

    The petitioner challenges the orders passed by the Electricity Ombudsman, Nagpur, dated 12/11/2013 and 23/11/2012.

    Mr. Kilor invited my attention to the provisions of the Electricity Act, 2003 namely Section 42(5) and the definition of the word ‘Grievance’ reflected in Regulation No. 2.1(c) of the Maharashtra Electricity Regulatory Commission (Electricity Supply and other Conditions of Supply) Regulations, 2005. Mr. Kilor also invited my attention to the judgment and order passed by this Court in Writ Petition No. 2032/2011. The submission of Mr. Kilor on the backdrop of the judgment of this Court in Writ Petition No. 2032/2011 and the observation that the directions to the Commission to refund the amount to the consumers or the order of such a nature will be a dispute between the parties of a civil nature would not be covered by the term ‘grievance’, is probably on the backdrop of the fact that this Court was not appraised of the view of the Apex Court in the matter of Maharashtra Electricity Regulatory Commission v. Reliance Energy Limited, reported in (2007) 8 SCC 381 and the fact that in the Electricity Act, a specific provision namely Section 145 oust the jurisdiction of the Civil Court. Therefore, the submission of Mr. Kilor is, the order passed by the Electricity Ombudsman, Nagpur dismissing the grievance application is unsustainable. The issue raised by Mr. Kilor requires consideration.

    Issue notice to the respondents, returnable on 15th of December, 2014.

    Use AI to get other relevant cases.

    Comments

    M/S. Darpan Multi Po... v. The Electricity Ombu...
    (Nov 17, 2014)