  • Section 11 of the Arbitration Act
  • Section 11 of the Arbitration and Conciliation Act, 1996
  • the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”)
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 11 of the Act
  • Section 11(8) of the Act
  • Clause 67 of the contract, Article 137 of the Limitation Act, 1963
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 11 of the Arbitration Act
  • Section 11 of the Arbitration and Conciliation Act, 1996
  • the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”)
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 11 of the Act
  • Section 11(8) of the Act
  • Clause 67 of the contract, Article 137 of the Limitation Act, 1963
Smart Summary

Factual and Procedural Background

The appellant, a partnership firm, was awarded a contract on 10-11-1998 for providing additional security fencing at Mullanpur. Work was completed on 10-7-2000 and a work-completion certificate issued. A final bill was prepared on 20-2-2001 and, on 10-4-2001, the Government paid the appellant only the undisputed portion of that bill.

Clause 67 of the General Conditions of Contract gave the Government two years from payment of the undisputed portion of the final bill to recover any over-payment from the contractor. After that two-year period lapsed without any governmental claim, the contractor issued a notice dated 23-2-2005 asserting several outstanding items and requesting a decision within thirty days, failing which adjudication by arbitration would be sought.

By letter dated 22-3-2005 the Garrison Engineer rejected the demand, stating that the contractor had signed a “No Further Claim” certificate and that no arbitrable dispute existed. On 24-3-2005 the contractor requested appointment of an arbitrator under Condition 70 of the contract and subsequently filed two Section 11 applications (Arbitration Case Nos. 184 and 89 of 2006).

On 12-3-2007 the Chief Justice of the Punjab & Haryana High Court dismissed both applications, holding that the claims were not “live” but time-barred. The contractor filed Civil Appeal Nos. 7184 and 7185 of 2008 before the Supreme Court, which heard both matters together.

Legal Issues Presented

  1. Whether the claims raised by the contractor in February 2005 were “live claims” or patently time-barred (“dead claims”) under the Arbitration and Conciliation Act, 1996.
  2. Whether, in exercising jurisdiction under Section 11 of the Act, the Chief Justice correctly refused to appoint an arbitrator on the ground that the claims were barred by limitation.
  3. Whether Clause 67, which limits governmental recovery to two years after payment of the undisputed portion of the final bill, has any bearing on the contractor’s ability to raise disputed claims after that period.

Arguments of the Parties

Appellant's Arguments

  • The February 2005 notice raised live, not time-barred, claims; limitation questions should have been left to the arbitral tribunal.
  • Payment on 10-4-2001 covered only the undisputed amount. The “No Further Claim” certificate pertained solely to that portion and did not waive disputed claims.
  • Clause 67 created a two-year defect-liability period for governmental recovery; once that period expired without any demand, the contractor was entitled to pursue its disputed claims through arbitration.
  • The High Court’s conclusion that limitation had expired ignored these contractual provisions and exceeded the proper ambit of Section 11 scrutiny.

Respondents' Arguments

  • Under Article 137 of the Limitation Act, 1963, any application concerning the final bill had to be made within three years of 10-4-2001; the Section 11 petitions filed in 2006 were therefore time-barred.
  • The contractor had signed a “No Further Claim” certificate, extinguishing any further rights or disputes.
  • The Chief Justice rightly exercised jurisdiction to reject a patently barred claim at the threshold.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
SBP & Co. v. Patel Engineering Ltd., (2005) 8 SCC 618 Chief Justice, when acting under Section 11, may decide preliminary issues such as jurisdiction, existence of arbitration agreement, and whether a claim is “live.” Relied on to acknowledge that the Chief Justice can reject an application if the claim is manifestly dead, but that power must be exercised cautiously.
Indian Oil Corporation Ltd. v. SPS Engineering Ltd., (2011) 3 SCC 507 Distinguishes between “dead” (patently time-barred) claims and claims involving disputed questions of limitation; borderline cases should be referred to arbitration. Applied to hold that the contractor’s claims, filed within five years of completion and supported by disputed facts, were not patently barred and should have been referred to arbitration.

Court's Reasoning and Analysis

The Supreme Court first reiterated the principles in SBP & Co.: the Chief Justice exercises judicial power under Section 11 and may refuse appointment only when the claim is evidently dead. It then examined Indian Oil Corporation, emphasizing that only manifestly long-barred claims—e.g., a decade after completion without acknowledgment—may be rejected; borderline or fact-dependent limitation issues must be left to the arbitral tribunal.

Applying these principles, the Court noted:

  • The contractor made its demand roughly four years after final payment—beyond three years but within five—placing it squarely within the “borderline” category described in Indian Oil Corporation.
  • Additional documents produced in the appeal showed that the 10-4-2001 payment was expressly for the “undisputed part” of the final bill, indicating that further disputed claims survived.
  • Clause 67’s reference to the “undisputed portion of the final bill” and its two-year window for governmental recovery supported the contractor’s contention that disputed items could still be pursued.
  • Determining whether the claims were time-barred would require scrutiny of bills, certificates, and other evidence—an exercise suited to an arbitral tribunal, not a Section 11 proceeding.

Consequently, the Court concluded that the High Court erred in branding the claims as dead and dismissing the Section 11 applications.

Holding and Implications

Appeals Allowed; High Court orders dated 12-3-2007 set aside. The contractor’s Section 11 applications are allowed and remitted to the Designated Judge of the Punjab & Haryana High Court to appoint an arbitrator—preferably by party consent, or otherwise by the court—within one month of the parties’ appearance on 25-7-2016.

Implications: The decision reinforces that the Chief Justice’s Section 11 power to reject claims on limitation grounds is confined to cases where the bar is patent and indisputable. Where factual inquiry is necessary—especially when contract documents suggest surviving disputed claims—the matter must be sent to arbitration. No new precedent is set, but the judgment strengthens the application of Indian Oil Corporation in borderline limitation cases.

To access the original judgment, please Sign In or Subscribe.

    Emm Enn Associates v. Commander Works Engineer And Others

    Ashok Bhushan, J.— These two appeals raising identical questions of law have been heard together and are being decided by this common judgment. For deciding both the appeals, it shall be sufficient to refer to facts and pleadings in Civil Appeal No. 7184 of 2008. Appeal No. 7184 of 2008 has been filed against the judgment 2007 SCC OnLine P&H 267, (2007) 4 Arb LR 425 of the Chief Justice of the Punjab & Haryana High Court in Arbitration Case No. 184 of 2006 by which judgment the learned Chief Justice has dismissed the application filed by the appellant for referring the dispute to an arbitrator in exercise of power under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”).

    2. Civil Appeal No. 7185 of 2008 has also been filed against the identical judgment of the learned Chief Justice in Arbitration Case No. 89 of 2006 by which the application filed by the appellant for appointing an arbitrator has been dismissed.

    3. Brief facts giving rise to Civil Appeal No. 7184 of 2008 now need to be noted.

    4. The appellant a partnership firm was allotted a contract on 10-11-1998 for providing additional security fencing at Mullanpur. The work was completed on 10-7-2000. Work completion certificate was issued. Final bill was prepared on 20-2-2001 and the payment of final bill was made to the petitioner on 10-4-2001. Payment of the undisputed part of the final bill was made by cheque dated 10-4-2001.

    5. Although Clause 67 of the general conditions of contract contemplated for recovery from the contractor in several contingencies one of which as referred in sub-clause (f) was that if as a result of any audit and technical examination, any overpayment is discovered in respect of work done under this contract, the contractor shall on demand make payment of a sum equal to the amount of overpayment. Sub-clause (g) further provided that the Government shall not be entitled to recover any overpayment beyond a period of two years from the date of payment of the undisputed portion of the final bill.

    6. Even though, two years' period expired after the payment of final bill, no demand for any recovery was issued by the Government. The contractor by letter dated 23-2-2005 served a notice stating that final bill amount as paid during April 2001 did not include the payments due to the contractor against several items which were claimed as per Appendix A annexed to the notice.

    7. It was further stated that the decision be communicated within thirty days failing which it shall be assumed that the claim is disputed and the contractor shall be left with no remedy except to seek adjudication by an arbitrator appointed in terms of the contract.

    8. The Garrison Engineer issued a letter dated 22-3-2005 informing that the contractor had signed the final bill without any protest and had given “No Further Claim” certificate. Hence no arbitrable dispute exists. The claim now intimated after the lapse of a period of approximately four years is baseless and hence denied.

    9. A letter dated 24-3-2005 was written by the contractor to the chief engineer in reference to notice dated 23-2-2005 with a prayer that the arbitrator under Condition 70 of the contract may kindly be appointed to adjudicate the dispute. The appellant thereafter filed an application under Section 11 of the Arbitration Act before the District Judge, Ropar. The application was ultimately taken by the Chief Justice of the High Court and by an order dated 12-3-2007 2007 SCC OnLine P&H 267, (2007) 4 Arb LR 425, the application was rejected taking the view that the appellant's claim is not a live claim. Aggrieved against the above judgment dated 12-3-2007 2007 SCC OnLine P&H 267, (2007) 4 Arb LR 425 in Arbitration Case No. 184 of 2006, Appeal No. 7184 of 2008 has been filed.

    10. Arbitration Case No. 89 of 2006 has also been filed by the appellant seeking appointment of an arbitrator under Section 11 of the Act in the said case and also the work was completed on 23-9-2000 and the final bill was paid on 10-4-2001. Notice along with list of claim was sent by the appellant on 23-2-2005 i.e. on the same day when notice in Arbitration Case No. 184 of 2006 has been sent.

    11. The Hon'ble Chief Justice giving the same reasons rejected the application in Arbitration Case No. 89 of 2006 holding that the claim made by the appellant is not a live claim. The Hon'ble Chief Justice by order dated 12-3-2007 2007 SCC OnLine P&H 267, (2007) 4 Arb LR 425 took the view that final bill has been paid on 10-4-2001, the notice having been given only on 23-2-2005 the period of limitation was over. With regard to Clause 67 of the contract, it was observed by the Chief Justice that embargo of two years as per sub-clauses (f) and (g) is with regard to the right of the Government for effecting recovery from the contractor which clause does not extend the period of limitation in favour of the contractor.

    12. Shri O.P. Gupta, the partner of the appellant firm has appeared in person and made his submission. We have also heard the learned counsel appearing for the respondents.

    13. The appellant's case is that the claim raised by the contractor by notice dated 23-2-2005, was not barred by time and was a live claim which ought not to have been rejected by the Chief Justice in exercise of his power under Section 11 of the Act. It is contended that the issues as to whether the claim is barred by time are the issues which ought to have been left for decision of the arbitrator. It is contended that payment in respect to the final bill made on 10-4-2001, was payment with regard to undisputed amount. Apart from undisputed amount there were other claims of the contractor and the “No Liability” certificate given by the appellant was only with regard to undisputed claim. Payment made on 10-4-2001 was the payment only in reference to the undisputed claim and that in no manner precluded the appellant from raising the claim.

    14. As per Clause 67 of the contract, there was two years' period for effecting any recovery from the contractor and when no claim against the contractor was raised during the aforesaid period, the appellant raised the claim for disputed amount which was not paid. The period of two years is defect liability period and it was clearly open for the appellant to raise the claim for disputed amount after expiry of the aforesaid period of two years.

    15. The respondents never adjudicated the disputed part of the final bill and after serving notice the appellant had rightly sought for adjudication by an arbitrator which application has been rejected by the Hon'ble the Chief Justice not on valid considerations.

    16. The learned counsel appearing for the respondents supported the judgment of the Chief Justice and contends that for filing any application limitation is three years as per Article 137 of the Limitation Act, 1963. Final bill had been paid on 10-4-2001, any application for any claim in respect to final bill ought to have been raised within three years. It is contended that the respondents have raised the preliminary objections in reply objecting to the application for arbitration filed by the appellant, which has rightly been rejected by the Chief Justice.

    17. We have considered the submissions of both the parties and have perused the record. What is the nature of jurisdiction of the Chief Justice while deciding an application under Section 11 of the Act has elaborately been considered by the seven-Judge Bench of this Court in SBP & Co. v. Patel Engg. Ltd. (2005) 8 SCC 618 In para 47 of the judgment, conclusions were recorded by the larger Bench. Conclusion (iv) is relevant for the present case which is quoted below:

    “47. We, therefore, sum up our conclusions as follows:
    ***
    (iv) The Chief Justice or the Designated Judge will have the right to decide the preliminary aspects as indicated in the earlier part of this judgment. These will be his own jurisdiction to entertain the request, the existence of a valid arbitration agreement, the existence or otherwise of a live claim, the existence of the condition for the exercise of his power and on the qualifications of the arbitrator or arbitrators. The Chief Justice or the Designated Judge would be entitled to seek the opinion of an institution in the matter of nominating an arbitrator qualified in terms of Section 11(8) of the Act if the need arises but the order appointing the arbitrator could only be that of the Chief Justice or the Designated Judge.”

    18. The Chief Justice exercises the judicial power while passing an order under Section 11 of the Act thus can examine the question as to whether the claim which has been raised before him survives and needs to be adjudicated. It goes without saying that if the Chief Justice finds that the claim is a dead claim, he can exercise jurisdiction in rejecting the application.

    19 . A two-Judge Bench of this Court in Indian Oil Corpn. Ltd. v. SPS Engg. Ltd. (2011) 3 SCC 507 had occasion to consider what is a “live claim” within the meaning of Section 11 of the Act. Elaborating the jurisdiction of the Chief Justice, under Section 11 of the Act following was laid down by this Court in para 14 of the judgment:

    “14. … The Chief Justice or his designate may however choose to decide whether the claim is a dead (long-barred) claim or whether the parties have, by recording satisfaction, exhausted all rights, obligations and remedies under the contract, so that neither the contract nor the arbitration agreement survived. When it is said that the Chief Justice or his designate may choose to decide whether the claim is a dead claim, it is implied that he will do so only when the claim is evidently and patently a long time-barred claim and there is no need for any detailed consideration of evidence. We may elucidate by an illustration: if the contractor makes a claim a decade or so after completion of the work without referring to any acknowledgment of a liability or other factors that kept the claim alive in law, and the claim is patently long time-barred, the Chief Justice or his designate will examine whether the claim is a dead claim (that is, a long time-barred claim). On the other hand, if the contractor makes a claim for payment, beyond three years of completing of the work but say within five years of completion of work, and alleges that the final bill was drawn up and payments were made within three years before the claim, the Court will not enter into a disputed question whether the claim was barred by limitation or not. The Court will leave the matter to the decision of the Tribunal. If the distinction between apparent and obvious dead claims, and claims involving disputed issues of limitation is not kept in view, the Chief Justice or his designate will end up deciding the question of limitation in all applications under Section 11 of the Act.”

    20 . Further, this Court has observed that an application under Section 11 of the Act is expected to contain pleading about the existence of a dispute and the applicant is not expected to justify the claim or plead extensively in regard to limitation or production of document to demonstrate that claim is within time in proceeding under Section 11 and that issue should normally be left to the Arbitral Tribunal. Following was observed in para 15: (Indian Oil Corpn. Ltd. case (2011) 3 SCC 507)

    “15. An application under Section 11 of the Act is expected to contain pleadings about the existence of a dispute and the existence of an arbitration agreement to decide such dispute. The applicant is not expected to justify the claim or plead exhaustively in regard to limitation or produce documents to demonstrate that the claim is within time in a proceeding under Section 11 of the Act. That issue should normally be left to the Arbitral Tribunal. If the Chief Justice or his designate is of the view that in addition to examining whether there is an arbitration agreement between the parties, he should consider the issue whether the claim is a dead one (long time-barred) or whether there has been satisfaction of mutual rights and obligation under the contract, he should record his intention to do so and give an opportunity to the parties to place their materials on such issue. Unless the parties are put on notice that such an issue will be examined, they will be under the impression that only questions of jurisdiction and existence of arbitration agreement between the parties will be considered in such proceedings.”

    21. From the above, it is clear that the Chief Justice may choose to hold a claim as a dead claim only when the claim is evidently and patently long time-barred claim and there is no need for any detailed consideration of evidence. An illustration has been given in para 14 as extracted above. The above illustration becomes relevant for the facts of the present case. In the present case also, the appellant has raised the claim beyond the three years of completing of the work but within five years of completion of the work.

    22. In the present case, the appellant has also contended that there is a defect liability period of two years during which any recovery can be made from the contractor. Further the categorical case of the appellant was that final payment made on 10-4-2001 was the final payment of the undisputed claim and there were other claims of the appellant which were disputed and the payment received on 10-4-2001 was with regard to undisputed claim. There being no adjudication with regard to disputed claim the claim raised by notice dated 23-2-2005 cannot be said to be barred by time or a dead claim.

    23. In the present appeal by IA No. 3 of 2012, the appellant has brought certain additional materials for consideration of the Court. By Annexure 16 certain certificates which were given by the contractor on 20-2-2001, that is, when the final bill was prepared, has been brought on record. The payment was made by cheque dated 10-4-2001 and paras 3/4 of the certificate filed at the 2nd page of Annexure 16 state as follows:

    “3. Printed certificate signed by the petitioner at the time of receiving payment of the undisputed part of the final bill.
    Received Rs 57,532. This payment is in full and final settlement of all money due under C WE/AF CHD/CHD-5/98-99 and I have no further claim in respect of the.… sd/- Contractor 4. Payment by cheque of the undisputed part of the final bill made by the dispersing officer, mentioned hereinbelow:
    Cheque No. H-916930 dated 10-4-2001 for Rs 57,532 issued in favour of M/s Emm Enn Associates on SBI AF Chandigarh Treasury.
    sd/-
    Signature of Dispersing Officer”

    24. Para 4 of the above certificate as quoted above clearly mentions payment by cheque of the undisputed part of the final bill and above certificate also clearly indicates that payment on 10-4-2001 was made of the undisputed part of the final bill which presupposes that there are certain other claims which are disputed. Clause 67 of the contract entered into between the parties also uses the expression “undisputed portion of the final bill”.

    25. The appellant had relied on Clause 67 which contains a heading “Recovery From Contractor” under sub-clauses (f) and (g) which is to the following effect:

    “(f) If, as a result of such audit and technical examination, any overpayment is discovered in respect of the work done under this contract, the contractor shall on demand make payment of a sum equal to the amount of overpayment or agree for effecting necessary adjustment from any amounts due to him by Government. If however, he refuses or neglects to make the payment on demand or does not agree for effecting adjustment from any amounts due to him, Government shall be entitled to take action as in sub-para (a) hereinbefore. If as a result of such audit and technical examination any underpayment is discovered, the amount of underpayment shall be duly paid to the contractor by Government.
    (g) Provided, that, nothing hereinbefore contained shall entitle the Government to recover any overpayment in respect of any price agreed between the C.W.E. or the G.E. and the contractor under the circumstances specifically prescribed for such method of assessment and that the said right of the Government to adjust overpayment from any sum due or from any sum which may become due to the contractor or from security deposit or security bond amount and adjust under payment, shall not extend beyond a period of two years from the date of payment of the undisputed portion of the final bill or in the case of minus bill, from the date, the net amount of the final bill is communicated to the contractor.”

    26. In sub-clause (g) the period of two years under which the Government is entitled to make recovery is “from the date of payment of the undisputed portion of the final bill”. The examination of the additional materials brought on this appeal, does indicate that the case required consideration of relevant bills and certificates and determination on the question as to whether the claim laid by the appellant was a dead claim and was not a live claim depended upon scrutiny of relevant documents. The pleadings in the proceeding under Section 11 by the appellant were clearly to the effect that on 10-4-2001, he was paid only undisputed part and the appellant has reserved his right to raise claim to the disputed part.

    27. In view of the Division Bench judgment in Indian Oil Corpn. Ltd. (2011) 3 SCC 507 supra para 14 as extracted above, the present was the case which ought to have been left for the decision by the Tribunal. We, however, have proceeded further to examine the claim raised by the appellant in his notice dated 23-2-2005. The pleadings of the appellant are categorical to the effect that the final payment made on 10-4-2001 was only with regard to undisputed portion and he has reserved his right to raise claim with regard to other disputed claims.

    28. The disputed claims having never been adjudicated, we are of the view that there was a dispute which needed an adjudication after looking into all relevant documents, bills and certificates which could have been appropriately examined by the Arbitral Tribunal and the observation of the Chief Justice “As the appellant has failed to prima facie show this Court that there was a live claim of the appellant” does not commend us.

    29. The claim raised by the petitioner in the facts of the case could not have been said to be a dead claim. Especially in view of the additional documents which have been placed before us by IA No. 3 of 2012. We are thus of the view that the order dated 12-3-2007 2007 SCC OnLine P&H 267, (2007) 4 Arb LR 425 passed in Arbitration Cases Nos. 184 and 89 of 2006 deserves to be set aside.

    30. As a consequence thereof, the application made by the appellant under Section 11 of the Act is allowed. We, however, consider it apposite to remit the case to the High Court (Designated Judge) to pass consequential orders for appointment of the arbitrator for deciding the disputes which have arisen between the parties. The appointment of the arbitrator may be made in the first instance with the consent of the parties and if, for any reason, it is not possible to do so then the Court will appoint the arbitrator in its discretion. It be done within one month from the date of the parties' appearance.

    31. The parties to appear before the Designated Judge in the High Court on 25-7-2016 to enable the Court to pass appropriate consequential order as directed above. Both the appeals are accordingly allowed.