  • Section 78-B of Indian Railways Act, 1890 (hereinafter called 1890 Act) on 20-1-1988, 24-3-1988, 7-7-1989
  • SECTION 13 RAILWAY CLAIMS TRIBUNAL ACT 1987
  • provisions of Section 124A of the Railways Act, 1989 (24 of 1989),
  • Indian Railways (Amendment) Act, 1961, the old Section 77
  • (c) under Clause (b) of sub-section (1) of Section 13
  • provision of Section 78-B of 1890 Act,
  • Section 78-B of the Railways Act.(2)
  • sub-section (1A) of Section 13
  • Section 78-B of 1890 Act.13.
  • Section 78-B of 1890 Act.7.
  • Section 78-B of 1890 Act,
  • Section 78-B of 1980 Act
  • Section 77 (78-B
  • Section 78-B,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 78-B of Indian Railways Act, 1890 (hereinafter called 1890 Act) on 20-1-1988, 24-3-1988, 7-7-1989
  • SECTION 13 RAILWAY CLAIMS TRIBUNAL ACT 1987
  • provisions of Section 124A of the Railways Act, 1989 (24 of 1989),
  • Indian Railways (Amendment) Act, 1961, the old Section 77
  • (c) under Clause (b) of sub-section (1) of Section 13
  • provision of Section 78-B of 1890 Act,
  • Section 78-B of the Railways Act.(2)
  • sub-section (1A) of Section 13
  • Section 78-B of 1890 Act.13.
  • Section 78-B of 1890 Act.7.
  • Section 78-B of 1890 Act,
  • Section 78-B of 1980 Act
  • Section 77 (78-B
  • Section 78-B,
Smart Summary

Factual and Procedural Background

Visakhapatnam Steel (Rashtriya Ispat Nigam Limited, Visakhapatnam) booked consignments of PVC Insulated Armoured Electrical Conductors between December 20, 1985 and August 3, 1987 and paid the freight as printed in the IRCA goods tariff. On delivery at the destination siding the consignments were not released unless higher freight was paid, the higher amounts having been collected by the goods clerk due to a printing mistake in the tariff. The Railway Board issued a circular dated 4-8-1987 correcting the tariff.

After becoming aware of the correction, Visakhapatnam Steel issued notices to the Railways under Section 78-B of the Indian Railways Act, 1890 on 20-1-1988, 24-3-1988, 7-7-1989 and 28-7-1989 seeking refund of overcharges. The Railways replied repudiating the claim on the grounds that the notices were not given within the six-month period required by Section 78-B and that the claim was barred by limitation. Visakhapatnam Steel filed an application before the Railway Claims Tribunal (O.A. No. 248 of 1990), which allowed the claim and directed the Railways to pay Rs. 6,40,882 with 12% interest per annum as excess freight collected.

The Union of India, represented by the General Manager, South Eastern Railway, Calcutta, appealed to this Court against the Tribunal's order dated 27-7-1998. The appeal challenges the Tribunal's allowance of the claim on grounds of non-compliance with Section 78-B and that the claim was time-barred under Section 17 of the Railway Claims Tribunal Act, 1987.

Legal Issues Presented

  1. Whether the claim made by Visakhapatnam Steel is liable to be rejected because it was not preceded, within six months, by a notice as contemplated under Section 78-B of the Indian Railways Act, 1890?
  2. Whether the respondent's claim for refund of excess freight is barred by limitation under Section 17 of the Railway Claims Tribunal Act, 1987?

Arguments of the Parties

Appellant (Union of India / Railways) — Principal Arguments

  • The notices under Section 78-B were not issued within the six-month period required by that provision and therefore the application should be rejected for non-compliance.
  • The claim filed before the Railway Claims Tribunal on 6-9-1990 is barred by the three-year limitation period in Section 17 of the Railway Claims Tribunal Act, 1987.
  • Reliance was placed on the Supreme Court decision in Jetmull Bhojraj v. D.H. Railway, AIR 1962 SC 1879, to support the contention that non-compliance with the statutory notice period defeats the claim.

Respondent (Visakhapatnam Steel) — Principal Arguments

  • The respondent issued its first notice on 20-1-1988 immediately after learning of the Railway Board's correction of the tariff by circular dated 4-8-1987; that notice therefore falls within the six-month period required by Section 78-B.
  • The application filed on 6-9-1990 was within the limitation period under Section 17 of the Railway Claims Tribunal Act, 1987.
  • The respondent relied on the liberal construction of Section 78-B, as reflected in the Supreme Court's decision in Jetmull Bhojraj, arguing that claimants should not be prevented from recovering loss merely because a notice was not issued in a technically strict manner when the purpose of the notice is to enable inquiry and prevent fraud.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Jetmull Bhojraj v. D.H. Railway, AIR 1962 SC 1879 The Supreme Court held that the object of the statutory notice (then Section 77, now Section 78-B) is to enable the railway to investigate and to guard against fraudulent or dishonest claims; notices under that provision should be liberally construed so as not to deprive legitimate claims. The court applied the principles in Jetmull to interpret Section 78-B liberally and to hold that the notices issued by Visakhapatnam Steel were adequate, supporting the Tribunal's conclusion that Section 78-B had been complied with.
Shamsul Haq v. Secretary of State, ILR 57 Cal 1286 (AIR 1930 Cal 332) Referred to in Jetmull for the proposition that the object of service of notice is to enable investigation and that notice should be liberally construed. Referenced via Jetmull; used as part of the body of authorities supporting liberal construction of notice requirements under Section 78-B.
Mahadeva Ayyar v. S.I Rly. Co., ILR 45 Mad 135 (AIR 1922 Mad 362) (FB) Referred to in Jetmull as an authority supporting the liberal construction of the notice requirement to protect legitimate claims while guarding against fraud. Referenced via Jetmull; formed part of the judicial context endorsing liberal construction of Section 78-B.
Governor-General in Council v. Gouri Shankar Mills Ltd., ILR 28 Pat 178 (AIR 1949 Pat 347) (FB) Referred to in Jetmull among authorities discussing the purpose of the notice provision and its liberal construction. Referenced via Jetmull; cited as part of the accepted approach that notices be liberally construed.
Meghraj Hirjee & Co. v. B.N. Rly. Ltd., AIR 1939 Nag 141 One of the High Court decisions referred to in Jetmull that elucidated the object of the notice provision. Referenced via Jetmull; contributed to the Court's understanding that the notice requirement is for investigation and prevention of fraud and should not be used to defeat legitimate claims.
Birla Cement Works v. G.M., Western Railways, AIR 1995 SC 1111 Holds that where notice under Section 78-B was sent beyond six months immediately the claim becomes barred by that provision; in the facts of that case the claim was rightly rejected as time-barred. The court distinguished Birla Cement on its facts: there the notice was sent beyond six months and claims were barred; in the present case the court found notices were within six months of discovery and thus Birla Cement did not control the result.

Court's Reasoning and Analysis

The court approached the dispute by first examining the text and purpose of Section 78-B of the Indian Railways Act, 1890, and then considering the interaction of Section 13 and Section 17 of the Railway Claims Tribunal Act, 1987.

1. Construction of Section 78-B and application to the facts:

  • The court noted the Supreme Court's pronouncement in Jetmull that Section 78-B (formerly Section 77) was intended to protect railway administrations from fraud and to enable investigation, and that notices under the provision should be given a liberal construction so as not to deprive legitimate claims.
  • It examined the notices sent by Visakhapatnam Steel and the annexed statements (showing dates of consignment and freight paid). It found that the consignments had been booked and freight paid according to the printed tariff, that a printing mistake caused higher freight to be collected, and that the Railway Board's circular of 4-8-1987 corrected the tariff.
  • The court observed that the respondent's first notice (20-1-1988) was issued within six months of the date on which the respondent became aware of the correction (i.e., after 4-8-1987). The facts that the circular correcting the tariff was issued on 4-8-1987 and that the notice was issued on 20-1-1988 were not disputed.
  • Applying the liberal construction endorsed in Jetmull, the court concluded that the notices satisfied Section 78-B and that the claim was therefore not barred for want of prior notice.

2. Limitation under Section 17 of the Railway Claims Tribunal Act, 1987:

  • The court stressed that Sections 13 and 17 must be read together. Section 17(1)(c) prescribes that claims under Section 13(1)(b) (refund of freight paid) must be made within three years from the date on which the fare or freight was paid to the railway administration.
  • The court reasoned that when freight was collected in error due to a tariff printing mistake and the error was corrected subsequently by a circular, a reasonable interpretation is that the claimant effectively paid the excess freight only on the date when the correction was issued (i.e., when the claimant could be said to have realized that the payment was an overcharge).
  • This interpretation prevents a railway administration from deliberately delaying issuance of a correction to defeat legitimate claims by running down the limitation period. The court therefore rejected the Railways' submission that the claim was barred by Section 17(1)(c).
  • The court distinguished Birla Cement Works (1995) on the facts because, in that case, the notice was admittedly sent beyond six months and therefore the claim was barred; by contrast, in the present case the notice was within six months of the claimant becoming aware of the overcharge.

Having applied the law to the undisputed factual matrix — that the Railway Board's correction was on 4-8-1987 and the first notice was on 20-1-1988 — the court concluded that the respondent had complied with Section 78-B and that the claim was not time-barred under Section 17.

Holding and Implications

Holding: The appeal is dismissed. The court upheld the Railway Claims Tribunal's order allowing the respondent's claim for refund of excess freight and directing payment of Rs. 6,40,882 with interest at 12% per annum. No costs were awarded.

Implications:

  • Direct effect: The Tribunal's award in favor of Visakhapatnam Steel is sustained and the appellant (Railways) must comply with the direction to pay the refund with interest as ordered by the Tribunal.
  • Interpretive outcome: The court applied the principle that Section 78-B should be construed liberally in line with Jetmull. It interpreted Section 17(1)(c) so that, in cases where excess freight was collected because of an error in the tariff and the error is corrected later, the limitation period runs from the date of correction (i.e., from when the claimant could reasonably be said to have become aware of the overcharge). This approach aims to prevent the railway from defeating claims by delaying correction of tariff errors.
  • On precedent: The court distinguished Birla Cement Works on the facts; it applied, rather than overruled, the line of authority favouring liberal construction of the notice requirement. The judgment upholds established principles rather than announcing an unrelated new rule of law.
Appeal dismissed.

    Union Of India v. Rashtriya Ispat Nigam Ltd. (Steel Plant) .

    JUDGMENT

    1. The Union of India represented by its General Manager, South Eastern Railway, Calcutta assails the order of the Railway Claims Tribunal, Secunderabad, dated 27-7-1998 made in O.A No. 248 of 1990, whereby and where-under the learned Tribunal allowed the claim of the respondent herein directing the appellant to pay a sum of Rs. 6,40,882/- with interest at 12% per annum being the excess freight amount or overcharges collected by the appellant from the respondent.

    2. The case of the respondent herein before the learned Tribunal in a nutshell is that between 1986 and 1988, Rashtriya Ispat Nigam Limited, Visakhapatnam (hereinafter called ‘Visakhapatnam Steel’), booked PVC Insulated Electrical Armoured Conductors from various destinations to its siding at Visakhapatnam duly paying the requisite freight charges at the place of booking. When the goods reached the destination, the same were not delivered to Visakhapatnam Steel on the ground that the freight charges were not correctly paid. Therefore Visakhapatnam Steel paid the freight charges as demanded by the goods clerk and got the goods released.

    3. At the relevant time, the applicable freight was governed by IRCA goods tariff Part-I, Vol. II at page 113. It appears insofar as the tariff applicable to PVC Insulated Armoured Conductors is concerned a printing mistake occurred, according to which the goods clerk collected the higher freight charges than what was actually prescribed. Be that as it is, the Railways issued a circular dated 4-8-1987 ordering the correctness. If the same is taken into consideration, the Railways collected more freight than prescribed. Therefore, Visakhapatnam Steel issued notices under Section 78-B of Indian Railways Act, 1890 (hereinafter called ‘1890 Act’) on 20-1-1988, 24-3-1988, 7-7-1989 and 28-7-1989. The Railways sent reply repudiating the claim on the ground that the claim was made in contravention of Section 78-B of 1980 Act and beyond the period of limitation of three years. Hence, Visakhapatnam Steel filed the application before the learned Tribunal presumably under Section 13 of the Railway Claims Tribunal Act, 1987 (for short, the Act).

    4. The appellant herein opposed the application by filing a written statement as well as two additional written statements. The appellant, inter alia, contended that the claim of the respondent is not valid and tenable under Section 78-B of 1890 Act, and that the claim is barred by limitation.

    The learned Tribunal framed four issues for consideration as under:

    1) Whether the collection of undercharges by the respondent from applicant in respect of the subject consignments correct and legal?

    2) Whether the application is maintainable?

    3) Whether the application is barred by limitation?

    4) What relief?

    On all the above issues, the learned Tribunal held against the appellant and directed the Railways to pay the claim amount.

    5. In this appeal, learned Counsel for the Railways, Sri Gowri Sankar Sanghi, pressed two grounds. First, he contends that the application is liable to be rejected for non-compliance of the provisions under Section 78-B of 1890 Act, in that, notice was not issued within six months as contemplated thereunder. Secondly, he contends that any claim before the Railway Claims Tribunal has to be preferred within three years under Section 17 of the Act and the claim having been preferred on 6-9-1990 is clearly barred by limitation. Reliance is placed on the judgment of the Supreme Court in Jetmull Bhojraj v. D.H Railway, AIR 1962 SC 1879.

    6. Per contra, the learned Counsel for Visakhapatnam Steel, Sri V. Ravinder Rao, submits that the respondent got issued first notice on 20-1-1988 immediately after coming to know about the correction made by the Railways on 4-8-1987 and, therefore, the said notice is within time as contemplated under Section 78-B of 1890 Act. He would also urge that as the application was filed before the learned Tribunal on 6-9-1990, the same is within limitation and it is not barred under Section 17 of the Act. He would also plead that the provision of Section 78-B of 1890 Act, as held by the Supreme Court in Jetmull Bhojraj v. D.H Railway (AIR 1962 SC 1879) (supra) should receive liberal construction and a claimant cannot be prevented from recovering the loss merely because a notice was not issued, as contemplated under Section 78-B of 1890 Act.

    7. The point that would arise for consideration are whether the claim made by Visakhapatnam Steel is liable to be rejected on the ground that it is not preceded by a notice as contemplated under Section 78-B of 1890 Act? and whether the claim of the respondent is barred by limitation as per Section 17 of the Act?

    Section 78-B of 1890 Act reads as under:

    78-B Notification of claims to refunds of overcharges and to compensation for losses. A person shall not be entitled to a refund of an overcharge in respect of animals of goods carried by railway or to compensation for the loss, destruction, damage, deterioration or non-delivery of animals or goods delivered to be so carried, unless his claim to the refund or compensation has been preferred in writing by him or on his behalf—

    (a) to the railway administration to which the animals or goods were delivered to be carried by railway, or

    (b) to the railway administration on whose railway the destination station lies, or the loss, destruction, damage or deterioration occurred,

    within six months from the date of the delivery of the animals, or goods for carriage by railway:

    Provided that any information demanded or inquiry made in writing from, or any complaint made in writing to, any of the railway administration mentioned above by or on behalf of the person within the said period of six months regarding the non-delivery or delay in delivery of the animals or goods with particulars sufficient to identify the consignment of such animals or goods shall, for the purposes of this section, be deemed to be a claim to the refund or compensation.

    8. By Indian Railways (Amendment) Act, 1961, the old Section 77 was substituted by Section 78-B, duly enacting another provision as Section 77. Be that as it is, Section 77, which was the direct precursor of Section 78-B of 1890 Act, came up for consideration before the Supreme Court in Jetmull Bhojraj v. D.H Railway (AIR 1962 SC 1879) (supra). Majority of the three Judge Bench after referring to Section 77 (78-B after 1961) opined that in enacting the above provision, the legislature never intended to deprive the legitimate claims for compensation and that it was intended to shield Railway administration against fraud. After referring to judgments of various High Courts it was observed thus:

    The High Courts in India have taken the view that the object of service of notice under this provision is essentially to enable the railway administration to make an enquiry and investigation as to whether the loss destruction or deterioration was due to the consignor's laches or to the wilful neglect of the railway administration and its servants and further to prevent state and possibly dishonest claims being made when owing to delay it may be practically impossible to trade the transaction or check the allegations made by the consignor. In this connection we may refer to a few of the decisions. They are: Shamsul Haq v. Secretary of State, ILR 57 Cal 1286 : AIR 1930 Cal 332; Mahadeva Ayyar v. S.I Rly. Co., ILR 45 Mad 135 : AIR 1922 Mad 362 (FB); Governor-General in Council v. Gouri Shankar Mills Ltd., ILR 28 Pat 178 : (AIR 1949 Pat 347) (FB); Meghraj Hirjee & Co. v. B.N Rly. Ltd., AIR 1939 Nag 141. Bearing in mind the object of the section it has also been held by several High Courts that a notice under S. 77 should be liberally construed. In our opinion that would be the proper way of construing a notice under that section. In enacting the section the intention of the legislature must have been to afford only a protection to the railway administration against fraud and not to provide a means for depriving the consignors of their legitimate claims for compensation for the loss of or damage cause to their consignments during the course of transit on the railways.

    9. The above principles cannot be ignored while appreciating the facts in this case. Along with the notices issued by Visakhapatnam Steel, the authorized officer went on enclosing statements showing the date of consignment and the freight amount paid at the place of origin. These notices were annexed to the application before the learned Tribunal. An analysis of these notices would show that the respondent booked consignment of PVC Insulated Armoured Electrical Conductors during the period from 20-12-1985 to 3-8-1987 duly paying the tariff as printed in the tariff book. When they were about to be taken delivery, the respondent was compelled to pay the higher tariff by reason of a printing mistake in IRCA Goods Tariff Part-I, Vol. II. The respondent has paid the higher tariff and taken delivery of the goods. The Visakhapatnam Steel only came to know about the correction ordered by the Railway Board by reason of circular dated 4-8-1987 and immediately thereafter within a period of six months, issued the first notice on 20-1-1988. These facts are neither disputed nor denied before learned Tribunal or before this Court. Even if it is taken that the respondent is aware of the correction ordered by the Railways, the same can be only after 4-8-1987, in which event the notice issued on 20-1-1988 is well within six months from the date of realizing that the respondent paid overcharges. Therefore, it cannot be said that the claim was made in contravention of Section 78-B of 1890 Act.

    10. Sections 13 and 17 of the Act read as under:

    13. Jurisdiction, powers and authority of Claims Tribunal.—

    (1) The Claims Tribunal shall exercise, on and from the appointed day, all such jurisdiction, powers and authority as were exercisable immediately before that day by any Civil Court or a Claims Commissioner appointed under the provisions of the Railways Act,—

    (a) relating to the responsibility of the railway administrations as carriers under Chapter VII of the Railways Act in respect of claims for—

    (i) compensation for loss, destruction, damage, deterioration or non-delivery of animals or goods entrusted to a railway administration for carriage by railway;

    (ii) compensation payable under Section 82A of the Railways Act or the rules made thereunder; and

    (b) in respect of the claims for refund of fares or part thereof or for refund of any freight paid in respect of animals or goods entrusted to a railway administration to be carried by railway.

    (1A) The Claims Tribunal shall also exercise, on and from the date of commencement of the provisions of Section 124A of the Railways Act, 1989 (24 of 1989), all such jurisdiction, powers and authority as were exercisable immediately before that date by any Civil Court in respect of claims for compensation now payable by the railway administration under Section 124A of the said Act or the rules made thereunder.

    (2) The provisions of the Railways Act, 1989 (24 of 1989) and the rules made thereunder shall, sofar as may be, applicable to the inquiring into or determining, any claims by the Claims Tribunal under this Act.

    17. Limitation.—

    (1) The claims Tribunal shall not admit an application for any claim—

    (a) under sub-clause (i) of Clause (a) of sub-section (1) of Section 13 unless the application is made within three years from the date on which the goods in question were entrusted to the railway administration for carriage by railway;

    (b) under sub-clause (ii) of clause (a) of sub-section (1) or, as the case may be, sub-section (1A) of Section 13 unless the application is made within one year of occurrence of the accident;

    (c) under Clause (b) of sub-section (1) of Section 13 unless the application is made within three years from the date on which the fare or freight is paid to the railway administration:

    Provided that no application for any claim referred to in sub-clause (i) of Clause (a) of sub-section (13) shall be preferred to the Claims Tribunal until the expiration of three months next after the date on which the intimation of the claim has been preferred under Section 78-B of the Railways Act.

    (2) Notwithstanding anything contained in sub-section (1), an application may be entertained after the period specified in sub-section (1) if the applicant satisfies the Claims Tribunal that he had sufficient cause for not making the application within such period.

    11. Section 17 of the Act cannot be understood in isolation without reference to Section 13 of the Act because the three clauses under sub-section (1) of Section 17 of the Act prescribe period of limitation with reference to the compensation for loss, destruction etc., under Section 13(1)(a)(i) of the Act, compensation payable under Section 82-A of 1890 Act and refund of fares or for refund of any freight paid in respect of animals or goods. Section 17(c) of the Act refers to period of limitation for making claim under Section 13(1)(b) of the Act. A plain reading of Section 17(1)(c) of the Act would show that when a claim is made under Section 13(1)(c) of the Act, an application has to be made before the learned Tribunal within three years from the date on which the fare or freight is paid to the Railway administration. In a case of this nature, when the Railways collected freight charges under a mistake and the same is corrected subsequently, it should be taken that the claimant paid the excess fare or freight only on the day when the correction order is issued. That would be reasonable way of interpreting Section 17(1)(c) of the Act. As otherwise it is possible that the Railways, having realized the mistake in the tariff order, may keep quiet and issue correction order after expiry of period of limitation to defeat, legitimate claims. Such being not the intention of the legislature, it is not possible to agree with the submission of the learned Counsel for the Railways that the claim is barred by limitation under Section 17(1)(c) of the Act. To reiterate, it is only on 4-8-1987, the Railway Board issued a circular correcting the tariff order and immediately thereafter Visakhapatnam Steel sought refund under Section 13(1)(b) of the Act by issuing a notice on 20-1-1988. Therefore the claim is not barred by limitation.

    12. The decision cited by the learned Counsel for the Railway in Birla Cement Works v. G.M, Western Railways, AIR 1995 SC 1111 (Paras 4 and 5) is distinguishable on facts. In that case, the appellant booked various consignment between May-June, 1989 and March, 1990 whereas a notice under Section 78-B of 1890 Act was sent on 21-1-1991 very much beyond six months. The rejection of the appellants claim by the Tribunal as well as the High Court was therefore upheld by the Supreme Court observing as under:

    Section 78-B of the Act provides that a person shall not be entitled to refund of overcharge or excess payment in respect of animals or goods carried by railway unless his claim to the refund has been preferred in writing by him or on his behalf to the railway administration to which the animals or goods were delivered to be carried by railway etc., within six months from the date of the delivery of the animals or goods for carriage by railway. The proviso has no application to the facts of this case. An over charge is also a charge which would fall within the meaning of Section 78-B of the Act. Since the claims were admittedly made under Section 78-B itself but beyond six months, by operation of that provision in the Section itself, the claim becomes barred by limitation. Therefore, the Tribunal and the High Court have rightly concluded that the petitioner is not entitled to the refund of the amount claimed.

    We do no find any ground for our interference with the order challenged in S.L.Ps The Special Leave Petitions are accordingly dismissed.

    In the facts and circumstances of the case, the appellant's claim was certainly untenable under Section 78-B of 1890 Act.

    13. In the result, for the above reasons, the appeal fails and is accordingly dismissed. No costs.

    Appeal dismissed.

    Use AI to get other relevant cases.

    Comments

    Union Of India v. Rashtriya Ispat Nigam Ltd. (Steel Plant) .
    (Dec 21, 2004)