  • Indian Contract Act, which enacts, S. 55
  • S. 63 of the Indian Contract Act,
  • S. 55 of the Indian Contract Act
  • S. 4 of the Sales of Goods Act,
  • Indian Contract Act,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Indian Contract Act, which enacts, S. 55
  • S. 63 of the Indian Contract Act,
  • S. 55 of the Indian Contract Act
  • S. 4 of the Sales of Goods Act,
  • Indian Contract Act,
Smart Summary

Factual and Procedural Background

The appeal arises from a contract between the appellant and the respondents whereby the appellant agreed to supply 4,000 sleepers of a special pattern at any station on the Bengal Nagpur Railway by 31st May, 1913. The appellant deposited Rs. 5,000 as security for liquidated damages for non-delivery by the stipulated date. Only 1,746 sleepers were delivered and passed inspection. The time for delivery was extended, but no further deliveries were made, and negotiations broke down in December 1913. The appellant sued for the return of the deposit and damages for lost profit on the undelivered sleepers. The respondents counterclaimed damages for non-delivery.

The Subordinate Judge found time to be of the essence initially, but held that due to respondents' delay in inspection, time ceased to be of the essence after extension. He awarded the appellant return of the deposit and damages. On appeal, the High Court reversed this decision, holding that time was of the essence, the appellant was at fault for non-delivery, the respondents had validly extended the delivery time until November 30, 1913, and that the appellant was in breach for failing to deliver by then. The High Court awarded damages to the respondents and allowed the respondents to deduct these from the deposit returned to the appellant.

Legal Issues Presented

  1. Whether time was of the essence of the contract and the effect of its extension on the parties' rights and obligations.
  2. Whether the respondents were entitled to damages for non-delivery after the extended delivery date.
  3. The applicability of liquidated damages provisions and the calculation of damages for breach of contract.
  4. Whether the respondents' procurement of sleepers from alternative sources affected their claim for damages.

Arguments of the Parties

Appellant's Arguments

  • The appellant contended that the respondents' delay in inspection prevented timely delivery and that time ceased to be of the essence after extension.
  • The appellant sought return of the deposit and damages for lost profit on undelivered sleepers.
  • The appellant argued damages could not be recovered because respondents supplied sleepers from other wood and made a greater profit than would have been made under the contract.

Respondents' Arguments

  • The respondents maintained that time was of the essence and that the appellant was in default for failing to have the sleepers ready by the original and extended dates.
  • They argued they were entitled to damages for non-delivery calculated as the difference between the contract price and the price they had to pay elsewhere.
  • The respondents counterclaimed damages and deducted these from the deposit returned to the appellant.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Indian Contract Act, Section 55 Effect of failure to perform a contract at the specified time when time is of the essence; contract becomes voidable at the option of the promisee. Established that time was originally of the essence and the contract could be voided for non-performance on time, but the respondents did not elect to avoid the contract.
Indian Contract Act, Section 63 Allows promisee to extend time for performance or dispense with performance in whole or part. Supported the respondents' right to prorogue the time for delivery, thereby continuing the contract beyond the original date.
Tyres v. Rosedale and Ferry hill Iron Co. (1873) 8 Ex. 305 Legal principle that extension of delivery time by mutual consent does not terminate the contract but substitutes the new date as the time for performance. Applied to hold that the extended delivery date was binding and failure to deliver by that date constituted breach.
Rodocanachi v. Milburn (1887) 18 QBD 67 Damages for non-delivery do not consider accidental profits or losses from intermediate contracts unrelated to the breach. Used to reject appellant's argument that respondents' profit from alternative timber supply reduced damages recoverable.
Williams Brothers v. E. L. T. Agins Limited (1914) AC 510 House of Lords affirmation of the principle in Rodocanachi v. Milburn regarding calculation of damages. Confirmed the principle that damages are calculated without regard to incidental profits or losses from other transactions.

Court's Reasoning and Analysis

The Court analyzed the contract under the Indian Contract Act, particularly Section 55, which affirms that when time is of the essence, failure to perform on time renders the contract voidable at the promisee's option. Here, the respondents did not avoid the contract but extended the time for delivery under Section 63, which allows such extension.

The Court found that the Subordinate Judge misinterpreted the provision limiting damages for non-performance at the original time when accepting late performance. The Court clarified that damages can still be claimed for non-performance at the extended time.

Relying on English authorities, particularly Tyres v. Rosedale and Ferry hill Iron Co., the Court held that an agreed extension substitutes the original time with the new date, binding the parties to performance by that date.

The appellant's argument that the respondents' alternative supply and resulting profit negated damages was rejected based on Rodocanachi v. Milburn and its affirmation by the House of Lords in Williams Brothers v. E. L. T. Agins Limited, which establish that incidental profits or losses are irrelevant to damage calculations.

Accordingly, the appellant was in breach for failing to deliver by the extended date and the respondents were entitled to damages calculated on the ordinary principles of contract law.

Holding and Implications

The appeal is dismissed.

The Court upheld the High Court's ruling that the appellant breached the contract by failing to deliver sleepers by the extended deadline. The respondents were entitled to damages for non-delivery, which could be deducted from the deposit returned to the appellant. The decision clarifies that extensions of time under the Indian Contract Act substitute the original delivery date and that damages for breach are calculated without regard to incidental profits or losses from alternative transactions. No new precedent was set beyond affirming established principles under the Indian Contract Act and relevant English case law.

    Muhammad Habidullah v. Bird And Company

    Lord Dunedin:-

    The present appeal arises out of a contract made between the appellant and the respondents by which the appellant was to supply 4,000 sleepers of a special pattern at any station on the Bengal Nagpur Railway by 31st May, 1913.

    As a condition of the contract, the appellant had to deposit and did deposit Rs. 5,000 with the respondents as security for liquidated damages at a certain rate per foot for all sleepers not delivered on the said May, 31. The sleepers had to pass inspection. Only 1,746 sleepers were delivered and passed inspection. The time for delivery was extended, but no more deliveries were made, and the parties in December 1913, broke off negotiations. The appellant then raised action asking for (1) the return of the deposit; and (2) damages in respect of his profit on the balance of sleepers not supplied. The respondents counter-claimed for damages in respect of sleepers not delivered.

    The Subordinate Judge held that time was of the essence of the contract as originally made, but that the respondents had by delaying inspection not given the appellant proper opportunity of supplying the whole of the sleepers by May 31; that there after both parties were willing and anxious that the contract should go on, time being, he held, under these circumstances no longer of the essence. He further held that when in the month of December the respondents alleged non-performance, and maintained that they would claim the penalty, that was equivalent to putting an end to the contract on their part, and he gave judgment for a return of the deposit and for damages calculated on the profit which would have accrued in respect of the unsupplied balance. On appeal, this judgment was reversed. The High Court, agreeing with the Subordinate Judge that time was of the essence of the contract as originally made, held that the fault in non-delivery by that date lay with the appellant, who never had 4,000 sleepers ready for delivery by that time, and could not excuse himself, because at one particular station of the railway there was no room to lay out 4,000 sleepers at one time. They held that the respondents had excused non-delivery at May 31,and had, in response to application to that effect by the appellant's agent, allowed the time of delivery to be prorogued until November 30; that non-delivery having been then made the appellant was in breach : that, although the liquidated damages condition could no longer apply, the respondents were entitled to damages for the non-delivered portion on the calculation of the profit which they would have made comparing the price under the principal contract with the railway company with the price they had to pay under the contract with the appellant. They accordingly dismissed the appellant's claim for damages, and gave him a decree for the deposit under deduction of the damages due to the respondents as above calculated.

    The view of the evidence which commended itself to the High Court, is set out with great minuteness in the judgment of the High Court, and as their Lordships agree with the learned Judges, they do not think it necessary to repeat what is there said. The crucial facts are as follows : (1) Time was of the essence of the original contract; (2) the appellant was in default in not making complete delivery in time , i. e., at May 31, 1913 ; (3) the appellant applied for and was granted by the respondents an extension of time until November 30,1913, for delivery of the balance over the 1,745 sleepers which had been delivered; and (4) delivery of the balance was not made by the respondents on November 30, and they were consequently in default.

    Their Lordships, however, think it necessary to give their opinion as to the law which applies to the above facts. The first point is settled by the Indian Contract Act, which enacts, S. 55 para. 1 : '

    "When a party to a contract promises to do a certain thing at or before a specified time, or certain things at or before specified times, and fails to do any such thing at or before specified times the contract, or so much of it as has not been performed, becomes void able at the option of the promisee, if the intention of the parties was that time should be of the essence of the contract."

    The respondents here did not elect to avoid the contract; they held it as subsisting, and agreed to prorogue the time of performance, This they were entitled to do. See S. 63 of the Indian Contract Act, which explicitly says so :

    "63 Every promisee may dispense with or remit, wholly or in part, the performance of the promise made to him, or may extend the time for such performance, or may accept instead of it any satisfaction which he thinks fit."

    The learned Subordinate Judge, in their Lordships' opinion, misread' the third paragraph of S. 55 ; that paragraph is as follows :

    " If, in case of a contract void able on account of the promisor's failure to perform his promise at the time agreed the promisee accepts performance of each promise at any time other than that agreed, the promisee cannot claim compensation for any loss occasioned by the non-performance of the promise at the time agreed, unless at the time of such acceptance, he gives notice to the promisor of his intention to do so."

    This clearly means that the promisee cannot claim damages for non-performance at the original agreed time, not that he cannot claim damages, for non-performance at the extended time, yet the learned Judge says :

    " Subsequent extension of time could not legally bind the plaintiff to complete it within the time so generously extended by defendant and intimated to plaintiff months after."

    Now apart from the terms of the Indian Contract Act, the law is as laid down in Tyres v. Rosedale and Ferry hill Iron Co., (1873) 8 Ex.305: 42L.J.Ex.185 : 21 W.R. 793 : 29 L J 751 Baron Martin in that case said :

    " The second question is one of law, and is a most important one - it arises over and over again every day in the ordinary transactions of mankind. It is this : There is a contract for the sale of goods to be delivered, say, in January, or upon a day of January. On the day before the delivery is to take place the vendor meets the vendee and says : 'It is not convenient for me to deliver the goods upon the day named and I will be obliged if you will agree that the goods shall be delivered at a later period,' and the vendee assents ; or the vendee goes to the vendor, and says : 'It is not convenient for me to receive the goods in January, or upon the day named, and will you agree that the delivery shall be postponed ? 'and the vendor assents; the latter is the present case, and the contention on the part of the defendants is that this puts an end to the contract, and that the defendants are not bound to deliver upon the later day. In my opinion the contention is not well-founded. It is impossible to distinguish the cases of the application coming from the vendors and one coming from the vendee."

    That opinion was affirmed in the Exchequer Chamber. The effect of S. 55 of the Indian Contract Act above quoted is, where the party having the option elects not to avoid, to put agreement after the original date on the same footing as an agreement, as put by Baron Martin, just before the original date. In England the matter is often complicated by the necessity of considering S. 17 of the Statute of Frauds and S. 4 of the Sales of Goods Act, but in the Indian Contract Act, there-is no section analogous to this.

    It is not necessary, therefore, to inquire whether Phvins v. Downing, (1876) 1. CPD 220 : 45 L J C P. 695 : 35 L T 263 is or is not reconcilable with Tyres v. Rosedale and Ferry hill Iron Co., (1873) 8 Ex.305: 42L.J.Ex.185 : 21 W.R. 793 : 29 L J 751. Difficulties which confronted the Court in Phvins v. Downing, (1876) 1. CPD 220 : 45 L J C P. 695 : 35 L T 263 do not arise here so that the law may safely be stated as in Tyres v. Rosedale and Ferry hill Iron Co, (1873) 8 Ex.305: 42L.J.Ex.185 : 21 W.R. 793 : 29 L J 751. Where, as here, a specific time is stated, then that substituted date must hold. If there were a simple waiver of the right to extension of the original time, then a reasonable time would be the proper time for delivery. It follows that there being no delivery on November 30, the appellant was in breach and damages are calculable in the ordinary way.

    The appellant, however, before the Board argued that the damages could not be recovered, because as a matter of fact the respondents supplied the sleepers from other wood which they had and made a profit on that supply greater than the profit which they would have made by the contract wood. The answer to this argument is to be found in the well known case of Rodocanachi v. Milburn, (1887) 18 Q B D. 67:35 W R 241 which was applied by the House of Lords in the recent case of Williams Brothers v. E. L. T. Agins Limited (1914) A C 510 :110 L J 865 : 83 L.J K B 715.

    " It is well settled that in an action for non-delivery or non-acceptance of goods under a contract of sale the law does not take into account in estimating the damages anything that is accidental as between the plaintiff and the defendant, as for instance an intermediate contract entered into with a third party for the purchase or sale of the goods."

    In the present case had the appellant supplied the timber the respondents would have made their profit and would, have still had the other timber to sell, upon which they were entitled to make such profit as they could.

    Their Lordships will humbly advise His Majesty to dismiss the appeal with costs.

    Appeal dismissed.