1. Kesar Singh who will be described in this order as the Contractor entered into four contracts No. CEW-16 of 1956–1957 for supply of charpoys at Jammu, contract No. CWEJ-16 of 55-56 for work on TC at Z station and contract CWEJ-9 of 56, 57, TC at Z station. He tendered for supply of 14438 chorpoys at the rate of 19 along with mosquito nets including clumps and gutties on 8-12-56. This tender was accepted by the Chief Engineer Western Command on 28-11-56 and the supply had to be completed by 31-12-57. The contractor was asked to suspend the work by the Engineer in charge vide his No. 8338-A/142.E8 under condition No. 6 of IAGW 1815-Z. The work remained suspended for some time. Later on in so called deviation of the previous contract another letter was sent to the Contractor by the Executive Engineer OC Works Section, No. 8412/334.E8, 969 Works Section dated 21-3-58 wherein it was stated that the contractor had supplied 1882 charpoys with mosquito net frames with gutties and clumps. He was further directed not to manufacture any more charpoys with mosquito frames, gutties and clumps upon the supplies already made. The balance of 12557 charpoys would be supplied without mosquito net frames. The rate for omission on mosquito net frames, gutties and clumps would be 4.33 per cent. The contractor was further asked to conform his agreement to the rate or forward his objections within seven days of that letter. Necessary amendment was to issue as soon as the rate was agreed to by the contractor. This was replied to by the contractor on 30th March/8rd April, 1958 (page 79 of the register). The contractor was prepared to accept a reduction of Rs. 1.50 as against Rs. 4.33 suggested by the Engineer on account of the omission of the mosquito net frames. He received a wireless message to attend the office on 9-8-58 and settle the rate amicably. On 22-6-58 the contract was cancelled with effect from 29-5-68. (Letter on page 92 of the register). A reduction of Rs. 4.49 per set was suggested by the Military authorities (page 95). In reply to this the contractor by means of his letter dated 9th September, 1958 informed the OC 969 Works Section that he had already submitted the rate of mosquito net frames. The rule was arrived at, agreed to and decided after prolonged discussion with the OC 969 Works and the ESO Mr. Jarath. The question of initiating a new rate did not at all arise. What was to be deducted on account of the omission of the mosquito net frames namely clumps and gutties from the costs supplied by the contractor remained undecided upto the last. The contractor brought a suit for a permanent injunction against the Union of India, the CE Western Command, the Commander Works Engineer 138 Works Section, the OC 969 Works Section with respect to all the four contracts mentioned above in the court of the Sub-Judge Jammu. The relief claimed by the contractor was four-fold; (1) that the defendants be restrained from carrying on any of the works of the contract; (2) that the defendants be restrained from refusing to accept supplies under the said contract; (3) that the defendants be restrained from refusing to make the 90 percent payments to the plaintiff for the works done and the supplies made and (4) general relief. The defendants appeared in that suit. They prayed that the proceedings in the suit be stayed under section 34 of the Arbitration Act. The Court by its order dated 16-8-58 stayed the suit and allowed the parties to go to arbitration. Later on Mr. M.L Raheja. Superintending Engineer Engineer-in-Chief's branch, New Delhi was appointed as the sole arbitrator of the dispute between the contractor and the Union of India in terms of the arbitration clause in the agreement, by the Engineer-in-Chief, Army Hqrs. New Delhi, vide his letter dated 29th August, 1958. An objection was taken by the contractor that as there were four contracts, a single arbitrator could not be appointed. Consequently, Mr. Raheja was appointed an arbitrator for contract No. CEW-16 of 56, 57 for supply of Charpoys at Jammu. The arbitrator held several proceedings in the case in the month of February 1963 and finally gave his award on 19th April, 1963. By this award he has directed the contractor Kesar Singh to pay to the Union of India a sum of Rs. 71,140.85 and has awarded Rs. 9,559 to the contractor against the Union of India, leaving a net balance of Rs. 61,581.64 payable by the contractor to the Union of India.
2. When this award was made, an application on behalf of the Union of India describing itself as the President of India in these proceedings, was made for making this award a rule of the court. The contractor Kesar Singh opposed this application and put in a long list of objections to the award being made a rule of the court. It is this dispute whether a decree in terms of the award should be passed or whether the award be set aside that has to be decided in this case. The case was originally argued by the late Mr. L.N Sharma on behalf of Kesar Singh and by Mr. B.L Suri on behalf of the Union of India. After hearing the arguments at length, it was found desirable to examine Mr. Raheja in these proceedings, vide order of this court dated 9-7-1965. Mr. Raheja appeared in the court and was examined. The parties' learned counsel also cross-examined him. His statement is a part of the record.
3. When Mr. Sharma argued the case he raised a number of points which need not he discussed in details now, but which were contained in the contractors' objections comprising of 10 pages of 29 paragraphs. S. Kesar Singh also filed a replication which covers 15 typed pages and an equal number of paras as the objections. After the examination of Mr. Raheja, the case had to be argued anew. In the meanwhile Mr. Sharma passed away and the case was then argued by Mr. Mahajan on behalf of the contractor Mr. Suri continued to retain the brief on behalf of the Union of India. Even Mr. Mahajan raised a number of objections to the award of Mr. Raheja being made a rule of the court. Mr. Mahajan stated (1) that there was no valid reference to arbitration, (2) the arbitrator was appointed without any notice and without consulting the contractor, (3) the award was made beyond the statutory period of four months, (4) the arbitrator had acted in violation of the principles of natural justice; (5) the award was bad as the arbitrator was a party man and was an employee of the Military Department of the Union of India and (6) the venue of the arbitration proceedings had been fixed at Delhi by the arbitrator which caused prejudice to the contractor and (7) the arbitrator otherwise misconducted himself on the following grounds:—
(a) he had shown partiality for the Union of India
(b) had fixed rates for non-supply without any evidence
(c) had not maintained any minutes of the record of the proceedings which were held before him
(d) a number of other reasons also were mentioned.
4. I shall not take up the objections of Mr. Mahajan in the same order as I have summarized them I shall first dispose of some of his objections which to my mind are of no consequence and do not affect the proceedings of the arbitrator at all.
5. About the question that the award was beyond four months. I have to refer to the arbitration clause in the agreement itself. Condition 36 of the contract in its amended form is as follows:—
“The arbitrator shall be deemed to have entered on the reference on the date he issues notice to both the parties, fixing the date of hearing”
6. The first schedule to the Arbitration Act of 1945 para 3 states that the arbitrator shall make an award within four months of his entering on the reference.
7. According to Mr. Raheja he entered in the reference on 1st January, 1963 by means of his letter ARB/CEW-16/98 and directed the parties to appear on 28th January, 1963 for hearing. This date was subsequently changed on the application of the contractor to 9-2-63 and the reference was heard by the arbitrator on 12th, 13th and 15th February so according to the interpretation of the words ‘entering upon reference as contained in the arbitration clause (if the arbitration agreement is otherwise valid) the award has been made by the arbitrator within four months of his entering upon the reference and is not therefore invalid. This objection of Mr. Mahajan has therefore no force.
8. About the venue of the arbitration proceedings, the grievance of the petitioner has been that the contract related to the supply of charpoys in Jammu, the sample was at Udhampur, and therefore, the proceedings held by the arbitrator at Delhi in spite of the protests of the contractor were vitiated and wrong. But the same clause, i.e condition No. 36 as amended gave an absolute discretion to the arbitrator to fix such place or places as the venue of the arbitration as he thought fit to his sole discretion. Therefore apart from the other implications of the failure of natural justice etc., fixing of Delhi as the venue of arbitration is rejected as a contention.
9. The objection that Mr. Raheja was appointed as an arbitrator without notice to the contractor is also not correct. The agreement as it is, gave the power to the Chief Engineer to appoint anybody as the arbitrator. That option has been exercised by the Chief Engineer and he has appointed Mr. Raheja. There is no warrant for the proposition that the contractor should have been consulted before any person was appointed as the arbitrator. This contention of the contractor is also rejected.
10. That the arbitrator is a Superintending Engineer in the Army Department does not disqualify him from acting as an arbitrator in these proceedings. The agreement authorized the CE to appoint any person as an arbitrator. A Obviously this was a term accepted by the con-tractor and therefore, he can have no grouse on this score. It has been held in AIR 1933 Sindh 75 that even a servant of one party can act as an arbitrator. On that score there is nothing wrong with the arbitration proceedings.
11. About the partiality of the arbitrator, 1 can safely say that the record does not display any manifest partiality shown by him. So far as his person is concerned, nothing has been established to indicate that the arbitrator has acted in a manner which would go to show that he wanted to show favour to the Union of India, the army authorities or the contractor. It is true that the arbitrator has decreed certain claims of the Union of India without any evidence, but such acts, even though not strictly in conformity with the practice of judicial courts, do not vitiate the arbitration proceedings as such. The arbitrator is a judge of the choice of the parties. He is not bound by the provisions of the Evidence Act. He can decide matters as best as he thinks fit. Parties are bound by his award. The only limitations on the powers of an arbitrator are that he should not violate the principles of natural justice; he should give a fair hearing to the parties and should give a reasonable time and opportunity to them to substantiate their respective claims. Broadly speaking the arbitrator's award in this case cannot be set aside on most of the above mentioned grounds, but suffers from some other infirmities which would be discussed at their proper place.
12. In this case it has been vehemently argued both by Mr. Sharma and Mr. Mahajan that there was no valid reference to arbitration. According to the learned counsel, the original agreement was for the supply of charpoys along with mosquito net Stings, i.e, clumps and gutties. That was the complete agreement. The contractor had made certain supplies under the original contract when his work was suspended. Later on the Executive Engineer Works Section 3 by means of his letter 8412/334.EB informed the contractor not to manufacture charpoys with mosquito net frames. This entailed an omission from the charpoys of mosquito net frames with gutties and clumps. A reduction of Rs. 4.33 per set was calculated by the Executive Engineer and communicated to the contractor. He was further asked to confirm his agreement to the rate or submit his objections. The contractor replied vide his letter date 30th March/3rd April, 1958 that he would supply the cots minus these things, but would be prepared to reduce the price by Rs. 1.50 per piece. This again was not accepted by the department. They suggested another figure of Rs. 4.49 vide their letter No. 8412/442.E dated, 29th August, 1958. Then he was called for a meeting by wireless. The last letter of the contractor on the subject is dated 9th August, 1958 (page 95) wherein he states that the rate of mosquito nets frames was agreed upon after prolonged discussions with the OC 969 Works Section and the ESO, Mr. Jarath. This shows that at the time of the dispute the rate of the new charpoys on account of the absence of mosquito nets gutties and clumps was not settled between the parties. There were offers, proposals and counter offers and counter proposals on either side. According to Mr. Mahajan it was a new contract which was sought to be substituted for the original contract, and hence in the absence of a legally completed contract the arbitration clause could not be invoked. The new contract had not come into being and the previous contracts stood rescinded or cancelled, though some of the terms of the old contract regarding the number of the charpoys etc. may have remained intact.
13. Mr. Suri controverted this assertion of the learned counsel by referring to condition 6 which permitted the operating officer to deviate by means of modification of design, addition to or omission from the supplies so on and so forth. It may be remarked here that Mr. Suri argued his case on the whole with admirable clarity about facts and was equally very well prepared with the law on the subject. But when we read this condition 5 the word ‘deviation’ applied only to lumpsum contracts. It may be stated that contracts are of two kinds. One is a lump sum contract; the other is a rate contract. As an instance of a lumpsum contract may be mentioned the case of the construction of a house for that house a certain plan is prepared showing windows, doors ceilings and fittings etc. In such a contract deviations can be made by changing the site of a door or window or the size thereof or the dimensions thereof or removing a certain partition wall etc. etc. In such contracts deviations are permissible and they are within the powers of the accepting authority. This is understandable because when such a contract is carried out, certain modifications may be thought necessary. But in a rate contract the rate is offered for a particular piece or a particular thing, as in this case the charpoys as originally designed. But if some change is introduced in the design parts or manufacture of the charpoys, the deviation is not permissible Mr. Raheja in his statement has admitted that this contract is a rate contract and therefore obviously under clause 5 the deviation was not applicable to such a contract, nor was it within the competence of the accepting officer to change any portion or parts of the charpoys. If any changes were introduced in the charpoys as originally contracted for it could be done by substituting a new contract for the old one. The old contract was entered into for charpoys with mosquito net frames clumps and gutties. The new contract was minus mosquito net frames, clumps and gutties. This was obviously a new contract and unless both sides agreed upon the new price to be paid for the charpoys or in the other words to the deduction being made on account of the omission of these things no new contract could be held to have come into existence. The conditions of the old contract stood rescinded or superseded and no new valid contract came into existence. There was no concord between the parties about the price. All that can be said in the present case is that the Military Department asked the contractor to supply certain cots without mosquito nets, gutties and clumps. They asked him for quotations. Either party gave him quotations which were not acceptable to the other and the rate was not settled upto last moment. If the department continued to accept supplies from him or if the contractor failed to supply a particular number, the remedy of either may have been and is different. But at any rule it is not remedy by a reference to the arbitration clause because the arbitration clause went away with the old contract. If the new contract came into existence and the new contract had an arbitration clause, a reference to a arbitration would be conceivable, otherwise it would be a reference without jurisdiction.
14. Mr. Suri, however, contended that the contractor had not objected to the jurisdiction of the arbitrator Moreover by his participation in the arbitration proceedings, he had waived this right. Therefore, the award was binding on him.
15. The contractor in his written objections before the arbitrator on page 10 has said:—
“The respondents, thereafter wanted the claimants to manufacture charpoys without the provision of mosquito net frames with gutties and clumps. The contract for the supply of charpoys indicated the item of charpoy to be an entire item inclusive of the mosquito net frames, gutties and clumps. The nature of the contract was therefore, changed and the original contract was undone by the respondents by ordering the aforesaid change in the material to be supplied. In law the hitherto existent contract and its stipulations ceased to have effect. The intention was to substitute the same by a new arrangement for the supply of charpoys without mosquito net frames, gutties and clumps and also by a new rate to be agreed to by the parties and that could be the beginning of a new adventure in the supply as distinct from the hitherto existing contract between the parties
“It was therefore imperative that to bring into existence a binding contract between the parties on new stipulations the rate for the new item of supply should be agreed to between the parties. The action of the respondents clearly indicated that they themselves had not determined what rate they would offer to the claimant to accept for the new arrangement”
16. On page 11 he further states:—
“The claimant begs to invite particular attention to this effect that in view of the nonexistence of an agreed arrangement between the parties to the revised supply there cannot be deemed to have been in existence any agreement or a compelling contract between the parties with regard to the supply of the charpoys, without mosquito net frames, gutties and clumps, and inasmuch as the respondents themselves had not made a positive offer to the claimant, since they were revising their own calculations, time and again, and since the claimant's offer had not also been accepted by the respondents there was no contract between the parties on 22nd may, 1958, which could be cancelled to any prejudice or damage to the claimant”
17. The contractor had taken this objection at the earliest time. The legal position in this behalf will be discussed at a later stage. First let me dispose of the factual objections of Mr. Suri.
18. Mr. Suri contends that in the suit of the contractor before the Sub-judge at Jammu, on an objection by the defendant's in that case that the proceedings in that suit be stayed under Section 34 of the Arbitration Act, the parties had agreed to the stay of the suit and had further agreed that the matter be referred to arbitration. Therefore according to Mr. Suri, the contractor was a willing party to the arbitration proceedings. It has to be recalled that suit was for a permanent injunction in respect of four contracts in which the present dispute was one of the four agreements entered into between the parties. When that suit was stayed, it was again an open question what would be referred to arbitration and what would be the nature of the arbitration proceedings. An arbitrator was appointed for all the four contracts. The contractor objected and later on the Chief Engineer appointed Mr. Raheja as the arbitrator of the present dispute. When the arbitrator called upon the parties to prefer their claims before him the contractor unequivocally pleaded before him that there was no subsisting contract regarding the supply of charpoys minus mosquito nets gutties and clumps, between the parties and the old contract had been superseded by an attempt at creating a new contract. Therefore the stay of the suit with the consent of the contractor has no binding effect of making the reference a valid one. I would add that any subsequent participation of the contractor in the proceedings, after having taken objection at the earliest possible moment before the arbitrator, would not amount to waiver in the eye of law in the present case Reference may be made to the following authorities.
AIR 1957 Punj 40, AIR 1958 Andh Pra 384, (1913) 21 Ind Cas 217 (Cal), AIR 1954 Mys 46, AIR 1951 SC 9. AIR 1965 Assam 81. AIR 1963 SC 1685 and AIR 1951 Cal 78.
19. In AIR 1963 SC 1885 it has been held that “the view that the Govt. of India having agreed to refer differences to arbitration and having taken part in the proceedings before the arbitrators and the umpire, had waived the objection as to the illegality of the contract and could not therefore raise any such objection in application for setting aside the award cannot be accepted as correct. The requirements of section 175(3) of the Govt. of India Act are mandatory and the fact that the Govt. of India did not contend before the arbitrator that there was in law no arbitration agreement on which the arbitrator was competent to ad would not invest the arbitration agreement with any validity. It is from the terms of the arbitration agreement that the arbitrator derives his authority to arbitrate; if in law there is no valid arbitration agreement the proceedings of the arbitrator would be unauthorised.”
20. In the Punjab authority AIR 1957 Punj 40 (Supra), a Division Bench of that court held that an arbitration agreement may be superseded by a new agreement which has the effect of extinguishing the existing agreement or by the performance of the terms of the new agreement entered into in satisfaction of the prior agreement. The question whether the parties did in fact enter into a new agreement in substitution of the original agreement or whether the terms of the new agreement have been performed as satisfaction must be determined by the court before it proceeds to enforce the arbitration clause.
21. There the case was remanded to the trial court which was directed to see whether the arbitration agreement had been superseded by a new agreement and if it was so, the arbitration clause would come to an end.
22. In AIR 1958 Andh Pra 884 it was held:
“Waiver and estoppel are not one and the same thing. They differ from each other in various respects. Waiver is an intentional relinquishment of a known right or such conduct as warrants an inference of the relinquishment of that right. It is an intentional act and implies consent to dispense with or forgo something to which he has a right. Thus waiver is created upon knowledge of all the facts by both the parties; but in case of estoppel by representation, the fact that the represented has knowledge of the facts destroys the plea of estoppel. Mere silence will not be waiver. A person may waive the provisions made for his individual benefit but he cannot be deemed to have waived in law the statutory provisions which are based on public policy.
Where, therefore, the plaintiff having nominated another arbitrator in place of his previous arbitrator in contravention of Rr. 62 and 64 of the Hyderabad Stocks Exchange Rules, the defendant at the earliest possible opportunity objected to the right of the plaintiff nominating him and pressed this objection in clear terms and made it clear that it was under protest that he was taking part in the proceedings;
Held that the defendant's objection to the jurisdiction of the arbitrator would not be considered to have been waived by his continuing to attend before the arbitrator and leading evidence. Whatever part he took in the proceedings before the arbitrator must be deemed to have been taken under continuous protests. Thus neither the plea of waiver nor of estoppel could be maintained. The award therefore must be held to be void as the arbitrator had no valid authority to make the same.”
23. A number of authorities, both Indian and English, have been discussed in this authority.
24. (1913) 21 Ind Cas 217 (Cal) is a case very much similar to the present case. In that case a contract between the parties provided that the plaintiff should deliver to the defendant certain goods within a certain time, and that any dispute arising out of the contract should be referred to arbitration. The time for delivery was extended by the plaintiff, but a term was introduced about the inspection of the Konds before delivery in the godowns of the plaintiff. Even after the expiry of the extended time, the plaintiff delivered and the defendant took a certain quantity of goods for the price of which this suit was brought. The defendant claimed to deduct a certain sum as damages, and he made this application that having regard to the arbitration clause in the original contract, the matter in difference might be referred to arbitration. The plaintiff stated that by the extension of the time for delivery a new contract had been substituted and the original contract was no longer subsisting. In that case a mere inspection of the goods before delivery was interpreted as rescinding the old contract and making the arbitration clause inapplicable. In this case an entirely new contract was sought to be entered into between the parties. The old contract as well as the arbitration clause on the basis of this authority stood abrogated.
25. In AIR 1951 Cal 78 it was held that an award can be challenged for want of jurisdiction under section 33
26. AIR 1965 Assam 81 is a very important authority relevant to the case before me. In that case a contractor who had to manufacture and supply a fixed quantity of material to the railway, also manufactured additional quantity against the agreement and supplied to the railway. It was provided by the contract that the parties could refer to an arbitration any matter if any dispute arose relating to the terms of the contract or any payment to be made under the contract or any matter connected with or arising out of the contract. The contract did not provide for any extra supply or for payment on enhanced rate. On the other hand clause 6(e) of the contract stated that no claim for extra or additional work or works not provided for by the contract of any kind whatsoever shall be admitted unless they shall have been executed under the written orders of the Engineer-in-charge which orders the contractor must produce as vouchers for the claim.” The contractor had been paid for the original quantity of material at the contracted rate. On a dispute regarding the enhanced rate claimed by the contractor and with regard to the manufacture of additional quantity which he had supplied to the railway, the matter was referred for arbitration and an award was filed under which enhanced rate was granted for supply of quantity under original contract and also for additional supply. The railway being dissatisfied by the award challenged the validity of the award. The award was set aside by the lower court.
27. On these facts it was held that the award was on the face of it in excess of jurisdiction of the arbitrator and the court had power to go into the question of the validity of the award and set aside the same.
“Under section 17 the court had ample power to go into the question of the validity of the award without any objection being filed by any of the parties to the arbitration and thereafter pronounce judgment in accordance with the award.
It could not be doubted that so far as the enhanced rate claimed by the contractor was concerned, that did not form part of any agreement. Thus the contractor had no right to claim the enhanced rate and any claim for enhanced rate could not be regarded as any dispute arising out of or connected with the agreement. From the very nature of the agreement, it could only have been the subject matter of a separate contract. If the contractor was not entitled to any enhanced rate even with regard to the materials manufactured and supplied under the contract he could not get enhanced rate for the supply of additional material. Clause 6(e) of the agreement has laid down that the railway could not consider the claim with regard to the extra or additional work or works not provided for by the contract, unless the order has been given by the Engineer-in-charge. But that clause did not mean that the additional supply if any, made would be treated to be a supply under the contract. There might be a separate contract for supply of additional material. Thus any dispute relating to such a supply could not be said to be dispute arising out of the contract or connected with the contract and hence could not be referred to arbitration under the terms of the contract. The arbitrator had no jurisdiction to give the award as the dispute decided by him did not form part of an agreement”
28. This authority also more than supports the view I have taken in this case.
29. In AIR 1951 SC 9 the arbitration clause which was the usual clause appended to such contracts provided for reference to arbitration of “all matters, questions, disputes, differences and/or claims arising out of and or concerning or relating to this contract.” In that case it was held that as the question turned upon the true interpretation of the contract and the parties had to take recourse to the contract to establish the claim, it was a dispute under or arising out of the contract and thus within the jurisdiction of the arbitrators.
30. But here the distinction is that this dispute does not at all arise out of the contract originally entered into between the parties. A new contract is sought to be created by giving new terms as the price of charpoys without mosquito net frames clumps and gutties. The parties never agreed to the price of the charpoys. With these specifications in the contract — being a rate contract — the deviation clause would not apply. Hence when no legal contract had come into existence, the question of the invoking the arbitration clause in the previous contract would not at all apply.
31. In view of what has been stated above, it is clear that there was no subsisting valid contract between the parties regarding supply of charpoys without mosquito net frames clumps and gutties. The old contract stood susperseded and there was no arbitration clause in the contract which subsisted between the parties at the time of this reference. This reference was therefore wholly uncalled for and any participation by the contractor before the arbitrator could not constitute waiver against him more so when he had at the earliest possible opportunity taken this plea before the arbitrator as detailed above.
32. There were other grievances made by the learned counsel for the contractor who stated that the arbitrator had not maintained any record of the proceedings had denied the petitioner an opportunity to lead his evidence, and had fixed the venue of the hearing at a place which was far away from the place of contract. The findings of the arbitrator were capricious, without any basis and on no material on the record. Before I discuss this aspect of the case I should dispose of Mr. Suri's argument in this behalf Mr. Suri said that it was not at all obligatory for the arbitrator to maintain any record of the proceedings, nor was he bound by the rules of evidence, nor equally had he the obligation to record specific findings on different matters in this behalf he referred me to the following authorities:—
AIR 1940 Lah 73, AIR 1954 Ajmer 21. AIR 1936 Lah 492. AIR 1947 Lah 177 and AIR 1943 Pat 285
33. He argued that an award could be set aside only when there was an error apparent on the face of the award, otherwise not: and an error apparent on the face of the award could not be the one which would be discovered after a long drawn process of reasoning as was held in AIR 1960 SC 137. In support of his contention Mr. Suri referred to AIR 1965 J and K 39, AIR 1965 J and K 28 also and AIR 1960 SC 137 (Supra) According to Mr. Suri there was no error apparent on the face of the award. He further stated that even the validity of an agreement of arbitration could not be challenged. It had however been held in AIR 1951 SC 9 (Supra) that once a dispute had been found within the scope of an arbitration clause, the court had no power to enter into the merits of the dispute I need not comment on these authorities as there is no dispute about the proposition of law enunciated therein. It has, however, been held in 23 Ind Cas 625 (AIR 1914 PC 105) that it is desirable that the arbitrator should maintain notes of the proceedings. In this case it has however been argued vehemently that the arbitrator by refusing to make a part of the record certain documents summoned by the contractor and exempting them on the question of privilege has prejudiced the contractor. The arbitrator admittedly has not maintained any record of the minutes of the proceedings. He spoke from his memory when he deposed in the court in this case. As already stated it would have been desirable for the arbitrator to have maintained a record of the proceedings conducted by him so that either party could have seen what proceedings were actually taken by him on any particular date. In his letter of 16th January, 1963 the contractor had requested the arbitrator to determine certain matters as preliminary and about production of evidence he had requested for the summoning of a number of Government officials at Jammu whose evidence would be necessary in the case. Further, we do not know what documents were actually produced by the Union of India about which they claimed privilege and which were actually held privileged by the arbitrator. Though the arbitrator is both a judge of fact and law vet the court has been deprived of looking at the documents and decide whether they actually would come within the definition of privileged documents. Anyway, that is not one only lacuna. It was put to the arbitrator in a number of questions whether he had disposed of the applications of the contractor pertaining to his preliminary objections and given him an opportunity to adduce his evidence. The arbitrator had not a very satisfactory answer to make. He tried to avoid the issue which necessitated the learned counsel for the contractor to put definite questions to him. The questions and the answers given by him have been recorded in his statement dated 22-12-1965. The overall impression that is left in one's mind after the statement of the arbitrator is perused is that he has not applied his mind to the objections and the insistence of the contractor to produce evidence. If as alleged by the contractor he was not allowed time to produce evidence, the award even though otherwise valid, would be liable to be set aside on that ground alone. It is not necessary in the case of an arbitrator that there should be misconduct on his part as understood in the ordinary parlance. An award is liable to be set aside if the arbitrator is guilty of legal misconduct. There may be nothing perverse or objectionable so far as the person of the arbitrator is concerned, but if there are certain things apparent from the file which amount to legal misconduct, the award is liable to be set aside.
34. A Division Bench of the Patna High Court in AIR 1951 Pat 201 observed:
“Where an arbitration clause in a contract for supply of bricks provided that the arbitrator was to settle disputes and claims arising out of the contract but the arbitrator in awarding compensation to the contractor look into consideration the moral obligation of the other party, the award is vitiated by illegality which is apparent on the face of the award and can be set aside.”
35. It was further held that where an arbitrator upon an erroneous construction of contract awarded compensation to the contractor, the error in construction of the contract was apparent on the face of the award and must be set aside.
36. In AIR 1958 SC 1050 it was held that where a Professor of a certain University had been dismissed wrongfully and mala fide and the award stated that the dismissal had no effect on his status and that he still continued to be a Professor of the University, and it directed specific enforcement of a contract of personal service, and as such involved a legal proposition which was clearly erroneous in view of Section 2(b) of the Specific Relief Act and therefore disclosed an error on the face of the award.
37. In AIR 1953 Nag 301 it was held that when no proper hearing of the matters in dispute were held by the arbitrator, there was misconduct of the proceedings vitiating the award.
38. In AIR 1956 Nag 245 it was held that the failure of the arbitrator to inquire into the objections raised by the party amounted to misconduct of the proceedings.
39. In AIR 1951 All 711 an arbitrator refused to record the evidence of a party and the award was set aside.
40. There were other objections raised by the learned counsel for the contractor which go to the merits of the case. This court while deciding whether a certain award should be made a rule of the court is not sitting as a court of appeal and on questions of fact which have been referred to an arbitrator, his decision is final and a court cannot interfere with such decision even if its own opinion, would be different on facts from that of the arbitrator. To that extent the objections of the learned counsel for the petitioner have not been seriously considered by me. I have come to the conclusion that there was no valid reference to arbitration and therefore the whole proceeding before the arbitrator and the final award was without jurisdiction which renders the whole award liable to be set aside.
41. Although I have held that the reference to arbitration in this case was without jurisdiction and hence the award was liable to be set aside on that ground alone. I have considered the other aspects of the matter which proceed on the assumption of a valid reference I thought it proper to record both findings. Assuming the arbitration proceedings valid there has yet been failure on the part of the arbitrator to consider the contention of the contractor; the contractor has not been given opportunity to produce evidence, some record has been withheld on the ground of privilege without even indirectly or incidently mentioning the nature and volume of the record held privileged. These lacunae are the violations of the principles of natural justice and denial of opportunity to the contractor to press and prove his case. The result is that the award is set aside, leaving the parties to bear their own costs.
DJ/KSB
42. Award set aside.