Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Maharashtra Ownership of Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act, 1963
  • S. 53(1) of the Maharashtra Regional and Town Planning Act, 1966 (hereinafter referred to as the said Act of 1966)
  • S. 53(1) of the Maharashtra Regional and Town Planning Act, 1966
  • ORISSA DEVELOPMENT AUTHORITIES ACT 1982
  • S. 353-A of the Mumbai Municipal Corporation Act, 1888
  • provisions of S. 368(2) of the Calcutta Municipal Act.
  • SPECIFIC RELIEF ACT 1963
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Maharashtra Ownership of Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act, 1963
  • S. 53(1) of the Maharashtra Regional and Town Planning Act, 1966 (hereinafter referred to as the said Act of 1966)
  • S. 53(1) of the Maharashtra Regional and Town Planning Act, 1966
  • ORISSA DEVELOPMENT AUTHORITIES ACT 1982
  • S. 353-A of the Mumbai Municipal Corporation Act, 1888
  • provisions of S. 368(2) of the Calcutta Municipal Act.
  • SPECIFIC RELIEF ACT 1963
Smart Summary

Factual and Procedural Background

The appellant, originally the plaintiff, applied for permission to construct a building with plans approved only for the ground floor by Respondent 1 Corporation. Despite this, the appellant illegally constructed seven additional floors without obtaining occupation or completion certificates. The appellant entered into agreements with flat purchasers and inducted them into possession of the flats by March 2001. Respondent 1 Corporation issued a notice under Section 53(1) of the Maharashtra Regional and Town Planning Act, 1966, stating that the construction of seven floors was unauthorized and contrary to the commencement certificate. The appellant admitted the mistake but claimed construction proceeded under pressure from flat purchasers and in anticipation of acquiring Transferable Development Rights (TDR), which were not secured. The appellant sought relief through a suit praying for mandatory orders directing Respondent 1 to process TDR files and restrain demolition of the building. The trial court dismissed the appellant's motion for injunction, leading to this appeal.

Legal Issues Presented

  1. Whether a builder who has illegally constructed floors beyond approved plans and inducted flat purchasers without completion or occupation certificates is entitled to discretionary and equitable relief of temporary injunction.
  2. Whether the appellant, having failed to apply for regularisation within the prescribed period under Section 53(3) of the Maharashtra Regional and Town Planning Act, 1966, can claim protection against demolition.
  3. The applicability of judicial discretion in granting interim relief in cases of unauthorized construction by professional builders.

Arguments of the Parties

Appellant's Arguments

  • The appellant constructed in anticipation of acquiring TDR, which is now available, enabling regularisation of the entire building.
  • The flat purchasers were placed in possession as they had invested substantial amounts, and the appellant was compelled to proceed due to their pressure.
  • Relied on Apex Court decisions in Corpn. of Calcutta v. Mulchand Agarwala and Syed Muzaffar Ali v. Municipal Corporation of Delhi to argue that injunction should have been granted.
  • Prayed for a mandatory injunction directing the Corporation to process the TDR files and restrain demolition until such processing.

Respondent 1 Corporation's Arguments

  • The construction by the appellant was unauthorized and beyond the sanctioned plan.
  • Pointed to various notices issued to the appellant regarding the unauthorized construction and occupation.
  • Urged confirmation of the trial court’s dismissal of the injunction motion based on the appellant’s conduct.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Corpn. of Calcutta v. Mulchand Agarwala, AIR 1956 SC 110 Distinction between trivial/formal breaches and serious breaches of building rules; demolition justified in serious breaches. Applied to show appellant’s breaches were serious, not trivial, thus justifying demolition and refusal of injunction.
Syed Muzaffar Ali v. Municipal Corporation of Delhi, 1995 Supp 4 SCC 426 Departure from authorised plans does not ipso facto justify demolition; however, serious breaches may require demolition. Used to emphasize that although not all unauthorized constructions warrant demolition, appellant’s case involved grave breaches.
Friends Colony Development Committee v. State of Orissa, 2004 8 SCC 733 Professional builders’ deliberate deviations are to be dealt with sternly; recommendation for heavy penalties to deter illegality. Supported the court’s stern approach towards the appellant as a professional builder who deliberately violated norms.
M.I Builders (P) Ltd. v. Radhey Shyam Sahu, 1999 6 SCC 464 No consideration to builders for unauthorized construction; judicial discretion cannot perpetuate illegality. Guided the court’s refusal to grant temporary injunction as it would encourage and perpetuate illegality by the appellant.
Wander Ltd. v. Antox India (P) Ltd., 1990 Supp SCC 727 Scope of appeal against discretionary orders under Order 43(1)(r) of CPC is limited; interference only if discretion is perverse or arbitrary. Used to affirm that the trial court’s discretionary order dismissing injunction should not be interfered with absent perversity.

Court's Reasoning and Analysis

The court noted the appellant’s construction beyond the sanctioned ground floor without approval or completion/occupation certificates. The appellant admitted the mistake and failure to secure TDR, which was a prerequisite for the additional floors. The appellant did not apply for regularisation within the one-month period prescribed under Section 53(3) of the Maharashtra Regional and Town Planning Act, 1966, thereby foregoing a statutory remedy.

The court emphasized that temporary injunction is an equitable and discretionary relief governed by the Specific Relief Act, 1963, and that appellate interference in discretionary orders is limited to cases of perversity or arbitrariness. The appellant’s conduct was found to be high-handed and deliberate, suppressing material facts such as completed construction and possession by flat purchasers when submitting amended plans.

Citing Apex Court precedents, the court distinguished between trivial and serious breaches, concluding the appellant’s violations were serious and deliberate. The court rejected the appellant’s reliance on cases allowing relief where breaches were minor or where delay justified leniency, noting that the appellant’s conduct did not merit such protection. The professional builder’s deliberate breaches warranted stern treatment to deter illegality.

While recognizing the hardship to flat purchasers, the court refused to grant injunction protecting the illegal construction but allowed a limited four-month period before demolition to enable purchasers to relocate or seek relief against the appellant. The court also imposed compensatory costs on the appellant for unnecessary litigation.

Holding and Implications

DISMISSED: The appeal from the order dismissing the injunction motion is dismissed.

The court refused to grant temporary injunction protecting the appellant’s unauthorized construction, holding that such relief cannot be extended to a professional builder who deliberately contravened building permissions and failed to avail statutory remedies. The appellant was ordered to pay compensatory costs of Rs. 30,000 to Respondent 1 Corporation. Demolition of the illegal floors will not be undertaken for a period of four months from the date of the order, solely to protect the interests of the flat purchasers, and not as a concession to the appellant. No new legal precedent was established; the decision reinforces existing principles that unauthorized constructions by professional builders warrant stern judicial response and that discretionary reliefs should not perpetuate illegality.

To access the original judgment, please Sign In or Subscribe.

    Leela Enterprises v. Bombay Municipal Corpn. And Others S

    The Judgment of the Court was delivered by

    A.S Oka, J.— This appeal from order was fully heard yesterday at admission stage and today it is kept for dictation of the judgment.

    2. The appellant in this appeal high-handedly and illegally constructed a building consisting of ground plus seven upper floors when permission granted was for construction of only ground floor. Without there being any occupation or completion certificate, he has inducted the flat purchasers in the flats in the building. The question before me is whether such a builder is entitled to grant of discretionary and equitable relief of temporary injunction.

    3. It is necessary to refer the facts of the case. The appellant is the original plaintiff. The appellant applied for permission to construct a building. Plans were approved by Respondent 1 Corporation for construction of only ground floor for residential use. Intimation of disapproval was issued on 9-12-1999. The commencement certificate was issued on 3-2-2000. On 27-8-2001 an application was made by the Architect of the appellant to Respondent 1 Corporation. In the said application it was stated that though earlier plans were approved for ground floor, additional seven floors were proposed in lieu of Transferable Development Rights (hereinafter referred to as TDR) admeasuring 1030 sq metres. It was stated in the application that Respondent 1 Corporation may process the files and issue TDR at the earliest.

    4. The case of the appellant-plaintiff is that as there was a dispute between the owners of TDR and the appellant, the transaction of acquiring TDR could not be materialised. In the meanwhile, the appellant entered into the agreements with prospective flat purchasers. The appellant proceeded with the construction of upper floors. The case of the appellant is that he proceeded in anticipation of acquisition of TDR. It is the specific case of the appellant that in March 2001, the flat purchasers were put in possession of the flats.

    5. A notice dated 3-12-2002 under S. 53(1) of the Maharashtra Regional and Town Planning Act, 1966 (hereinafter referred to as the said Act of 1966) was issued by Respondent 1 Corporation to the appellant stating therein that the work of seven floors is beyond the approved plan and was contrary to the commencement certificate. It is stated in the notice that the user of the ground floor is changed from residential to shop and the building is unauthorisedly occupied.

    6. A reply was sent by the appellant on 15-1-2003 to the said notice in which it is stated that the efforts of the appellants made earlier for securing TDR could not materialise. The appellant accepted that a mistake has been committed by carrying on construction. It is stated that due to pressure exerted by the flat purchasers, the appellant was required to put them in possession of their respective flats. It is stated that the appellant was in the process of acquiring TDR and therefore the matter should not be processed further. Thereafter, letter dated 12-3-2003 was sent by the Assistant Engineer of Respondent 1 to the owner of the property calling upon him to get the building vacated. A copy of the said letter was forwarded to the Architect of the appellant. By a letter dated 1-4-2003, the appellant informed the Executive Engineer of Respondent 1 that the appellant was in process of acquiring TDR and necessary compliance will be made within one and half months and a request was made to Respondent 1 not to take any further action. The suit was filed by the appellant praying for various reliefs. The prayers made in the said suit read thus:

    (a) That by a mandatory order of this Hon'ble Court the defendants be directed to—

    (i) Process all the files listed in para 9 hereinabove pending with the Chief Engineer (DP) of the defendant Corporation and issue the Development Right Certificate as per the proposal submitted by the plaintiffs and thereafter.

    (ii) Consider the proposal for regularisation of the suit Building No. 3 ‘A’ wing, Leela Vaibhav situated on plot of land bearing CTS No. 872-A, Village Kandivali (West) after giving personal hearing to the plaintiffs and pass a reasoned order.

    (b) That the defendants, their servants, agents, officers, employees and/or any other person claiming through them during final determination and one month after the reasoned order is communicated to the plaintiffs be restrained by an order and injunction of this Hon'ble Court from taking any steps and/or acting in furtherance of the said notice dated 12-3-2003 of Ext. ‘G’ hereto issued under S. 353-A of the Mumbai Municipal Corporation Act, 1888 and notice under S. 53(1) of the Maharashtra Regional and Town Planning Act, 1966 or demolishing the suit Building No. 3 ‘A’ wing, Leela Vaibhav situated on plot of land bearing CTS No. 872-A of Village Kandivali at Kandivali (W), Mumbai or any part thereof.

    7. A notice of motion was taken out by the appellant-plaintiff for injunction restraining Respondent 1 Corporation from taking any steps in furtherance of notice dated 12-3-2003 of demolition of the building in question.

    8. The notice of motion was opposed by Respondent 1 Corporation by filing an affidavit-in-reply. It is pointed out that the construction made by the appellant is unauthorised. A reference was made to various notices issued by Respondent 1 Corporation. By impugned judgment and order, the learned trial Judge dismissed the notice of motion.

    9. Shri Narula, learned counsel appearing for the appellant submitted that the construction was carried out by the appellant in anticipation of TDR becoming available. He submitted that the requisite TDR is now available and on the basis of the said TDR which is now available the construction of the entire building can be regularised. He stated that as the files are pending before Respondent 1 for processing the TDR, the prayer (a)(i) in the plaint was made by the appellant. He submitted that in the interests of the flat purchasers the construction was completed and the flat purchasers were placed in possession as they had invested substantial amounts. Shri Narula placed reliance on the decision of the Apex Court in Corpn. of Calcutta v. Mulchand Agarwala AIR 1956 SC 110). He heavily relied upon the decision of the Apex Court in Syed Muzaffar Ali v. Municipal Corpn. of Delhi 1995 Supp 4 SCC 426. He submitted that now it is possible to regularise the construction. He urged that in view of the mandate of the decisions of the Apex Court, injunction ought to have been granted by the trial court as now sufficient TDR is available.

    10. The learned counsel for Respondent 1 submitted that considering the conduct of the appellant, impugned judgment deserves to be confirmed. The learned counsel for Respondent 1 has taken me through various documents on record.

    11. It is well settled that the relief of temporary injunction under Or. 39 of the Civil Procedure Code, 1908 is a discretionary and equitable relief. The principles relating to grant of injunction are governed by the Specific Relief Act, 1963 which enshrines the principles of equity. It is also well settled that the scope of an appeal preferred under Or. 43(1)(r) of the said Code for challenging a discretionary order is limited. The position of law in that behalf is no longer res integra. If the discretion is exercised by the trial court reasonably and in judicial manner, merely because the appellate court would have taken a different view of the matter may not justify interference with the exercise of discretion by the trial court. Unless the order is shown to be perverse or arbitrary, interference cannot be made with the exercise of discretion. Since the appeal against the discretionary order is said to be an appeal on principle, the scope of the appeal is limited as stated above. Therefore, this appeal will have to be decided keeping in mind the aforesaid principles which are laid down by the Apex Court in Wander Ltd. v. Antox India (P) Ltd. 1990 Supp SCC 727

    12. The building plan of the appellant was sanctioned in December 1999 only in respect of the ground floor. It is an admitted position that though no application was made thereafter for obtaining sanction for construction of upper floors, the appellant proceeded with the construction. In fact in para 8 of the plaint a specific averment is made that in or about March 2001 to avoid further complications on account of legal proceedings which may be initiated by the flat purchasers, the plaintiffs handed over the possession of the flats in the suit building to the respective purchasers. Thus, the construction of the seven upper floors was completed in March 2001. It is interesting to note that on 27-8-2001 the Architect appointed by the appellant submitted a letter to the Assistant Engineer of the Building Proposals Department of Respondent 1 Corporation. Along with the said letter he forwarded amended plans. It is pertinent to note that in the said letter the fact that the construction of upper floors is completed and that the flat purchasers are inducted is completely suppressed by the Architect. The amended plans which were tendered along with the letter were for additional seven floors on the basis of FSI which was likely to become available on the basis of acquisition of TDR admeasuring 1030 sq m. The averments made in para 5 of the plaint clearly show that the efforts made by the appellant for acquiring TDR from the TDR owners could not be materialised.

    13. A notice was issued under S. 53(1) of the said Act of 1966 by Respondent 1 Corporation on 3-12-2002. Notice alleges that there is an unauthorised construction of 7 floors and that though sanctioned user of the ground floor was residential, the user was unauthorisedly changed to a shop. Another ground in the notice is that the building was unauthorisedly occupied. A reply was sent by the appellant to the said notice. In the reply the appellant admitted the mistake committed by him. The appellant also admitted that the efforts to secure TDR have failed. It is stated there was a shortage of TDR. It is contended that due to time-bound agreement entered into with the respective flat purchasers, the appellant was required to part with possession of the flats in favour of the flat purchasers.

    14. Necessary reference will have to be made to S. 53(1) of the said Act of 1966 which read thus:

    “53. Power to require removal of unauthorised development.—(1) Where any development of land has been carried out as indicated in sub-s. (1) of S. 52, the Planning Authority may, subject to the provisions of this section, serve on the owner a notice requiring him, within such period, being not less than one month, as may be specified therein after the service of the notice, to take such steps as may be specified in the notice—

    (a) in cases specified in cl. (a) or (c) of sub-s. (1) of S. 52 to restore the land to its condition existing before the said development took place,

    (b) in cases specified in cl. (b) or (d) of sub-s. (1) of S. 52 to secure compliance with the conditions or with the permission as modified:

    Provided that, where the notice requires the discontinuance of any use of land, the Planning Authority shall serve a notice on the occupier also.

    (2) In particular, such notice may, for purposes of sub-s. (1), require—

    (a) the demolition or alteration of any building or works;

    (b) the carrying out on land of any building or other operations; or

    (c) the discontinuance of any use of land.

    (3) Any person aggrieved by such notice may, within the period specified in the notice and in the manner prescribed apply for permission under S. 44 for retention on the land of any building or works or for the continuance of any use of the land, to which the notice relates, and pending the final determination or withdrawal of the application, the mere notice itself shall not affect the retention of buildings or works or the continuance of such use.

    (4) The foregoing provisions of this chapter shall, so far as may be applicable; apply to an application made under sub-s. (3).

    (5) If the permission applied for is granted, the notice shall stand withdrawn; but if the permission applied for is not granted, the notice shall stand; or if such permission is granted for the retention only of some buildings, or works, or for the continuance of use only a part of the land, the notice shall stand withdrawn as respects such buildings or works or such part of the land, but shall stand as respects other buildings or works or other parts of the land, as the case may be; and thereupon, the owner shall be required to take steps specified in the notice under sub-s. (1) as respects such other buildings, works or part of the land.

    (6) If within the period specified in the notice or within the same period after the disposal of the application under sub-s. (4), the notice or so much of it as stands is not complied with the Planning Authority may—

    (a) prosecute the owner for not complying with the notice; and where the notice requires the discontinuance of any use of land any other person also who uses the land or causes or permits the land to be used in contravention of the notice; and

    (b) where the notice requires the demolition or alteration of any building or works or carrying out of any building or other operations itself cause the restoration of the land to its condition before the development took place and secure compliance with the conditions of the permission or with the permission as modified by taking such steps as the Planning Authority may consider necessary including demolition or alteration of any building or works or carrying out of any building or other operations; and recover the amount of any expenses incurred by it in this behalf from the owner as arrears of land revenue.

    (7) Any person prosecuted under cl. (a) of sub-s. (6) shall, on conviction, be punished with imprisonment for a term which shall not be less than two thousand rupees but which may extend to five thousand rupees, and in the case of a continuing offence, with a further daily fine which may extend to two hundred rupees for every day during which such offence continues after conviction for the first commission of the offence.”

    15. Sub-s. 3 provides a remedy to the person aggrieved by the notice under sub-s. 1 of applying for permission under S. 44 for retention of the building. The application has to be made within the period specified in the notice. A period of one month was given by the said notice to the appellant. Admittedly the appellant has not applied for retention of the structure within the time specified under sub-s. 3 of S. 53 by invoking S. 44 of the said Act of 1966. S. 44 contemplates application being made to the Planning Authority for permission for development. S. 44 contemplates that the application shall be in writing in such form and shall contain such particulars and shall be accompanied by such documents as may be prescribed. R. 6 of the relevant rules prescribes form of such application and accompaniments of such application.

    16. Thus, the appellant did not avail of the remedy available under sub-s. 3 of S. 53. In fact, till today no such application has been made by the appellant. In the reply dated 15-1-2003 sent to the notice, the appellant has candidly admitted that he could not secure TDR.

    17. Therefore, scenario which emerges is that there was never any permission granted for construction of seven upper floors. The application made on 27-8-2001 was not considered by Respondent 1 Corporation obviously because at no point of time the appellant secured the requisite TDR. As stated earlier, in the application filed by the Architect on 27-8-2001, there was suppression of material fact that the construction of seven floors was completed and the flat purchasers were already inducted in possession.

    18. Shri Narula has placed reliance on a decision of the Apex Court in Corpn. of Calcutta v. Mulchand Agarwala. The Apex Court in para No. 13 has held thus: (AIR p. 115)

    “13. … It must be remembered that the building rules are enacted generally for the benefit of the public, and where the rules have been violated and proceedings are taken for an order for demolition of the building under S. 363 what has to be decided is whether the breaches are of a formal or trivial character in which case the imposition of a fine might meet the requirements of the case, or whether they are serious and likely to affect adversely the interests of the public, in which case it would be proper to pass an order for demolition.”

    19. In para 14 of the judgment, the Apex Court held that there was a justification for passing the order of demolition.

    20. However, the Apex Court did not pass the order of demolition in view of long delay and in view of provisions of S. 368(2) of the Calcutta Municipal Act. The reliance placed on this decison is not going to help the case of the appellant. In this case the appellant is guilty of serious breaches.

    21. Shri Narula invited my attention to para 4 of the decision of the Apex Court in Syed which read thus: (SCC p. 427)

    “4. However, it is to be pointed out that the mere departure from the authorised plan or putting up a construction without sanction does not ipso facto and without more necessarily and inevitably justify demolition of the structure. There are cases and cases of such unauthorised constructions. Some are amenable to compounding and some may not be. There may be cases of grave and serious breaches of the licensing provisions or building regulations that may call for the extreme step of demolition.”

    22. All that the Apex Court has said is that mere departure from the authorised plan or putting up a construction without sanction does not ipso facto necessarily and inevitably justify demolition of the structure. The Apex Court, however, held that there may be cases of grave and serious breaches of the Building Regulations that may call for extreme step of demolition. As stated earlier, present case is the case of grave and serious breaches by the appellant as he was knowing fully well that the permission granted related ground floor only to the and he constructed seven upper floors.

    23. A reference will have to be made to the recent decision of the Apex Court in Friends Colony Development Committee v. State of Orissa 2004 8 SCC 733. The case before the Apex Court arose out of illegal development carried out by a builder to which provisions of the Orissa Development Authorities Act, 1982 were applicable. In para 25 of the decision, the Apex Court has made a distinction in case of professional builders. The Apex Court observed that the professional builder and deviations by such builder can safely be assumed to be deliberate and done with the intention of earning profits and hence deserve to be dealt with sternly so as to act as a deterrent for future. The Apex Court has recommended to the State Government to think of levying a heavy penalty on such builders which can be utilised for compensating and rehabilitating the innocent buyers. At this stage a reference will have to be made of another decision of the Apex Court in M.I Builders (P) Ltd. v. Radhey Shyam Sahu 1999 6 SCC 464. What has been held by the Apex Court is that no consideration should be shown to the builder or any other person where construction is unauthorised. The Apex Court in para 73 held thus: (SCC p. 529)

    “73. The High Court has directed dismantling of the whole project and for restoration of the park to its original condition. This Court in numerous decisions has held that no consideration should be shown to the builder or any other person where construction is unauthorised. This dicta is now almost bordering the rule of law. Stress was laid by the appellant and the prospective allottees of the shops to exercise judicial discretion in moulding the relief. Such a discretion cannot be exercised which encourages illegality or perpetuates an illegality. Unauthorised construction, if it is illegal and cannot be compounded, has to be demolished. There is no way out. Judicial discretion cannot be guided by expediency. Courts are not free from statutory fetters. Justice is to be rendered in accordance with law. Judges are not entitled to exercise discretion wearing the robes of judicial discretion and pass orders based solely on their personal predilections and peculiar dispositions. Judicial discretion wherever it is required to be exercised has to be in accordance with law and set legal principles. As will be seen in moulding the relief in the present case and allowing one of the blocks meant for parking to stand we have been guided by the obligatory duties of the Mahapalika to construct and maintain parking lots.”

    The case of the appellant-plaintiff is that due to pressure exerted by the flat purchasers he had to proceed with the construction of the building. The Maharashtra Ownership of Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act, 1963 has been enacted for the benefit of flat purchasers. If S. 3 of the said Act of 1963 is considered along with Rr. 3 and 4 of the Rules framed under the said Act of 1963, it is obvious that obtaining building permission is a condition precedent for executing an agreement for sale in favour of the flat purchasers. That is why the law provides for giving inspection of the sanctioned plan to the flat purchasers before execution of the agreement for sale contemplated by the said Act of 1963. The appellant is a professional builder. There is no reason for showing any leniency to the builder like the appellant who has high-handedly proceeded with illegal construction of seven floors.

    24. It is to be noted here that as of today there is no application made for regularisation. The appellant is claiming that he has acquired certain TDR and files for grant of such TDR are yet to be processed. The prayer is for mandatory injunction directing the Corporation to process the files. The law provided remedy to the appellant to apply for regularisation in terms of sub-s. 3 of S. 53 of the said Act of 1966. Unfortunately, within the time prescribed by the law, any such application has not been made.

    25. There is one more aspect of the matter which needs serious consideration. In August 2001 the Architect of the appellant submitted the amended plans. Admittedly by that time huge construction of seven floors was completed and the flat purchasers were placed in possession of the flats. It cannot be said that the officers concerned of Respondent 1 Corporation had no knowledge of the said construction. However, till the end of year 2002 no action was taken by the officers concerned of the Respondent 1 Corporation. Even after the builder failed to submit the proposal for regularisation within one month from the date of service of the notice dated 3-12-2002, the officers concerned only kept on corresponding with the owner and the builder requesting them to vacate the building.

    26. Mr. Narula lastly submitted that limited prayer for grant of injunction be considered till the time the files are processed for acquiring the TDR.

    27. Grant of temporary injunction is purely equitable and discretionary relief. In many matters, this Court has time and again protected unauthorised constructions for a limited period to enable the Municipal Corporation to consider the proposal for regularisation. However, considering the conduct of the appellant such relief cannot be granted in favour of the appellant. It is to be noted here that as of today also the TDR is not actually available and there is no proposal submitted for regularisation. Discretionary relief of temporary injunction cannot be granted in favour of such a builder who has taken law in his own hands. As held by the Apex Court in M.I Builders discretionary relief cannot be granted in favour of the appellant as grant of any such relief will encourage illegality and will perpetuate illegality. In case of illegal constructions, interim injunction for protecting the structure can be granted only when there is a breach of principles of natural justice, or when construction is prima facie shown to be legal or when an unauthorised construction can be prima facie protected in terms of policies of the local authority concerned. In a given case, considering the overall conduct of the plaintiff and facts and circumstances of the case, protection can be granted for a limited period for allowing consideration of applications for regularisation. This is certainly not one of those cases where limited protection can be granted. The recalcitrant conduct of the appellant comes in the way of granting even a limited protection. The construction has been deliberately carried out with full knowledge of the fact that it is contrary to building permission. A professional builder like the appellant needs to be dealt with sternly.

    28. It is obvious that the real sufferers will be the flat purchasers. The construction of the seven upper floors of the building cannot be tolerated at all. However, if the demolition is undertaken immediately, the flat purchasers will not get enough time to shift elsewhere or to seek appropriate relief against the appellant. Therefore, demolition will have to be postponed for a reasonable time. Notwithstanding the dismissal of this appeal, for a period of four months from today Respondent 1 Corporation will not demolish the building. It is made clear that the time of four months is granted only for benefit of flat purchasers and the said time is not granted to enable the appellant to apply for regularisation.

    29. The appellant dragged Respondent 1 in unnecessary litigation. This is a fit case where professional builder like the appellant should be ordered to pay compensatory costs. In fact there cannot be any better case where a litigant is made to pay compensatory costs. The amount of costs is quantified at Rs. 30,000.

    30. Hence I pass the following order:

    (i) Appeal from order is dismissed. The appellant is directed to pay compensatory costs of Rs. 30,000 to Respondent 1 Corporation within a period of six weeks from today.

    (ii) Respondent 1 Corporation will not take any action of demolition for a period of four months from today.

    (iii) Parties to act upon an authenticated copy of this order.

    Use AI to get other relevant cases.

    Comments

    Leela Enterprises v. Bombay Municipal Corpn. And Others S
    (Apr 27, 2005)