Factual and Procedural Background

A limited company, the plaintiff, filed a suit against the Municipal Board of Bareilly (defendant) seeking recovery of Rs. 19,048-1-9 as the price for a motor lorry and a pumping apparatus supplied. The plaint stated that the defendant purchased these items and agreed to pay in instalments, but failed to pay the balance. The defendant contested the suit alleging the lorry was defective and not in accordance with the contract, claiming the contract was null and void and denying liability for interest. The suit was initially dismissed by the Court of first instance. On appeal, the court dismissed both the plaintiff's appeal and the defendant's cross-objection. The plaintiff then filed the present appeal against the dismissal of his appeal.

Legal Issues Presented

  1. Did the plaintiff agree to sell to the defendant a lorry of a particular description? If so, what were the particulars of the lorry agreed to be sold?
  2. Did the lorry supplied answer to the description of the one agreed to be supplied?
  3. If the lorry supplied did not answer to the description agreed upon, can the defendant refuse to pay the price, having regard to the provisions of Section 118 of the Contract Act?
  4. Is the defendant entitled to any and what compensation? How is the question of compensation affected by the fact that no notice under Section 118 of the Contract Act was given?
  5. Is the plaintiff entitled to any and what interest?

Arguments of the Parties

Plaintiff's Arguments

  • The plaintiff claimed delivery of the lorry and pumping apparatus was made in good working order on 3rd September 1921.
  • The defendant agreed to pay the price in instalments but failed to pay the balance.
  • The plaintiff sought the balance amount with interest at 12% per annum.

Defendant's Arguments

  • The lorry supplied was not in accordance with the contract and had several defects, rendering it unserviceable.
  • The plaintiff had agreed to supply a new lorry consuming not more than 1¼ gallons of petrol per hour, but supplied one not meeting this description.
  • Alleged fraud on the part of the plaintiff, though no particulars were furnished.
  • Claimed the contract was null and void and denied liability to pay interest.
  • Claimed entitlement to a refund of Rs. 5,000 paid, but did not pay court-fee or formally claim refund.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Section 118 of the Contract Act Buyer’s right to accept or refuse goods when warranty is broken; buyer may keep goods for reasonable trial period but loses right to reject if kept longer. The court applied this section to hold that the defendant had the right to examine the lorry and refuse it if it did not conform, but if kept beyond reasonable trial, he lost the right to refuse payment.
Section 73 of the Contract Act Entitlement to damages (interest) for breach of contract. The court held the plaintiff entitled to interest at 12% per annum as damages for breach of contract.

Court's Reasoning and Analysis

The court first examined whether the lorry supplied conformed to the contract. It found the lorry delivered was in good order, free from defects, and met the contract specifications. The court then considered the defendant's right under Section 118 of the Contract Act to refuse the goods if they did not meet the contract description. It clarified that the buyer may keep the goods for a reasonable time to test their conformity but loses the right to reject if the goods are kept beyond that period. The court rejected the defendant’s claim that the plaintiff promised a new lorry, finding no such stipulation was made. Even if the defendant expected a new lorry but received a reconditioned one, Section 118 would apply, allowing for compensation only if notice was given timely. Since no such notice was given, the defendant was not entitled to compensation or refund. Finally, the court addressed interest, holding that the plaintiff was entitled to interest under Section 73 of the Contract Act at the rate claimed, as damages for breach of contract.

Holding and Implications

Appeal allowed.

The court modified the decree of the lower courts and decreed the plaintiff's claim in full with costs. Interest on the claim amount was awarded at 6% per annum from the date of suit institution until realization, with costs bearing interest at the same rate. The decision directly affects the parties by affirming the plaintiff’s right to recover the price and interest, and rejecting the defendant’s claims for refund or compensation. No new precedent was set beyond the application of established provisions of the Contract Act.

    Empire Engineering Co. v. Municipal Board

    1. This is the plaintiff's appeal. His suit was practically dismissed by the Court of first instance. On appeal by him and on a cross-objection, puts in by the defendant, the learned Judges composing the Bench hearing the appeal agreed in dismissing the cross-objection, but differed as to the result of the appeal. The result was that both the appeal and the cross-objection failed. It is against the order of the Court dismissing the appeal that the present appeal has been-failed. A limited company, described as “plaintiff,” brought the suit of which this appeal has arisen for recovery of Rs. 19,048-1-9 being the price of a motor lorry and a pumping apparatus supplied by it to the defendant, the Municipal Board of Bareilly. The plaint was a simple one. It stated that the defendant, the Municipal Board of Bareilly, had purchased from the plaintiff the articles mentioned and agreed to pay the price in certain instalments detailed in the plaint. It further stated that delivery of the lorry, the pumping apparatus and other implements was made, all in good working order, on 3rd September 1921, hut the defendant did not pay the balance of the price due to him. He accordingly claimed the balance of the price with interest at 12 per cent per annum.

    2. The defence, so far as it is now material, was that the lorry supplied was not “in accordance with the contract” and was on test found to have several defects in it and did not prove to be serviceable, that the plaintiff had agreed to supply a new lorry and one which would not consume more than 1¼ gallons petrol in an hour, but the plaintiff supplied one which did not answer to the descriptions. The defendant also pleaded fraud on the part of the plaintiff but did not furnish any particulars beyond what has already been stated in this summary of his case. The defence ended by saying that the contract was null and void and the plaintiff had no right to maintain the suit. The defendant also contended that he was entitled to a refund of the sum of Rs. 5,000 which he had admittedly paid towards the price. The defendant, however, did not pay any court-fee and did not claim a refund. The liability of the defendant to pay interest was denied.

    3. It will be noticed that on the pleadings as described above, the issues that arose in the case were the following:

    1. Did the plaintiff agree to sell to the defendant a lorry of a particular description? If so, what were the particulars of the lorry agreed to be sold?

    2. Did the lorry supplied answer to the description of the one agreed to be supplied?

    3. If the lorry supplied did not answer to the description agreed upon, can the defendant refuse to pay the price, having regard to the provisions of Section 118 of the Contract Act.

    4. Is the defendant entitled to any and what compensation? How is the question of compensation affected by the fact that no notice under Section 118 of the Contract Act, was given?

    5. Is the plaintiff entitled to any and what interest?

    4. (Their Lordships then discussed evidence that the lorry delivered in September 1921, was in all respects a machine in good order and condition, free from all defects, and in all respects answered to the Contract, proceeded.)

    5. Point No. 3.— Supposing that the lorry delivered to the defendant did not answer, in its entirety, to the article ordered, the defendant had every right to refuse to accept the article. He could use the article sufficiently long to find out whether it answered or not the description of what he wanted. Section 118 of the Contract Act, lays down the law on the point and the illustrations make the law absolutely clear. That section briefly lays down that when there has been a contract with a warranty for sale of goods which at the time of the contract was not ascertained, and the warranty is broken, the buyer may accept the goods or refuse to accept them, when tendered. It further lays down that it is open to the buyer to keep the goods for a reasonably sufficient time in order to examine or try them in order to decide whether he would refuse or accept them. The user of the goods, however, must be limited to the trial and must not go beyond that. Such being the law, when the lorry was placed in the hands of the defendant, it was the latter's duty to have it thoroughly examined, and if necessary, by an expert. After examination, the defendant could decide either to keep it or to return it. If, however, he kept it for a period longer than it was necessary to keep it for the purpose of ascertaining whether it answered or not to the contract, he lost his right to return it or to refuse to pay the price.

    6. On behalf of the respondent, reliance was placed on English law and it was argued that there is a difference between a “condition” of a Contract and a “warranty.” It was urged that where the condition of a contract is broken, there can be no contract at all. It is, however, to be pointed out that our Indian law has deliberately, we must take it, avoided the distinction between a condition and a warranty. The illustrations given under S. 118, will make the matter clear. In illustration (c), B makes two pairs of shoes for A by A's order. A tries both, but uses one pair more than a mere trial requires. The shoes do not fit him. He cannot return the pair which no has used more than was necessary for the purpose of a trial. He must keep them and pay for them. The other pair he can return. It was certainly a “condition” to the acceptance of the shoes by A, that the shoes should fit. It may very well be said that it was a condition of the contract that the shoes should fit the person ordering them. Yet the case is put under S. 118 as fully covered by it. We are governed by the Indian law and must decide the case in accordance with its principles.

    7. Then it was urged that as the defendant ordered a new lorry and he got a second-hand one and there could be no contract, in law, if the parties were not agreed as to what was to be supplied. On the facts, we have found that such was not the case. The defendant never stipulated for a new lorry, nor did the plaintiff firm ever promise one.

    8. Supposing, however, that the defendant expected a new lorry and was given a reconditioned one. Even then S. 118 would apply. He could only ‘expect’ what he had bargained for. There was the lorry before the defendant and he had every opportunity and right to have it thoroughly examined. Further, if there was a breach of the warranty, on the ground that the lorry was not a new one, the defendant could claim compensation, provided he gave notice of his intention to claim compensation within a reasonable time, after discovering the breach of the warranty. That was, under the law, the defendant's only right after he had accepted the goods after an exercise of his right of acceptance or refusal. The defendant now cannot refuse to pay for the goods which he has kept and used.

    9. Point No. 4.— In dealing with point No. 3, we have already dealt with the question of compensation. The question of compensation was not definitely raised. The defendant said in para. 16 of the written statement that he was entitled to a refund of the part payment made by him we have already said that the defendant did not claim the amount as a set off for his counter claim nor did be pay any court-fee on it.

    10. On the merits, however, the defendant has no case. It was incumbent on him to give notice of his intention to claim compensation, as soon as he discovered (if ever) the fact that the warranty had been broken by delivery of an article that did not implement the contract. The defendant is not entitled to any compensation, nor to any refund of any part of the price paid by him.

    11. Point No. 5.— The question of interest, has not been discussed before us it arose, because there is the claim for interest and the defence was that no interest was payable. The contract has been broken and the plaintiff is entitled to interest by way of damages under Section 73 of the Contract Act. The rate of interest is reasonable, being 12 per cent per annum. We allow the plaintiff interest at the rate claimed, by way of damages. The result is that the appeal succeeds, the decree of the Court below and of this Court are modified and the claim is decreed in full with costs throughout. Interest on the amount of the claim will be paid at six per cent per annum from the date of the institution of the suit till realization, and the costs will bear interest at the same rate from this date till realization.

    R.M/R.K

    12. Appeal allowed.

    Use AI to get other relevant cases.

    Comments

    Empire Engineering Co. v. Municipal Board
    (Mar 16, 1929)