  • Section 15 of the RST Act read with Section 8(5) of the CST Act
  • a fiscal statute
  • Article 32
  • Article 14
  • sub-section (5) of Section 8 of the Central Sales Tax Act, 1956
  • Section 15 of the Rajasthan Sales Tax Act, 1994
  • Section 14(2) of the RST Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2004 INSC 559
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 15 of the RST Act read with Section 8(5) of the CST Act
  • a fiscal statute
  • Article 32
  • Article 14
  • sub-section (5) of Section 8 of the Central Sales Tax Act, 1956
  • Section 15 of the Rajasthan Sales Tax Act, 1994
  • Section 14(2) of the RST Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Smart Summary

Factual and Procedural Background

The State of Rajasthan framed the “Rajasthan Sales Tax/Central Sales Tax Exemption Scheme for Industries, 1998” pursuant to its Fourth New Industrial Policy. The Scheme granted graded exemptions from sales tax to various categories of industrial units, including sick units, and came into force on 1-4-1998 under Section 15 of the Rajasthan Sales Tax Act, 1994 and Section 8(5) of the Central Sales Tax Act, 1956.

Annexure ‘B’ of the Scheme set different exemption rates for: (1) general new units, (2) certain specified “very prestigious” industries, (3) all categories of cement plants, and (4) sick units. Respondent-companies J.K. Udyog and J.K. Synthetics Ltd., both sick cement manufacturers, applied for exemption, asserting that serial no. 4(a) entitled them to the higher, tapering benefits accorded to new units under serial no. 1.

While their applications were pending, the State issued a corrigendum dated 30-9-1999 (published 7-1-2000) clarifying that sick units would receive the same benefit as “new units at serial nos. 1, 2 and 3 as the case may be,” thereby limiting sick cement units to the flat 25% rate applicable to new cement plants under serial no. 3.

The Screening Committee thereafter applied the corrigendum. The respondents challenged the corrigendum, the Screening Committee’s decisions, and consequential provisional assessments before the Rajasthan High Court. A learned Single Judge, and on appeal a Division Bench, held that the corrigendum was an “amendment” operative only prospectively from 7-1-2000 and that accrued rights under the original Scheme were unaffected. The State of Rajasthan appealed to the Supreme Court.

Legal Issues Presented

  1. Whether the respondents had a vested or accrued right to the higher exemption available to new units under serial no. 1 from the date their applications were certified complete (clause 4(h)).
  2. Whether the corrigendum dated 30-9-1999 operated merely as a clarification/correction or as a prospective amendment capable of reducing existing benefits.
  3. Whether limiting sick cement units to the flat 25% rate violated Article 14 of the Constitution by discriminating against them vis-à-vis other sick units or new cement units.
  4. Whether the State was entitled to recover differential sales tax for the period after 7-1-2000 despite the High Court judgment and the respondents’ inability to pass the tax on to buyers.

Arguments of the Parties

Appellants’ Arguments (State of Rajasthan and Authorities)

  • The corrigendum was a true corrigendum, not an amendment; it merely made explicit the original intent to place sick units of a particular industry on the same footing as new units of that industry (i.e., sick cement units with new cement units under serial no. 3).
  • Even if treated as an amendment, the State had power under Section 15 of the RST Act, Section 8(5) of the CST Act, and clause 9 of the Scheme to modify or withdraw concessions in the public interest.
  • Exemptions are concessions and confer no indefeasible, vested rights absent promissory estoppel, which the respondents failed to establish.
  • The Scheme, properly read with the corrigendum, is non-discriminatory because it treats all cement units—new or sick—uniformly at 25%.

Respondents’ Arguments (J.K. Udyog & J.K. Synthetics Ltd.)

  • The Scheme as originally notified placed all sick units, irrespective of industry, under serial no. 4(a) and entitled them to the tapering benefits of serial no. 1; those rights crystallised upon certification of their applications under clause 4(h).
  • The corrigendum, issued under inseverable powers of both the RST Act and CST Act, could not retrospectively curtail exemptions because Section 8(5) CST Act contains no power of retrospective withdrawal.
  • Even if prospective, the corrigendum violated Article 14 by treating sick cement units worse than sick units of other industries and even worse than sick cement units that had earlier availed exemptions (serial no. 4(b)).
  • Equity demanded protection for taxes not collected from customers during the period the High Court judgment stood un-stayed.

Table of Precedents Cited

PrecedentRule or Principle Cited ForApplication by the Court
Shri Bakul Oil Industries v. State of Gujarat (1987) 1 SCC 31Exemptions are concessions; no vested right to their continuance.Relied on to hold respondents had no indefeasible right to unchanged exemption rates.
Kasinka Trading v. Union of India (1995) 1 SCC 274Same principle on concessional nature of exemptions.Cited to support power of Government to modify concessions.
Shrijee Sales Corpn. v. Union of India (1997) 3 SCC 398Concessionary exemptions can be withdrawn unless promissory estoppel applies.Used to refute claim of vested rights.
STO v. Shree Durga Oil Mills (1998) 1 SCC 572Promissory estoppel subject to equity and public interest.Invoked to show no estoppel barred the State’s action.
British Physical Lab India Ltd. v. State of Karnataka (1999) 1 SCC 170Equitable relief when assessee relied on State’s own invalid notification.Distinguished; court found no comparable equities here.
State of Rajasthan v. Mahaveer Oil Industries (1999) 4 SCC 357Benefits enjoyed pendente lite can be withdrawn if final decision goes against assessee.Cited to justify recovery of differential tax after reversal of High Court decision.
Shri Digvijay Cement Co. v. State of Rajasthan (1997) 5 SCC 406Earlier judgment invalidating concessional notifications.Referred to in discussion of subsequent overruling; not decisive for present case.
Shree Cement Ltd. v. State of Rajasthan (2000) 1 SCC 765Equitable relief following overruling of earlier decision.Differentiated; circumstances deemed absent here.
Union of India v. West Coast Paper Mills Ltd. (2004) 2 SCC 747Rights under a judgment remain precarious when appeal is pending.Used to deny respondents’ claim to retain benefits during pendency of State’s appeal.

Court's Reasoning and Analysis

1. Nature of Rights: The Court reaffirmed that a tax exemption is a revocable concession. Absent promissory estoppel, beneficiaries possess only a defeasible right that may be altered or withdrawn under the same statutory power conferring it.

2. Absence of Vested Interest: For J.K. Synthetics, no Screening Committee sanction had ever issued; hence no vested right could arise. Even assuming provisional entitlement from clause 4(h), clause 9 allowed modification “in public interest,” making any benefit inherently subject to change.

3. Interpretation of Scheme and Corrigendum: Reading the Industrial Policy and Annexure ‘B’ together, the Court held that “new unit” in the Policy referred to the corresponding category of that industry (serial nos. 1, 2 or 3). Cement plants were expressly segregated in serial no. 3; therefore sick cement units could not claim the tapering benefits of serial no. 1. The corrigendum merely clarified this pre-existing intent and removed ambiguity; it was neither irrational nor discriminatory.

4. Article 14 Challenge: Without the corrigendum, the Scheme would create an illogical preference for sick cement units that had never enjoyed exemption over those that had, and over new cement units. The corrigendum ensured parity within the cement sector and thus furthered, rather than violated, equality.

5. Retrospectivity and Recovery: The State expressly disclaimed retrospectivity prior to 7-1-2000. Benefits already enjoyed up to that date were preserved. However, post-7-1-2000 exemptions had to conform to the corrigendum, and the State could recover differential tax. Reliance on High Court decisions pending appeal did not confer an indefeasible shield, and equitable precedents cited by respondents were distinguishable.

Holding and Implications

APPEALS ALLOWED; HIGH COURT JUDGMENT SET ASIDE.

Consequences:

  • Respondent companies may retain exemptions actually enjoyed up to 7-1-2000.
  • From 7-1-2000 onward, they are entitled only to the flat 25% exemption applicable to cement units under serial no. 3 as clarified by the corrigendum.
  • The State may recover differential sales tax for the post-7-1-2000 period, but no interest or penalty shall be levied provided the principal is paid within the timeframe specified by the authorities.

The decision clarifies that industrial exemption schemes remain inherently mutable and that clarification notifications aligning a scheme with overarching policy objectives will be upheld, thereby limiting the scope for industries to claim higher benefits based on arguable ambiguities.

To access the original judgment, please Sign In or Subscribe.

    State Of Rajasthan And Another v. J.K Udaipur Udyog Ltd. And Another

    Ruma Pal, J.— A scheme was framed by the first appellant granting exemption to industrial units from payment of sales tax on intra-State and inter-State sale of goods and by-products manufactured within the State of Rajasthan. By a subsequent notification the extent of the percentage of exemption available to sick industries was sought to be corrected. The disputes in these appeals relate to the interpretation of the Scheme and the effect of the corrigendum.

    2. The Scheme was part of the Fourth New Industrial Policy of the State. The Policy stated that the object of the Scheme was to make Rajasthan “a most favoured destination for industries” and to encourage the setting up of industries in the State. The Policy describes the nature of the exemptions which were sought to be granted to the different kinds of industries with exemption/deferment incentives for 11 years in respect of some industries and 14 years for others. A greater incentive was granted to industries being set up in the five industrial growth centres in the State. The incentives available during the first year were to be gradually tapered off to a particular percentage of the fixed capital investment at different rates in respect of some industries. However, in respect of cement industries the percentage of exemption proposed was at a flat rate of 25% for 11 years. According to the Policy the Scheme would also give benefits for the first time to sick units. The sick units were classified into two categories as follows:

    “(1) Those units which have not availed of any benefits in the past will get full benefits on a par with a new unit.
    (2) Those units which have availed of sales tax benefits in the past will get ST benefit on a tapering basis up to 11 years (maximum 80% and minimum 10% exemption/deferment on a tapering basis).”

    3. Pursuant to this Policy the Rajasthan Sales Tax/Central Sales Tax Exemption Scheme for Industries, 1998 (referred to as “the Scheme”) was framed and notified in exercise of the powers conferred on the State Government by Section 15 of the Rajasthan Sales Tax Act, 1994 (referred to as “the RST Act”) and by sub-section (5) of Section 8 of the Central Sales Tax Act, 1956 (referred to as “the CST Act”), the Scheme came into force from 1-4-1998. Clause 1(b) of the Scheme envisages that

    “an industrial unit which commences commercial production during the operative period of this Scheme, shall be entitled to claim benefits under this Scheme”.

    Clause 3(a) provides that the Scheme shall be applicable to:

    (i) the new industrial units;
    (ii) the industrial units going for expansion;
    (iii) the industrial units launching diversification; and
    (iv) the sick industrial units.

    4. A “new industrial unit” has been defined in clause 2(k) as:

    “(i) ‘New industrial unit’ means an industrial unit which commences commercial production during the operative period of this Scheme including a unit set up on the site of an existing industrial unit by making separately identifiable capital investment; subject to, however, that where an industrial unit manufacturing the same product is established on the site of an existing unit, the benefit permissible for a new unit shall be available to it only on the production in excess of 80% of the installed capacity of the existing unit.
    (ii) ‘New industrial unit’ shall also include a sick unit:
    (a) which has not availed of any benefits of exemption from tax or deferment of tax;
    (b) which has been appraised by financial institution and appropriate rehabilitation plan has been formulated; and
    (c) which has been purchased by a new management other than by way of collusive transfer and such management has made additional fixed capital investment not less than 25% of the depreciated value of the assets of such unit.”

    5. The respondents in these appeals viz. M/s J.K Udyog and J.K Synthetics Ltd. were writ petitioners before the High Court of Rajasthan and are Companies which manufacture cement in different units within the State of Rajasthan. The respondent Companies in these appeals are undisputedly “sick”.

    6. The description of the type of units, extent of the percentage of exemption from tax liability, the maximum exemption permissible under the Scheme and the maximum time-limit for availing the exemption under the Scheme have been set out in Annexure ‘B’ to the Scheme.

    7. We set out below the material portion of Annexure B to the Exemption Scheme:

    Sl. No. Type of units Extent of the percentage of exemption from total tax liability Maximum exemption in terms of percentage of eligible fixed capital investment (FCI) Maximum availing limit for exemption from tax 1 2 3 4 5 1. New units other than the units mentioned at Sl. Nos. 2 and 3 and units going in for expansion or diversification. 1st year 2nd year 3rd year 4th year 5th year 6th year 7th year 8th year 9th year 10th year 11th year 100% 90% 80% 70% 60% 50% 50% 40% 40% 30% 30% 100% of eligible fixed capital investment in cases where such investment exceeds Rs 150.00 lakhs, and 125% of eligible FCI in cases where such investment does not exceed Rs 150.00 lakhs. Eleven years 2. (a) New units of knitwears, gems and jewellery, textile, electronics and telecommunications, computer software, footwear and leather goods and ceramics. (b) Very prestigious units. 1st year 2nd year 3rd year 4th year 5th year 6th year 7th year 8th year 9th year 10th year 11th year 12th year 13th year 100% 100% 90% 80% 70% 60% 50% 50% 40% 40% 30% 30% 30% 125% of eligible fixed capital investment Thirteen years 3. All categories of cement plants/units including pioneering to prestigious unit, very prestigious/premier units except mini-cement plants mentioned in Annexure A 25% of total liability 100% of eligible FCI Eleven years 4. Sick units: (a) Sick units which have not availed of benefits of exemption from tax or deferment of tax previously. Same benefits which are available to new units at Sl. No. Eleven years (b) Other sick units which have availed of the benefits of exemption from tax or deferment of tax. 1st year 2nd year 3rd year 4th year 5th year 6th year 7th year 8th year 9th year 10th year 11th year 80% 70% 60% 50% 40% 30% 20% 10% 10% 10% 10% 100% of eligible fixed capital investment in cases where such investment exceeds Rs 150.00 lakhs and 125% of FCI in cases where such investment does not exceed Rs 150.00 lakhs. Eleven years

    8. It is apparent from this annexure that for the purposes of deferring the rate of exemption the industries were classified into three categories under Sl. Nos. 1, 2 and 3 according to the kind of industry. Cement plants/units have been separately placed in Sl. No. 3.

    9. According to the respondent Companies, however, sick units were treated as a special category, and irrespective of the nature of the industry, were covered by Sl. No. 4. It is the respondent's case that as far as their cement units were concerned they were not covered by Sl. No. 3 but by Sl. No. 4(a) and thus, according to them, they were entitled to the higher benefits accorded to new units under Sl. No. 1. According to them the words under column 3 against Sl. No. 4 made this clear.

    10. According to the appellants on the other hand, this was never the intention of the State Government which had wanted to treat sick industrial units of a particular kind on par with new industrial units of that kind in the matter of grant of exemption. But we are anticipating the dispute which is considered in detail subsequently. Returning to the Scheme: the procedure for obtaining exemption under the Scheme has been provided in clause 4, the relevant extract of which reads as under:

    “Sanction of benefits under the Exemption Scheme and issue of eligibility certificate.—(a) In order to avail the benefit under this Scheme, the applicant industrial unit shall have to obtain sanction from the State-level Screening Committee or district-level Screening Committee, as the case may be. The Screening Committees shall act as quasi-judicial authorities whose decisions shall be final subject to other provisions provided for in this Scheme.
    (b)-(d)***
    (e) The appropriate Screening Committee shall, after having examined the application of an industrial unit and after having gathered or collected such other information, documents or evidence as may be considered necessary and after having got conducted such further enquiry as deemed proper in the circumstances of the case, sanction the benefits under this Scheme to the said unit if it is found fully covered by the provisions of this Scheme and is not in any way debarred or disqualified to claim the said benefits. However, in particular, the said Screening Committee shall reject the application of the applicant unit—
    (i) where its case does not fall within the parameters of this Scheme; or
    (ii) where it has failed in spite of adequate opportunity being given, to supply any information asked for or adduce any evidence required for; or
    (iii) where any case of avoidance or evasion of tax is pending against it at any forum or it is found penalised for such offence, within a period of two years immediately preceding the date of the filing of the application; however, the said Screening Committee may waive this disqualification in an appropriate case if the offence is technical or venial in nature or has been compounded.
    (f) In case of sanction of benefits under the Scheme, such sanction shall be communicated in writing to the assessing authority of the applicant unit, who shall issue eligibility certificate to the said unit in Form C, appended to this notification, within a period of seven days from the date of the receipt of the sanction, and a copy of such certificate shall also be sent to the Member Secretary of the Screening Committee concerned.
    (g) The eligibility certificate issued under this Scheme shall remain in force till the permissible exemption from tax in accordance with the provisions of this Scheme is not exhausted, or till such certificate is not amended, suspended or revoked.
    (h) The benefits under this Scheme shall be available from the date of the application filed by the applicant unit completed in all respects, as certified by the Member Secretary of the appropriate Screening Committee.
    (i) During the currency of the eligibility certificate, the unit concerned shall be exempted from payment of tax on the intra-State sales/inter-State sales of the goods and by-products manufactured by it within the State including the waste items derived therefrom and the packing material used therewith.”

    11. The order in which the steps envisaged for grant of benefits under this clause of the Scheme was therefore:

    (1) making of an application by the industrial unit;
    (2) the certification of the application as complete and the provisional availability of the benefits [clause 4(h)];
    (3) the examination of the application by the Screening Committee after collecting information/enquiry, etc. [clause 4(e)];
    (4) the sanction or rejection of the application by the Screening Committee [clause 4(e)];
    (5) in case of sanction, the communication of the sanction to the assessing authority [clause 4(f)];
    (6) the issuance of eligibility certificate by the assessing authority within seven days [clause 4(f)];
    (7) the availability of exemption from payment of tax during the currency of the eligibility certificate until the exemption was either exhausted or unless the certificates were amended, suspended or revoked [clause 4(i)].

    12. The respondent Companies applied for exemption under the Scheme claiming benefits on a par with units under Sl. No. 1. As far as M/s J.K Synthetics Limited is concerned, the Director of Industries certified that the application was complete. The certificate issued under Section 4(h) on 20-2-1999 made it clear:

    “This certificate will not be treated as sanction of incentive under the Sales Tax Exemption Scheme, 1998. Incentive if any availed under clause 4(h) of the aforesaid Scheme will be entirely at the risk of the unit, subject to decision of the State-level Screening Committee. A suitable undertaking shall be taken by the assessing authority concerned in this regard from the unit.”

    13. In terms of the requirement, M/s J.K Synthetics Limited gave an undertaking in writing to the effect that the incentives availed by the Company from the date of completion of the application till the grant of sanction of eligibility certificate would be entirely at the risk of the Company and in case the Company's application was rejected for any reason, the Company shall pay the tax which was being availed of on the basis of the certificate of completion.

    14. While the application of M/s J.K Synthetics was pending for consideration by the Screening Committee, the corrigendum was issued on 30-9-1999, by the Finance Department inter alia, amending the third column against Sl. No. 4 of Annexure B by replacing the phrase “new units at Sl. No. 1” with “new units at Sl. Nos. 1, 2 and 3 as the case may be”. Thus sick cement units under Sl. No. 4(a) were expressly put on a par with new cement units under Sl. No. 3.

    15. M/s J.K Synthetics Limited submitted a representation to the Screening Committee that the corrigendum should not affect the Company. The Screening Committee deferred its decision on the ground that as the particular unit of M/s J.K Synthetics Limited in respect of which the exemption was claimed was not sick, although the Company itself had been declared sick, it should await the rehabilitation programme duly approved by BIFR providing the benefit of Sales Tax Incentives Scheme to all such units. While deferring the case till the approval of the rehabilitation programme by BIFR, the Screening Committee said that the unit could avail of the benefit under the Scheme to the extent permissible under the corrigendum. Neither any sanction under clause 4(e) and consequently no eligibility certificate under clause 4(f) have been issued to M/s J.K Synthetics Limited under the Scheme till today.

    16. As far as M/s Udaipur Udyog Limited is concerned, its application under the Scheme was certified as complete under clause 4(h) on 26-7-1999 and was sanctioned on 30-12-1999. However, the quantum of benefit was granted in terms of the corrigendum from the date of issuance of the corrigendum. The eligibility certificate was issued to M/s J.K Udyog on 29-2-2000 also restricting the benefits under the Scheme on the basis of the corrigendum.

    17. Since the respondents had been availing of the higher rates of exemption against Sl. No. 1, consequent upon the decision of the Screening Committee granting the benefits under the corrigendum, provisional assessment orders and notices were issued to both the respondent Companies by the Sales Tax Authorities over the differential sales tax.

    18. M/s J.K Synthetics Limited and J.K Udyog Limited filed separate writ petitions before the High Court of Rajasthan challenging the corrigendum dated 30-9-1999; in the alternative a prayer was made to hold that the corrigendum had no application to the respondent Companies; for quashing the decisions of the Screening Committee insofar as the respondent Companies were given the benefit of the Exemption Scheme on the basis of the corrigendum and for quashing the provisional assessment orders and notices.

    19. The submission of the respondent Companies before the High Court inter alia was that the Scheme as originally framed allowed the Companies to avail of the benefit of the Exemption Scheme under Sl. No. 4(a) read with Sl. No. 1 for a period of 11 years up to a maximum limit of hundred per cent of the Companies' eligible fixed capital investment at percentages of the total tax liability ranging from 100% in the first year to 30% in the 11th year. These rights of the Companies under the Scheme were claimed to be crystallised with effect from the date of the certification of their applications under clause 4(h), which could not be taken away by the corrigendum with retrospective effect.

    20. The learned Single Judge accepted the submission of the respondent Companies that the impugned corrigendum really amounted to an amendment of the Scheme. But it was held that the State Government was competent to modify the Scheme and, therefore, the respondent Companies were entitled to relief in terms of the Scheme as originally notified up to the date of amendment and subsequent thereto as provided in the corrigendum. Since the corrigendum had been published in the Official Gazette on 7-1-2000 it was held that it would be applicable with effect from that date.

    21. Several appeals were preferred both by the State of Rajasthan as well as by the respondent Companies from the decision of the learned Single Judge. The Division Bench disposed of all the appeals by the judgment impugned before us. The appellate court agreed with the learned Single Judge that the corrigendum notification was in fact an amendment of the Scheme and therefore, this would operate only prospectively i.e from 7-1-2000. The plea of the respondent Companies that the State Government was bound by the principles of promissory estoppel from modifying or amending the Scheme was negated by the Division Bench. The respondent Companies have not sought to challenge this conclusion before us. The Division Bench however held that the rights of the respondent Companies of enjoying the benefit under the original Scheme including the maximum amount of exemption, the maximum period of exemption, and the percentage of exemption were available to the respondent Companies with effect from the date of certification of their applications under clause 4(h) and were substantive and that these rights could not be affected adversely unless the subsequent notification clearly manifested an intention to do so. It was held that the corrigendum did not contain any such explicit provision nor could any inference be drawn that accrued rights were to be affected. It was held that even if this proposition was unacceptable, the amendment was arbitrary and violative of Article 14 being discriminatory vis-à-vis other sick industries. It was further held that the amendment could not discriminate against sick cement plants which had not availed of benefits of tax exemption earlier, so that such sick industries were treated in a manner worse than sick cement industries which had availed of exemptions from sales tax earlier. The Division Bench accordingly held that the respondent Companies were entitled to avail of the benefits under the Scheme as originally notified in the manner provided in column 3 of Serial No. 1 of Annexure B read with Serial No. 4(a) and that such rights were not affected by the corrigendum published on 7-1-2000. However, the corrigendum notification itself was not quashed as had been prayed for.

    22. The appellants have impugned the decision of the Division Bench and have contended that the Division Bench had erred in fact and in law in coming to the conclusion that the respondent Companies had a vested right to the benefits of the Scheme as available to new units under Sl. No. 1 of Annexure ‘B’ to the Scheme. It is pointed out that as far as J.K Synthetics is concerned, its application has not been sanctioned at all. It is contended that the corrigendum notification was in fact a corrigendum and not an amendment, and that the corrigendum merely made explicit the intention of the State Government to treat the sick units of a particular industry on a par with new units of such industries. It is further contended that even if the corrigendum were construed as an amendment, the State Government had the power to withdraw or modify the benefit of the Scheme not only under Section 15 of the RST Act read with Section 8(5) of the CST Act but also under clause 9 of the Scheme which provides for the power to the State Government to review or modify the Exemption Scheme “as and when needed in public interest”. It is submitted that an exemption is in the nature of a concession and was by that reason a defeasible right. It is submitted that exemptions granted could not create any vested right in the beneficiaries of the exemption to the continued grant of the exemption until and unless the beneficiary was able to establish that the State Government was bound by the principles of promissory estoppel from modifying or withdrawing the concession. It is submitted that since the respondent Companies had failed to establish any promissory estoppel on the part of the State Government, the Government could withdraw or modify the concession given at least from the date of the publication of the corrigendum notification. As far as the High Court's findings on the issue of discrimination is concerned, it is submitted that in fact there were no other cement units in the State in comparison with which it could be said that the respondent Companies were being unfairly treated. The language of Sl. No. 3 in Annexure B was also relied upon to contend that the corrigendum was not discriminatory and merely treated sick cement units and new cement units equally.

    23. Counsel for the respondent Companies has submitted that there was no power in the State Government to issue the corrigendum with retrospective effect. It is submitted that the Scheme was issued not only under Section 15 of the RST Act but also under Section 8(5) of the CST Act. The exercise of the power was thus, to use counsel's language, “inseverable”. It is argued that as there is no power under Section 8(5) of the CST Act to withdraw an exemption with retrospective effect the entire exercise of issuing the corrigendum must fail. In addition, it is submitted that even Section 15 of the Act did not allow the State Government to withdraw an exemption with retrospective effect. It is stated that under clause 4(h) read with clause 5(g), on the date on which the respondent Companies' application was certified as being complete, rights accrued to the industrial units which could not be withdrawn and it was not necessary to rely upon the principle of promissory estoppel for the purpose of claiming continued exemption. It is submitted that the subsequent notification was not a corrigendum but an amendment of the Scheme and could not be construed as amounting to withdrawal of the rights conferred under the Scheme as originally published. It is submitted that sick units have been treated as a class apart irrespective of the nature of industry. It is also submitted that the corrigendum if construed in the manner advocated by the appellants, would be violative of Article 14. Finally, it is submitted that in any event this Court should protect the respondent Companies insofar as they had availed of the benefits of the Scheme as originally published at least from the date of the order of the High Court. It is submitted that the High Court had struck down the corrigendum notification. Therefore, Annexure B as originally notified would revive. The decision of the High Court not having been stayed by this Court, the respondent Companies had not and indeed could not recover the sales tax from their customers by virtue of Section 14(2) of the RST Act and it would in these circumstances be inequitable to saddle them with sales tax liability for the period subsequent to the decision of the High Court. Reliance has been placed on the decision of this Court in State of Rajasthan v. Mahaveer Oil Industries (1999) 4 SCC 357 in support of the submission.

    24. The issue whether the subsequent notification should be read as a correction or an amendment of the Scheme as originally notified would be relevant only if the appellants sought to give retrospective effect to it. Since the appellants have stated before us that they do not intend to take away the benefits which may have actually been enjoyed by the respondent Companies prior to the date of publication of the corrigendum viz. 7-1-2000, a determination of the issue would be an academic exercise and a consideration of the several decisions cited with regard to the principles for deciding whether a statutory provision has retrospective effect, is unnecessary. The question is whether the subsequent notification could operate as far as the respondent Companies are concerned with effect from 7-1-2000. The answer to this question would depend upon the nature of the rights of the respondent Companies under the Scheme.

    25. An exemption is by definition a freedom from an obligation which the exemptee is otherwise liable to discharge. It is a privilege granting an advantage not available to others. An exemption granted under a statutory provision in a fiscal statute has been held to be a concession granted by the State Government so that the beneficiaries of such concession are not required to pay the tax or duty they are otherwise liable to pay under such statute. The recipient of a concession has no legally enforceable right against the Government to grant of a concession except to enjoy the benefits of the concession during the period of its grant. This right to enjoy is a defeasible one in the sense that it may be taken away in exercise of the very power under which the exemption was granted. (See Shri Bakul Oil Industries v. State of Gujarat (1987) 1 SCC 31, Kasinka Trading v. Union of India (1995) 1 SCC 274 and Shrijee Sales Corpn. v. Union of India (1997) 3 SCC 398.)

    26. In this case the Scheme being notified under the power in the State Government to grant exemptions both under Section 15 of the RST Act and Section 8(5) of the CST Act in the public interest, the State Government was competent to modify or revoke the grant for the same reason. Thus what is granted can be withdrawn unless the Government is precluded from doing so on the ground of promissory estoppel, which principle is itself subject to considerations of equity and public interest. (See STO v. Shree Durga Oil Mills (1998) 1 SCC 572.) The vesting of a defeasible right is therefore, a contradiction in terms. There being no indefeasible right to the continued grant of an exemption (absent the exception of promissory estoppel), the question of the respondent Companies having an indefeasible right to any facet of such exemption such as the rate, period, etc. does not arise.

    27. In any event, the High Court erred in fact in holding that M/s J.K Synthetics had a vested right to the benefits of the Scheme. Clause 4 of the Scheme clearly provides that the benefits under the Scheme were subject to the sanction of the Screening Committee. No sanction has been issued to M/s J.K Synthetics till date.

    28. Apart from this, the exemption being a creature of the Scheme is subject to the Scheme. Clause 9 of the Scheme makes it clear that the right under the Scheme was temporary in the sense that the Scheme could be modified or reviewed. It is true that clause 9 also provides that such review or modification could take place only in the public interest. But nevertheless the right conferred was a modifiable or revocable one. If any right under the Scheme is held to be unmodifiable it would be contrary to the Scheme itself. Therefore, even if one were to assume that the respondent Companies were entitled to the benefits of the Scheme on a par with new units under Sl. No. 1 with effect from the date of the certification of their application under clause 4(h), the right could be modified with effect from the date on which the Scheme was modified. The further argument of the respondent that the subsequent notification could not be construed as a modification and would apply only to subsequent applicants is unacceptable. There is no ambiguity in the language of the subsequent notification. On the contrary the use of the word corrigendum itself indicates that the intention was to correct and to rectify what the State Government thought had been erroneously done.

    29. Coming now to the question of public interest. The Fourth New Industrial Policy pursuant to which the Scheme had been framed by the State Government was indisputably in the public interest. Therefore, if the intention of the State Government was to effectuate the Policy by issuing the subsequent notification it cannot be said that the State Government was not acting in the public interest. The Industrial Policy which resulted in the Exemption Scheme expressly provided that the rate of benefits which were to be given to sick industrial units which had not availed of any such benefits in the past would be on a par with a new unit. But does this mean that the words “new unit” in the Policy referred to industries under Sl. No. 1? We think not. New units of different kinds of industries had been separately classified both under the Policy and under Sl. Nos. 1, 2 and 3 of Annexure B to the Scheme. Each of the three categories at Sl. Nos. 1, 2 and 3 have been granted different rates of exemption. Serial No. 1 relates to new industries not covered by Sl. Nos. 2 and 3. It is therefore, the residuary category and any new industry covered by Sl. Nos. 2 and 3 would not be covered by Sl. No. 1. Serial No. 2 speaks of particular industries such as knitwears, gems and jewellery, textile, electronics, telecommunications, computer software, footwear and leather goods and ceramics. This category of industries has been subclassified under the heads of (a) “new units”, and (b) “very prestigious units”. A very prestigious unit is not defined in the Scheme itself but is referred to in the Industrial Policy as those industries which have a fixed capital investment of Rs 50 crores or more and regular employment of 250 persons. Sl. No. 3 makes no such distinction and refers to “all categories” of cement plants except mini-cement plants mentioned in Annexure ‘A’ to the Scheme. Subject to the exception of Annexure A all categories of cement plants/units including new units have been allowed exemption of 25% of the total tax liability for 11 years. There is no tapering of the incentive for the 11 years that the benefit was to be available as is the case under the other serial numbers. “All categories” would necessarily include new cement plants and sick industrial units falling within the definition of clause 2(k)(ii), which were also entitled to the same level of benefit as all other new cement units. It would be incongruous to grant sick industrial units which do not fall within clause 2(k)(ii) higher benefits than sick industrial units which do. Since a sick industrial unit is granted a particular benefit subject to the fulfilment of various conditions, it implies that the industry which fulfils the conditions would be better off than the one which does not. If we were to accept the respondents' interpretation of the original notification under Sl. Nos. 4(a) and (b), higher benefits would be available to sick industrial units which did not comply with the conditions imposed under clause 2(k)(ii). Such a conclusion is not only illogical but would serve to make a distinction between sick industrial units on an irrational basis. Clause 2(k)(ii) therefore indicates that the highest benefit that a sick industrial unit can claim under the Scheme, is to be treated on a par with new industries.

    30. The thrust of the Industrial Policy was to give an incentive to new entrepreneurs. It is true that there are separate provisions for “sick industries”, but given the main object of the Policy, to make Rajasthan a “most favoured destination for industries”, it could not have been the intention of the State Government to give a lower benefit to new industries and to give higher benefits to sick industrial units already established in the State. However, when the Scheme was first notified, although the body of the Scheme effectuated the objective, the entry under column 3 against Sl. No. 4 in Annexure B did not clearly reflect this. Doubtless the interpretation put by the respondent Companies and accepted by the High Court on the entries against Sl. No. 4, as it originally stood in Annexure B, is a possible interpretation, but in our opinion Annexure B was equally susceptible of the interpretation put forward by the appellants before us, particularly in the context of the Industrial Policy.

    31. It was to clarify this ambiguity that the subsequent notification was issued by the State Government to correct or amend Annexure B to the extent that it could be interpreted in a manner not in keeping with the published Industrial Policy of the State and the substantive provisions of the Scheme.

    32. For these reasons also the corrigendum cannot be said to be violative of Article 14. On the contrary, if the corrigendum were not to be given effect to, the entire Scheme would operate irrationally by making an invidious distinction between sick cement units as we have already said. The irrationality is also apparent vis-à-vis industries referable to Sl. No. 2. Under the Scheme, the highest rate of exemption and greatest benefits are granted to new units under Sl. No. 2. If the respondents' interpretation of the corrigendum is accepted, a sick industry of a particular kind which otherwise falls under Sl. No. 2 would, by virtue of the entry against Sl. No. 4, be entitled to much lesser than new units of the same kind of industry as it would be treated on a par with new units of different kinds of industries under Sl. No. 1. This is perhaps the reason why the corrigendum was not challenged by those industries covered by Sl. No. 2 which are sick and which are not new industrial units within the meaning of clause 2(k)(ii) of the Scheme. Although it appears to us that Sl. No. 3 would include all categories of cement industries, the question whether Sl. No. 4(b) would relate to sick cement industries not covered by clause 2(k)(ii) or Sl. No. 4(a) is not an issue which requires to be finally decided in this case, particularly when there is no such industry before us which claims the benefit of clause 4(b).

    33. Learned counsel for the respondents' additional contention is that the Screening Committee had proceeded on the basis that the sick cement units were covered under Sl. No. 4 and not Sl. No. 3. It is argued that such decision of the Screening Committee being final in terms of clause 4(a) of the Scheme, it was not open to the State to contend otherwise. The argument is without force. The finality given to the decision of the Screening Committee in terms of clause 4(a) is “subject to other provisions provided for in the Scheme”. Any decision of the Screening Committee cannot be contrary to the provisions of the Scheme. Besides, all that the Screening Committee has held is that the respondent Companies are to be treated on a par with other cement companies, with effect from the date of the subsequent notification. That is also what the appellants contend, namely, that Sl. No. 4(a) expressly puts sick cement units on a par with new cement units under Sl. No. 3.

    34. The respondent Companies are therefore required to avail of the benefits under the Scheme on the basis of the corrigendum with effect from 7-1-2000. Learned counsel for the respondent Companies may be right in his contention that if a sanction is granted and an eligibility certificate issued on the basis of the sanction, then having regard to the provisions of clause 4(h) the period of exemption under the sanction ought to cover the date of the certification of the application as complete under clause 4(h). But it is again unnecessary to decide the ambit of the Screening Committee's power, as the appellants have not argued that the benefits of the higher rate of exemption already availed of by the respondent Companies with effect from the date of certification under clause 4(h) up to 7-1-2000 should be taken away from them.

    35. This brings us to the last argument of the respondent Companies viz. that they should not be made liable for the sales tax on the basis of the corrigendum for the period they had availed of the exemptions after the decision of the High Court. The submission proceeded on the basis that the High Court had quashed the corrigendum notification. As we have noted earlier the Division Bench had not quashed the corrigendum notification but had contented itself with construing it. The mere fact that this Court has not granted a stay of operation of the decision of the High Court would not give the respondent Companies any right to the fruits of that decision if the decision is ultimately reversed by this Court. Besides, the respondent Companies should have been aware that with the admission of the appeal from the High Court's order their rights thereunder were precarious. (See Union of India v. West Coast Paper Mills Ltd. (2004) 2 SCC 747, SCC at p. 753.)

    36. The mere circumstance that the respondent Companies having availed of the Exemption Scheme were prohibited from collecting the tax from their customers or that they had not collected the sales tax from their customers (which assertion is strongly disputed by the appellants), is of no consequence. The primary liability to pay the sales tax is on the seller. The seller may or may not be entitled to recover the same from the purchaser. The State Government is entitled to recover the same from the respondent Companies irrespective of the fact that the respondent Companies may have lost the chance of passing on their liability to pay sales tax to their purchasers.

    37. It is true that this Court has on some occasions granted relief from payment of sales tax to an assessee despite having found against the assessee on equitable considerations. But on every occasion there was something more than the mere impossibility of the assessee passing on the tax to its purchasers. Thus in the case of British Physical Lab India Ltd. v. State of Karnataka (1999) 1 SCC 170 the State Government had itself issued a notification reducing the rate of tax. The notification was struck down by the Court. The State Government then sought to recover the difference between the reduced rate as had been notified by it and the rate generally applicable. This Court granted relief to the assessee since the State Government had itself issued the notification concerned.

    38. Similarly in Shree Cement Ltd. v. State of Rajasthan (2000) 1 SCC 765 relief was granted having regard to the peculiar history of the case. By three notifications covering 1990 to 1994 issued by the State of Rajasthan the rate of tax payable by local dealers in respect of inter-State sales had been reduced. The notifications were challenged by cement manufacturers from outside the State. The High Court rejected the challenge. When the non-local cement manufacturers came to this Court, this Court held that the notifications were void and quashed them. (Shri Digvijay Cement Co. v. State of Rajasthan (1997) 5 SCC 406.) A fourth notification was subsequently issued by the State of Rajasthan similar to the earlier three notifications which had been quashed. The fourth notification was challenged directly before this Court by means of a writ petition under Article 32. This time the Bench which entertained the writ petition disagreed with the view expressed earlier by this Court in respect of Shri Digvijay Cement (1997) 5 SCC 406 and referred the matter to a larger Bench. The Constitution Bench overruled the decision in Shree Digvijay Cement (2000) 1 SCC 688. The question then was whether the local manufacturers would be entitled to the benefit of the decision of the Constitution Bench despite the fact that the notifications under which they had availed of a lower rate of tax had been decided against them in Shri Digvijay Cement (1997) 5 SCC 406. This Court held in favour of the local manufacturers. The circumstance that the notifications were subsequently held to be valid by a larger Bench operated to protect them from liabilities which had arisen by virtue of the earlier erroneous decision.

    39. In State of Rajasthan v. Mahaveer Oil Industries (1999) 4 SCC 357 this Court allowed the assessee to retain benefits under a scheme up to 4-4-1994 despite the fact that the assessees were held not entitled to such benefits, on the ground that in another proceeding this Court had allowed similar industries to retain the benefit up to 4-4-1994. What is of significance is that the assessees were denied further benefit even though they had been successful before the Single Judge, before the Division Bench of the High Court and no stay had been obtained from this Court at any stage. It was said:

    “The respondents have been aware throughout that the judgment of the Single Judge was appealed against. Even after the Division Bench dismissed the appeal the matter was carried further by filing the present special leave petition/appeal before this Court. The respondents continued to enjoy the benefits of the said two Schemes since no stay was obtained. Nevertheless, the question whether the respondents are entitled to the said benefits, has been sub judice throughout. Since the appeal is now being decided against the respondents, they cannot claim the benefit of an eligibility certificate which was granted entirely on account of a judgment of a Single Judge in their favour which is now being set aside.”

    40. As far as M/s J.K Synthetics is concerned, their right to obtain benefits under the Scheme by reason of clause 4(b) was in any event provisional. The undertaking given by this Company was to the effect that the benefits of the Scheme were being availed at the risk of the Company till the sanction was granted by the Screening Committee. Since no sanction has been granted to the Company, the Company was aware that its rights to the benefits under the Scheme were conditional and that it might be called upon to meet its sales tax liabilities in the event sanction was not granted on its application.

    41. In such circumstances, it must be open to the State Government to recover sales tax dues, as it is entitled to under the RST Act, allowing the respondent Companies to only keep such benefits as had been already availed of by them up to 7-1-2000 and thereafter at the rates specified and according to the provisions of the Scheme as modified by the corrigendum notification. However, no interest or penalty will be charged from the respondent Companies by the appellants on the differential amounts for the period the matter was sub judice before this Court provided the respondent Companies pay the principal amount of sales tax within such time as may be specified by the appellants in this regard.

    42. We, therefore, allow the appeals and set aside the impugned decision without any order as to costs.