Factual and Procedural Background

The petitioner sought quashing of the decision of the first respondent to pre-qualify the second respondent (a joint venture consisting of Progressive Construction Limited and the Intertech–Lenhydro Consortium, Russia) for the civil works of the Koteshwar Dam, Spillway and Powerhouse under Tender Specification No. THDC/RKSH/CD/197.PQ/99. Clause 10.2 of the pre-qualification document required (i) a minimum annual turnover of ₹50 crores in any one of the last five years and (ii) the successful completion of at least one concrete dam/barrage involving placement of 2.5 lakh m³ of concrete.

The first respondent’s Standing Committee, after examining financial data and certificates concerning experience on the Bureya Hydroelectric Project in Russia, recommended the joint venture for pre-qualification. Seven parties, including this joint venture, were accordingly pre-qualified in June 2001. The petitioner challenged that decision in a writ petition before the Delhi High Court, which dismissed the petition, holding the second respondent “fully qualified and eligible to carry out the contract.”

The petitioner then approached the Supreme Court under Article 136. Because caveats had been entered, the Court heard the matter on merit at the preliminary hearing stage and delivered the present order.

Legal Issues Presented

  1. Whether the second respondent satisfied the technical and financial criteria in clause 10.2 of the pre-qualification document for the Koteshwar Hydroelectric Project.
  2. Whether the High Court was justified in refusing to interfere with the first respondent’s decision to pre-qualify the second respondent.

Arguments of the Parties

Petitioner's Arguments

  • Lenhydro Project, a constituent of the joint venture, is only a design firm and not involved in actual construction; Intertech Services likewise lacks construction experience.
  • The affidavit claiming 3.5 million m³ of concrete placement at the Bureya Hydroelectric Project is inaccurate because the project was allegedly executed by JSC Boguchangesstroy as turnkey contractor.
  • Letters from SHC Institute Hydro Projects and the Chamber of Commerce and Industry of the Russian Federation describe Lenhydro merely as a design engineering company with no construction role, casting doubt on its experience.
  • The certificate dated 22-11-1999 from Bureya Hydro Power Project is ambiguous and lacks details of actual construction work performed by Lenhydro.

Respondents' Arguments

  • The joint venture submitted an MOU detailing obligations, experience, and financial status of all partners, showing Progressive Construction Ltd. as lead partner and Lenhydro as the entity meeting concrete placement requirements.
  • Affidavits and certificates—including one dated 31-7-1999 from Lenhydro’s Chief Engineer and a subsequent certificate from the Russian Ministry of Fuel and Power Engineering—confirm successful completion of a 140 m high concrete dam at Bureya involving 3.5 million m³ of concrete and monthly placement exceeding 20,000 m³.
  • Additional certificates (11-6-2002 and 1-8-2002) clarify that during 1993-97 Lenhydro was entrusted with construction, technical support, and quality control for the multistage Bureya project; the later involvement of Boguchangesstroy from 1998 did not negate Lenhydro’s earlier construction role.
  • On the basis of these documents, the Standing Committee correctly concluded that the joint venture met all pre-qualification requirements.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Supreme Court examined the documentary evidence relied upon by both sides. It found that:

  • The letters cited by the petitioner (from SHC Institute Hydro Projects and the Chamber of Commerce and Industry) made only general statements about Lenhydro’s design capabilities and did not directly address whether Lenhydro had executed the Bureya construction work.
  • The internet reference list produced by the petitioner covered only the period from 1997 onward and therefore did not contradict the respondents’ evidence relating to 1993-97.
  • Certificates produced by the respondents—dated 22-11-1999, 11-6-2002 and 1-8-2002—support the assertion that Lenhydro participated in actual construction, technical support, and quality control of the Bureya Hydroelectric Project, including the requisite volume of concrete placement.
  • Given this material, the first respondent’s decision to pre-qualify the joint venture was neither arbitrary nor unreasonable. Consequently, the High Court rightly declined to interfere under Article 226.

The Court concluded that no ground existed to disturb the High Court’s dismissal of the writ petition.

Holding and Implications

DISMISSED – The Supreme Court found no merit in the special leave petition and affirmed the High Court’s decision.

Implications: The second respondent’s pre-qualification for the Koteshwar Hydroelectric Project stands confirmed, allowing the tender process to proceed. The order is confined to the facts of this tender evaluation and sets no new precedent.

To access the original judgment, please Sign In or Subscribe.

    Continental Construction Ltd. v. Tehri Hydro Development Corporation Ltd. And Another

    S. Rajendra Babu, J.— This petition is directed against an order made by the High Court of Delhi in a writ petition wherein the petitioner prayed for quashing the decision of the first respondent that the second respondent has the pre-qualification for the construction of Koteshwar Dam Spillway and Powerhouse Civil Work of Koteshwar Hydroelectric Project pursuant to Tender Specification No. THDC/RKSH/CD/197.PQ/99. The pre-qualification document under clause 10.2 provided as follows:

    “10.2 The minimum pre-qualification criteria for the work of construction of ‘Koteshwar Dam, Spillway and Powerhouse Works’ would be as under:
    (i) The bidder should have minimum annual turnover of Rs 50 crores in any one of the last five years.
    (ii) The bidder should have successfully completed the construction of at least one concrete dam/barrage involving placement of minimum 2.5 lakh cubic metres of all grades of concrete against a single contract in a hydroelectric/irrigation project.” (only relevant part extracted)

    The challenge to the pre-qualification of the second respondent was met by the first respondent on the following basis:

    “1. Amongst the 7 parties, recommended to be pre-qualified for the subject work, one of the parties recommended was M/s Progressive Construction Limited, in joint venture with the Consortium of Intertech: Lenhydro, Russia (named as Respondent 2 in the writ petition). In the pre-qualification bid, documents submitted by M/s Progressive Construction Limited in joint venture with the Consortium of Intertech Lenhydro, Russia the party had, inter alia, provided memorandum of understanding (MOU), purporting to be an agreement between M/s Progressive Construction Limited, with its Head Office at Hyderabad (India) and the Consortium of Intertech Service (Head Office at Saint Petersburg, Russia) and Institute Lenhydro Project (Head Office at Saint Petersburg, Russia), formed to submit the pre-qualification bids to THDC in response to the subject tender. The MOU had described Intertech Lenhydro Consortium having experience, skill and specialized experience in construction of dams, underground tunnels, ports etc. Further, the said MOU had laid down the detailed obligations, responsibilities and working arrangements for submission of bids and undertaking the subject works in the event, the contract was awarded to the joint venture. Along with the documents, the joint venture had also provided details concerning experience and financial status of all the respective joint venture partners.
    2. As per information provided by the joint venture of Progressive Construction Limited and Consortium of Intertech Services: Institute Lenhydro Project, it was disclosed that M/s Progressive Construction Limited would be the joint venture lead partner. It was further indicated in the submitted documents that Institute Lenhydro Project, one of the joint venture partners, had successfully completed Bureya Hydroelectric Project on Bureya river, far-east of Russia, which was a 140 m high concrete dam. It was further stated that this massive gravity dam contains 3.5 million cu m concrete about 30% of which being dry RCC which is placed into downstream part of the dam. This experience detail was supported by an affidavit dated 31-7-1999, signed for and on behalf of Institute Lenhydro Project, by their Chief Engineer and authorised signatory declaring that Institute Lenhydro Project had executed Bureya Hydroelectric Project, as per details given in the foregoing. It was also indicated in the affidavit that the work was done for the Government of Russia.
    3. The answering respondent vide Letter No. THDC/RKSH/CD-197/2607 dated 18-11-1999 intimated to Progressive Construction Limited who were disclosed to be the leader of the joint venture, that the claim of meeting the PQ requirements of having completed construction of dam involving 2.5 lakh cu m concrete based on the credential of their joint venture partner, Lenhydro Project, had been laid on the self-certification made by Lenhydro Project to the effect that they have placed 3.5 million cu m concrete in Bureya HEP. Similarly, the claim of having achieved more than 20,000 cu m concrete placement in a single month was also laid on self-certification through an affidavit furnished by Institute Lenhydro Project. They were required vide this communication dated 18-11-1999 to arrange to furnish a certificate in support of meeting the above PQ requirements.
    4. In response to this, Progressive Construction Ltd. vide their letter dated 24-11-1999 addressed to Senior Manager (Contracts) furnished the certificate issued by Bureya HPP, an open joint stock company “UES of Russia” under Ministry of Fuel and Power Engineering of Russia. While forwarding the said certificate by Bureya HEP, it was intimated by Progressive Construction Ltd. that the certificate was in support of the successful completion of the Project as well as also the total quantities of concrete/peak month quantity of concrete executed by their joint venture partners M/s Lenhydro Project. The original letter of confirmation issued by the joint stock company Bureya HPP under Ministry of Fuel and Power Engineering of Russia was later forwarded by Progressive Construction Ltd. vide Letter No. PCL/ND/Koteshwar/2206 dated 29-11-1999 by their letter also it was intimated that the said letter of confirmation certifies total works of concreting having been done by their joint venture partners M/s Lenhydro Project for Bureya HPP in Russia.
    5. The Standing Committee on pre-qualification, on detailed examination of bids submitted by various parties, had noted in regard to PCL-Intertech: Lenhydro Consortium based on information/documents furnished by them, that the annual turnover of M/s Progressive during the year 1998-99 has been Rs 158.11 crores. The joint venture partners, M/s Institute Lenhydro Project, Russia have successfully completed 140 m high concrete gravity dam on Bureya river for Bureya Hydroelectric Project, Russia involving 35 lakh cu m of concrete placement. The peak rate of concrete placed by the party in a single month on this project was more than the required rate of 20,000 cu m. It was also noted that M/s Progressive achieved a monthly rate of 2,50,307 cu m for earth and rock excavation in the month of June 1994 for Srisailam Right Bank Canal Work. M/s Institute Lenhydro Project, having worked on Bureya HEP, Russia, have adequate experience in reinforced cement concrete technology. Based on the information provided, and documents submitted by this joint venture in response to the pre-qualification tenders, the Standing Committee recommended pre-qualification of PCL-Intertech: Lenhydro Consortium joint venture. It was intimated to the applicant that since the pre-qualifying requirements relating to concreting were being met by the Consortium of Intertech: Lenhydro Project, Intertech: Lenhydro Consortium needs to be nominated as the leader of the joint venture. This was accepted and confirmed by the applicant vide Letter No. PCL/ND/THDC/2000/2275 dated 22-5-2000.
    6. Based on the recommendations of the Standing Committee, the answering respondent THDC, pre-qualified seven parties in June 2001, including the joint venture of M/s Progressive Construction Limited and Consortium of Intertech-Lenhydro, Russia, for submission of bids for the civil construction works of Koteshwar Hydroelectric Project.”

    In view of these pleadings, the High Court held that “on consideration of the rival submissions and pleading on record, it is abundantly clear that Respondent 2 is fully qualified and eligible to carry out the contract” and the writ petitioner did not, before the bids were opened, raise any objection regarding the experience and financial capacity of Respondent 2. The High Court, therefore, dismissed the writ petition filed by the writ petitioner.

    2. In this case the respondents had entered caveats. We asked them, even at the stage of preliminary hearing before issuing notice, to address the arguments on the merits of the matter. Having heard the parties in the case, we have passed this order.

    3. In the writ petition filed before the High Court the petitioner contended (i) that one of the constituents of the second respondent Lenhydro Project is not a company engaged in actual physical execution/construction of works; rather, it was only a design firm; (ii) Intertech Services is not a construction company engaged/having experience in actual execution/construction of concrete dam, spillway and powerhouse works; and (iii) the statement made by the authorised signatory of Lenhydro Project that the said constituent has executed Bureya Hydroelectric Project, far-east Russia is not correct as in fact the said project has been built by JSC Boguchangesstroy as turnkey contractor.

    4. In support of this contention, the learned counsel for the petitioner relied upon a letter issued by SHC Institute Hydro Projects and letter dated 25-5-2002 by the Chamber of Commerce and Industry of the Russian Federation which stated that “Lengibroproyekt is a specialized design engineering company in the field of hydroelectric projects where it enjoys good standing as a design firm. This firm does not involve itself in executing projects nor is it known to associate or act as a turnkey contractor”; that letter dated 22-11-1999 (Annexure P-12) issued by Bureya Hydro Power Project is ambiguous inasmuch as it only refers to successful completion of the contract by the Russian constituent of the second respondent without any details thereto; that Bureya Hydro Power Project on Bureya river was, in fact, constructed by Boguchangesstroy as a turnkey contractor as per the information obtained from the reference list of the project built by JSC Boguchangesstroy for the years 1997-2000. It is also contended that during the period from 1993 to 1997 “Lenhydroproject” merely got executed construction work project at Bureya Hydro Power Station even as per certificate dated 15-7-2002 issued by the Chief Engineer of the parent company of the Russian constituent of the 2nd respondent. On this basis it is contended that the second respondent had not placed any satisfactory material to show that it had necessary experience as required under the pre-qualification documents.

    5. The letters issued by SHC Institute Hydro Projects and the Chamber of Commerce and Industry of the Russian Federation do not specifically deal with whether the 2nd respondent had in fact executed the construction work of Bureya Hydro Power Station Project but makes general reference. The reference list obtained from the Internet gives information from 1997 onwards and not for the earlier period. Therefore, these three documents are not helpful to the petitioner. The stand of the respondents is that Bureya Hydro Power Station Project is a multistage project; that during the period 1993-97, the Russian constituent of the 2nd respondent was entrusted with the construction, technical support and quality control of Bureya Hydro Power Station Project and they were providing construction machinery, material, manpower etc. during the execution of works. Certificate issued on 1-8-2002 in this regard by the parent company is made available by the 2nd respondent. Another certificate dated 11-6-2002 was relied upon along with the letter dated 22-11-1999 issued in this regard. Next stage of project from 1998 onwards was executed by a sub-contractor JSC Boguchangesstroy and Boguchangesstroy had not figured for the earlier period prior to 1998. This project has nothing to do with the earlier project. The clear stand of the respondents on the basis of these documents is that apart from general designing work they were also engaged in actual construction of the project. If upon the material made available to the 1st respondent by the 2nd respondent its pre-qualification has been decided, the High Court is justified in not interfering under Article 226 of the Constitution.

    6. In the light of this position, we find no merit in this petition and the same stands dismissed. No costs.

    Use AI to get other relevant cases.

    Comments

    Continental Construction Ltd. v. Tehri Hydro Development Corporation Ltd. And Another
    (Sep 5, 2002)