AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Order 2, Rule 2 of the Code of Civil Procedure
  • Section 41 of the Arbitration Act
  • Section 14 of the Arbitration Act
  • Section 11 of the Code of Civil Procedure
  • The Arbitration Act
  • Articles 32 and 226 of the Constitution of India
  • Section 114 of the Code of Civil Procedure
  • Section 114 read with Order 47 Rule 1 of the Code of Civil Procedure
  • Mulla's Code of Civil Procedure (Volume II, 14th Edn.) at p. 894
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Order 2, Rule 2 of the Code of Civil Procedure
  • Section 41 of the Arbitration Act
  • Section 14 of the Arbitration Act
  • Section 11 of the Code of Civil Procedure
  • The Arbitration Act
  • Articles 32 and 226 of the Constitution of India
  • Section 114 of the Code of Civil Procedure
  • Section 114 read with Order 47 Rule 1 of the Code of Civil Procedure
  • Mulla's Code of Civil Procedure (Volume II, 14th Edn.) at p. 894
Smart Summary

Factual and Procedural Background

The appellant, contractor K.V. George, entered into a contract dated 22-4-1978 with the respondents for constructing an embankment across Musaliyar Padom as part of the Kallada Irrigation Project. The work was to be completed by 30-3-1980. Alleging non-completion, the respondents terminated the contract on 26-4-1980 “at the risk and cost” of the contractor.

Two separate arbitral references followed:

  • Arbitration Case No. 132 of 1980 – filed by the contractor on 2-7-1980 for enhanced rates and interest. The respondents submitted a defence and a counter-claim of Rs 28,84,000. On 22-1-1981 the arbitrator allowed Claim 1 (35 % rate increase) but expressly deferred decision on the counter-claims.
  • Arbitration Case No. 276 of 1980 – filed later by the contractor challenging the contract’s termination and raising 13 further claims. An award dated 29-10-1981 granted additional rate increases, refunds, and rejected the Government’s counter-claims.

Judicial interventions ensued:

  1. The contractor sought to make the first award a rule of court (O.P. (Arb.) 81/1981). On 18-8-1981 the Sub-Judge remitted the matter to the arbitrator for fresh consideration of the counter-claims. Upon review (I.A. 3780/1981) the same court reversed itself and passed a decree in terms of the first award.
  2. The contractor also moved to enforce the second award (O.P. (Arb.) 296/1981). On 18-3-1982 the Sub-Judge made that award a rule of court, rejecting the respondents’ plea of res judicata.
  3. The State filed MFAs 291 & 304 of 1982 before the Kerala High Court. By judgment dated 10-4-1987 the High Court:
    • set aside the review order and remitted Arbitration Case 132/1980 for decision on both claims and counter-claims, holding the arbitrator guilty of misconduct for ignoring the counter-claims (MFA 291/1982); and
    • set aside the second award, applying constructive res judicata and Order 2 Rule 2 CPC (MFA 304/1982).

The contractor obtained special leave and filed the present appeals before the Supreme Court.

Legal Issues Presented

  1. Whether the High Court rightly set aside the trial court’s review order and the first arbitral award on the ground that the arbitrator committed misconduct by failing to adjudicate the respondents’ counter-claims.
  2. Whether the second arbitral award (Arb. Case 276/1980) was barred by the doctrines of res judicata, constructive res judicata, and Order 2 Rule 2 CPC, as applied to arbitration through Section 41 of the Arbitration Act.

Arguments of the Parties

Appellant’s Arguments

  • The High Court ignored Section 114 and Order 47 Rule 1 CPC; the trial court validly reviewed its earlier remittal because the counter-claims were later considered in the second award, curing any misconduct.
  • Principles of res judicata and constructive res judicata do not apply; under the contract disputes had to be first raised before departmental authorities, and many claims were not yet “ripe” when the first reference was made.
  • Order 2 Rule 2 CPC was inapplicable because the causes of action were separate and had not matured at the time of the first reference.

Respondents’ Arguments

  • No ground existed for review; the Sub-Judge correctly remitted the first award as the arbitrator had ignored the counter-claims.
  • Section 41 of the Arbitration Act attracts CPC provisions; hence res judicata, constructive res judicata, and Order 2 Rule 2 bar the second reference because all disputes arose upon termination of the contract on 26-4-1980.
  • The arbitrator’s failure to decide the counter-claims amounted to misconduct, vitiating the first award and rendering the second award incompetent.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Mohd. Hafiz v. Mirza Muhammad Zakariya, AIR 1922 PC 23 Order 2 Rule 2 CPC – bar against splitting a single cause of action Used to show that the contractor, having sought partial relief in the first reference, was barred from later seeking additional relief arising from the same termination.
Daryao v. State of U.P., AIR 1961 SC 1457 Public-policy foundation of res judicata; applicability even to constitutional proceedings Cited to affirm that res judicata principles, being matters of public policy, apply equally to arbitration proceedings via Section 41.
Satish Kumar v. Surinder Kumar, AIR 1970 SC 833 Claims referred to arbitration merge into the award; subsequent proceedings on the same claims are barred Supported the conclusion that, once an award is rendered, parties cannot initiate fresh arbitration on matters that could have been included earlier.

Court's Reasoning and Analysis

The Supreme Court affirmed the High Court’s two principal findings:

  1. Misconduct in first award: An arbitrator must adjudicate both claims and counter-claims submitted to him. By ignoring the Government’s counter-claims, the arbitrator violated this duty. Consequently, the first award dated 22-1-1981 was “wholly illegal” and the trial court’s later review order lacked any “error apparent” or “sufficient reason” under Order 47 Rule 1 CPC. The High Court correctly reinstated the original remittal.
  2. Bar to second award: Termination on 26-4-1980 generated a single, comprehensive cause of action; the contractor was obliged to raise all resulting disputes in the first reference. Applying:
    • Order 2 Rule 2 CPC (as explained in Mohd. Hafiz) – prohibition against splitting one cause of action;
    • Section 11 CPC res judicata and its constructive branch – to prevent multiplicity of proceedings; and
    • Section 41 Arbitration Act – importing CPC provisions into arbitration,
    the Court held that the second arbitral reference was incompetent. Previous Supreme Court dicta in Daryao and Satish Kumar underscored that finality and merger principles apply equally in arbitral contexts.

Accordingly, the Supreme Court concluded that the High Court rightly set aside both the review order and the second award.

Holding and Implications

APPEALS DISMISSED; HIGH COURT JUDGMENT AFFIRMED. Costs of Rs 5,000 were imposed on the appellant.

Immediate effect: the first award remains remitted for fresh decision on both claims and counter-claims; the second award stands quashed. The ruling reinforces that CPC doctrines of res judicata, constructive res judicata, and Order 2 Rule 2 apply fully to arbitration proceedings under Section 41 of the Arbitration Act, ensuring finality and preventing fragmented arbitral claims.

To access the original judgment, please Sign In or Subscribe.

    K.V George v. Secretary To Government, Water And Power Department, Trivandrum And Another

    B.C Ray, J.— Special leave granted.

    2. These appeals on special leave have been filed by the contractor, K.V George against the judgment and order passed on 10-4-1987 by the Kerala High Court in MFAs Nos. 291 and 304 of 1982 whereby the High Court set aside the judgment of the Sub-Court, Trivandrum in O.P (Arb.) No. 296 of 1981 as also the award of the arbitrator in AC No. 276 of 1980 and directed that the arbitrator will dispose of the Arbitration Case No. 132 of 1980 in the light of the judgment of the sub-court in O.P (Arb.) No. 81 of 1981 in accordance with law considering the claim of the contractor appellant and the counterclaim of the respondents.

    3. The appellant who is a contractor entered into a contract with the respondents on 22-4-1978 in connection with the construction of a embankment across Musaliyar Padom between Chaniage 2573.5 M to 2827 M of E.B Main Canal of Kallada Irrigation Project. The work was required to be completed by 30-3-1980 i.e two years from the date of selection notice which was dated 30-3-1978. As the appellant failed to complete the work as per the terms of the contract, the respondents sent a notice dated 26-4-1980 to the appellant cancelling the contract at his risk and cost. On 2-7-1980 the appellant filed a claim being Arbitration Case No. 132 of 1980 before the named arbitrator i.e the Chief Engineer (Arbitration), Vellayambalam, Trivandrum claiming enhancement of rates in respect of the earth work involved in the contract, interest on delayed payments and costs. The second respondent, the Superintending Engineer, K.I.P Circle, Karnataka filed a defence statement stating inter alia in para 2(1) that the time of completion of the work was fixed as 24 months from the date of handing over site to the contractor and he could have anticipated all such variations before quoting rates. As per agreement the rates once agreed will not be enhanced. The department is not bound to pay the claimant a revision of schedule. In para 2(m) it has also been pleaded that as per agreement the contractor is bound to carry out additional and extra items of works that arise during execution. The additional and extra items of works done by the contractor are quite meagre when compared to the total volume of the work. The extra and excess items were covered by supplemental agreement. The contractor was not able to complete even 35 per cent of the total work within the time for completion of the work and as such the claimant is not entitled to attributed delay on this account. A counterclaim was filed by the Superintending Engineer, K.I.P Circle, Kottarakkara, Respondent 2 wherein a claim of a sum of Rs 28,84,000 was made.

    4. The arbitrator by his order dated 22-1-1981 made the award in regard to Claim 1 directing the respondents to pay 35 per cent increase in the agreed rate for the item of earth work excavating and filling for forming the compacted embankment with earth from barrow area. Claim 1 was thus allowed. Claims 2 and 3 regarding interest were disallowed. As regards counterclaimes 1 and 2, it was ordered that those issues will be considered separately and so no award was made.

    5. The appellant thereafter filed O.P (Arb.) No. 81 of 1981 in the Court of Sub-Judge, Trivandrum under Section 14 of the Arbitration Act for making the award a rule of the court. On objections being raised by the respondents, the Court of the Sub-Judge after hearing the parties by order dated 18-8-1981 remitted the reference to the arbitrator for fresh consideration on the ground that the arbitrator did not consider the counterclaims made by the respondents. The appellant thereafter filed IA No. 3780 of 1981 in the Court of Sub-Judge praying that the order dated 18-8-1981 may be reviewed. In the meantime, the appellant filed another Arbitration Case No. 276 of 1980 before the same arbitrator in respect of the wrongful termination of the contract and also raised 13 items of claims therein. The arbitrator after going through the objections of the respondent made an award on 29-10-1981 whereby he ordered that the rearrangement of the work should not be at the risk and cost of the appellant. As regards Claim 2, he ordered 30 per cent increase in rates (as per original and supplemental agreement) for all items of work carried out by the appellant except on items covered by Award No. 132 of 1980 dated 22-1-1981. Claims 3 and 5 were rejected. As regards Claim 4 an increase of 20 per cent in the agreed rates for these items was allowed. Claim 11 regarding interest was disallowed. It was also stated in the award inter alia that the claimant shall be entitled to the refund of the security amount as well as refund of the retention amounts, the claimant shall be entitled to his final bill in terms of the award, the counterclaim for recovery of costs on rearrangement of work and also the counterclaims filed by the respondent dated 8-4-1981 were declined. The appellant filed O.P (Arb.) No. 296 of 1981 for making the second award a rule of the court. A statement of defence was filed by the respondents wherein it has been stated inter alia in para 6 that:

    “The claims made in this petition under paras 6(ii), (iii), (iv), (v), (vi) (vii) and (viii) are barred by res judicata and constructive res judicata. No work was done by the claimant after termination of the contract on 24-6-1980. The claim petition in Arbitration Case No. 132 of 1980 was filed by the claimant before the Hon'ble arbitrator on 2-7-1980. It was open to him to raise these claims in that arbitration petition. Having not done this raising of these claims now which are all bogus and imaginary is barred by constructive res judicata. He had not raised these claims before Chief Engineer (next superior authority) and also before the hon'ble arbitrator in his petition dated 27-10-1980. Hence it is prayed that the above claims may not be taken up for arbitration and they may be rejected.”
    It has also been stated in sub-para (iv) of para 6 that:
    “(iv) As above. Also there had been no error in the rates. The claimant was paid at his agreed rates, and he had received it and also no dispute lies on it. Claim may be rejected. Work done was recorded as per Item 7 of application of agreement and was paid as per agreement.”

    6. The Sub-Judge by order dated 18-3-1982 made the award a rule of the court dismissing the plea of res judicata raised by the respondents in O.P (Arb.) No. 296 of 1981. The respondents filed two appeals being FMS Nos. 291 and 304 of 1982 before the High Court of Kerala at Ernakulam which held that the arbitrator could not review its order on the facts of the present case and so allowed FMAs No. 291 of 1982. The High Court also allowed FMA No. 304 of 1982 holding that principles of constructive res judicata would apply to the arbitration case. Feeling aggrieved by the aforesaid judgment and order passed in FMAs Nos. 291 and 304 of 1982, the appellant contractor has preferred the instant appeals on special leave.

    7.Mr. Bhatt, learned counsel appearing on behalf of the appellant has submitted in the first place that the High Court was wrong in reversing the judgment and order of the trial court without considering the provisions of Section 114 as well as Order 47 Rule 1 of the Code of Civil Procedure inasmuch as Order 47 Rule 1 clearly provides that review of an order may be made either on account of some mistake or error apparent on the face of the record, or for any other sufficient reason. In the instant case, the first award was set aside by the trial court on the ground that the counterclaim filed on behalf of the respondents was not considered by the arbitrator and so it remitted the same for consideration afresh. It has been held by the High Court that the refusal to consider the counterclaims had rendered the prior award liable to be set side for misconduct of the arbitrator and the proceedings. It has been urged by the learned counsel that the counterclaim has been fully considered in the second award made by the arbitrator and as such the first award cannot be set aside on the ground of non-consideration of a counterclaim and it cannot be treated as misconduct of the arbitrator and the proceedings for non-consideration of the counterclaim in the first award. It has been further contended in this connection that the finding of the High Court to the effect that the subsequent award passed by the arbitrator dealing with the counterclaims did not have the effect of mitigating the misconduct of the arbitrator or of condoning the error on the face of the award, is also not sustainable inasmuch as the counterclaim filed by the respondents was duly considered by the arbitrator in the second award made by him.

    8. It has also been submitted by the learned counsel for the appellant that the principles of res judicata and constructive res judicata are not applicable to the award made in Arbitration Case No. 291 of 1981 inasmuch as the disputes that were raised were not ripe for being referred to arbitration in view of the terms of the contract that the contractor had to raise the dispute before the Superintending Engineer and thereafter before the Chief Engineer and had to wait till the end of the stipulated period. It has been further submitted that since the period was not over, the claims that have been raised subsequently in the second claim petition before the arbitrator could not be raised in the first claim petition before the arbitrator and as such the second award made by the arbitrator cannot be said to have been barred by res judicata as provided in Section 11 of the Code of Civil Procedure or by the rules of constructive res judicata. The judgment and order of the High Court in allowing FMA No. 304 of 1982 setting aside the award made in Arbitration Case No. 296 of 1981 is unwarranted and as such it is not sustainable. It has also been contended that the claim made in the second claim petition before the arbitrator is not barred by Order 2, Rule 2 of the Code of Civil Procedure inasmuch as the disputes raised in the second claim petition before the arbitrator were not ripe for reference as the appellant had to wait till the end of the stipulated period in accordance with the terms of the contract. The judgment and order of the High Court in allowing the FMA No. 304 of 1982 is not legal and valid and is liable to be set aside.

    9. Mr Abdul Khadir, learned counsel appearing on behalf of the respondents on the other hand urged before this Court that the Sub-Judge acted legally in directing the arbitrator to dispose of the Arbitration Case No. 132 of 1980 in the light of the judgment of the Sub-Court in O.P (Arb.) No. 81 of 1981 and in setting aside the order of review because no case for review nor any sufficient cause has been made out for exercising the power of review under Section 114 read with Order 47 Rule 1 of the Code of Civil Procedure. The High Court, it has been submitted, was right in holding that the order of review was unwarranted and in setting aside the same and directing the arbitrator to dispose of the reference in accordance with law considering the claim of the contractor appellant and the counterclaim of the respondents. It has been further submitted by Mr Abdul Khadir that in view of the provisions of Section 41 of the Arbitration Act which specifically provides that the provisions of the Code of Civil Procedure shall apply to arbitration proceedings, the principles of res judicata or of constructive res judicata will apply to arbitration proceeding. The appellant contractor having not raised all his claims in his first claim petition made to the arbitrator for decision and award having been made thereon, the second claim petition before the arbitrator making certain other claims in Arbitration Case No. 276 of 1980 is barred by the principles of constructive res judicata inasmuch as on the termination of the contract by order dated 26-4-1980 the contractor could have raised all his disputes arising out of the contract at that time, but the appellant chose to take only some of the issues arising from the said breach of contract before the arbitrator. The second claim petition raising some issues before the arbitrator is therefore, hit by the principles of constructive res judicata and the High Court rightly allowed the appeal setting aside the award made in Arbitration Case No. 276 of 1980. It has also been submitted that the provisions of Order 2 Rule 2 of the Code of Civil Procedure apply to the arbitration case and the appellant having not sought reference of all the issues, he should be deemed to have surrendered those issues and he is debarred from raising those issues in a subsequent claim petition made before the arbitrator. In this connection, he has cited the ruling in Mohd. Hafiz v. Mirza Muhammad Zakariya AIR 1922 PC 23. The learned counsel drew our attention to para 2(i) of the objections filed by the respondents in Arbitration Case No. 132 of 1980 wherein it has been stated that:

    “... As per agreement the rates once agreed will not be enhanced. The department is not bound to pay the claimant a revision of schedule.”

    10. It has been further submitted by the learned counsel on behalf of the respondents that the appellant was not entitled to an increase in the rates as he claimed increase with the agreement and the claim that has been made is untenable.

    11. It has been lastly submitted on behalf of the respondents that the arbitrator has misconducted himself and the proceedings by not deciding the counterclaim filed by the Government while considering the claim filed by the appellant and making an award. The High Court has rightly held that the arbitrator misconducted himself and the proceedings and allowed the appeal, setting aside the second award made by the arbitrator in Arbitration Case No. 276 of 1980.

    12. The first question that falls for consideration in this case is whether the finding of the High Court setting aside the order of review made in IA No. 3780 of 1981 and setting aside the order made in O.P (Arb.) No. 81 of 1981 dated 18-8-1981 whereby the case was remanded to the arbitrator is sustainable or not. Admittedly, the appellant filed a claim petition being Arbitration Case No. 132 of 1980 making certain claims before the arbitrator. The respondents filed the counterclaims. The arbitrator without considering the counterclaims kept the counterclaims for subsequent consideration and made an award. The trial court set aside the award and remitted the same to the arbitrator for making a fresh award considering the claims and counterclaims filed by the parties. On an application for review, the trial court set aside the order and passed a decree in terms of the award. It is not disputed that the arbitrator did not at all consider the counterclaims and kept the same for consideration subsequently while making award in respect of the claims filed by the appellant. Undoubtedly, this award made by the arbitrator is not sustainable in law and the arbitrator has misconducted himself and in the proceedings by making such an award. It is the duty of the arbitrator while considering the claims of the appellant to consider also the counterclaims made on behalf of the respondents and to make the award after considering both the claims and counterclaims. This has not been done and the arbitrator did not at all consider the counterclaims of the respondents in making the award. As such the first award dated 22-1-1981 made by the arbitrator in Arbitration Case No. 132 of 1980 is wholly illegal and unwarranted and the High Court was right in holding that the arbitrator misconducted himself and the proceedings in making such an award and in setting aside the same and directing the arbitrator to dispose of the reference in accordance with law considering the claim of the contractor and the counterclaim of the respondents. The order allowing the application for review by the trial court is also bad inasmuch as there was no mistake or error apparent on the face of the order dated 18-8-1981 made in O.P (Arb.) No. 81 of 1981 nor any sufficient reason has been made out for review of the said order. The order dated 18-8-1981 is legal and valid order and the order dated 18-3-1982 allowing the application for review being IA No. 3780 of 1981 and setting aside the order in O.P (Arb.) 81 of 1981 dated 18-8-1981 is, therefore, bad and unsustainable.

    13. With regard to the submission that the issues that have been raised in the second claim petition before the arbitrator is barred under the provisions of Order 2 Rule 2 of the Code of Civil Procedure, it is convenient to refer to a passage in Mulla's Code of Civil Procedure (Volume II, 14th Edn.) at p. 894:

    “... This rule does not require that when several causes of action arise from one transaction, the plaintiff should sue for all of them in one suit. What the rule lays down is that where there is one entire cause of action, the plaintiff cannot split the cause of action into parts so as to bring separate suits in respect of those parts.”

    14. It is pertinent to refer in this connection to the decision in Mohd. Hafiz v. Mirza Muhammad Zakariya AIR 1922 PC 23 wherein a mortgage deed provided that if the interest was not paid for six months the creditor should be competent to realise either the unpaid amount of the interest due to him or the amount of principal and interest, by bringing a suit in court without waiting for the expiration of the time fixed, and the plaintiff, more than 3 years after (i.e time fixed), brought a suit for interest alone and got a decree. It was held that the second suit for principal and arrears of interest was not maintainable as under Order 2, Rule 2 of the CPC he must be deemed to have relinquished his claim for further relief, he having exercised the option of suing for interest alone. It was further held that the cause of action referred to in the rule is the cause of action which gives occasion to, and forms the foundation of, the suit, and if that cause enables a man to seek for larger and wider relief than that to which he limits his claim, he cannot afterwards seek to recover the balance by independent proceedings.

    15. In the instant case, the contract was terminated by the respondents on 26-4-1980 and as such all the issues arose out of the termination of the contract and they could have been raised in the first claim petition filed before the arbitrator by the appellant. This having not been done the second claim petition before the arbitrator raising the remaining disputes is clearly barred.

    16. With regard to the submission as to the applicability of the principles of res judicata as provided in Section 11 of the Code of Civil Procedure to arbitration case, it is to be noted that Section 41 of the Arbitration Act provides that the provisions of the Code of Civil Procedure will apply to the arbitration proceedings. The provisions of res judicata are based on the principles that there shall be no multiplicity of proceedings and there shall be finality of proceedings. This is applicable to the arbitration proceedings as well. It is convenient to refer to the decision in Daryao v. State of U.P AIR 1961 SC 1457, (1962) 1 SCR 574 wherein it has been held that the principles of res judicata will apply even to proceedings under Articles 32 and 226 of the Constitution of India. It has been observed that:

    “Now, the rule of res judicata as indicated in Section 11 of the Code of Civil Procedure has no doubt some technical aspects, for instance the rule of constructive res judicata may be said to be technical; but the basis on which the said rule rests is founded on considerations of public policy. It is in the interest of the public at large that a finality should attach to the binding decisions pronounced by courts of competent jurisdiction, and it is also in the public interest that individuals should not be vexed twice over with the same kind of litigation. If these two principles form the foundation of the general rule of res judicata they cannot be treated as irrelevant or inadmissible even in dealing with fundamental rights in petitions filed under Article 32.”

    17. In Satish Kumar v. Surinder Kumar AIR 1970 SC 833, Civil Appeal No. 162 of 1962, dated 11-10-1962 (SC) it has been observed that:

    “The true legal position in regard to the effect of an award is not in dispute. It is well settled that as a general rule, all claims which are the subject-matter of a reference to arbitration merge in the award which is pronounced in the proceedings before the arbitrator and that after an award has been pronounced, the rights and liabilities of the parties in respect of the said claims can be determined only on the basis of the said award. After an award is pronounced, no action can be started on the original claim which had been the subject-matter of the reference.... This conclusion, according to the learned Judge, is based upon the elementary principle that, as between the parties and their privies, an award is entitled to that respect which is due to judgment of a court of last resort. Therefore, if the award which has been pronounced between the parties has in fact, or can, in law, be deemed to have dealt with the present dispute, the second reference would be incompetent. This position also has not been and cannot be seriously disputed.”

    18. Considering the above observations of this Court in the aforesaid cases we hold that the principle of res judicata or for that the principles of constructive res judicata apply to arbitration proceedings and as such the award made in the second arbitration proceeding being Arbitration Case No. 276 of 1980 cannot be sustained and is therefore, set aside. The High Court has rightly allowed the FMA No. 304 of 1982 holding that the appellant contractor was precluded from seeking the second reference. No other points have been raised before us by the appellant.

    19. In the premises aforesaid, we dismiss these appeals with costs quantified at Rs 5000 and affirm the judgment and order dated 10-4-1987 made by the High Court.

    Use AI to get other relevant cases.

    Comments

    K.V George v. Secretary To Government, Water And Power Department, Trivandrum And Another
    (Oct 5, 1989)