  • The report of the World Bank in regard to the dams which are being constructed in Gujarat
  • Section 14 sub-section (2) of the Coal Bearing Areas (Acquisition and Development) Act, 1957
  • Madhya Pradesh Projects Displaced Persons (Re-settlement) Act, 1985
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • The report of the World Bank in regard to the dams which are being constructed in Gujarat
  • Section 14 sub-section (2) of the Coal Bearing Areas (Acquisition and Development) Act, 1957
  • Madhya Pradesh Projects Displaced Persons (Re-settlement) Act, 1985
Smart Summary

Factual and Procedural Background

Two writ petitions were before the Supreme Court of India:

  • WP No. 529 of 1986 concerns the Hasdeo Bango Dam Project in Madhya Pradesh. Although the State legislature enacted the Madhya Pradesh Projects Displaced Persons (Re-settlement) Act, 1985, the project was not notified under that Act. The petition alleges that a large number of tribal inhabitants will be uprooted without any statutory scheme for their resettlement and rehabilitation.
  • WP No. 522 of 1986 is filed under the Coal Bearing Areas (Acquisition and Development) Act, 1957. The petitioner contends that the Central Government has failed to constitute a Tribunal under Section 14(2) of that Act for determination of compensation claims.

At this interlocutory stage, the Court primarily examined whether appropriate administrative steps had been taken by the respondents and adjourned both matters to enable the Governments involved to provide further information and consider corrective action.

Legal Issues Presented

  1. Whether the Hasdeo Bango Dam Project should be brought within the ambit of the Madhya Pradesh Projects Displaced Persons (Re-settlement) Act, 1985 so that affected tribal communities receive statutory rehabilitation and resettlement.
  2. Whether a Tribunal, as mandated by Section 14(2) of the Coal Bearing Areas (Acquisition and Development) Act, 1957, has in fact been constituted for the area concerned and, if so, where it is located and who presides over it.

Arguments of the Parties

Petitioners' Arguments

  • WP No. 529/1986: The State’s failure to notify the Hasdeo Bango Dam Project under the 1985 Act leaves thousands of tribals without statutory rehabilitation.
  • WP No. 522/1986: No Tribunal has been constituted under Section 14(2) for the relevant coal bearing area, preventing displaced persons from claiming compensation.

State Government’s Position

  • WP No. 529/1986: The State identified land in 10 villages for resettlement, but that land is already occupied, creating a risk of displacing another population.
  • WP No. 522/1986: The Land Acquisition Officer’s counter-reply asserts that a Tribunal “has been constituted,” although counsel could not provide its location or presiding officer’s name.

Union of India’s Position (WP No. 522/1986)

  • Counsel for the Union of India lacked instructions regarding the existence or location of the Tribunal.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

WP No. 529/1986: The Court observed that the very purpose of the 1985 Act is to ensure meaningful rehabilitation of tribals displaced by State projects. Given that objective, the Court found it “difficult to see” why the Hasdeo Bango Dam Project had not been included. It emphasised that legislation should not remain “merely a paper legislation with cosmetic effect.” The Court also expressed concern that the land earmarked for resettlement was already occupied, which could create a second wave of displacement. It directed the State to:

  • Re-examine inclusion of the project under the 1985 Act within two weeks.
  • Identify alternative cultivable lands so that the resettlement plan does not break up tribal homogeneity or community life.
  • Consider guidelines from various reports, including a World Bank report on dam projects in Gujarat, as useful indicators for rehabilitation schemes.

WP No. 522/1986: The Court noted the conflicting positions: the petitioner asserted non-existence of a Tribunal, while the State’s own affidavit claimed the opposite without supplying details. In view of this “unenviable position” of counsel and absence of concrete information, the Court adjourned the matter for one week, directing counsel for both the Union of India and the State of Madhya Pradesh to obtain precise instructions about the Tribunal’s constitution, location, and presiding officer. It indicated that, if such a Tribunal exists, compensation claims must be filed there.

Holding and Implications

Holding: ADJOURNED WITH DIRECTIONS.

Implications: The State Government must reconsider bringing the Hasdeo Bango Dam Project under the 1985 Resettlement Act and locate suitable land for displaced tribals. Both the State and Union Governments must clarify the status of the compensation Tribunal under the Coal Bearing Areas Act. No final adjudication on merits was made; the petitions remain pending, and compliance with these interim directions will shape subsequent proceedings. No new legal precedent was set, but the order underscores judicial insistence on effective implementation of statutory rehabilitation schemes.

    Gramin Sewa Sanstha v. State Of M.P And Others

    WP No. 529 of 86 1. We are informed that the Madhya Pradesh legislature has enacted the Madhya Pradesh Projects Displaced Persons (Re-settlement) Act, 1985 but unfortunately, the Hasdeo Bango Dam Project has not been brought under the coverage of this Act with the result that there is no statutory obligation on the Madhya Pradesh Government to provide re-settlement and rehabilitation of the large number of tribals who will be uprooted as a result of implementation of this Project. If the object and purpose of the Act is to provide resettlement and rehabilitation to the tribals so uprooted as a result of the projects being undertaken by the State Government, it is difficult to see why this large project of Hasdeo Bango Dam has not yet been brought within the Act. We adjourn the writ petition for two weeks in order to enable the State Government to consider whether the Hasdeo Bango Dam Project should be brought within the coverage of the Act so that the Act may not remain merely a paper legislation with cosmetic effect but becomes really meaningful and effective to provide the resettlement and rehabilitation to the large number of tribals affected by this Project.

    2. We are also informed that though land in 10 villages mentioned in para 7 of the additional counter reply filed on behalf of the State Government to the writ petition has been earmarked by the State Government for re-settlement of the displaced tribals, such land is not available because it is already occupied by other persons who themselves will be uprooted if such land is acquired and made available for the tribals displaced on account of the Hasdeo Bango Dam Project. If this is true, the remedy might be worse than the disease because in order to re-settle one set of displaced persons the State Government would be displacing another set of persons. We would, therefore direct the State Government to consider in the meanwhile as to whether the cultivable land at any other place or places can be made available for the tribals who are displaced on account of the present project. The State Government will also bear in mind the problem of rehabilitation and resettlement of tribals' communities settled in the land which is sought to be acquired for the project and it is therefore necessary that the provision for resettlement which is made for them must be a provision which does not affect their homogenity or communal life. There are guidelines for re-settlement and rehabilitation of tribals which have been laid down in various reports and particularly in the report of the World Bank in regard to the dams which are being constructed in Gujarat and those guidelines may serve as useful indicators for the purpose of considering what provisions can be made for resettlement and rehabilitation of the tribals who would be displaced on account of the present project.

    3. The writ petition is adjourned to October 1, 1986.

    WP No. 522 of 86 4. Miss Nandita Hakser, learned counsel appearing on behalf of the petitioner states that though Section 14 sub-section (2) of the Coal Bearing Areas (Acquisition and Development) Act, 1957 provides for the constitution of a Tribunal by the Central Government for the purpose of determining the amount of compensation payable under that Act, no such Tribunal has been constituted by the Central Government insofar as area in question is concerned. The learned counsel appearing on behalf of the State Government draws our attention to para 3 of the counter-reply filed on behalf of the Land Acquisition Officer, Bilaspur, M.P: “to the knowledge of the answering respondent, such tribunal has been constituted by Respondent 1”. It seems from this averment that the Land Acquisition Officer, Bilaspur has knowledge that the Tribunal has been constituted by the Central Government for the area in question under Section 14 of sub-section (2) of the Act. Having regard to this positive averment made by the Land Acquisition Officer we ask the learned counsel for the State Government to tell us as to where the Tribunal is located and who is the officer presiding over the Tribunal but the learned counsel has not been able to give this information since he has no instruction nor is there anyone on behalf of the State Government to give any instruction. We asked learned counsel appearing on behalf of the Union of India: he also seems to be in an unenviable position. We are, therefore, constrained to adjourn the writ petition for one week in order to enable learned counsel for the Union of India and the State of M.P to obtain necessary instructions but if the Tribunal has been constituted under Section 14 of sub-section (2) having jurisdiction over the area in question, claims for compensation would have to be filed by the displaced persons before the said Tribunal.

    5. The writ petition is adjourned for one week.