Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 68-C of the Act
  • Article 19(1)(g) of the Constitution
  • Article 32 of the Constitution
  • Section 9 of the Code of Civil Procedure
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 68-F of the Act, Subsection (1-A)
  • Section 68-C of the Motor Vehicles Act, 1939
  • Section 68-C and Section 68-D of the Act
  • Section 68-D of the Motor Vehicles Act, 1939
  • Article 14 of the Constitution
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 68-C of the Act
  • Article 19(1)(g) of the Constitution
  • Article 32 of the Constitution
  • Section 9 of the Code of Civil Procedure
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 68-F of the Act, Subsection (1-A)
  • Section 68-C of the Motor Vehicles Act, 1939
  • Section 68-C and Section 68-D of the Act
  • Section 68-D of the Motor Vehicles Act, 1939
  • Article 14 of the Constitution
Smart Summary

Factual and Procedural Background

On 26 February 1959 the Government of Uttar Pradesh published a draft scheme under Section 68-C of the Motor Vehicles Act, 1939, proposing to grant the State Transport Undertaking exclusive rights to operate stage-carriage services on the Saharanpur–Delhi inter-State route. The scheme was approved and republished on 29 September 1959 under Section 68-D(3). Thirty-two private operators challenged the approved scheme before the Allahabad High Court, which on 30 October 1961 restrained the State from enforcing the scheme against them and directed a fresh inquiry. A similar order was made on 7 February 1962 for eighteen additional operators. Consequently, the scheme remained operative only against non-petitioning operators, while the successful petitioners and the State Transport Undertaking continued running their services.

For over two decades the State Government did not conclude the reconsideration ordered by the High Court, largely because civil courts repeatedly issued injunctions—despite Section 9 of the Code of Civil Procedure barring such suits—preventing further action. By the time the present Article 32 petitions reached the Supreme Court, the delay had stretched to twenty-six years, creating differential treatment among operators and, according to the petitioners, infringing their fundamental rights under Articles 14 and 19(1)(g) of the Constitution.

Legal Issues Presented

  1. Whether the twenty-six-year delay in finalising or reconsidering the 1959 transport scheme renders the scheme and all consequential proceedings invalid.
  2. Whether the prolonged delay violates the petitioners’ fundamental rights under Articles 14 and 19(1)(g) of the Constitution.
  3. What remedial orders the Supreme Court should issue in light of the delay and the precedent on timely disposal of schemes under Chapter IV-A of the Motor Vehicles Act.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Yogeshwar Jaiswal v. State Transport Appellate Tribunal
(1985) 1 SCC 725; AIR 1985 SC 516
State must approve, modify, or reject a draft scheme under Sections 68-C/68-D within a “reasonably short time”; unreasonable delay constitutes abuse of process and can justify quashing the scheme. The Court invoked this principle to hold that the twenty-six-year delay was unreasonable and warranted quashing the 1959 scheme.
Phool Chand Gupta v. Regional Transport Authority, Ujjain
(1985) 4 SCC 190
Quashing of a draft scheme that remained pending for twenty years without approval, underscoring that prolonged inaction invalidates the scheme. Used to reinforce that an even longer delay (twenty-six years) in the present case required similar relief—complete annulment of the scheme.

Court's Reasoning and Analysis

The Supreme Court observed that the High Court’s 1961 and 1962 directions had not been followed for twenty-four years, primarily due to civil-court injunctions that should not have been granted. This “unreasonable delay” produced two constitutional problems: (i) discriminatory treatment among operators, violating Article 14, and (ii) an unjustified restriction on the profession and trade of operators not allowed to ply on the route, infringing Article 19(1)(g).

Relying on Yogeshwar Jaiswal, the Court reiterated that Sections 68-C and 68-D require expeditious action; prolonged delay renders a scheme “antiquated, outmoded and purposeless.” The earlier decision in Phool Chand Gupta, where a twenty-year-old draft scheme was quashed, demonstrated the appropriate remedy. Given that the present delay was even longer, the Court concluded that merely directing an expedited hearing would not cure the constitutional violations.

It therefore exercised its powers under Article 32 to: (a) quash the draft scheme published on 26 February 1959 and all proceedings taken thereafter; (b) forbid the State Government from continuing the pending hearing; and (c) clarify that while the State Transport Undertaking may issue a fresh draft scheme under Section 68-C, it may continue running its current services only until 28 February 1986 or until replaced by permits issued under Section 68-F(1-A) or Chapter IV, whichever occurs earlier.

Holding and Implications

Writ petitions ALLOWED; the 1959 transport scheme and all consequential proceedings are QUASHED.

Immediate Effect: The State Government is restrained from pursuing the long-pending proceedings. The U.P. State Transport Undertaking may operate under its existing permits only until 28 February 1986 or until substituted by fresh or temporary permits, whichever is earlier.

Broader Implications: Although no new legal doctrine was formulated, the decision reinforces existing Supreme Court jurisprudence that extraordinary delay in processing transport schemes under Chapter IV-A is intolerable and subject to judicial annulment. The judgment also signals that civil-court interference through injunctions is improper where statutory schemes prescribe a complete code, thereby promoting timely and orderly resolution of public transport planning.

To access the original judgment, please Sign In or Subscribe.

    Shri Chand v. Government Of U.P, Lucknowand Others

    E.S Venkataramiah, J.— These two petitions are filed under Article 32 of the Constitution. The petitioners have questioned the validity of the proceedings which are pending before the State Government pursuant to a draft scheme published under Section 68-C of the Motor Vehicles Act, 1939 (hereinafter referred to as “the Act”) on February 26, 1959 proposing to authorise the State Transport Undertaking of Uttar Pradesh to operate stage carriages on the inter-State route between Saharanpur and Delhi to the total exclusion of all other operators. After overruling the objections which had been received in response to the said draft scheme the State Government approved the scheme and published it under sub-section (3) of Section 68-D of the Act on September 29, 1959. The validity of the said approved scheme was challenged before the High Court of Allahabad by 32 operators. By its judgment dated October 30, 1961 the High Court of Allahabad directed the State Government not to enforce the approved scheme against the said 32 persons who had filed the writ petitions and it further directed that the State Government should hold a fresh enquiry if necessary into the question whether the scheme should be approved or not. Thereafter in another batch of writ petitions disposed of on February 7, 1962 a similar order was passed in favour of 18 other petitioners. The approved scheme, however, became final as regards other operators. The result was that while the petitioners who had filed the writ petitions were able to operate their stage carriages on the route those who had not filed the writ petitions could not operate. The U.P State Road Transport Corporation however commenced to operate its stage carriages too. Even though the judgment was delivered by the High Court of Allahabad in the year 1961 it has not been possible for the State Government to consider whether approval should be given to the draft scheme either with or without modification as regards the 50 operators pursuant to the judgment of the High Court. All the petitioners in the writ petitions who were permitted to operate their vehicles have been running their services all these 24 years. It has thus resulted in discrimination. We are informed that the State Government has not been able to hear the objections to the scheme as per the judgment of the High Court because of certain orders of injunction passed by the civil courts restraining the State Government from proceeding with the hearing in suits filed by or at the instance of one or the other of the 50 operators who have been running their services on the route in question. It is very strange that the civil courts have issued such orders of injunction from time to time thus effectively preventing the State Government from disposing of the matter. We are of the view that this is a case in which civil courts should not have issued an order of injunction at all since such suits are barred under Section 9 of the Code of Civil Procedure. Be that as it may, the situation created by the unreasonable delay in the approval of the scheme has not merely resulted in the violation of Article 14 of the Constitution but also of the fundamental right of the other operators guaranteed under Article 19(1)(g) of the Constitution. This Court in Yogeshwar Jaiswal v. State Transport Appellate Tribunal (1985) 1 SCC 725, AIR 1985 SC 516 has observed at pp. 518-519 thus:( and 4)

    “The provisions of Section 68-C and Section 68-D of the Act clearly indicate that any scheme which is intended for providing efficient, adequate, economical or properly co-ordinated transport service should be approved either as it is or in a modified form or rejected, as the case may be, within a reasonably short time as any extraordinary delay is bound to upset all or any of the factors, namely, efficiency, adequacy, economy or coordination which ought to govern an approved scheme under Chapter IV-A of the Act. On account of various reasons such as the growth of population and the development of the geographical area adjacent to the area or route in question, any unreasonable delay may render the very proposal contained in the scheme antiquated, outmoded and purposeless. Hence there is need for speedy disposal of the case under Section 68-D of the Act.
    . . . Delay in performance of statutory duties amounts to an abuse of process of law and has to be remedied by the court particularly when the public interest suffers thereby. Hence if there is an unreasonably long and unexplained delay in the State Government passing orders under Section 68-D of the Act, the Court may issue a mandamus to the State Government to dispose of the case under Section 68-D of the Act within a specified time or may in an appropriate case even issue a writ in the nature of certiorari quashing the scheme and a writ in the nature of prohibition directing the State Government not to proceed with the consideration of the scheme published under Section 68-C of the Act because Section 68-D does not confer an unfettered discretion on the State Government to deal with the case as it likes. The power under Section 68-D has to be exercised having due regard to the public interest.”

    2. Following the observations in the above decision in Yogeshwar Jaiswal case (1985) 1 SCC 725, AIR 1985 SC 516 in Phool Chand Gupta v. Regional Transport Authority, Ujjain (1985) 4 SCC 190 we have quashed a draft scheme published in the year 1965 since it had not been approved by the State Government of Madhya Pradesh and had not been published as required under Section 68-D of the Act even though a period of 20 years had elapsed from the date of publication of the draft scheme. In the instant case the delay is in the order of 26 years. In view of the above decisions we allow these writ petitions and quash the impugned scheme published on February 26, 1959 and the proceedings which have taken place till now pursuant thereto and direct the State Government not to proceed with the hearing of the matter. It is now open to the State Transport Undertaking of Uttar Pradesh to publish a fresh draft scheme under Section 68-C of the Act if it is of opinion that it is necessary to do so. We, however, permit the State Transport Undertaking to run the stage carriage vehicles which it is now running on the route in question under permits issued pursuant to the scheme which is now quashed, till February 28, 1986 or till they are replaced by temporary permits to be issued under sub-section (1-A) of Section 68-F of the Act after the publication of a fresh draft scheme or by permits issued under Chapter IV of the Act, whichever is earlier.

    3. The writ petitions are accordingly allowed. There shall be no order as to costs.