  • Section 79(j) of the Electricity (Supply) Act, 1948, for short, 1948 Act.
  • Section 24(1), Indian Electricity Act, 1910, for short, the 1910 Act,
  • provisions of Clause 19(c)(iii) and also of Clause 31(d).
  • Clause (d). Section 39 of 1910 Act
  • Section 79(j) of 1948 Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 79(j) of the Electricity (Supply) Act, 1948, for short, 1948 Act.
  • Section 24(1), Indian Electricity Act, 1910, for short, the 1910 Act,
  • provisions of Clause 19(c)(iii) and also of Clause 31(d).
  • Clause (d). Section 39 of 1910 Act
  • Section 79(j) of 1948 Act
Smart Summary

Structured Summary of the Provided Opinion

Factual and Procedural Background

The petitioner is a small-scale industrial unit (the "Company") operating a factory at Banmore, District Morena manufacturing "Kattha-cutck", using Khair wood supplied under an agreement dated 19-12-1981. The respondent is the Madhya Pradesh Electricity Board (the "Board"). The Board provided two LT service connections to the Company on 26-2-1982: Service Connection No. 2824/1158 (80 H.P.) and No. 2556/1156 (90 H.P.). Inspections and surveillance occurred: a "Vigilance Inspection" on 16-3-1991 (reports filed as Annexures P/V and P/VI) that found the meters intact, and a surprise check on 22-8-1991 (Panchnama Annexure P/IX) in which inner seals of the meters were found tampered with. On the night of 22-8-1991 officers of the Board, accompanied by police guards, disconnected the Company's supply, rendering about 200 employees idle.

The Company filed a petition on 26-8-1991 and related interim applications. On 9-9-1991, the Court directed restoration of supply on conditions, including payment of Rs. 50,000 by the Company on an ad hoc basis and directed the Board to make an assessment of dues with the Company's cooperation. Subsequent orders required compliance by the Board. An application (I.A. No. VI/92) filed on 29-12-1992 resulted in a Vacation Judge's order on 30-12-1992 directing restoration of Service Connection No. 2556/1156 upon deposit of Rs. 33,397 (Annexure P/39) and directing the Board to file a return within two weeks; the matter was to be listed for final hearing in the third week of January 1993.

The Company did not deposit the sum ordered and the factory remained closed for about two and a half months. The Board filed its return late (25-2-1993). In its return the Board contended the Company had been stealing electricity from 1987 to September 1991 and produced two retrospective "assessment bills" (amounts given in the return as Rs. 7,24,137.83 and Rs. 6,51,256.61). The Board also asserted an F.I.R. was lodged on 22-8-1991. The Company disputed those bills and contested the disconnection and the validity of arrears shown in Annexure P/39.

This matter was listed before the Court initially on 8-2-1993 because the Company complained that the Board was delaying filing its return. The return ultimately appeared on 25-2-1993, and hearing concluded on 27-2-1993.

Legal Issues Presented

  1. Whether, at any time, the Board legally, lawfully and competently disconnected the supply of power to the Company's factory in respect of the service connections (with the principal dispute focused on Service Connection No. 2556/1156).
  2. Whether the two retrospective "assessment bills" prepared by the Board (as per Annexure P/11) are valid and enforceable, and whether there is any legal basis for the arrears claimed in Annexure P/39.

Arguments of the Parties

Company (Petitioner) — Counsel Shri Chitaley

  • Clause 31(e) of the Board's "General Conditions" cannot override statutory protections, namely Section 24(1) of the Indian Electricity Act, 1910, which requires at least seven clear days' written notice before cutting or disconnecting supply for non-payment.
  • If there is any dispute regarding liability for charges, the Board is bound by Sub-section (2) (of Section 24 as described) to refer the dispute to the Electrical Inspector and cannot exercise the power under Sub-section (1) until the Inspector has decided.
  • Clause 31(e) cannot be exercised arbitrarily; to do so would violate Article 14 of the Constitution (equal protection/absence of arbitrariness).
  • Clauses 19(c)(i), 27(c) and 31(d) of the Conditions of Supply impose specific metering, billing and notice rules which were not followed; Clause 19(c)(iii) provides how consumption should be determined when a meter is defective (average of prior three months).
  • The Conditions of Supply do not have independent statutory force unless they are shown to be regulations framed under Section 79(j) of the Electricity (Supply) Act, 1948; even if they are so regarded, they cannot prevail over Section 24 of the 1910 Act and Article 21.
  • Reliance was placed on authority that vague bills without basis cannot impose liability (citing Gajendra Singh v. M.P.E.B.).

Board (Respondent) — Counsel Shri K.N. Gupta

  • The Board asserted that the Company had been stealing electricity and relied on Clause 31(e) of the Conditions of Supply to justify immediate disconnection where malpractices (including unauthorised alterations and theft) are detected; argued that supply cannot be restored until the two assessment bills (amounts stated in the return) are paid.
  • The Board maintained that the "assessment bills" represent the difference in consumption for a three-year period, adjusted for payments made, and supported disconnection until those bills are paid.
  • The Board's counsel relied on Clause 31(e) and analogies with other judicial decisions (including Aditya Rotor Spin v. U.P. State Electricity Board) upholding similar regulatory provisions enacted under Section 79 of the 1948 Act.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Gajendra Singh v. M.P.E.B., 1992 (II) MPWN 171 That a vague bill giving no basis for demand is not a bill by which liability can be saddled on a consumer. The Court relied on this authority to support the conclusion that the retrospective "assessment bills" lacked a reasonable basis and could not be enforced.
Olga Tellis, AIR 1986 SC 180 Holds that the right to livelihood is embraced within Article 21 of the Constitution. The Court invoked this principle to read the protection of Article 21 into situations where disconnection of essential services (like electricity) may deprive persons of livelihood and thus require procedural safeguards.
Board of Trustees v. Dilip Kumar, AIR 1983 SC 109 Article 21 creates a protective shield against denial of basic civilizational amenities. Used to reinforce that deprivation of essential services engages Article 21 and procedural safeguards (natural justice) are implicated when services are cut.
Municipal Corporation of Delhi v. M/s. Ajanta Iron and Steel Co., AIR 1990 SC 882 Prior notice of disconnection is mandatory where theft of electricity is alleged; allegation must be separately dealt with and proved before penal consequences are imposed. The Court relied on this decision to hold that prior notice and due process are required before disconnecting supply on a theft allegation; theft must be judicially established before penal consequences are imposed.
Kuldeep Singh Dhingra v. Municipal Corporation of Delhi, AIR 1992 Delhi 228 Pre-decisional hearing is mandatory in cases involving denial of essential services. Invoked to support the necessity of hearing and natural justice prior to disconnection on disputed allegations.
Southern Steelmet and Alloys Ltd. v. Karnataka Electricity Board, AIR 1991 Karnataka 267 Requirement of following principles of natural justice where theft of electricity is alleged; interpretation of relevant regulation enacted under section 79 of 1948 Act to require such safeguards. Cited to show that even where regulations appear barren, they ought to be construed to require natural justice; used to buttress the Court's approach to Clause 31(e).
M.P.E.B. v. Basantibai, AIR 1988 SC 71 Addressed Section 26(6) (as interpreted by the Apex Court) and contexts where disputes need not be referred to the Electrical Inspector. The Court agreed that the ratios of this decision (and Regal Theatre) were not applicable to the instant facts concerning tampering and suspected theft; it accepted that Section 26(6) did not cover all situations of alleged tampering.
Regal Theatre v. M.P.E.B., AIR 1987 MP 276 Decision considered in relation to Board powers under statutory framework (discussed by the Court but held not applicable to present facts). The Court held the ratio inapplicable on the facts before it (tampering/theft allegations and absence of required notices/procedures).
Aditya Rotor Spin (P.) Ltd. v. U.P. State Electricity Board, AIR 1991 Allahabad 196 Upheld the constitutional vires of a regulation (Regulation 22) under Section 79 of the 1948 Act; the case considered vires but not necessarily scope. The Court considered this authority but distinguished it: noted that the Allahabad decision dealt with vires, not scope, and that it did not take into account the Apex Court's reasoning in Ajanta Iron and Steel Co.'s case.
Indian Aluminium Co.'s case, AIR 1975 SC 1967 Addressed limits of Section 79(j) of the 1948 Act and whether delegated regulations can impair substantive statutory rights. Relied upon by the petitioner's counsel and accepted by the Court to the extent that delegated "principles" cannot impair rights conferred by statute; used to justify reading Clause 31(e) in harmony with other clauses and with natural justice.

Court's Reasoning and Analysis

The Court identified the principal issue as whether the Board lawfully disconnected the Company's electricity supply (principally Service Connection No. 2556/1156) and whether the retrospective assessment bills and claimed arrears were legally sustainable.

The Court examined the relevant provisions of the Board's "General Conditions" (in particular Clauses 19(c)(i) and (iii), 27(c), 31(d) and 31(e)) alongside statutory provisions from the Indian Electricity Act, 1910 (notably Section 24(1), and other statutory references mentioned in the opinion).

  1. Compliance with statutory notice requirements: The Court found that no statutory notice as required by Section 24 or even the contractual notice under Clause 27(c) (seven clear days' notice of intention to discontinue for non-payment) was given before the disconnection. The action was thus procedurally flawed.
  2. Validity of the "assessment bills": The Court concluded that the two retrospective "assessment bills" were based on conjecture and arbitrary assumptions (for example, presuming extremely high monthly consumption figures over a three-year period) and were inconsistent with Clause 19(c)(iii) (which prescribes averaging prior three months where meters are defective) and Clause 31(d) (which limits retrospective higher tariff revision ordinarily to six months unless engineer gives reasons for a different period). The Court found the bills lacked reasonable basis and were illegal.
  3. Clause 31(e) and natural justice: Although Clause 31(e) authorized the Board to disconnect supply where malpractices such as unauthorised alterations or theft are detected, the Court held that Clause 31(e) must be read subject to principles of natural justice and the protections of Article 21 (right to life including aspects of livelihood). The Court read the requirement of prior notice/hearing into Clause 31(e) — especially because disconnection of essential services affects livelihood and may impose penal consequences ahead of judicial determination of theft.
  4. Interaction of subordinate conditions/regulations with statute and Constitution: The Court accepted the petitioner's contention that delegated conditions cannot override statutory safeguards under Section 24(1) or constitutional protections. Where Clause 31(e) could be read as authorising summary disconnection on suspicion, it had to be harmonised with Clause 31(d), Clause 19(c), Clause 27(c) and constitutional mandates; otherwise it could not stand.
  5. Remedy and directions: Given the illegality of the bills and the disconnection, the Court quashed the assessment bills and the claimed arrears, found the disconnection illegal and unconstitutional, and directed immediate restoration subject to limited conditions (described below).

Holding and Implications

PETITION ALLOWED

Holding (core ruling emphasized): The Court quashed the two retrospective "assessment bills" and the claimed arrears, held the Board's discontinuation of electricity supply to Service Connection No. 2556/1156 to be illegal and unconstitutional, and directed restoration of that service connection within 24 hours.

Direct implications and orders made by the Court (as specified in the opinion):

  • The Court quashed the two "assessment bills" (amounts are recorded in the opinion at different places as Rs. 7,24,137.83 and Rs. 6,51,256.61 in the Board's return, and later the Court refers to quashing two bills for Rs. 7,24,137.83 and Rs. 6,61,256.61).
  • The Court quashed the unsubstantiated arrears of Rs. 26,459/- shown in Annexure P/39.
  • The Board was directed to restore Service Connection No. 2556/1156 within 24 hours to enable the Company to resume production.
  • The Board remains free to pursue legal and appropriate demands in a lawful manner regarding alleged theft, but only after theft is judicially established in criminal proceedings instituted by the Board (i.e., penal consequences or enforcement of retrospective claims cannot precede judicial determination of theft).
  • The Board may, meanwhile and within two weeks, act in accordance with Clause 31(d) if so advised, subject to the Company's right to challenge any such action.
  • The Company shall not claim refund of the Rs. 50,000 deposited earlier under this Court's order until further steps; the admitted liability of Rs. 6,940 shall be adjusted by the Board against that deposit immediately; future dues after restoration will be payable on proper bills drawn in accordance with law.
  • The petition succeeds and is allowed in terms of the Court's directions; each party to bear its own costs.

The opinion does not indicate that the Court was laying down any novel binding precedent beyond its application of established principles (it primarily applied and harmonised existing statutory provisions, contractual conditions and constitutional protections).


This summary is strictly based on the information contained in the provided opinion and does not include any material or inference beyond that text.

    Harsh Wood Products Pvt. Ltd. v. State Of Madhya Pradesh And Others

    1. This matter was listed before us for the first time on 8-2-1993 when complaint was made to us that respondent Madhya Pradesh Electricity Board, for short, the 'Board' was designedly delaying the proceedings by not filing return to the serious detriment of the petitioner, despite order passed on 30-12-1992 for the matter to be heard and finally decided in the third week of January, 1993, allowing two weeks' time to the respondents to file return. The return came on record on 25-2-1993 and hearing was taken up on the same date, but concluded on 27-2-1993.

    2. The petitioner Company, for short, the 'Company', which is registered as a Small Scale Industrial Unit is running a factory at Banmore, District Morena, where manufacturing of Kattha-cutck is undertaken. The raw material used is Khair wood which is supplied by the Forest Department of the State Government under agreement dated 19-12-1981. The Board provided to the Company's factory L. T. power connection since 26-2-1982; Service Connection No. 2824/1158, being in respect of a 80 H.P. motor and the other connection No. 2556/1156 being for 90 H.P. motor. In para 6 of the petition is given particulars of the bills raised for the electricity consumed under those connections from April, 1990 to March, 1991. It is stated that on 16-3-1991, the "Vigilance Inspection" was made of the Company's factory and reports thereof, Annexures P/V and P/VI are filed. Both meters of the two connections were found intact and in para 9 is given the details of bills drawn for the consumption made between April, 1991 and July, 1991. On 22-8-1991, there was a surprise check again at the Company's factory when a Panchnama, Annexure P/IX, was prepared showing that although on the meter boxes of the two meters, the outer seals were intact, the inner seals in the meters were tampered with. Late in the night on the same date, some officers of the Board swooped on the Company's factory along with Police Guards and disconnected the supply made through the service connections aforesaid rendering idle about 200 employees in service of the Company, engaged in the factory.

    3. On 28-8-1991, the petition filed by the Company on 26-8-1991 was listed before the Court when prayer for ad interim writ was rejected, but for final hearing, the case was directed to be listed on 16-9-1991 and in the meantime, within two weeks, return had to be filed. Because of default of the Board, another application was moved for interim writ and that was heard on 9-9-1991. On the condition of making payment by the Company of Rs. 50,000/- in two equal instalments on ad hoc basis, Board was directed to restore the connection. It was also directed that the Board shall make an assessment of the dues payable by the Company in accordance with law and in the assessment proceedings, Company's cooperation shall be secured and further, the Board was allowed to take all permissible and feasible measures to protect against suspected theft of electricity in future while restoring the electric connection. It appears that subsequently on 6-8-1992, another order, another Division Bench of this Court had to pass directing the Board to comply with the order dated 9-9-1991. On 29-12-1992, another application for interim writ (I.A. No. VI of 1992) was filed with respect to which the learned Vacation Judge passed an order on 30-12-1992 that on the Company depositing Rs. 33,397/- to fulfil the demand raised by the Board as per Annexure P/39, the service connection No. 2556/1156 (90 H.P.), disconnected on 22-12-1992, shall be restored and, as earlier stated, the Board was asked to file return within two weeks and matter was directed to be listed in the third week of January, 1993 for final hearing.

    4. Admittedly, the Company did not deposit the amount aforesaid and the Factory is closed for the last about 2 1/2 months. The stand taken by the Company is that already overpayment was made under this Court's earlier direction and regular payments of bills drawn by the Board were being made by the Company of which particulars were furnished in the application filed on 15-7-1992. In para 5 of the said I.A. No. VI/92, particulars are given of demands raised and payments made with respect to electricity supplied for the service connection 2556/1156 between August, 1992 and November, 1992. At para 6 ibid, it is further stated that although as per the said bill (Annexure P/39), in the month of November, 1992, 501 units were only consumed as the factory was not running in full force because of non-availability of raw materials, minimum charges payable for the month were shown as Rs. 6,940.00 along with imaginary arrears of Rs. 26,495.00, though no such arrear was at all payable. The Company accordingly sent a bank draft dated 23-11-1992 for Rs. 6,940/- vide copy Annexure P/40 which was not accepted and returned back on 8-12-1992 vide Annexure P/41 on the ground that full payment had to be made including the arrears.

    5. No reply the Board filed to the said I. A. VI/92, but return came later, on 25-2-1993, as stated above. Board has taken the stand that the Company was stealing energy for the last many months from 1987 to September, 1991 and the malpractices of the Company were detected in the course of inspection made on 22-8-1991. Surprisingly, the Board has also taken the stand that one of its own officials is a privy to the clandestine activity and at his instance, the Vigilance Report, aforesaid, dated 16-3-1991 was doctored. It is not disputed in the return that two "assessment bills" were prepared and sent to the Company by the Board with a letter, Annexure P/11, dated 26-8-1991, wherein it was stated that an F.I.R. was lodged at Banmore Police Station on 22-8-1991 with respect to theft of electricity by the Company and the assessment made in the bills for three years represented "the difference consumption of energy" while giving credit for the payments made. Obviously, no action was taken by the Company on those bills as they were served on the Company on 28-8-1991, after the matter became sub judice since 26-8-1991. However, by telegram, Annexure P/XV, dated 3-9-1991, the demand was disputed and Board was asked to withdraw the notices and restore the connection. Supporting the stand taken in the return, Board's counsel Shri K.N. Gupta, has relied on Clause 31 (e) of General Conditions for Supply of Electrical Energy and Scale of Miscellaneous and General Charges, printed in a booklet so captioned, published on 1-10-1974 by the Board and has submitted that until those two bills, for Rs. 7,24,137.83 (for Service Connection No. 2556/1156) and Rs. 6,51,256.61 (for Service Connection No. 2824/1158), are paid, supply of elctricity cannot be restored to the Company and indeed an arrears of Rs. 26,495/- shown in Annexure P/39 is also to be paid for restoration of electric connection.

    6. The main question that falls for our decision in this case is -- whether, at any time, the Board legally, lawfully and competently disconnected the supply of power to the Company's factory in respect of Service Connections aforecited. However, it must be pointed out that the dispute now is limited to Service Connection No. 2556/1156 (90 H.P.) inasmuch as the other Service Connection No. 2824/1158 (80H.P.) was disconnected on 22-11-1992 at the request of the Company inasumuch as due to shortage of raw materials, one metar (80 H.P.), was not being operated. The subsidiary question indeed is also, if the two "assessment bills" aforesaid (as per Annexure P/11) are valid and enforceable and indeed if there is any legal basis for the arrears shown in the bill, Annexure P/39. If the two questions are decided against the Board, it would be our Constitutional obligation to issue mandamus to the Board to restore immediately without ado, supply of electrical energy to the Company's factory to Service Connection No. 2556/1156, granting the Company the relief prayed in that regard. It is true that by several interim orders, passed in this matter by this Court from time to time, the basis of the two "assessment bills" above-referred has been essentially eroded when discarding the same, restoration of supply of electricity to the factory of the Company was ordered from time to time. However, legality of those two bills not being decided in those orders, it becomes our duty to do so now in finally disposing of this petition.

    7. Petitioner's counsel, Shri Chitaley, has submitted that all along, at all stages, the Board had been acting illegally and unconstitutionally and Clause 31 (e) cannot be pressed as the valid authority by the Board to support their stand. His first contention is that nothing can override the provisions contemplated under Section 24(1), Indian Electricity Act, 1910, for short, the 1910 Act, contemplating "not less than seven clear days' notice in writing" to be given to the consumer when it is proposed to "cut or disconnect any electric supply line" of any consumer due to his neglect to pay any charge for energy supplied to him. He submitted also that if there was any "dispute" with respect to the Company's liability for payment of charges for the supply of energy, the Board was bound to refer the same, as per Sub-section (2), to Electrical Inspector and the power conferred under Sub-section (1) cannot be exercised until the Inspector has given his decision. He has also assailed the Board's stand that Clause 31 (e) contemplates power validly exercisable in such a case and submitted further that the power contemplated there under cannot be exercised arbitrarily as that would be violative of the Constitutional mandate of Article 14. He has cited several decisions in that regard to which we shall refer in due course. Counsel has also relied on Clauses 19(c)(i), 27(c) and 31 (d) of the said Conditions of supply. It is also his contention that the said "Conditions of Supply" have no statutory force and those, as contended by Board's counsel, Shri K.N. Gupta, are not to be regarded as "Regulations" framed under Section 79(j) of the Electricity (Supply) Act, 1948, for short, 1948 Act. It is also his contention that in any case, even if those are regarded as such "Regulations", they cannot prevail against section 24 of 1910 act which carries in it the Constitutional mandate of Article 21. Clause 31 (e) being a form of subordinate legislation is implicitly subjected also to legislative mandate of Section 24(1).

    8. Whatever worth they are, if the said "Conditions" contain any provisions which impair or taint the Board's stand, they cannot be ignored because on same provisions, Shri Chitaley has relied. Clause 19(c)(i) contemplates, "Payment for electricity supplied shall be made by consumers according to readings of meters or apparatus" and as per Sub-clause (iii), if the meter "ceases to function or becomes incorrect, the electricity supplied to the consumer during the period in which the said meter ceased to function or became defective shall be determined by taking average of the electricity supplied during the preceding three months in which the said meter had not ceased to function or was not defective". Clause 27(c) provides that if the consumer fails to pay the bill sent to him within the period allowed for payment, the Board shall give to such consumer seven clear days' notice of intention to discontinue the supply of electrical energy and on the expiry of such period if frill payment has not been Made, the Board shall discontinue the supply .....". We extract now Sub-clauses (d) and (e) of Clause 31 :-

    "(d) If energy supplied for a specific purpose under a particular tariff is used without the board's knowledge and/or consent for a different purpose not contemplated in the contract for supply and for which higher tariff is applicable than the electricity consumption bills already rendered for the service shall be revised charging the appropriate higher tariff for the previous six months from the date of detection of misuse unless in the opinion of the Engineer there are convincing reasons for adopting a different period. The imposition of this higher rate will not relieve the consumer from any proceedings and penalties which may be imposed under law.

    (e) Where any consumer is detected in the commission of any malpractice with reference to his use of electrical energy including unauthorised alterations to installations, unauthorised extension and use of devices to commit theft of electrical energy the Board may, without prejudice to its other rights, cause the consumer's supply to be for with disconnected. The supply may be restored in the discretion of the Divisional Engineer of the Board if the consumer forthwith compensates the Board and pays all dues as per bill and takes such other actions as he may be directed by the Divisional Engineer of the Board to take in this connection".

    9. In the instant case, admittedly, as per the "assessment bills", retrospectively liability is saddled for three years on pure surmises and conjectures and without any valid basis ignoring obviously provisions of Clause 19(c)(iii) and also of Clause 31(d). What is, however, undisputed is that no previous notice in any form of any sort, as statutorily contemplated under Section 24 or even under Clause 27(b), aforesaid, was served on the company and in an almost arbitrary manner, the supply of electricity to Company's factory was disconnected. A bare perusal of the aforesaid two "assessment bills" is sufficient to convince a layman even of total lack of any reasonable basis for the same, much less, the same conforming in any manner to the legal basis herein pointed out. In one case, consumption is presumed at 29,004 units per month (for 90 H.P. meter) and in the other case, at 25,782 units per month (for 80 H.P. meter), in both cases, reckoned for the period August, 1988 to July, 1991. That socalled "best judgment assessment" is supported in the return on the ground that consumption was not reckoned for running of the electric meters for 24 hours, but only for 15 hours a day while admitting still that for 365 days of the year, consumption was calculated. The illogical and wholly arbitrary basis of assessment is so apparent that one living in a fools' paradise may only be convinced of its validity.

    10. Apart from the fact that retrospective assessment can date back only to six months, if the guideline of Clause 31 (d) is to be followed, what is obvious is that the Labour Law Regulations contemplating fixed working hours and holidays (Sunday in any case) are totally ignored even if one overlooks the apparent fallacy of the factory being allowed to run to full capacity despite the industry being a regulated industry in respect of supply of raw materials coming from the State Government. In any case, even if Clause 31 (e) is put forth as justification for the action of disconnection, the said two "assessment bills" can hardly provide basis for the action taken. Such a bill as contemplated in Clause 31 (e) is to conform to the guidelines contemplated under Sub-clause (d) and also of 19(c), Sub-clauses (i) and (iii). Reliance, indeed, we consider appropriate of Shri Chitaley on this Court's decision in Gajendra Singh v. M.P.E.B., 1992 (II) MPWN 171, wherein the vies taken was that "a vague bill giving no basis for the demand is not a bill of which liability can be saddled on the consumer". Obviously, therefore, there was no scope even for power under Clause 31(e) to be invoked for the action taken.

    11. It is true, as Shri Gupta has contended, Clause 31 (e) does not provide expressly for any prior notice or hearing to the consumer for the proposed action, but in our view, principles of natural justice spring into action in such a case and the Rule audi alterant pattern is to be read into Clause (e), for the additional reason that under our Constitutional dispensation use of both executive or statutory power is tampered by requirements of Article 21 in a case of any person being deprived of essential services like water, electricity, telephone etc. Right to livelihood whether of a single person or of a group of persons and effect denial thereof on the society at large, in such cases, is likely to be involved and Olga Tellis, AIR 1986 SC 180, has now settled the law that such a right is embraced by Article 21 of the Constitution. Earlier also, in Board of Trustees v. Dilip Kumar, AIR 1983 SC 109, the Apex Court took the view that Article 21 has created a protective shield against denial to any person of finer graces of human civilisation. Support for this view, we find in a recent decision of the Apex Court in Municipal Corporation of Delhi v. M/s. Ajanta Iron and Steel Company (Pvt.) Ltd., AIR 1990 SC 882, which, on facts, is similar to the instant case in that allegation of theft of electricity was made even in that case. Their Lordships held that prior notice of disconnection in such a case is a mandatory requirement because the allegation of theft had to be dealt with separately and unless and until the allegation has been proved, the consumer is not supposed to suffer advance penalty for a Criminal activity. In Kuldeep Singh Dhingra v. Municipal Corporation of Delhi, AIR 1992 Delhi 228, their Lordships' decision is invoked in a similar case to hold that pre-decisional hearing in such a case was mandatory. In Southern Steelmet and Alloys Ltd. v. Karnataka Electricity Board, AIR 1991 Karnataka 267, also, a case of theft of electricity, the requirement of following principles of natural justice is stressed and the relevant Regulation enacted in that case under section 79 of 1948 act was so construed though the provision was barren.

    12. We agree with Shri Gupta that the ratios of the two decisions, in M.P.E.B. v. Basantibai, AIR 1988 SC 71, or in Regal Theatre v. M.P.E.B., AIR 1987 MP 276, are not applicable to the instant case. As held by the Apex Court, Section 26(6) does not deal with the case of any dispute' 'regarding the commission of fraud in tampering with the meter and breaking the body seal is outside the ambit of Section 26(6)" and the dispute need not be referred to the Electrical Inspector. Even so, we have found no justification of the respondent, as held above, for their action impugned herein, invoking Clause 31 (e) itself. Reliance Shri Gupta placed on a D.B. decision of Allahabad High Court in Aditya Rotor Spin (P.) Ltd. v. U. P. State Electricity Board, AIR 1991 Allahabad 196, to submit that Regulation 22 interpreted therein upholding the Constitutional vires thereof, is similar to Clause 31 (e) and, therefore, the Company in the instant case cannot impugn Board's action of disconnection of supply of energy to it without notice or hearing. To that contention, as is rightly submitted by Shri Chitaley, there are three answers. One, the question only of vires of a Regulation was considered and not of its scope in that case; two, that was a case of a "Regulation" enacted under section 79 of 1948 act while in this case it has not been established that Clause 31 (e) is so enacted; three, the decision does not take note of Apex Court's view expressed in Ajanta Iron and Steel Co.'s case (supra). Shri Chitaley further submitted, relying on Indian Aluminium Co.'s case, AIR 1975 SC 1967, that Section 79(j) of 1948 Act does not admit within its ambit power to evolve such "principles" as may impair consumer's statutory right secured otherwise. He submitted, therefore, that Clause 31(e) cannot stand alone as a valid provision even if that is accepted as a "Regulation" and only by harmonising that with Sub-clause (d) and reading that along with Clauses 27(c) and 19(c) and interpolating therein the requirement of natural justice, that can be saved. We have no hesitation to accept that contention.

    13. Having found both "assessment bills" aforesaid to be illegal and unconstitutional, it is necessary now to see if there is any justification for the status quo to, be allowed to continue maintaining action of the Board of discontinuing supply of electricity to the Company's factory on the ground that the demand raised there under or the arrears claimed in the bill for November, 1992 (Annexure P/39) is not paid. We have already noticed that in the return, the averments made in regard to that claim in I.A. No. VI/92 by the Company are not contested. It appears, as stated in para 6 of the said application, the Board perhaps wanted to penalise once again the Company on the assumption of its stealing electricity because in November, 1992, only 501 units were shown consumed. No reasons are given in Annexure P/41 (Board's letter to the Company) for claiming the arrears and to substantiate validity of that claim. On the other hand, details are given in para 5 of the application of the payments made for the preceding months of August, 1992 to October, 1992 in the sum of Rs. 6,552.00, Rs. 4,536.00 and Rs. 4,508.00 respectively, the Board arbitrarily refused to accept payment made of Rs. 6,940/- by Bank draft, Annexure P/40 and on that pretext, it acted arbitrarily in discontinuing the supply of electricty to Company's factory especially when the Company had already made payment of Rs. 50,000/-on ad hoc basis, under this Court's order, and the question of validity of the so-called' 'best judgment assessment bills" was pending disposal in this matter.

    14. In this context, at the risk of repetition, we may state that we have sustained validity of the apparently unconstitutional Clause 31(e) by reading down the provision and interpolating therein the requirement of natural justice and subjecting the same additionally to the guidelines contemplated under the preceding Clause (d). Section 39 of 1910 Act makes "theft" of electricity an offence to be tried judicially and punished in terms thereof as mandated by Articles 20(1) and 21 of the constitution and any penal action taken before the trial may be liable to be challenged under Article 14 of the Constitution. Before the allegation of theft is judicially examined and offence is found established, if any action in terms of Clause 31(3) is taken, that will fall foul of the Constitutional mandate as the arbitrary action of disconnection may render unemployed workers in the factory (sometime in hundreds, as in this case) infringing thereby their Constitutionally protected right of livelihood.)

    15. For all the aforesaid reasons, we have no hesitation to quash the two "assessment bills" for Rs.7,24,137.83 and Rs.6,61,256.61, raised in respect to Service Connection Nos. 2556/1156 and 2824/1158 respectively and to quash also the imaginary and unsubstantiated arrears of Rs. 26,459/-claimed in the Bill, Annexure P/39. We hold the action of the Board discontinuing supply of electricity to the factory of the Company in respect of the existing Service Connection No. 2556/1156, to be illegal and unconstitutional. Accordingly, we direct the respondent Board to restore within 24 hours the Service Connection No. 2556/1156 of the Company to enable it to resume production in the factory. However, we make it clear that with respect to the claim of the Board against electricity stolen by the company, it shall be open to the Board to raise legal and appropriate demand in a legal and lawful manner, but, as observed by the Apex Court in Ajanta Iron and Steel Co.'s case (supra), it shall be possible for them to do so only when theft is judicially established on the same being held proved in the criminal proceeding which the Board instituted against the Company. Indeed, it shall, however, be open to the board to act in the meantime, within two weeks, in accordance with Clause 31 (d) if so advised, subject to the right of the petitioner Company to challenge the same. Accordingly, till then, the Company shall not claim refund of Rs. 50,000/- deposited under this Court's order, but the admitted liability with respect to Rs. 6,940/- shall be adjusted immediately by the Board against the said deposit and for all future dues also for the energy supplied on restoration of the Service Connection, the Company shall be liable for regular payment on submission by respondent Board of bills drawn in accordance with law.

    16. In the result, the petition succeeds and is allowed in terms of the above directions. We leave the parties to bear their own costs.