  • 3-4-68. Art. 11 of the Limitation Act 1963 (old Art. 311
  • provisions of Section 78B of the Railways Act 1890
  • S. 66. Proviso (2) of the Evidence Act
  • Art. 31 of the Limitation Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Judges
Acts
  • 3-4-68. Art. 11 of the Limitation Act 1963 (old Art. 311
  • provisions of Section 78B of the Railways Act 1890
  • S. 66. Proviso (2) of the Evidence Act
  • Art. 31 of the Limitation Act
Smart Summary

Structured Summary of the Provided Opinion

Factual and Procedural Background

The plaintiff sued the defendant (a railway administration) for recovery of compensation for non-delivery of two consignments of galvanized wire netting sent under two railway receipts:

  • First consignment: 6 rolls (19,200 sq. ft.) despatched from Duttapukur on 28-6-1964 under R/R No. A 116018 to Mal Junction via N.F. Railway for delivery to the Sub-Divisional Officer (P.W.D), Mal Construction Sub-division. A claim for Rs. 7,207.68 was lodged on 4-12-1964 for non-delivery, but the defendant did not pay.
  • Second consignment: 6 rolls (19,200 sq. ft.) despatched from Duttapukur on 13-6-1966 under R/R No. 049390 to Dalgaon for delivery to the Sub-Divisional Officer (P.W.D), Gairkata Sub-division. A claim for Rs. 7,221.12 was lodged on 14-11-1966 for non-delivery, but the defendant did not pay.

In its written statement the defendant asserted (inter alia) that the first consignment had been delivered at Naerakata on 22-7-1964 (with a receipt dated 25-7-1964) and that the plaintiff had been informed by letter dated 20-8-1966. For the second consignment the defendant disputed the plaintiff's title and quantity/value, alleged non-compliance with Section 78B of the Railways Act 1890 and pleaded limitation.

The court recorded seven specific issues for decision. The plaintiff examined two witnesses; the defendant led no oral evidence. The court considered documentary exhibits including the railway receipts, claim correspondence and other letters referenced in the pleadings and affidavits.

Legal Issues Presented

  1. Is the plaintiff owner of the goods covered by Railway Receipt No. A 116018 dated 28th June 1964 and Railway Receipt No. A 049390 dated 13th June 1966 as alleged in the plaint?
  2. Did the defendant take all due and reasonable care and precaution for the carriage and the transit of consignments in question as a man of ordinary prudence would take under similar circumstances (as alleged in paras 6 and 10 of the written statement)?
  3. Did the defendant deliver the goods covered by Railway receipts dated 28th June 1964 and 13th June 1966 to the consignee, Sub-Divisional Officer, P.W.D, Mal Construction Sub-Division?
  4. (a) Did the plaintiff serve notice under S. 80 of the Civil P.C dated 7th Feb. 1568 to the General Manager, Eastern Railway Administration as well as the General Manager, N.F. Railway claiming Rs. 14,428.80 as alleged in para 10 of the plaint?
  5. (b) Were the notices under S. 80 of Civil P.C legal or valid?
  6. Is the suit barred by limitation?
  7. Is the suit not maintainable by reason of non-compliance with the provisions of S. 78B of the Railways Act 1890?
  8. To what relief, if any, is the plaintiff entitled?

Arguments of the Parties

Plaintiff's Arguments

  • The plaintiff asserted ownership of the consignments and that both consignments were despatched by the plaintiff from Duttapukur to the respective consignees under the stated R/Rs.
  • Both consignments were not delivered at destination; the plaintiff lodged claims for compensation (Ext. E for the first consignment and Ext. I for the second) and pursued correspondence with the railway and the consignee.
  • The plaintiff served notices required under S. 78B of the Railways Act in respect of both claims and served notices under S. 80 of the Civil Procedure Code on the General Managers before instituting suit.
  • For the second consignment the plaintiff relied on documentary and oral evidence (including communications from the consignee) to show a claim had been lodged on behalf of the plaintiff.

Defendant's Arguments

  • The defendant alleged delivery of the first consignment at Naerakata on 22-7-1964 against a receipt dated 25-7-1964 and that the plaintiff was informed on 20-8-1966.
  • For the second consignment the defendant disputed the plaintiff's title to the goods and the quantity/valuation, and contended non-compliance with S. 78B of the Railways Act 1890.
  • The defendant pleaded that the suit (or at least the claim in respect of the first consignment) was barred by limitation.
  • The defendant argued that the railway receipts had been endorsed in favour of the consignee and that the consignee (not the plaintiff) had the right to sue; alternatively that plaintiff was not the proper party.
  • The defendant objected to certain copies of documents tendered by the plaintiff on grounds of secondary evidence or because originals were in the defendant's possession.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
AIR 1961 Cal 359 Rule that failure to put essential and material parts of one's case to an opponent's witness in cross-examination amounts to acceptance of that witness's testimony on those points; cross-examination obligation to avoid surprise and injustice. The court applied this principle to hold that the defendant, having failed to cross-examine the plaintiff's witness Kundu on whether the consignee had lodged a claim on behalf of the plaintiff, must be taken to have accepted the plaintiff's account and could not later deny that a claim was made by/for the plaintiff in respect of the second consignment.
AIR 1964 Cal 290 Where action is founded on contract, the right to sue belongs to the person who entered into the contract (ordinarily the consignor); endorsement/delivery of a railway receipt does not transfer the contract or the right to sue on the contract to the endorsee. The court relied on this authority to reject the defendant's contention that only the consignee (endorsee) could sue. The court held the plaintiff, being a party to the contracts evidenced by the R/Rs, was entitled to sue for breach of those contracts.
AIR 1966 SC 395 Principle that an endorsee of a railway receipt cannot sue the railway on the contract of carriage if not party to the contract; endorsee has rights of delivery, and as owner may sue for conversion or negligence, but not on the contract. The court cited this Supreme Court authority to support the proposition that endorsement does not transfer the contractual right to sue the railway; this reinforced the court's conclusion that the plaintiff could maintain the action.
AIR 1965 SC 195 Supportive authority on the limits of rights of an endorsee of a railway receipt in relation to suing on the contract of carriage. This case was cited as further support for the court's view that mere endorsement does not transfer the contract and the endorsee cannot sue on the contract.
AIR 1973 Cal 74 Supportive Calcutta High Court authority consistent with the principle that an endorsee does not acquire the right to sue on the contract of carriage merely by endorsement of railway receipt. The court cited this as additional support for its conclusion regarding who may sue on the contract of carriage.
AIR 1962 SC 1716 Rule on limitation: time runs from the date "when the goods ought to have been delivered"; the clock starts after a reasonable period for delivery has elapsed; reasonable time depends on facts and circumstances and is generally the normal period of transit between stations unless special circumstances appear. The court applied this principle to determine that, in the absence of special circumstances, the reasonable time for delivery from Duttapukur to Mal Junction was about 6–10 days and therefore the claim for the first consignment (despatched 28-6-64) was barred by limitation when suit was filed on 3-4-68.
AIR 1975 Cal 417 Calcutta High Court authority relied on the limitation point (supporting the defendant's contention on limitation). The court noted this authority as reinforcing the conclusion that the first consignment claim was time-barred.

Court's Reasoning and Analysis

The court proceeded by examining the pleaded issues, documentary exhibits and the oral testimony given by the plaintiff's two witnesses. The analysis proceeded in the following steps, strictly following the material in the opinion:

  1. Burden of proof and delivery: The court emphasized that the onus to prove safe delivery at the destination lay on the defendant. For both consignments the defendant produced no oral evidence to explain its handling of the goods in transit. In respect of the first consignment the defendant asserted delivery at Naerakata but did not discharge the onus; the court therefore accepted the plaintiff's position on non-delivery.
  2. Evidentiary rulings and claims: For the second consignment, the defendant originally objected to use of a copy of the R/R and to other secondary evidence; the court overruled these objections because the original documents were in the defendant's possession and the copy was admissible under S.66 proviso (2) of the Evidence Act. The court further held that correspondence and communications from the consignee (including reminders and a claim lodged with Chief Commercial Manager) supported the plaintiff's case that a claim was in fact made on behalf of the plaintiff.
  3. Effect of failure to cross-examine: Applying the principle from AIR 1961 Cal 359, the court held that because the defendant did not cross-examine the plaintiff's witness Kundu on whether the consignee lodged a claim on behalf of the plaintiff, the defendant had effectively accepted the witness's testimony on that point and could not later dispute it.
  4. Notices under S. 78B and S. 80: The court found that valid notices under Section 78B of the Railways Act were given in respect of both claims, and that service of notice on one railway administration was sufficient under S.78B. The court also recorded that notices under S.80 Civil Procedure Code were served upon both General Managers before institution of suit and were received; though validity of those notices had been challenged in the written statement, the defendant did not press that challenge at hearing.
  5. Ownership and right to sue: Although the defendant disputed the plaintiff's ownership, the court accepted the plaintiff's witnesses' testimony that the plaintiff owned the goods. More importantly, relying on AIR 1964 Cal 290 and related authorities, the court held that where an action is founded on contract the right to sue belongs to the party who entered into the contract (ordinarily the consignor). The court therefore rejected the argument that endorsement of the R/R to the consignee precluded the plaintiff from suing on the contract of carriage.
  6. Limitation: The court applied the Supreme Court's guidance (AIR 1962 SC 1716) that limitation runs from when the goods ought to have been delivered, i.e., after a reasonable transit period. Evidence showed normal transit from Duttapukur to Mal Junction would be about 6–10 days. No special circumstances were shown to extend that period. Given the first consignment was despatched on 28-6-64 and suit instituted on 3-4-68, the claim in respect of the first consignment was time-barred. The claim in respect of the second consignment was not barred.
  7. Issues of price and quantum: The court found no dispute as to the price of the second consignment and no substantive argument on that point; accordingly the court accepted the stated amount for the second consignment (Rs. 7,221.12).
  8. Conclusion on issues: The court answered the enumerated issues by (a) holding the plaintiff was the consignor and entitled to sue; (b) finding the defendant failed to discharge the onus regarding due care and delivery; (c) holding notices under S.78B and S.80 were given and valid; and (d) finding the first consignment claim was barred by limitation while the second was not.

Holding and Implications

Holding:

Suit decreed; decree for Rs. 7,221.12 in favour of the plaintiff against the defendant.

The decree carries interim interest at the rate of 9% per annum on the awarded sum and interest on the judgment at the rate of 6% per annum. The plaintiff is also awarded costs (certificate for two counsel). The defendant was directed to pay the decree amount within three months of the date of the order, failing which the plaintiff may execute the decree.

Direct consequences for the parties:

  • The plaintiff recovers Rs. 7,221.12 (plus the stated interest and costs) for the second consignment.
  • The plaintiff's claim in respect of the first consignment (despatched 28-6-1964) was held to be barred by limitation and therefore not recoverable in this suit.
  • The defendant's pleas that the plaintiff lacked title or that endorsement to the consignee transferred the right to sue were rejected; the plaintiff as consignor could maintain the action on the contract of carriage.

Broader implications: The opinion applies established authorities on (a) the consequences of failing to cross-examine on material points, (b) the rights of a consignor to sue on a contract of carriage notwithstanding endorsement of a railway receipt, and (c) the computation of limitation for non-delivery claims. The judgment does not purport to lay down a novel legal principle beyond application of those authorities to the facts; no new precedent is stated in the provided opinion.

    Traders Syndicate v. Union Of India

    1. The plaintiff sued the defendant on two contracts of carriage of goods for recovery of compensation for non-delivery of the consignments.

    2. On 28-6-64 the plaintiff at Duttapukur delivered to the Eastern Railway 6 rolls of galvanised wire netting 19.200 sq. ft. for carrying the same a Railway's risk to Mal junction through N.F Rly. and the defendant issued R/R No. A 116018 dated 28-6-64 in respect to the same. The goods were to be delivered to the consignee. Sub-Divisional Officer (P.W.D) Mal Construction Sub-division. The defendant failed to deliver the goods at the destination. A claim was duly lodged with the Chief Commercial Superintendent. (Claim) N.F Railway to the extent of Rs. 7207.68 but the defendant failed to pay the said sum or any part thereof. The defendant in the written statement alleged that these goods were duly delivered at Naerakata on 22-7-64 against a clear receipt dated 25-7-64 and the plaintiff was duly informed about the same by letter dated 20-8-66.

    3. On 13-6-66, the plaintiff again delivered to the Eastern Railway Administration at Duttapukur another 6 rolls of galvanized wire netting containing 19.200 sq. ft. valued at Rs. 7221.12 to be delivered at Dalgaon to the consignee Sub-divisional Officer (P.W.D) Gairkata Sub-division under relevant R/R No. 049390 dated 13-6-66. The defendant failed to deliver the goods and the plaintiff duly lodged a claim for the said sum with the Chief Commercial Manager (Claim) N.F Rly. but the defendant failed and neglected to pay the said amount or any portion thereof. In the written statement the defendant disputed the plaintiff's title over the said goods and also the quantity or value thereof. It was alleged that the suit was bad for non-compliance of the provisions of Section 78B of the Railways Act 1890 and the plaintiff's claim was barred by limitation. The following issues were raised for decision:

    1. Is the plaintiff owner of the goods covered by Railway Receipt No. A 116018 dated 28th June 1964 and Railway Receipt No. A 049390 dated 13th June 1966 as alleged in the plaint?

    2. Did the defendant take all due and reasonable care and precaution for the carriage and the transit of consignments in question as a man of ordinary prudence would take under the similar circumstances for the same as alleged in paras 6 and 10 of the written statement?

    3. Did the defendant deliver the goods covered by Railway receipts dated 28th June 1964 and 13th June 1966 to the consignee, Sub-Divisional Officer, P.W.D, Mal Construction Sub-Division?

    4. (a) Did the plaintiff serve notice under S. 80 of the Civil P.C dated 7th Feb. 1568 to the General Manager. Eastern Railway Administration as well as the General Manager. N.F Railway claiming Rs. 14,428.80 as alleged in para 10 of the plaint?

    (b) Were the notices under S. 80 of Civil P.C legal or valid?

    5. Is the suit barred by limitation?

    6. Is the suit not maintainable by reason of non-compliance with the previsions of S. 78B of the Railways Act 1890?

    7. To what relief, if any is the plaintiff entitled?

    4. The plaintiff examined two witnesses. The defendant did not adduce any oral evidence. The booking of 6 rolls of galvanized wire netting on 28th June 1964 is proved by R/R No. A 116018 being Ext. ‘A’ in the suit which is a common document. None on behalf of the defendant came forward to tell the court how the defendant had dealt, with these goods during transit. According to the plaintiff those goods were not delivered at the destination. It appears from Ext. ‘E’ dated 4-12-64 that the plaintiff had lodged a claim with the Chief Commercial Superintendent (Claims) of N.F Railway to the extent of Rs. 7,207.68 for non-delivery of the goods covered by R/R No. A 116018 and a copy thereof was sent to the Sub-divisional Officer. P.W.D, Mal Construction, Sub-division the consignee thereof. The onus to prove safe delivery of the goods at the destination is on the defendant, but the defendant failed to discharge this onus.

    5. Another 6 rolls of galvanized wire netting containing 19,200 sq. ft. were despatched by the plaintiff from Duttapukur Railway Station to Dalgaon on 13-6-66 to be delivered to the consignee the Sub-divisional Officer (P.W.D). Gairkata sub-division. The relevant R/R No. 049390 is admitted in para 7 of the written statement. A copy of this R/R was sought to be tendered by the plaintiff which was objected to by the defendant's counsel. The defendant disclosed the original R/R being item No. 5 of its affidavit-of-document affirmed on 19-8-75 by one Radhika Raman Ghosal whereas the plaintiff disclosed a copy thereof. This is a common document being P.D 15.DD 5 and the original of which is admittedly in possession of the defendant. Hence the objection is overruled. This document is Ext. ‘H’ in the suit. The despatch of the goods is further proved by the forwarding note No. 559 dated 29-4-66 being Ext. 7. By letter dated 19-8-66 the consignee informed the defendant that the goods did not arrive (Ext. EE). A reminder was sent to the defendant about non-delivery on 11-11-66 (Ext. FF). According to the plaintiff, the defendant failed to deliver the goods. The defendant also did not prove delivery. It appears that the consignee lodged a claim with the Chief Commercial Manager (Claims) N.F Rly. for compensation of Rs. 7,221.12 and forwarded a copy thereof to the plaintiff. Objection was taken by the defendant's counsel against tendering this copy of the claim on the around that it was a secondary evidence. The original claim is in possession of the defendant. The copy will be admissible under S. 66. Proviso (2) of the Evidence Act without service of notice to produce on the defendant. Hence the objection cannot be sustained. This claim in respect of the second consignment is Ext. ‘I’ in the suit. According to the plaintiff this claim was made by the consignee on behalf of the plaintiff at plaintiff's request and direction (Kundu Qs 90-91, 93-97 and 159-162). From the correspondence disclosed it appears that the consignee kept on informing the plaintiff about the developments to the claim case (Exts. CC and II). Finally, having failed to realise the compensation money, the consignee asked the plaintiff to take step in the matter directly (Ext. HH). There is no cross-examination of the plaintiff's witness on his evidence on this point. No suggestion was put to Kundu that the claim was not lodged on behalf of the plaintiff which was a must. Without such a suggestion, the defendant's counsel was not entitled to argue that no claim in respect of the second consignment was made by the plaintiff and Kundu's evidence on this point should be rejected. AIR 1961 Cal 359 is an authority on this point. In para 10 of this report at p. 362 it was held:—

    “Whenever the opponent has declined to avail himself of the opportunity to put his essential and material case in cross-examination, it must follow that he believed that the testimony given could not be disputed at all. It is wrong to think that, this is merely a technical rule of evidence. It is a rule of essential justice. It serves to prevent surprise at trial and miscarriage of justice, because it gives notice to the other side of the actual case that is going to be made when the turn of the party on whose behalf the cross-examination is being made comes to give and lead evidence by producing witness. It has been stated on high authority of the House of Lords that this much a counsel is bound to do when cross-examining that he must put to each of his opponent's witness in turn, so much of his own case as concerns that, particular witness or in which that witness has any share. If he asks no question with regard to this, then he must be taken to accept the plaintiff's account in its entirety.”

    6. If the defendant wanted to argue that the plaintiff did not put forward any claim in respect of the 2nd consignment and there was no notice under S. 78B of the Act in respect of this claim, it was the bounden duty of the defendant's counsel to cross-examine Kundu on this point and put his case to him that the plaintiff never made any claim in respect, of the second consignment. In absence of such cross-examination and suggestion I am bound to hold that the defendant had accepted plaintiff's case on this point in its entirety.

    7. The first, consignment is dated 28-6-64 and the claim in respect thereof was lodged by the plaintiff on 4-12-64 (Ext. E). The second consignment is dt. 13-6-66 and the claim for non-delivery of these goods was lodged on 14-11-66 (Ext. I). In the premises I hold that due and valid notices under S. 78B of the Railways Act were given to the defendant in respect of both the claims. Service of such a notice on one of the two Railway administrations is sufficient under Section 78B of the Act.

    8. Before institution of the suit, the plaintiff served two notices under S. 80 of the Civil P.C on both the General Managers of Eastern Railway and N.F Rly. which were duly received by the defendant. Although the defendant challenged the validity of the said two notices in the written statement and raised an issue thereon, the same was not pressed at the time of hearing.

    9. In the plaint, the plaintiff claimed to be the owner of the goods consigned but the defendant disputed the same in the written statement. Both the plaintiff's witnesses Kundu and Bose in their respective oral testimony said that the goods belonged to the plaintiff. No documentary evidence on this point was disclosed by the plaintiff. The defendant's counsel submitted that the plaintiff was not the owner of the said goods and as such it could not institute the suit. He further submitted that the relevant R/Rs were endorsed in favour of the consignee and it is the consignee who had the right to bring the action. I am unable to accept these submissions of the defendant's counsel. The plaintiff was a party to both the contracts of carriage evidenced by the two R/Rs and it was the plaintiff who was entitled to sue the defendant for compensation for committing breaches of these contracts by non-delivery of the goods. AIR 1964 Cal 290 is an authority in this point. It was held in para 40(i)(a):—

    “Where the action is founded on contract, the right to maintain an action on the contract belongs to the person who entered into the contract. Ordinarily that person is the consignor.”

    10. Therefore the question whether the plaintiff was the owner of the goods or not was not relevant for the purpose of this suit. I do not think there is any substance in the argument of the defendant's counsel that on account of the endorsement of the R/Rs in favour of the consignee, it is the consignee who has the right to bring the action. AIR 1964 Cal 290 also lays down that mere endorsement or delivery of R/R does not transfer the contract contained in or evidenced by the railway receipt to the transferee. An endorsee of a railway receipt cannot sue the railway on the contract, of carriage not being a party to the contract even if the property in the goods covered by the R/R has been transferred to the endorsee. In such a case, the endorsee, as the owner of the goods, can sue the railway in his own name for conversion or negligence only. A mere endorsee, whether he is the consignee, or someone else, only has the right to receive delivery of the goods but has no right to bring an action on the contract of carriage. AIR 1966 SC 395. AIR 1965 SC 195 and AIR 1973 Cal 74 also support this view. I however, accept the evidence of the plaintiff's witnesses regarding the plaintiff's ownership over the goods consigned. There is no reason for disbelieving them on this point.

    11. It was submitted by the defendant's counsel that so far as the first consignment is concerned, the plaintiff's claim is barred by limitation. The goods were despatched on 28-6-64 and suit was instituted on 3-4-68. Art. 11 of the Limitation Act 1963 (old Art. 311 will govern the case. On behalf of the defendant reliance was placed on AIR 1962 SC 1716. In this case, the Supreme Court while dealing with the old Art. 31 of the Limitation Act held that time would run from the date “when the goods ought to have been delivered” and could not be postponed on the basis of subsequent conduct of the parties. “When the goods ought to have been delivered” will mean that time would begin to run after a reasonable period has elapsed on the expiry of which the goods should have been or ought to have been delivered. What will be the reasonable time will depend upon the facts and circumstances of each case. If the correspondence disclosed any special circumstances for delay or threw light on the question of determining the reasonable time for the carriage of the goods from the place of despatch to the place of destination, then it would be open to the court to take into account the facts mentioned in the correspondence. The Supreme Court further held in para 12 at page 1721:

    “……… in the absence of any special circumstance the reasonable time would practically be the same between two stations as would normally or usually or ordinarily be taken for the carriage of goods from the one station to the other.”

    12. In the present case no special circumstances appear from the correspondence disclosed in the suit or from the oral testimony of the plaintiff's witnesses. It was admitted by the witness Bose that normal time taken for carriage of goods from Duttapukur to Mal Junction would be about 6 to 10 days (Bose Qs. 234, 237). In absence of any special circumstances the normal time taken for delivery of goods despatched from Duttapukur on 28-6-64 to Mal Junction cannot be more than the middle of July 1964. The suit was instituted on 3-4-68, long after expiry of three years from the time when delivery of goods ought to have been given. The plaintiff's claim in respect of the first consignment is therefore, barred by limitation. I am also fortified on this point by AIR 1975 Cal 417 relied on the defendant's counsel. There is no question of limitation in respect of the second consignment.

    13. So far as the price of the goods under second consignment is concerned, no issue has been raised, no argument advanced and there is no dispute about the same. The issues are, therefore, answered as follows:—

    Issue No. 1— Yes. Issues Nos. 2 & 3— The defendant did not adduce any evidence and failed to discharge the onus. Issue No. 4(a)— Yes. Issue No. 4(b)— Yes. Issue No. 5— Claim in respect of the first consignment dated 28-6-64 is barred by limitation but not the claim in respect of consignment dated 13-6-66. Issue No. 6— The notice under S. 78-B was duly served and the suit is maintainable.

    14. In the premises, there will be a decree for Rs. 7,221.12 in favour of the plaintiff against the defendant. The plaintiff will be entitled to interim interest on the aforesaid sum at the rate of 9% per annum, interest on judgment at the rate of 6% per annum and costs. Certified for two counsel. The defendant is directed to pay the said sum within 3 months from date, in default the plaintiff will be entitled to execute this decree.

    Suit decreed.

    Use AI to get other relevant cases.

    Comments

    Traders Syndicate v. Union Of India
    (Jul 21, 1982)