AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Smart Summary

Factual and Procedural Background

This appeal under section 37 of the Arbitration and Conciliation Act, 1996 challenges the order of 24th November 2005, whereby the learned Single Judge dismissed the section 34 petition (OMP 431 of 2005) that sought interference with the arbitral award dated 20th August 2005, as modified on 3rd October 2005. The dispute arose from a contract awarded by the appellant to the respondent for a four-laning project of a segment of National Highway 31 in West Bengal. The respondent commenced work using aggregates sourced from Balason/Matigara river banks, which the appellant opposed, directing the use of aggregates from Pakur instead. The respondent claimed compensation for the extra lead cost incurred due to this change, leading to arbitration and subsequent award in favor of the respondent’s claim for bituminous work but rejecting the claim for concrete work. The appellant challenged the award, contending it was in excess of the contract and raised issues regarding the interpretation of contract clauses and the validity of test reports relied upon by the arbitral tribunal.

Legal Issues Presented

  1. Whether the arbitral award was in excess of the contract awarded to the respondent under the Arbitration and Conciliation Act, 1996.
  2. Whether the court exercising jurisdiction under section 34 of the Act can interfere with the arbitral tribunal’s interpretation of contract clauses, particularly clause 507.2.2 of the MoRTH specifications.
  3. Whether the use of aggregates sourced from riverbeds (Balason/Matigara) complied with the contract specifications and whether the respondent was justified in making the bid based on such assumption.
  4. Whether the arbitral tribunal correctly applied the principle of contra proferentem in interpreting the contract.
  5. Whether the award’s reliance on the IIT Kharagpur report and the ASTM:D-3625 test over the specified AASHTO T-182 test was justified.
  6. Whether the claim for extra lead cost related to Bituminous Concrete works was properly entertained by the arbitral tribunal.

Arguments of the Parties

Appellant's Arguments

  • The amended clause 507.2.2 of the MoRTH specifications does not permit the use of aggregates sourced from riverbeds; the word "shingle" is surplusage and should be disregarded.
  • The contra proferentem rule was wrongly applied as the contract was commercial and fully understood by both parties before signing.
  • The respondent’s bid assumption that aggregates from Balason/Matigara could be used is contradicted by its own documents and the physical requirements in Table 500-8 of the MoRTH specifications.
  • The IIT Kharagpur report’s reliance on ASTM:D-3625 test is misplaced since the contract specifies the AASHTO T-182 test.
  • Lime cannot be considered an approved anti-stripping agent as required under the contract.
  • The arbitral tribunal’s allowance of the claim for extra lead cost for Bituminous Concrete works was beyond jurisdiction as no such claim was originally raised.
  • The arbitral tribunal failed to properly appreciate the appellant’s documents, which would have led to a different conclusion.

Respondent's Arguments

  • The arbitral tribunal’s interpretation of clause 507.2.2 of the MoRTH specifications is the only plausible interpretation and correctly allows material sourced from riverbeds.
  • The limited jurisdiction of courts under sections 34 and 37 of the Act precludes interference with the arbitral award.
  • The aggregates from Balason/Matigara comply with the physical requirements under Table 500-8, as supported by the IIT Kharagpur report.
  • The award is justified and no grounds exist for setting it aside.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd., 2003 5 SCC 705 Limited grounds for interference under section 34; courts should not reappraise evidence or sit in appeal over arbitral findings. The court reiterated that a plausible view of the arbitral tribunal should not be interfered with unless there is absurdity or patent illegality.
Food Corporation of India v. Joginderpal Mohinderpal, 1989 2 SCC 347 Supports limited interference under section 34 and principles of arbitration awards. Cited to reinforce the limited scope of judicial interference in arbitral awards.
Gujarat Water Supply and Sewerage Board v. Unique Erectors (Gujarat) (P) Ltd., 1989 1 SCC 532 Principles limiting court interference with arbitral awards. Used to support the principle that courts should not disturb plausible arbitral decisions.
Sudarsan Trading Co. v. The Govt. of Kerala, 1989 2 SCC 38 Limits on judicial review of arbitration awards. Reiterated the principle of limited judicial interference.
Delhi Development Authority v. R.S Sharma and Co., 2008 13 SCC 80 Restatement of grounds for setting aside arbitral awards under section 34. Outlined principles such as award being contrary to substantive law, contract terms, public policy, or patently illegal.
Grid Corporation of Orissa Ltd. v. Balasore Technical School, 2000 9 SCC 552 Supports limited judicial interference in arbitration awards. Relied upon for the principle that courts should not reappreciate evidence.
Northern Railway v. Sarvesh Chopra, 2002 4 SCC 45 Limited scope of judicial review of arbitral awards. Reinforced the principle of limited interference.
State Of Rajasthan v. Nav Bharat Construction Co., 2006 1 SCC 86 Judicial interference only for patent illegality or violation of public policy. Applied to emphasize the court's limited jurisdiction under section 34.
Hindustan Zinc Ltd. v. Friends Coal Carbonisation, 2006 4 SCC 445 Award cannot be contrary to terms of the contract; patent illegality vitiates award. Cited to argue that the award must conform to the contract and illegality must go to the root of the matter.
R.S Builders v. DDA, 2008 2 Arb. L.R 361 Delhi Interpretation of contract clauses and arbitration principles. Relied upon by appellant to challenge plausibility of tribunal’s interpretation.
Tehri Hydro Development Corporation Ltd. v. Lanco Construction Ltd., 2007 3 Arb. L.R 194 Delhi Application of contra proferentem rule in contract interpretation. Invoked to argue against the tribunal’s application of contra proferentem.
Delhi Development Authority v. Sunder Lal Khatri & Sons, 2009 1 Arb. L.R 240 Delhi Insufficiency of reasons in arbitral award as ground for setting aside. Appellant relied on this to contend award lacked sufficient reasoning.
Oil and Natural Gas Corporation Ltd. v. Schlumberger Asia Services Ltd., 2006 3 Arb. L.R 610 Assessment of bid documents and contract assumptions. Used to argue against the respondent’s bid assumptions being justified.

Court's Reasoning and Analysis

The Court began by affirming the limited scope of judicial intervention under section 34 of the Arbitration and Conciliation Act, 1996, emphasizing that courts should not reappraise evidence or substitute their own views for those of the arbitral tribunal unless the award is patently illegal or shocks the conscience. The Court relied heavily on Supreme Court precedents to restate these principles.

Regarding the contract interpretation, the Court found the arbitral tribunal’s view that the word "shingles" in clause 507.2.2 was deliberate and not an erratum to be a plausible interpretation. The tribunal’s application of the contra proferentem rule was held to be within its jurisdiction, given the commercial nature of the contract and the circumstances.

The Court rejected the appellant’s contention that the IIT Kharagpur report’s use of the ASTM:D-3625 test was improper, noting the tribunal’s findings that this test was more stringent than the contractually specified AASHTO T-182 test and that lime could be used as an anti-stripping agent in certain contexts.

The Court declined to reappraise the evidence regarding whether the respondent’s bid assumed use of aggregates from Balason/Matigara, upholding the tribunal’s findings as supported by material.

On the issue of the claim for extra lead cost related to Bituminous Concrete works, the Court found no merit in the appellant’s contention that the award exceeded the claims raised, observing that the contract specifications and award language supported the tribunal’s decision.

Overall, the Court found no grounds to interfere with the arbitral award or the Single Judge’s dismissal of the section 34 petition.

Holding and Implications

The appeal is dismissed as without merits.

The Court upheld the arbitral award and the Single Judge’s order dismissing the section 34 petition, confirming the limited scope of judicial interference under the Arbitration and Conciliation Act, 1996. The decision leaves the arbitral award intact and requires the parties to bear their own costs. No new precedent was set; the ruling reinforces established principles restricting court intervention in arbitration awards absent patent illegality or violation of public policy.

To access the original judgment, please Sign In or Subscribe.

    National Highways Authority Of India v. Lanco Infratech Ltd. .

    Najmi Waziri, J.:— This appeal under section 37 of the Arbitration and Conciliation Act, 1996 (“Act”) challenges the order of 24th November, 2005 (“impugned order”), of the learned Single judge dismissing OMP 431 of 2005 (“section 34 petition”) as not disclosing any ground warranting interference under section 34 of the Act with the award of the Arbitral Tribunal dated 20th August, 2005, as modified by the order dated 3rd October, 2005 (“Award”). The appellant primarily contends that the award was in excess of the contract that came into existence upon the award of tender by the appellant to the respondent for the project of four-laning of KM 476.150 to KM 500.000 of Dhalkola to Islampore sub-section 2 of National Highway 31 in the State of West Bengal.

    2. In the impugned order, the learned Single Judge, while reiterating the dicta of the Supreme Court in Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. . 2003 5 SCC 705., held that the Court, when exercising jurisdiction under section 34 of the Act, ought to not sit in appeal over the findings of the arbitral tribunal. It was reiterated that the Court ought to not reappraise evidence or facts merely because the Court could have come to a different conclusion on the basis of the material available and that short of absurdity or patent illegality, a view of the arbitral tribunal, so long as it is a plausible view, ought to not be interfered with by the Court. The judgements of the Supreme Court in Food Corporation of India v. Joginderpal Mohinderpal . 1989 2 SCC 347., Gujarat Water Supply and Sewerage Board v. Unique Erectors (Gujarat) (P) Ltd. . 1989 1 SCC 532., and Sudarsan Trading Co. v. The Govt. of Kerala . 1989 2 SCC 38., were cited in this regard.

    3. Before an inquiry into the facts in the matter is embarked upon, it would be necessary to clarify that the impugned order is certainly not in error so far as the findings qua limited jurisdiction of the Court under section 34 of the Act is concerned. The issue that a Court exercising jurisdiction under section 34 of the Act has limited grounds on which an award may be interfered with is no longer res integra. A restatement of the law on this subject can be found in the decision of the Supreme Court in Delhi Development Authority v. R.S Sharma and Co. . 2008 13 SCC 80., wherein the Court, relying on the earlier dicta in Grid Corporation of Orissa Ltd. v. Balasore Technical School . 2000 9 SCC 552., Northern Railway v. Sarvesh Chopra . 2002 4 SCC 45., State Of Rajasthan v. Nav Bharat Construction Co. . 2006 1 SCC 86., Hindustan Zinc Ltd. v. Friends Coal Carbonisation . 2006 4 SCC 445., and Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. . 2003 5 SCC 705., held:

    “21. From the above decisions, the following principles emerge:

    (a) An award, which is

    (i) contrary to substantive provisions of law; or

    (ii) the provisions of the Arbitration and Conciliation Act, 1996, or

    (iii) against the terms of the respective contract; or

    (iv) patently illegal; or

    (v) prejudicial to the rights of the parties; is open to interference by the court under Section 34(2) of the Act.

    (b) The award could be set aside if it is contrary to:

    (a) fundamental policy of Indian law; or

    (b) the interest of India; or

    (c) justice or morality.

    (c) The award could also be set aside if it is so unfair and unreasonable that it shocks the conscience of the court.

    (d) It is open to the court to consider whether the award is against the specific terms of contract and if so, interfere with it on the ground that it is patently illegal and opposed to the public policy of India.”

    4. Negatively stated, the Court exercising jurisdiction under section 34 of the Act has certain restrictions placed on it, such as:

    4.1 It ought to not re-appreciate evidence merely to arrive at a different conclusion.11

    4.2 If the interpretation of the contract by the arbitral tribunal — even if it leads to Issues of law — is a plausible interpretation, Court ought to not interfere with it even if it would have come to a different interpretation.12

    4.3 If in arriving at quantum of damages, the arbitral tribunal chose a particular formula, Court ought to not interfere with it simply because another formula could have been chosen, as long as the contract does not provide for any formula and the formula adopted by the arbitrator is an acceptable and reasonable one.13

    4.4 If the Court is to set aside the award as being unfair or unreasonable, the award should be such as to shock the conscience of the court.14

    4.5 Even to hold an award as being opposed to public policy, the illegality must be patent and should go to the very root of the matter it cannot be a frivolous or trivial illegality.15

    5. Shorn of irrelevant details, the case of the appellant commences from the award of the tender in the aforementioned project to the respondent, whose bid was found successful. According to the appellant, the contract came into existence after the respondent was given sufficient opportunities to apprise itself of the particulars of the same and the requirements thereunder. The project, which the respondent was to undertake for the appellant, was to involve certain civil engineering works, which were to be undertaken on the basis of the specification (Third Edition) issued by the Ministry of Surface Transport, (“MoRTH specifications”). It is not in dispute that the amendments and modifications to the MoRTH specifications were made a part of the contract.

    6. The work had indeed commenced; the respondent sought to complete the work using aggregates based on crushed stones sourced from the river banks of Balason/Matigara. This was opposed by the appellant, who directed that only aggregates from Pakur shall be used. Admittedly, neither the contract nor the tender documents provide for aggregates from Pakur being used. Aggregates from Pakur were used by the respondent as directed and the project work was undertaken under protest.

    7. Pakur being admittedly further from the project site than Balason/Matigara, disputes arose as to whether the extra lead involved in procuring the aggregates from Pakur was to be borne by the appellant or the respondent. When the matter was eventually referred to the arbitral tribunal, two claims were raised by the respondent while work was still under way — both in respect of the extra lead — one qua bituminous work and the other qua concrete work.

    8. The respondent's claim contended that its bid was on the basis that aggregates based on crushed stones from Balason/Matigara may be used for the works. It had contended that it was only in view of the appellant's insistence that aggregates from Pakur were used for undertaking the works. It contended that the extra lead involved in procuring the aggregates from Pakur was a cost not contemplated in the bid and not forming a part of the contract, was an expense that ought to be compensated for by the appellant, who insisted on its usage.

    9. The appellant opposed the claims. It contended that its insistence was not to use aggregates from Pakur, but to not use aggregates from Balason/Matigara, which do not meet the MoRTH specifications, it contended that given the fact that the aggregates from Balason/Matigara would not conform to MoRTH specifications, the contention of the respondent that its bid was based on the assumption that aggregates from Balason/Matigara may be used is specious and fit to be disregarded. It contended that there is no basis for claiming extra lead, when the aggregates from Balason/Matigara could never be used without going against the terms of the contract.

    10. Both parties were firstly at issue over whether clause 507.2.2 of the MoRTH specifications, as amended by the parties, could be read to include aggregates based on material sourced from river beds — which the aggregates from crush stones from Balason/Matigara were. While it is doubtless that even the material as specified in clause 507.2.2 were to meet further requirement to be regarded as suitable per the MoRTH specifications — which shall be shortly adverted to — the first of the disputes, essentially, was qua whether such aggregates could be used in the project. The respondent contended in the affirmative, the appellant in the negative. Similar was the issue qua clause 1004 read with clause 1007. The distinction being that clause 507.2.2 is qua bituminous work and clause 1004 read with clause 1007 being qua concrete work.

    11. The parties were thereafter at issue over whether aggregates based on material sourced from Balason/Matigara were compliant with the physical requirements in Table 500-8. The respondent contended in the affirmative, arguing that the report from IIT Kharagpur sets out that the aggregates based on material sourced from Balason/Matigara would meet the physical requirements if lime is used as a filler. The appellant contended in the negative on three bases (a) that its own reports from other laboratories set out that the aggregates based on material sourced from Balason/Matigara do not meet the physical requirement; (b) that the report from IIT Kharagpur allows lime to be used only as a filler, not as an anti-stripping agent; (c) that the findings in the report from IIT Kharagpur were not based on the AASHTO T-182 test, which was specified in the MoRTH specifications and ought to not be considered.

    12. The three member arbitral tribunal passed a majority award in favour of the respondent's first claim and rejected the second claim. The reasoning of the tribunal, as can be ascertained from the Award, is as follows:

    12.1 The dispute turns on whether the respondent is right in assuming that aggregates from Balason/Matigara could be used for bituminous work and concrete work.

    12.2 Clause 507.2.2, even post amendment, retained the word shingles. Shingles are material sourced from riverbeds.

    12.3 The appellant's contention that the word shingles is surplusage and ought to be disregarded cannot be accepted. The appellant's further contention that the intent of the amendment was to ensure that material sourced from riverbeds ought not to be used is not borne out from the contract. This is a fortiori since clause 1007 specifically deletes all references to material sourced from riverbeds.

    12.4 It is a dispute involving interpretation of clause 507.2.2

    12.5 Applying the principle of interpretation of contra proferentem, the existence of the word shingles post amendment, must be interpreted to mean that material sourced from riverbeds may be used for bituminous works, provided they meet the physical requirements in Table 500-8.

    12.6 This is further supported by the existence of the provision in the MoRTH specification that allows usage of anti-stripping agents in hydrophyilic aggregates of approved quality and in suitable doses.

    12.7 The report from IIT Kharagpur indicates that the aggregates based on material sourced from Balason/Matigara would meet the physical requirements specified in Table 500-8 if lime is used as a filler.

    12.8 The report from IIT Kharagpur is based on the ASMT:D-3625 test, which is “more serious” than the specified AASHTO T-182 test.

    12.9 Although lime is not specified as an anti-stripping agent, there is no provision forbidding its usage as an anti-stripping agent either. Further, MoRTH's manual for construction and supervision of bituminous work specifically mentions that hydrated lime may, on occasions, be used instead of propriety (sic) anti-stripping agent.

    12.10 Thus, the respondent was justified in making the bid on the assumption that aggregates based on material sourced from Balason/Matigara may be used for the bituminous works.

    12.11 Thus, the respondent is entitled to the first claim.

    12.12 Since clause 1004 read with clause 1007 removes all references to any material sourced from riverbeds, the use of the same was clearly prohibited.

    12.13 Thus, the respondent was not justified in making the bid on the assumption that aggregates based on such material may be used.

    12.14 Thus the respondent is not entitled to the said claim.

    Since there is no dispute qua the basis of calculation, it would be unnecessary to relate the reasoning for the same herein. Furthermore, since there is no challenge to the dissenting award, the same need not be related here either.

    13. The respondent sought a clarification of the Award under section 33 of the Act. It submitted that the operative portion of the Award has erroneously scored out the letters BC, after the letters DBM, both within parentheses, after the words “bituminous works”. The respondent contended that the award was for all bituminous works, i.e, both Dense Bituminous Macadam and Bituminous Concrete and the letters BC, which stand for Bituminous Concrete ought to not have been scored out. This was opposed by the appellant on the ground that the claim was only for Dense Bituminous Macadam and hence the scoring out was warranted.

    14. The appellant also appears to have sought a clarification in the Award under section 33 of the Act. It appears to have sought a clarification that in the part of the Award reproducing clause 507.2.2, the words “…coarse aggregate shall consist of crushed stone shingle, They shall…” ought to read as “…coarse aggregate shall consist of crushed stone, shingle. They shall…”

    15. By their order of 3rd October, 2005, the tribunal amended the award and directed that for Bituminous Works (BC) the additional expenditure incurred on transportation of aggregates from Pakur shall be worked out on the same principle as indicated in pages 19 and 20 of the award. It further allowed the amendment sought for by the appellant.

    16. The appellant preferred the section 34 petition challenging the award. The appellant contended inter alia:

    16.1 That the amended clause 507.2.2 of the MoRTH specifications, in its letter and spirit, does not allow for aggregates based on material sourced from riverbeds being used.

    16.2 That lime cannot function as an anti-stripping agent — which ideally should be fatty acids and amines with long hydrocarbon chains.

    16.3 That the ASTM:D-3625 is not more serious than the AASHTO T-182 test and ought to not have been given preference.

    16.4 That the amended clause 507.2.2 of the MoRTH specification does not contain the word crushed, and hence the word shingles would have no relevance.

    16.5 That the respondent's contention that the bid is based on the assumption that aggregates based on material sourced from Balason/Matigara is belied by its own documents.

    16.6 That the claim for extra lead for material procured for Bituminous Concrete works was not even raised and the amendment to the Award, allowing the same, is clearly an excess of jurisdiction.

    16.7 That the arbitral tribunal has failed to appreciate various documents submitted by the appellant in support of its case. Had the same been appreciated, the arbitral tribunal would have arrived at a different conclusion than the one arrived at.

    17. The impugned order, as earlier recounted, dismissed the section 34 petition. By it, the learned Single Judge reasoned:

    17.1 The objections raised by the appellant pertain to interpretation of the contract, which is in the dominion of the arbitrator.

    17.2 The Court ought to not interfere with the interpretation of the contract as given by the arbitrator.

    17.3 The grounds in the section 34 petition are, in effect, an appeal from the Award. The court exercising jurisdiction under section 34 of the Act cannot sit in appeal over the findings in the Award.

    17.4 The grounds are merely regarding the tribunal's appreciation of material before it, which cannot be interfered with under section 34 of the Act.

    17.5 The Award, as modified by the order of 3rd October, 2005, merely provides for the consequences arising out of the extra lead incurred by the respondent procuring aggregates from Pakur, on the basis of the tribunal's interpretation of the clauses of the contract. It cannot be said to be in excess of the contract.

    18. Challenging the same, the appellant has filed the instant appeal. Since a large portion of the submissions pertained to clause 507.2.2 of the MoRTH specification, although irrelevant, it may be useful to set the same out below. The portions removed by the amendment are set out in bold:

    “507.2.2 Coarse aggregates: The Coarse aggregates shall consist of crushed stone, crushed gravel/shingle or other stones. They shall be clean, strong, durable, of fairly cubical shape and free from disintegrated pieces, organic or other deleterious matter and adherent coating. The Aggregates shall preferably be hydrophobic and of low porosity. If the hydrophilic aggregates are to be used the bitumen shall be treated with anti stripping agents of approved quality in suitable doses. The aggregates shall satisfy the physical requirements set forth in Table 500-8.

    If crushed gravel/shingle is used, not less than 90% by weight of the gravel/shingle pieces retained on 4.75 mm sieve shall have at least two fractured faces. The portion of the total aggregate passing 4.75 mm sieve shall have a sand equivalent value of not less than 50 when tested in accordance with the requirement of IS:2720 (Part-37).”

    19. Senior Counsel Mr. Chetan Sharma, contended on behalf of the appellant that the Award fell into an error in holding that clause 507.2.2 of the MoRTH specifications permitted using aggregates based on shingles. He submitted that the terms of the contract do not admit of such an interpretation; that the word shingle is a mere surplusage and has no useful meaning in the provision; that it is hardly a plausible interpretation that the word shingle would have any meaning when it is immediately preceded by a stroke (the character that this is a clear indication that it was mere erratum that it subsisted in the clause post amendment. He further submitted that the interpretation placed upon clause 507.2.2 by the tribunal is implausible and ought to have been set aside by the learned Single Judge in exercise of his powers under section 34 read with section 28(3) of the Act. In support of this contention, he cited the judgement of this Court in R.S Builders v. DDA . 2008 2 Arb. L.R 361 Delhi.

    20. He next contended that the arbitral tribunal had misapplied the contra proferentem principle in the facts of the case. He submitted that there was no circumstance warranting the application of the contra proferentem rule, as the respondent was — or was at least deemed to be — fully aware of all the terms of the contract and had sufficient opportunities to seek clarification before it even bid for the tender. He contended that the contra proferentem rule ought to not have been used in the circumstances of the case, as it can hardly be said that the appellant was the proferens in the contract, which was a commercial contract signed by both parties. He submitted that in view of the same, the learned Single Judge ought to have set the Award aside. He relied on the decision of a learned Single Judge of this Court in Tehri Hydro Development Corporation Ltd… v. Lanco Construction Ltd…. . 2007 3 Arb. L.R 194 Delhi. in support of his submission.

    21. Learned Counsel also contended that even assuming that the word shingle was not an error, and that shingles/material sourced from riverbeds were to be allowed, it still does not justify the respondent making the bid on the assumption that material from Balasore/Matigara could be used. This, he contends, is in view of the fact that the material from Balasore/Matigara ought were not in compliance of the physical requirements as specified in Table 500-8 of the MoRTH specifications. He contended that the findings in the report from IIT Kharagpur ought to not be placed reliance on, since it is based on the ASTM:D-3625, while the proper test as per the contract is the AASHTO T-182 test. He submitted that this makes the instant dispute a fit case for exercise of the powers under section 34 of the Act to set aside the Award. He relied upon the judgement of this Court in Delhi Development Authority v. Sunder Lal Khatri & Sons . 2009 1 Arb. L.R 240 Delhi to contend that insufficiency of reasons in the award is a ground for setting aside the award.

    22. Learned Counsel also contended that the report from IIT Kharagpur only recommended lime being used as a filler. He submitted that a filler is different from an anti stripping agent. He submitted that the provisions of clause 507.2.2 of the MoRTH specifications allowed usage of an approved anti-stripping agent in case of hydrophilic substances, which hydrated lime is admittedly not. He submitted that the Award, which proceeds on the premise that as long as hydrated lime is not prohibited, its usage cannot be regarded as illegal, is patently and manifestly illegal. This illegality, he submits, goes to the very root of the matter and vitiates the entire award, which is premised on this illegality. He contends that the learned Single Judge ought to have set the Award aside in view of the same. He drew the attention of this Court to the judgement of the Supreme Court in Hindustan Zinc Ltd. v. Friends Coal Carbonisation . 2006 4 SCC 445., to the issue that an award cannot be contrary to the terms of the contract.

    23. He then submitted that the material on record before the arbitral tribunal clearly indicated that the contention of the respondent that its bid was based upon the assumption that aggregates based on material sourced from Balason/Matigara may be used is specious. He drew reference to the bid documents, specifically the document pertaining to methodology to submit that the methodology specified by the respondent is not one that could be used in respect of anything other than crushed stones which the material from Balason/Matigara was not. He submits that the Award clearly fell into an error in holding that the respondent's bid was based upon the assumption that aggregates based on material sourced from Balason/Matigara may be used. He contended that this was sufficient ground for the learned Single Judge to have set the Award aside. He relied on the judgement of this Court in Oil and Natural Gas Corporation Ltd. v. Schlumberger Asia Services Ltd. . 2006 3 Arb. L.R 610. in this regard.

    24. Lastly, he contended that there is no material on record to show that a claim in respect of Bituminous Concrete works (which is governed by clause 512 of the MoRTH specifications but has the same requirement qua material as Dense Bituminous Macadam works — clause 507.2.2) had been raised or prosecuted by the respondent. He submitted that the application under section 33 of the Act is not one that could have been made by the respondent when the original statement of claim contained neither averments nor a claim for extra lead incurred in procuring aggregates from Pakur for Bituminous Concrete works. He submits that this falls squarely within the provisions of section 34(2)(a)(iv) of the Act and ought to have been set aside.

    25. Counsel for the respondent opposed the appeal and contended that the learned Single Judge had rightly refused to interfere with the award. He contended that the interpretation placed on clause 507.2.2 of the MoRTH specification by the arbitral tribunal is not only a plausible interpretation, it is the only interpretation. He submitted that the mention of the word shingle therein, when read in conjunction with the lack of similar words in clause 1004 read with 1007 of the MoRTH specifications, is a clear indication of the intent of the appellant to allow the material sourced from riverbeds.

    26. He contended that there is no basis for the section 34 petition or the present appeal. He submits that the limited jurisdiction under section 34 and section 37 of the Act does not permit the Court to decide the present appeal. He also contended that the arbitral tribunal has rightly come to the conclusion that the aggregates based on the material sourced from Balason/Matigara do comply with the physical requirements under Table 500-8 of the MoRTH specifications; he drew reference to the report from IIT Kharagpur in this regard.

    27. The primary contention, as earlier stated, of the appellant is that the interpretation placed by the Award on clause 507.2.2 of the MoRTH specifications is incorrect. This court finds itself unable to agree with the contention. The arbitral tribunal has considered the terms of the MoRTH specifications and also considered the fact that the provisions of 507.2.2 of the MoRTH specifications do specify the word shingle while clause 1004 read with clause 1007 thereof does not, and consequently held that the same indicates that shingle being retained in clause 507.2.2 is not an erratum. This is a plausible interpretation of the contract; even if not mentioned, it is apparent that it follows the principle enunciated in the maxim expressio uni us est exclusio alterius21 — a well-established rule of interpretation qua deeds and other instruments.22 The law as laid down by the Supreme Court in its various judgements enjoins this Court from interfering with the interpretation placed by the arbitral tribunal upon a contract, so long as it is plausible; this Court shall not interfere with the same.

    28. The second contention qua the interpretation placed upon the contract was that the rule of contra proferentem ought to not have been applied in this matter as it was a commercial contract signed by the parties after all terms have been understood fully. Thus, it is contended that there is no mandate to construe the terms of the contract against the appellant. Indeed, it is a well established principle of construction of contract that if the terms employed by one party are unclear, an interpretation against that party will be preferred. This proposition of law appears in the award of the arbitral tribunal at paragraphs 2.6.5 to 2.7.3, and there is no dispute as to its validity.23 Following from this proposition of law, the arbitral award stated that “[w]e will be justified in giving effect to the meaning of the word “shingles” more favourable to the contractor and accept his submission so far as the construction of the clause goes.” The learned single judge declined to enter this debate as it related to the construction of the contract — a matter properly reserved within the domain of the arbitral tribunal. Given that no argument as to an error in law has been pursued, the interpretation placed on the contract is a matter within the jurisdiction of the arbitral tribunal, and thus, even if an error exists, this is an error of fact within jurisdiction, which cannot be re-appreciated by the Court under sections 34 or 37 of the Act.24 The appellant, rather, invites the Court to question the inferences drawn from an application of this rule of law; such re-appreciation is impermissible.

    29. The contention of the appellant qua the report from IIT Kharagpur is clearly an issue of appreciation of facts. As earlier observed, this Court is enjoined from re-appreciating evidence merely to arrive at a different conclusion from the arbitrator. It can hardly be said that the findings of the arbitrator are patently erroneous or without material to support the same. It has observed inter alia that the ASTM:D-3625 test is more serious than the AASHTO T-182 test, that lime's anti stripping properties have been discussed in MoRTH's manual for construction and supervision of bituminous work and that clause 507.2.2 itself provides for use of an anti-stripping agents in case of hydrophilic material, before coming to its conclusions qua the report from IIT Kharagpur. The learned Single Judge has rightly refused to interfere with the Award on this count and this Court shall follow suit.

    30. Similarly, the contention that the respondent's bid was not based on the assumption that material from Balason/Matigara may be used has to be rejected. This Court will not re-appreciate evidence merely to come to a different conclusion than the arbitral tribunal.

    31. This Court, once again, finds itself unconvinced by the contentions of the appellant on this ground. It has been contended that the claim has been only for Dense Bituminous Macadam works and the award, to the extent it awarded extra lead in respect of material procured for Bituminous Concrete works, deserves to be set aside with under section 34(2)(a)(iv). This Court is unimpressed with the contention. The Award, in paragraph 2.6 et. seq., discusses bituminous works. That no discussion under clause 512 of the MoRTH specifications is made in the Award is understandable, inasmuch as the MoRTH specifications, in clause 512, itself refers to clause 507.2.2, which — as stated earlier — was the subject matter of discussion in the Award. The Award, discussing the first claim in paragraph 3.1 et. seq. discusses claims for DBM etc. (Bituminous Works). The wordings used in the said paragraphs, once again, is bituminous works, as opposed to Dense Bituminous Macadam as sought to be contended by the appellant herein. The Declaration about the future of the Award in paragraph 3.6 et. seq. also employs the words Bituminous Works. Even the MoRTH specifications provide for both Dense Bituminous Macadam works and Bituminous Concrete works under the same chapter.

    32. Especial reliance was sought to be placed by the appellant upon the insertion of the figures and letters (DBM) in sub-paragraph (i) of the Final Award at paragraph 4.0 to contend that the Award has intentionally restricted itself to the claim made based on extra lead for Dense Bituminous Macadam works and that the scoring out sought to be clarified by the application under section 33 was rightly made. This Court finds itself, once again, unconvinced by this argument. It is not the case of the appellant that the term bituminous works refers only to Dense Bituminous Macadam works, nor is such a contention borne out from the records. Should the appellant have wanted to so contend, it is reasonable to assume that the appellant ought to have sought the clarification under section 33 of the Act. Given the same, this Court finds no substance in this contention as would warrant interference with the impugned order.

    33. For the above reasons, this Court finds no reasons to interfere with the impugned order. Consequently, the appeal is dismissed as being without merits. The parties are left to bear their own costs.

    Use AI to get other relevant cases.

    Comments

    National Highways Authority Of India v. Lanco Infratech Ltd. .
    (Mar 7, 2014)