AMICUS AI
Citation Codes
Neutral Citations
2012 DHC 7614
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2012 DHC 7614
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
Smart Summary

Factual and Procedural Background

This petition under Section 34 of the Arbitration and Conciliation Act, 1996 was filed by the Union of India (through its Executive Engineer, Construction Division-III, CPWD) challenging an arbitral Award dated 24 February 2011 rendered by the learned sole Arbitrator in disputes between the Petitioner and Pt. Munshi Ram & Associates Pvt. Ltd. The disputes arose from an agreement for construction of Type‑V quarters at R.K. Puram, New Delhi. The contract specified commencement of work on 22 December 1995 and completion within 21 months (by 21 September 1997). The Petitioner records a provisional completion date of 30 January 2001, with outstanding defects and unfinished items; the Superintending Engineer granted extension of time (EoT) up to 30 June 2002 for final completion and no separate completion certificate was issued. The Respondent invoked arbitration on 3 January 2009; this Court appointed the learned Arbitrator by order dated 27 October 2009 (Arb. P. No. 59 of 2009). The Respondent filed 14 claims before the Arbitrator, of which four claims (Nos. 3, 4, 6 and 11) were rejected by the Arbitrator.

Legal Issues Presented

  1. Whether the Respondent's claims were barred by a contractual limitation under Clause 25 of the agreement and, relatedly, whether Clause 25 was void to the extent it extinguished rights by reason of Section 28 of the Indian Contract Act, 1872 (as amended).
  2. Whether the learned Arbitrator's refusal to treat the claims as time‑barred was correct, having regard to the dates of provisional completion, finalisation/payment of the final bill and invocation of arbitration.
  3. Whether the arbitral Award suffered from mala fides or amounted to profiteering by the contractor, such as to warrant interference under Section 34 of the Arbitration and Conciliation Act.
  4. Whether the Arbitrator provided reasons for attributing entire delay in completion to the Petitioner, and whether that reasoning met the requirement of Section 31(3) of the Act.
  5. Whether specific awards in respect of (a) Claim No. 1 (market rates for deviated quantities and extra items), (b) rebate calculations, (c) machinery/T&P & staff assessments, (d) loss of profit percentage, (e) costs (Claim No. 13) and (f) post‑Award interest (including interest on interest) were legally sustainable.

Arguments of the Parties

Petitioner's Arguments (Union of India / CPWD)

  • The Respondent's invocation of the arbitration clause on 3 January 2009 was time‑barred under Clause 25 of the agreement because provisional completion was recorded on 30 January 2001 and the finalisation/payment of the bill occurred earlier (balance towards escalation allegedly paid on 30 March 2007) — invocation was beyond the 90 days prescribed by Clause 25.
  • The learned Arbitrator erred in holding that Clause 25 was hit by Section 28 of the Indian Contract Act; reliance was placed on pre‑amendment precedents (notably The Vulcan Insurance Co. Ltd. v. Maharaj Singh and other authorities) to argue that contractual clauses prescribing limitation for claims were not necessarily invalid.
  • The Arbitrator wrongly attributed the whole delay in completion to the Petitioner and failed to give reasons compliant with Section 31(3) of the Act.
  • Specific challenges to parts of Claim No. 1 (Parts C and D), rebate calculations and some assessments of rates and deductions were advanced as errors of law or fact by the Arbitrator.
  • It was contended that the Arbitrator erred in awarding interest on interest (post‑Award interest computed on interest component).

Respondent's Arguments (Pt. Munshi Ram & Associates Pvt. Ltd.)

  • The Arbitrator correctly rejected the limitation objection because Section 28 (as amended with effect from 8 January 1997) renders void clauses that extinguish rights or discharge liability on expiry of a specified period so as to prevent enforcement — Clause 25, to the extent it extinguishes rights, is void.
  • The final bill relied upon by the Petitioner was not a true final bill: it bore withholdings for pending items and did not bear the Respondent's signature; the Respondent had not received the final bill till 10 May 2008, and the arbitration invocation on 3 January 2009 fell within the statutory limitation period.
  • Post‑amendment authorities (including Single Judge and Division Bench decisions of this Court) support the proposition that the amendment to Section 28 applies to disputes arising after the amendment even if the contract predates it; the Respondent relied on those authorities to uphold the Arbitrator's decision.
  • The delays were due to obstructions at site, change of foundation design, failure to issue drawings and decisions in time; the Respondent had applied for EoT and produced the hindrance register and an application (Exhibit C‑244) showing delays attributable to the Petitioner.
  • On costs, the Respondent did not controvert the Petitioner's claim that the Respondent had undertaken to bear arbitration costs when seeking arbitration; notwithstanding that, the Arbitrator had awarded costs which the Court ultimately set aside in part.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
The Vulcan Insurance Co. Ltd. v. Maharaj Singh, (1976) 1 SCC 943 Pre‑amendment authority holding that a contract clause providing a period for lodging a claim was not necessarily invalid; distinguished between clauses limiting period and clauses extinguishing rights. Recognised as the earlier legal position pre‑amendment; the Court explained that the distinction drawn in this decision does not survive the 1997 amendment to Section 28 of the Contract Act for post‑amendment disputes and therefore cannot be relied upon to save Clause 25 to the extent it extinguishes rights.
National Insurance Co. Ltd. v. Sujir Ganesh Nayak & Co., (1997) 4 SCC 366 Reiteration (pre‑amendment) of the position in Vulcan regarding contractual limitation clauses. Noted as part of the pre‑amendment jurisprudence that the Court reviewed and then distinguished in light of the amendment to Section 28.
Wild Life Institute Of India, Dehradun v. Vijay Kumar Garg, (1997) 10 SCC 528 Pre‑amendment decision reflecting the earlier distinction regarding limitation clauses. Observed to have been rendered before the amendment; treated as part of the pre‑amendment body of law and not persuasive to defeat the effect of the post‑1997 Section 28 amendment.
P. Manohar Reddy & Bros. v. Maharashtra Krishna Valley Development Corporation, (2009) 2 SCC 494 Decision arising under the Arbitration Act, 1940; did not discuss the effect of the amendment to Section 28 of the Contract Act. The Court noted that this authority did not address the specific issue whether the 1997 amendment altered the pre‑amendment position; accordingly its applicability to the present question was limited.
Hindustan Construction Corporation v. Delhi Development Authority, 1999 1 ArbLR 272 Single Judge decision applying the amended Section 28 and holding contractual limitation clauses extinguishing rights to be void. Counted among Single Judge authorities post‑amendment that rejected the pre‑amendment distinction and supported the view that clauses extinguishing rights on expiry are void under amended Section 28.
Kalyan Chand Goyal v. Delhi Development Authority, 1998 (47) DRJ 772 Single Judge decision applying amended Section 28. Relied upon as part of the cohort of post‑amendment Single Judge decisions which the Court treated as consistent with the amended legislative position.
Explore Computers Pvt. Ltd. v. Cals Ltd. & Anr., 131 (2006) DLT 477 Single Judge decision holding the earlier distinction did not survive after the amendment to Section 28. Cited as an authority supporting the proposition that post‑amendment clauses which extinguish rights are void and cannot be used to defeat claims.
Pandit Construction Company v. Delhi Development Authority, 2007 (3) ArbLR 205 (Delhi) Single Judge decision addressing whether the amendment applies to contracts entered into before the amendment and holding the amendment applies to subsequent events. Relied on to support the Court's view that even if a contract was executed before 8 January 1997, the amended Section 28 applies to events (final bills, disputes) occurring after the amendment.
M/S Manohar Singh & Sons v. M/S Raksha Karamchari Coop Gr H Soc (decision dated 22 Dec 2009 in CS(OS) No. 2684‑A of 1998) Single Judge authority cited among post‑amendment decisions rejecting the pre‑amendment distinction. Included in the set of Single Judge decisions relied upon to show the post‑amendment approach to contractual limitation clauses.
Chander Kant & Co. v. The Vice Chairman, DDA (decision dated 26 May 2009 in Arb. P. No. 246 of 2005) Division Bench decision holding that the law in force when the dispute arises governs, not the law when the contract was entered into. The Court relied on this Division Bench authority to hold that the amendment to Section 28 applies to disputes arising after the amendment even if the contract pre‑dated it; it reinforced the conclusion that Clause 25 is void to the extent it extinguishes rights.
D.D.A v. Pandit Construction Co. (decision dated 19 April 2012 in FAO(OS) No. 382 of 2007) Division Bench decision upholding the Single Judge view that Clause 25 of the General Conditions would be void post‑8 January 1997. Relied upon to affirm that the amendment to Section 28 changed the substantive law and that Clause 25 would be void to the extent it extinguished claims.
State of Haryana v. S.L. Arora & Company, (2010) 3 SCC 690 Supreme Court decision addressing the permissibility of awarding interest on interest (post‑Award interest computed on interest component). Applied by the Court to set aside the Arbitrator's direction granting post‑Award interest on the interest component (i.e., interest on interest) in respect of Claim Nos. 10 and 14; the Award was clarified to grant post‑Award interest only on the principal amounts.

Court's Reasoning and Analysis

The Court proceeded by analysing (a) the limitation objection under Clause 25; (b) the effect of the 1997 amendment to Section 28 of the Indian Contract Act and the applicable precedents; (c) factual matters bearing on when limitation commenced; and (d) specific challenges to parts of the Award. The Court's step‑by‑step reasoning, as shown in the opinion, is summarized below.

1. Limitation and Section 28 (Amendment):

  • The Petitioner relied on Clause 25 (90 days) and alleged that invocation of arbitration on 3 January 2009 was time‑barred. The Arbitrator had rejected this preliminary objection by an order dated 1 May 2010.
  • The Arbitrator's factual findings (recorded in the Award) included that the final bill produced by the Petitioner contained several withholdings (amounts withheld for pending extra/substituted items, quality control, pending sanction for deviations) and did not bear the Respondent's signature; the Respondent had not received a final bill until 10 May 2008. On that factual matrix, invocation on 3 January 2009 was within the statutory limitation period of three years from 30 March 2007 as calculated by the Arbitrator.
  • On the legal issue, the Court set out Section 28 as amended (effective 8 January 1997) and observed that the amendment expanded Section 28 to treat as void contractual clauses which extinguish the rights of any party or discharge liability on the expiry of a specified period so as to restrict enforcement.
  • The Court reviewed pre‑amendment decisions (e.g., Vulcan, National Insurance, Wild Life Institute) and explained that the distinction drawn in those cases between clauses limiting the period and clauses resulting in forfeiture no longer survives the 1997 amendment. It relied on a series of Single Judge and Division Bench decisions of the Delhi High Court applying the amended Section 28 and holding that clauses extinguishing rights are void.
  • On the facts of the present case — work completed 30 January 2001, final bill effectively paid on 12 March 2007 with deductions giving rise to disputes, and the Respondent invoking arbitration on 3 January 2009 — the Court concluded the Arbitrator was correct to hold Clause 25 void to the extent it extinguishes rights and that the claims were not time‑barred.

2. Application of Post‑Amendment Law to Pre‑Amendment Contracts:

  • The Court accepted authorities (including Pandit Construction and its affirmation by a Division Bench) holding that even where a contract predates the amendment, if the events giving rise to the dispute (preparation/finalisation of final bill, etc.) occur after the amendment, the amended Section 28 applies. The Court applied this principle to the facts where the work and billing events extended into the post‑amendment period.

3. Mala fides / Profiteering Allegation:

  • The Petitioner alleged mala fides and profiteering by the contractor. The Court treated these as bald, vague and unsubstantiated allegations. Noting that the Petitioner had accepted parts of the Award and had made partial payments (with specific claims and amounts detailed in the Award), the Court found it inconsistent to allege profiteering in the absence of substantiated proof. The Court therefore rejected the mala fides contention.

4. Delay in Completion and Section 31(3):

  • The Court examined paragraph 5.4 of the Award where the Arbitrator, after studying documents (including the EoT application and hindrance register), concluded the delay was due to obstructions at site, change in foundation design, failure to issue drawings/decisions and other failures of the Petitioner. The Arbitrator relied on Exhibit C‑244 (application for EoT with hindrance register entries).
  • The Court held that the Arbitrator had indeed adverted to reasons (by reference to material on record) and that the finding attributing delay to the Petitioner was not devoid of reasons as contemplated by Section 31(3) of the Act.

5. Claim No. 1 — Market Rates for Deviated Quantities and Extra Items:

  • The Arbitrator analysed Clause 12 and related sub‑clauses regarding altered, additional or substituted work and deviation limits. The Court emphasised that foundation work is treated separately under Clause 12 (foundation items are excluded from the general operation of Clause 12(vi)).
  • The Arbitrator identified six foundation sub‑items where deviation exceeded 25% and calculated the differential based on market rates versus agreement rates, arriving at a deviation percentage (noted as 549% for those sub‑items) and an allowed increase in foundation cost. The Arbitrator explained the methodology (labour coefficient, labour muster rolls, cement & steel at agreement rates, other materials at market rates, profit at 15% per Clause 10(cc)).
  • The Court found no patent illegality in the Arbitrator's approach or calculations, and rejected the Petitioner's method of aggregating all foundation items to compute a net deviation that would bring the deviation within limits, because Clause 12(vi) expressly excludes foundation work from that aggregation approach.
  • On Part D (extra items less paid), the Arbitrator relied on supporting charts (Exhibit C‑218) and applied DSR or department running bill rates as appropriate; the Court found sufficient explanation in the Award and did not fault the Arbitrator's determinations.

6. Rebate and Related Deductions:

  • The Arbitrator held the unconditional rebate of 1.80% was properly limited to the tendered amount before rebate and calculated as Rs. 11,54,862, and found that conditions for the other rebates (1%, 0.50%, 0.50%) were not fulfilled by the Petitioner; thus the balance rebates could not be retained.
  • The Court examined a CPWD letter (12 December 1995) and the contractor's acceptance letter (24 November 1995) and concluded that the rebates were offered on the tendered rates and that the phrase “applicable on the gross value of the work done” meant the rebates (calculated on tendered amount) would be deducted from the gross value of the bill, not that rebates were to be calculated on the gross amount. The Arbitrator's decision on rebates was upheld.

7. Machinery, T&P, Staff, Loss of Profit and Other Heads:

  • The Arbitrator assessed machinery/T&P rentals (22.3 months at Rs. 1,40,000 per month; remaining period at Rs. 80,000 per month) and staff costs (40 months at Rs. 43,000 per month) with cogent reasons and a methodology; the Court found no patent illegality in these assessments.
  • The Arbitrator did not uniformly award 15% for all heads; overhead was assessed at 3%, certain claims (Nos. 4 and 6) were not awarded, and Claim No. 8 was partly awarded. The Court found the Arbitrator's approach acceptable on the record.

8. Costs (Claim No. 13):

  • The Arbitrator had awarded Rs. 4,00,000 towards arbitration costs and Rs. 10,000 as costs imposed on the Petitioner. The Court accepted the Petitioner's uncontested submission that the Respondent had undertaken, at the stage of seeking arbitration, to bear the cost of arbitration. On that basis, the Court set aside the Award in respect of Claim No. 13.

9. Interest and Interest on Interest:

  • The Arbitrator computed interest and arrived at figures including an interest component; however, in paras 19.5 and 20.0 the Arbitrator included interest in a gross figure and directed post‑Award interest to be paid on the interest component also.
  • Relying on the Supreme Court decision in State of Haryana v. S.L. Arora & Company (2010) 3 SCC 690, the Court held that the Arbitrator's direction awarding post‑Award simple interest on the interest component (i.e., interest on interest) was legally unsustainable. Consequently the Award was clarified/set aside to the extent it granted post‑Award interest on interest; post‑Award interest was directed to be payable only on the principal award amounts.

Holding and Implications

Holding: The Court upheld the impugned arbitral Award in the main but modified it in two respects: (a) the portion of the Award granting costs under Claim No. 13 was set aside; and (b) the direction granting post‑Award interest on the interest component (interest on interest) in respect of Claim Nos. 10 and 14 was set aside and clarified so that post‑Award interest is payable only on the principal amounts awarded. The remainder of the arbitral Award was upheld.

Implications:

  • Direct effect on the parties: The Petitioner remains liable to comply with the arbitral Award as upheld, subject to the two specified modifications (no award for costs under Claim No. 13 and no post‑Award interest on interest). The Respondent retains the remainder of the sums awarded by the Arbitrator subject to the Court's clarifications.
  • On the law: The Court applied the post‑1997 amended Section 28 of the Indian Contract Act to hold that contractual clauses which extinguish rights on expiry of a specified period are void; it followed Division Bench and Single Judge precedents holding that the law in force when the dispute arises governs even if the contract predates the amendment. The opinion did not purport to create a novel precedent beyond applying and affirming the existing post‑amendment line of authorities in this jurisdiction.

Disposition: The petition is disposed of in the terms indicated (Award upheld except as modified above).

To access the original judgment, please Sign In or Subscribe.

    Union Of India Petitioner v. Pt. Munshi Ram & Associates Pvt. Ltd.

    JUDGMENT

    1. The challenge in this petition under Section 34 of the Arbitration and Conciliation Act, 1996 (‘Act’) by the Petitioner Union of India through its Executive Engineer, Construction Division-III, Central Public Works Department (‘CPWD’) is to an Award dated 24th February 2011 passed by the learned sole Arbitrator in the disputes between the Petitioner and the Respondent, Pt. Munshi Ram & Associates Pvt. Ltd. arising out of the work of construction of certain Type-V quarters at R.K Puram, New Delhi, for which an agreement was entered into.

    2. In terms of the agreement, the work was to commence on 22nd December 1995 and was to be completed within 21 months, i.e, by 21st September 1997. According to the Petitioner, as per the provisional completion certificate recorded by it, the date of completion was 30 January 2001. It is stated that since there were outstanding defects and unfinished items, the Superintending Engineer (‘SE’) granted extension of time (‘EoT’) upto 30 June 2002 for the final completion. It is stated that no separate completion certificate was issued.

    3. As a result of the disputes between the parties, the Respondent invoked the arbitration clause on 3rd January 2009. Thereafter, by an order dated 27 October 2009, in Arb. P. No. 59 of 2009, this Court appointed the learned Arbitrator. The Respondent filed 14 claims before the learned Arbitrator, out of which four, namely, Claim Nos. 3, 4, 6 and 11 were rejected.

    Clause prescribing limitation for preferring claims

    4. As noted in the impugned Award, the Petitioner herein raised three preliminary objections on 30 March and 7 April 2010. One of the preliminary objections was that the claims were barred by limitation under Clause 25 of the agreement. It is contended that the work was provisionally completed on 30 January 2001 and the bill for the undisputed items was finalized on 2 March 2007 and the balance towards escalation was paid on 30 March 2007. It was submitted that since the Respondent had invoked Clause 25 of the agreement only on 3 January 2009, i.e, 7 years and 11 months after recording of the provisional completion and 1 year and 10 months after finalisation of the bill, the invocation of the arbitration clause was well beyond 90 days as prescribed in Clause 25.

    5. In rejecting the above preliminary objection by order dated 1 May 2010, the learned Arbitrator observed that in view of Section 28(b) of the Indian Contract Act, 1872 (‘CA’) an amendment agreement in restraint of legal proceedings contrary to the mandate of Article 137 of the Limitation Act, 1963 (‘LA’) would be void and any clause extinguishing the right of a party or discharging any party from its liability in respect of the contract on expiry of a specific period, so as to restrict the time period would be void. It was further observed that the arbitration clause was invoked by the Respondent on 3 January 2009 within the statutory limitation period of three years from the alleged date of 30 March 2007. Further, it was noted that the copy of the final bill, as submitted by the Petitioner herein and disputed by the Respondent, showed that Rs. 40,000 was withheld for pending extra items and substituted items; Rs. 10,000 was withheld for pending quality control; Rs. 20,000 was withheld for pending sanction for deviation statement ALR and AHR items and Rs. 20,000 was withheld pending sanction of non-ALR and non-AHR items. Also, the final bill did not bear the signature of the Respondent. Accordingly, it was held that this could not be said to be the final bill. In fact, the Respondent had not received the final bill till 10 May 2008. Consequently, it was held that the claim was not barred by limitation. As noted in the impugned Award, the Petitioner then filed an application under Sections 12, 13 and 18 of the Act against the above order and this application was rejected by the learned Arbitrator by an order dated 23 June 2010.

    6. Mr. Ajay Verma, learned counsel for the Petitioner, submitted that the learned Arbitrator erred in observing that the time period of 90 days under Clause 25 of the CPWD Conditions of Contract was hit by Section 28 of the CA. He placed reliance on the decisions in The Vulcan Insurance Co. Ltd. v. Maharaj Singh, (1976) 1 SCC 943, P. Manohar Reddy & Bros. v. Maharashtra Krishna Valley Development Corporation, (2009) 2 SCC 494, Himachal Pradesh State Forest Company Limited v. United India Insurance Company Limited, (2009) 2 SCC 252 and Wild Life Institute Of India, Dehradun v. Vijay Kumar Garg, (1997) 10 SCC 528.

    7. Countering the above submissions, it is pointed out by Ms. Anusuya Salwan, learned counsel for the Respondent that the decisions in Wild Life Institute Of India, Dehradun v. Vijay Kumar Garg and The Vulcan Insurance Co. Ltd. v. Maharaj Singh were rendered at the time when Section 28 of the CA had not been amended. She relied on the decisions of the learned Single Judges of this Court in Explore Computers Pvt. Ltd…Plaintiff; v. Cals Ltd. & Anr…Defendants., 131 (2006) DLT 477, Pandit Construction Company v. Delhi Development Authority, 2007 (3) ArbLR 205 (Delhi), M/S Manohar Singh And Sons v. M/S Raksha Karamchari Coop Gr H Soc, [decision dated 22 December 2009 in CS(OS) No. 2684-A of 1998). She has also placed reliance on the decision of the Division Bench (‘DB’) of this Court in Chander Kant & Co. v. The Vice Chairman, DDA (decision dated 26 May 2009 in Arb. P. No. 246 of 2005).

    8. At the outset, it requires to be noted that the legal position that existed prior to the amendment of Section 28 of the CA in 1997 was governed by the decision in The Vulcan Insurance Co. Ltd. v. Maharaj Singh. It was held that a clause in a contract providing for limitation for a party to lodge its claim was not invalid. A distinction was drawn between the agreements that limited the period of limitation and those that did not limit the period within which a party might enforce its rights but provided for the forfeiture or the waiver of the right if no suit was brought within the period stipulated in the agreement. It was held that the latter type of agreements was outside the scope of Section 28 of the CA and was binding between the parties. This was reiterated in National Insurance Co. Ltd. v. Sujir Ganesh Nayak & Co.(1997) 4 SCC 366. It is only where an agreement curtailed the period of limitation that it was held as offending section 28 of ca. It was this legal position that was reiterated in Wild Life Institute Of India, Dehradun v. Vijay Kumar Garg.

    9. Section 28 CA, which has been amended with effect from 8 January 1997, reads as under:

    “28. Agreements in restraint of legal proceedings void.- Every agreement,-

    (a) by which any party thereto is restricted absolutely from enforcing his rights under or in respect of any contract, by the usual legal proceedings in the ordinary tribunals, or which limits the time within which he may thus enforce his rights;

    or

    (b) which extinguishes the rights of any party thereto, or discharges any party thereto from any liability, under or in respect of any contract on the expiry of a specified period so as to restrict any party from enforcing his rights, is void to that extent.”

    10. The change brought about by the above amendment is that it also treats as void clauses of a contract which seek to extinguish right of any party or discharge any party from liability on the expiry of specified period so as to prevent an aggrieved party from enforcing its rights. After the enactment of the above amendment, a series of judgments were passed by the learned Single Judges of this Court holding that the distinction sought to be carved out by the earlier decisions in The Vulcan Insurance Co. Ltd. v. Maharaj Singh, National Insurance Co. Ltd. v. Sujir Ganesh Nayak & Co. and Wild Life Institute Of India, Dehradun v. Vijay Kumar Garg did not survive. These decisions included Hindustan Construction Corporation. v. Delhi Development Authority Authority1999 1 ArbLR 272, Kalyan Chand Goyal v. Delhi Development Authority 1998 (47) DRJ 772, Explore Computers Pvt. Ltd. v. Cats Ltd. and Pandit Construction Company v. Delhi Development Authority.

    11. It may be noted that the decision of the learned Single Judge of this Court in Pandit Construction Company v. Delhi Development Authority (supra) also dealt with the issue whether the amendment would apply even where the contract was entered into prior to the date of the amendment. This was answered by holding that “though the contract may have been entered into before the amendment to the provision, starting from the preparation of the final bill everything has happened after the amended provision came into play and the amendment changing the substantive law, it would certainly apply to the contract at hand.” The decision of the learned Single Judge has been upheld by the DB of this Court in D.D.A v. Pandit Construction Co. [decision dated 19 April 2012 in FAO(OS) No. 382 of 2007]. It has been held that “the position post January 08, 1997 would be that Clause 25 of the General Conditions of Contract would be void.” On the facts of that case, it was noted that even though the agreement was dated 30 November 1990, i.e, prior to the amendment to Section 28 of the CA, “the work lingered on till April 28, 1998. The final bill was prepared on July 05, 1999 and intimation of it be finalized sent to the respondent on March 20, 2001.” Reference was made to the decision of the DB of this Court in Chander Kant and Co. v. The Vice Chairman, DDA (supra), which held that the law as in force when a dispute arises has to be considered and not that in force when a contract is entered into.

    12. In view of the above settled position in law, as far as the present case is concerned, although the date of start of the work was 22 December 1995, the work was actually completed on 30 January 2001. The decision in P. Manohar Reddy & Bros. v. Maharashtra Krishna Valley Development Corporation (supra) was dealing with the case that arose under the Arbitration Act, 1940 and did not actually discuss the issue whether the amendment to section 28 of ca brought about the change to the legal position existing prior to the amendment. The execution of the contract in that case also appears to have been completed prior to the amendment. The decision in Himachal Pradesh State Forest Company Limited v. United India Insurance Company Limited (supra) appears to have proceeded on the basis that the amendment had been repealed. This is clear from para 11 of the said judgment which records that “During the resumed hearing, the learned counsel for the appellant candidly admitted that the amendment had been made but had thereafter been repealed and the matter would, thus, have to be examined under Section 28 of the Contract Act, as originally placed.” In fact, there has been no repeal of the amendment. It was wrongly informed by learned counsel for the Appellant in that case that the amendment to Section 28 of the CA stood repealed. Consequently, the law, as explained by the DBs of this Court in Chander Kant & Co. v. The Vice Chairman, DDA and D.D.A v. Pandit Construction Company would hold good.

    13. For the aforementioned reasons, this Court upholds the view taken by the learned Arbitrator in the order dated 1 May 2010 that Clause 25 to the extent that it extinguishes the rights of the Respondent to make any claims whatsoever if not made in the prescribed period would be hit by Section 28 CA and, therefore, the claims were not barred by limitation.

    14. Even otherwise, this Court finds that the reliance placed by the Petitioner on the purported date of completion to be the starting point of limitation is impermissible. The final bill was, in fact, paid only on 12 March 2007 and as has been pointed out by the learned Arbitrator, there were many deductions made which gave rise to the disputes. Consequently, the invocation of the arbitration clause by the Respondent on 3 January 2009 cannot be said to be time-barred.

    Malafides

    15. It is next submitted that the impugned Award was an example of “blatant profiteering by the contractor from the arbitration” and that the claims have been “decided by the arbitrator in a wholly mala fide manner.” The above submission is countered by the Respondent by pointing out that the Petitioner, in fact, accepted the impugned Award in part in respect of Claim 1 Part 1(B) for a sum of Rs. 11,049.57, Claim 1 Part 1(e) for Rs. 2,30,210 and Claim No. 8 for Rs. 2,44,181 and has even made payment for Rs. 4,85,441 on 30 September 2011.

    16. As far as the submission that the impugned Award is passed mala fide is concerned, this Court finds that this is a bald allegation which is vague and unsubstantiated. If indeed a part of the impugned Award has been accepted by the Petitioner, it is not understood how it can assail the impugned Award as being an incident of profiteering by the Contractor. Also, out of the sum of Rs. 2,53,41,400 that has been granted to the Respondent by the impugned Award, a sum of Rs. 1,34,74,942, in fact, pertained to the final bill. The material supplied was, in fact, paid for by the Respondent. Therefore, merely because the amount awarded in the impugned Award is higher than the tendered amount cannot, by itself, make the impugned Award opposed to the public policy of India warranting interference under Section 34 of the Act. What requires to be examined is whether on the basis of the evidence on record, the impugned Award of the learned Arbitrator suffers from any patent illegality on any of the grounds under Section 34 of the Act.

    Delay in completion of the work

    17. It is next contended by Mr. Verma that the finding of the learned Arbitrator that the entire delay in completion of the work was attributable to the Petitioner was without reasons and, therefore, hit by Section 31(3) of the Act. Ms. Salwan contends in reply that the above criticism is not justified as the learned Arbitrator has, in fact, referred to the reasons given by the Respondent in its application for EoT and thereafter, set out his conclusion in para 5.4 of the impugned Award.

    18. A perusal of the impugned Award shows that the learned Arbitrator has set out in para 5.2 the version of the Respondent (the Claimant in the arbitral proceedings) as to the reasons for the delay in the completion of the work. Thereafter, in para 5.3, he has set out the reasons given by the Petitioner (the Respondent in the arbitral proceedings) for the delay in the completion of the work. Thereafter, in para 5.4, the learned Arbitrator has held as under:

    “5.4 After study of all documents on record, reasons given in application for extension of time etc., I find that the work was delayed due to obstructions at site, change of design of foundation, failure to issue drawings and decisions in time for planning & execution and due to various other reasons as stated by claimant. The entire delay has been fully due to failure on part of respondent to perform contractual obligations on their part. This has resulted in extra expenditure on equipments, plants & machinery, staff, overhead expenses etc. Claimant are entitled to compensation for expenditures.”

    19. Although at first blush it appears that the above para only sets out the conclusion of the learned Arbitrator and not the reasons, on a careful perusal it shows that the learned Arbitrator adverted to the reasons “given in application of extension of time.”

    20. On 13 June 2002 the Respondent wrote a letter to the Petitioner requesting for EoT. This letter, along with the photocopy of the hindrance register, has been placed on the arbitral record and is marked as Exhibit C-244. There has been no denial of the fact that EoT was granted without levy of compensation upto 30 June 2002. The hindrance register entries show that the delays were clearly attributable to the Petitioner. It was sought to be contended by the learned counsel for the Petitioner that the above hindrance register or the letter granting EoT was not traceable in the records of the Petitioner. However, this Court is unable to accept this plea at the present stage. With Exhibit C-244, being the application by the Respondent for EoT enclosing the copies of the hindrance register, forming part of the arbitral record the Petitioner ought to should have raised such an objection before the learned Arbitrator. No such protest appears to have been made by the Petitioner. It is too late in the day for the Petitioner to deny the above exhibit and what it constitutes. The reasons given in the above letter were what weighed with the learned Arbitrator in coming to the conclusion in para 5.4 of the impugned Award that the delay had been entirely due to the failure on the part of the Petitioner to perform its contractual obligations. It cannot be, therefore, said that the said conclusion was not based on any reasons as contemplated by Section 31(3) of the Act.

    Claim No. 1

    21. Claim No. 1 was for a sum of Rs. 7,50,54,582 for balance payment for the work done as per the final bill. Mr. Verma confined his submissions to Part C relating to “market rate for deviated quantity” and Part D being “extra items less paid in final bill.”

    22. The case of the Respondent was that the quantities of various items in the agreement had increased far beyond the deviation limit of 25% due to inflation. It was submitted that the depth of the foundation had increased from 1.5 mtrs. to 8.5 mtrs. and, therefore, the market rates were payable under Clause 12 A of the agreement. It is submitted by the Respondent that it wrote several letters to the Petitioner stating that it would be able to carry out the extra work only at the market rates and that no reply was received to those letters. Consequently, the Respondent proceeded on the footing that its demand for market rates for the extra work was accepted by the Petitioner. The case of the Petitioner, on the other hand, was that in terms of Clause 12 of the agreement the market rates were not payable for the extra work and Clause 12 A did not have any application at all.

    23. The learned Arbitrator noted the above submissions and also discussed the clauses of the agreement. The learned Arbitrator then awarded a sum of Rs. 94,34,995 for the dues payable between the market rates and the agreement rates, both for the foundation work as well as the superstructure work.

    24. The relevant Clause 12 of the agreement in this regard reads as under:

    “CLAUSE 12. The Engineer-in-Charge shall have power to make any alterations in omissions from additions to or substitutions for the original specifications, drawings, designs and instructions, that may appear to him to be necessary during the progress of the work and the contractor shall carry out the work in accordance with any instructions which may be given to him in writing signed by the Engineer-in-Charge, and such alterations, omission, additions or substitutions shall not invalidate the contract and any altered, additional or substituted work which the contractor may be directed to do in the manner above specified as part of the work shall be carried out by the contractor on the same conditions in all respects on which he agreed to do the main work. The time for the completion of the work shall be extended in the proportion that the altered, additional or substituted work bears to the original contract work, and the certificate of the engineer-in-charge shall be conclusive as to such proportion. Over and above this a further period to the extent of 25 per cent or such extensions shall be allowed to the contractor. The rates for such additional altered or substituted work under this clause shall be worked out in accordance with the following provisions in their respective order:

    (i) If the rates for the additional, altered or substituted work are specified in the contract for the work, the contractor is bound to carry out the additional, altered or substituted work at the same rates as are specified in the contract for the work.

    (ii) If the rates for the additional, altered or substituted work are not specifically provided in the contract for the work, the such rates will be derived from the rates for a similar class of work as are specified in the contract for the work.

    (iii) If the altered, additional or substituted work includes any work for which no rate is specified in the contract for the work and cannot be derived from the similar class of work in the contract, then such work shall be carried out at the rates entered in C.P.W.D Delhi schedule of rates 1993…with correct slip no. one … minus/plus percentage which the total tendered amount bears to the estimated cost of the entire component work put to tender.

    (iv) If the rates for the altered, additional or substituted work cannot be determined in the manner specified in the sub-clauses (i) to (iii) above, then the rates for such work shall be worked out on the basis of the concerned Schedule of Rates of the District specified above minus/plus the percentage which the total tendered amount bears to the estimated cost of the entire component work put to tender. Provided always that if the rate for a particular part or parts of the item is not in the Schedule of Rates, the rates for such part or parts will be determined by the Engineer-in-Charge on the basis of the prevailing market rates when the work was done.

    (v) If the rates for the altered, additional or substituted work cannot be determined in the manner specified in sub-clauses (i) to (iv) above, then the contractor shall within 7 days of the date of receipt of order to carry out the work, inform the engineer-in-Charge of the rate which it is his intension to charge for such class of work supported by analysis of the rate or rates claimed and the Engineer-in-Charge shall determine the rate or rates on the basis of prevailing market rates, and pay the contractor accordingly. However, the Engineer-in-Charge, by notice in writing, will be at liberty to cancel his order to carry out such class of work and arrange to carry it out in such manner as he may consider advisable. But under no circumstances, the contractor shall suspend the work on the plea of non-settlement of rates of items, falling under this clause.

    (vi) Except in case of items relating to foundations, provision contained in sub-clauses (i) to (v) above shall not apply to contract or substituted items as individually exceed the percentage set out in the tender documents (referred to herein below as deviation limit), subject to the following restrictions.

    a) The deviation limit referred to above is the net effect (algebraical sum) of all additions and deductions ordered on all items.

    b) Extra items and foundation work shall not exceed the Deviation limits.

    …...

    For the purpose of operation of clause 12(vi) the following works shall be treated as work relating to foundations:

    (a) For buildings, compound wall plinth level or 1.2 metres (4ft.) above ground level whichever is lower, excluding items of flooring and D.P.C but including base concrete below the floors.

    …...

    (f) For open storm water drains, all items of work except lining of drains.

    …...

    The rate of any such work except the items relating to foundations which is in excess of the deviation limit shall be determined in excess of the deviation limit shall be determined in accordance with the provisions contained in Clause 12 A.”

    25. The work of foundation is, therefore, not governed by Clause 12 A. The reference to the said clause in the impugned Award, while discussing this claim, does not affect the validity as such of the impugned Award.

    26. The learned Arbitrator has calculated the sub-items of foundation where the deviation was more than 25%. There were 6 such sub-items and by working out the difference between the market rate and the agreement rate, the total amount payable in respect of the extra work for foundation was calculated as Rs. 21,08,789.45. Mr. Verma sought to rely on Annexure P-10 to the petition to show the basis on which the payment was made in the final bill. What the Petitioner has sought to do is to total up all the items constituting the foundation work and by aggregating all such items, both as regards the quantity as well as the rate, has determined the deviation percentage as 7.47%. This was sought to be explained to the Court by referring to Clause 12(vi)(a) which states that the deviation limit is the net effect “of all additions and deductions ordered on all items.” However, the Petitioner overlooks the main Clause 12(vi) which starts with the words “except in case of items relating to foundations ….”. Clearly, therefore, Clause 12(vi)(a) cannot apply to the foundation work and, therefore, the deviation is not to be determined by totaling the additions and deductions on all items.

    27. There is no dispute on the actual quantity executed in respect of the 6 sub-items of the deviation where the deviation took place. These are Sub-Items 1.1 relating to earth work in excavation over areas, 1.3 (filling available earth), 1.4 (extra for additional lift), 2.1.1 (providing/fixing c.c 1:5:10 in footings), 3.1.1 and 3.1.2 (RCC in rafts, footings etc.). The learned Arbitrator has actually not granted the market rate but has correctly observed that the deviation percentage was well above 25%. It was, in fact, 549%. Accordingly, in the impugned Award he accepted the increase in the cost of foundation to Rs. 35,63,685. This Court has been shown the basis on which the learned Arbitrator arrived at the above figure. In the impugned Award, the learned Arbitrator has given the methodology for arriving at the rate. He has explained that they were “mainly based on Labour coefficient as per Delhi Analysis of Rates for CPWD, rates for Labour as per Muster Rolls paid by claimant, cement & steel at issue rates stipulated in the agreement, other material at market rates assesses as reasonable and profit at 15% on the basis of Clause 10(cc).” The learned Arbitrator has then proceeded to allow Part C of Claim No. 1 to an extent of Rs. 94,34,995 as against the claim of Rs. 1,53,53,413.

    28. This Court is not persuaded to hold that the learned Arbitrator has committed any patent illegality in coming to the above conclusion. It is based on a correct appreciation of both the facts as well as the relevant clauses of the agreement. Even as regards the differential rates for the superstructure, the reasoning contained in the impugned Award cannot be faulted.

    29. Mr. Verma next submitted that under Part D, the learned Arbitrator erred in allowing a sum of Rs. 17,18,159 for extra items less paid in final bill. The differential rate given in the column, as explained by the charts produced by the Respondent, is marked as Exhibit C-218. The learned Arbitrator allowed the payment of extra items applying Delhi Schedule of Rates, 1993 (‘DSR’) in respect of 5 sub-items. He adopted the rates indicated by the Department itself in the running bills in respect of 5 others. There is sufficient explanation available on record which has been referred to by the learned Arbitrator. For the above reasons, the objection as regards the impugned Award in respect of Parts C and D of Claim No. 1 is hereby rejected.

    Rebate

    30. The next issue concerns the grant of rebate. It was found that the Petitioner had deducted a total of 4 rebates of 3.80% in the interim and the final bills despite repeated protest by the Respondent. The unconditional rebate of 1.80% was held limited to the tender amount before rebate (Rs. 6,41,59,006 which worked out to Rs. 11,54,862). It was observed by the learned Arbitrator that the following 3 rebates could be availed of by the Petitioner only upon fulfilling the conditions indicated in the agreement:

    “(ii) 1% (one percent) on the tendered amount for monthly payment which shall be made if the net value of work done since previous bill is not less than Rs. 8.00 lacs (eight lacs only).

    (iii) 0.50% (zero point five zero) on the tendered amount if the final bill for undisputed items is paid within six months from date of completion of work as recorded by Engineer in charge.

    (iv) 0.50% (zero point five zero percent) on the tendered amount for releasing of security deposit after six months of expiry of completion dates but before seven months.”

    31. The learned Arbitrator has categorically found that as a matter of fact the Petitioner herein failed to fulfill the conditions for availing the above rebates. It was held that only the recovery of the unconditional rebate of 1.80% in the sum of Rs. 11,54,862 was justified. Accordingly, the balance amount was asked to be paid.

    32. Mr. Verma submitted that the calculation of the rebate was erroneous as it ought not to have been on the tendered amount but on the gross amount. He referred to the letter dated 12 December 1995 written by the CPWD to the Contractor which stated, inter alia, that “all the four rebates as above totaling to 3.80 (three point eight zero percent) offered by you shall be applicable on the gross amount of the bill excluding the additional altered and substituted items payable under clause 12 of the agreement and shall be recovered individually from each running account bill and final bill.”

    33. It is seen that the above letter dated 12 December 1995 was in response to a letter dated 24 November 1995 written by the Respondent by which it accepted all the conditions of that letter. The said letter clearly stated that the Respondent was offering the unconditional rebate of 1.80% and the further rebates of 1%, 0.50% and 0.50% on “our tendered rates.” The expression that the rebate in the rates “shall be applicable on the gross value of the work done” did not mean that they had to be calculated with reference to the gross value. It only meant that the rebates, as calculated on the tendered amount, would be deducted from the gross value of the work as indicated in the bills. It is also seen that it is only at the stage of the final bill that the deductions were said to be made by hand on the rebate amounts. There is no basis for such deductions. The learned Arbitrator, therefore, rightly decided the issue of rebate in favour of the Respondent.

    34. As regards the machinery and T&P, the learned Arbitrator has given cogent reasons for assessing the rental value for a period of 22.3 months at Rs. 1,40,000 per month which was actually far less than the DSR. For the remaining period up to 30 January 2001, i.e, 18 months, it was assessed at Rs. 80,000 per month. The above determination can hardly be said to be suffering from any patent illegality. Likewise, as far as staff is concerned, he assessed it for 40 months at Rs. 43,000 per month.

    35. This was a satisfactory method of disposing of Claims 2 and 5 and cannot be faulted.

    Loss of Profit

    36. It is sought to be contended that the loss of profit at best could be 10% of the total value of the work and not 15%. The learned Arbitrator has, in fact, not adopted a uniform rate of 15%. For instance, the overhead expenditure was assessed at 3%. No amount was awarded towards idle labour. Significantly, Claim No. 4 for loss due to abnormal increase in prices of materials and Claim No. 6 for loss of profitability/turnover has not been awarded. Even as regards Claim No. 8 on account of balance amount towards escalation, the learned Arbitrator has only awarded Rs. 7,13,344.

    Costs

    37. Under Claim No. 13, the learned Arbitrator has awarded Rs. 4,00,000 towards the cost of arbitration and further Rs. 10,000 as costs imposed on the Petitioner. Mr. Verma is right in his submission that even at the stage of seeking arbitration the Respondent had undertaken to bear the cost of arbitration. This is unable to be disputed by the Respondent. If, indeed, the Respondent undertook to bear the cost of arbitration then the impugned Award in respect of Claim No. 13 cannot be sustained. Accordingly, the impugned Award as regards Claim No. 13 is hereby set aside.

    Interest

    38. Finally, it was submitted that the learned Arbitrator erred in awarding the Respondent interest on interest.

    39. It is seen that under para 19.0 of the impugned Award, Claim Nos. 10 and 14 have been considered together. The learned Arbitrator has calculated the total interest at Rs. 7,16,428. He has awarded simple interest @ 12% per annum on the sums awarded against Claim Nos. 1, 2, 5, 7 and 8 from 31 July 2001 to 24 February 2011 and thereafter @ 12% per annum from 1 April 2007 to 24 February 2011 against Claim No. 9. Likewise, he has computed the interest under Claim No. 12 and, therefore, the total interest amount was Rs. 2,91,07,610. However, in paras 19.5 and 20.0, while giving a summary of the Award in respect of the different claims, the learned Arbitrator has also included the interest component under Claim Nos. 10 and 14 and determined the total figure at Rs. 5,44,49,010. Post-Award interest has been asked to be paid on the interest component also. In light of the decision of the Supreme Court in State of Haryana v. S.L Arora & Company(2010) 3 SCC 690 the above direction of the learned Arbitrator is legally unsustainable. Although the correctness of the said decision has been referred to a larger Bench of the Supreme Court, it still holds the field. Consequently, the impugned Award to the extent it grants post-Award simple interest on the interest component already covering Claim Nos. 10 and 14 is hereby set aside.

    Conclusion

    40. Consequently, the impugned Award in respect of costs under Claim No. 13 is set aside and the Award as regards post-Award interest is clarified as being payable only on the principal awarded amount and not on the interest amount under Claim Nos. 10 and 14. The rest of the impugned Award is upheld as it is. The petition is disposed of in the above terms.