With reference to the discussion had with you, we are pleased to renew and
re-allot to you, with effect from 1.4.88, contract for running both the covered
car parking and cycle/scooter stand at the abovementioned premises on the
following terms and conditions:
1. ...........
2.
3.
Yours faithfully,
_ Sd Gopal Ansal
Director‖
7.14 Ex.P-56/A does not contain any direction or condition to the parking contractor to
ensure that vehicles were to be parked in conformity with the plan sanctioned by the
authorities. This aspect is important, because by the time this agreement was entered into by
the accused, it was known that there were two electrical transformers in that parking lot.
There was need to ensure a higher degree of care, at all times, to conform to the parking plan,
avoid congestion in parking. Crucially, it was necessary that the parking contractor, as well as
the owner and occupier of the building, ensured that sufficient space was available for
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 222
vehicles to leave the building, and also that the 16' parking aisle mandated by the parking
sanctioned plan was kept for free movement of vehicles, at all times.
7.15 As far as oral testimony goes, in cross examination, PW-24 stated that a car had been
parked one and a half metres away from the transformer room; PW-27, the fireman, Bansilal
Meena, mentions about flames in the parking area, when he went, to quell the fire. Ex. PW-
35/A, the report of Shri K.V. Singh, also mentions about existence of burnt vehicles in the
parking area. PW-49/A, the report of the Chief Fire Officer, R.C. Sharma, mentions about
existence of cars 1 meter away from the transformer. He mentions, significantly that no
parking lines existed separating the areas; there were no separation line near the transformer,
for parking of vehicles. The fire, according to him, was confined to the DVB transformer
room and a number of cars and scooters in the parking area. PW-56, the parking contractor
deposed that cars were parked at a distance of 3-4 feet from the transformer room and that
one Contessa car was parked just touching the transformer room; but he deposed that
according to his employee, that vehicle was forcibly parked by its owner there. He also stated
that 18 car parking tokens were issued; he stated that a further 8-10 cars were parked in the
ground floor, belonging to the staff. This was corroborated by Ex. PW. 56/B (seized by
memo PW.56/C dated 31-7-1997) a description of the tokens issued for the show; they
mention issuance of 18 tokens at 3-30 PM. The seizure memo dated 7-7-1997, Ex. PW-78/C
corroborates this evidence; 16 cars, both in burnt and un-burnt condition were seized on that
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 223
date. The photographs PW-61/191, PW-61/208 and PW-61/211 also bear out the fact that
several cars were parked in the ground floor; many of them were in burnt condition. These
photographs were taken at site, on 29th July, 1997, by Gautam Roy, PW-61, Scientific
Assistant, CFSL. Ex. PW-2/A, a report by PW-2, confirms that in the original plan sanctioned
by MCD, a 16 feet width passage in front of the transformer was to be left
unoccupied/vacant. However, he stated that vehicles were parked on this area, which affected
free and smooth movement of vehicles. PW-64 says that the parking lot was affected by fire.
7.16 It was urged on behalf of the first two accused that permitting parking in the building
could not be construed as unlawful, as indeed there was sanction for this purpose, in the plans
proposed by the cinema, in 1973 and 1974. Reliance was placed on sanctioned plans, which
allowed parking of cars in the ground floor of the building, and two wheeler vehicles and
cycles in the basement. It was therefore contended that instead of manning the parking, the
cinema management decided to hand over this activity to a third party independent
contractor, PW-56. The initial contract in this regard was entered into in 1977; it was
renewed later in 1988. The said accused No. 1 &2 had no control over PW-56 or the manner
in which he performed his job; they could not be therefore held responsible for the so-called
improper parking of vehicles, even if it was proved that excess vehicles were parked. Having
given the contract to someone, who had functioned responsibly for more than 20 years, it
could be reasonably expected by the said accused that there would be no lapse in the manner
of performance of such contract by PW-56. It was urged, therefore, that the accused could not
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 224
reasonably be expected to foresee that the parking would be operated in a different manner,
or negligently.
7.17 This court has considered the materials on record. Ex. PW-56/A and other documents,
PW-56/B and Ex. PW-56/C were all put to the Accused Nos. 1 and 2, in questions under
Section 313. Accused No. 2, who had signed the letter Ex. PW.56/A, claimed ignorance
about the arrangement. Both accused said that they knew about the parking contract, and the
existence of cars in the parking lot. The sanctioned plans no doubt indicate that 15 cars could
be parked inside the ground floor premises; they also contain clear triangular demarcations
for this purpose. These plans (Ex. PW-15/Y-3; PW-102/C-16) show this position. Yet, these
plans also reveal that a 16 foot passage had to be maintained, for passage of the vehicles.
Furthermore, the number of cars parked on that date were about 28, according to PW-56. He
was also not present at the spot, when the fire occurred. He went there later. One of those cars
definitely was very near the transformer room. Many of these cars were burnt. The parking
contract does not disclose that the contractor was made aware about the conditions imposed
in the sanctioned plan, regarding restrictions on the number of cars which could be parked, or
about the need to maintain the passage, unimpeded at all times; the arrangement was also not
subject to any kind of check or supervision. All these show serious and grave omissions,
amounting to illegalities, in the manner of maintenance and supervision of the parking lot.
These omissions assume grave overtones, in view of the fact that the existence of two
transformers, (one without the sanction of the MCD) were within the knowledge of the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 225
cinema management, which was the occupier and owner of the ground floor. The fact that
they chose to ―outsource‖ the parking operation to PW-56 was for their convenience.
However, the nature of their responsibility to ensure that the premises were safe, could not be
disclaimed. Both under the Cinematograph Act, as well as generally, they had a duty to
ensure that vehicles which were parked in the ground floor immediately below the viewing
area (first floor) were maintained keeping all safety standards in mind. It is therefore held
that the parking lot was managed in a negligent manner, which was a significant contributory
to the fire.
Structural Deviations
7.18 The aspect concerning structural deviations has to be closely scrutinized, in view of
prosecution case that the deviations were a major contributory to the fire incident, resulting in
death of the 59 persons, in the balcony of the cinema hall, and grievous injury to 100 others.
It would be necessary at the outset to notice that the question of deviations was addressed
both during the trial, as well as in the appeals, by reference to documentary evidence,
particularly reports prepared by experts, as well as reports prepared by municipal agencies, at
the request of the licensing department i.e. the Delhi Police.
The substance of these reports, contained in two charts, shown below, with reference to the
exhibit numbers, outlining the deviations alleged, at the relevant points of time, are extracted
below:
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 226
7.19 The trial court noticed that the first inspection of the cinema hall took place in 1983.
The inspection report outlined certain deviations and irregularities. The document was
produced and marked as Ex. PW-17/B. The trial court recorded that:
―In 1983, due to fire incident in LPG godown at Shakur Basti and Gopala
Tower, Lt. Governor ordered for inspection of all cinema houses. Accordingly,
Joint Team of competent authorities inspected Uphaar Cinema on different
dates and structural and fire safety deviations were observed in Uphaar
Cinema on which the license of Uphaar Cinema was suspended for a period of
four days. Against this order, the licensee obtained stay order on 28.6.1983.
On account of said Stay Order, the temporary permits were issued and this
practice continued till 13.6.97.‖
It was noticed, later in the judgment that:
―41. On 1.2.1984, accused Sushil Ansal, Chairman of M/s Green Park
Theaters Associated Pvt. Ltd requested for renewal of cinema license. Shri S P
Aggarwal, Chief Fire Officer cum Deputy Commissioner ( Water) inspected
Uphaar cinema and pointed out certain deviations. On 16.5.84 Gopal Ansal
Director of Green Park Theaters informed that they have substantially
rectified the deviations and then again on 31.5.84 Uphaar cinema was
inspected and consequentially, permit of Uphaar Cinema was renewed from
time to time upto 23.4.85 and subsequently upto 23.4.87 from 23.4.85 to
23.4.87.‖
7.20 The accused Sushil and Gopal Ansal contended that the trial court ignored an
intervening document, Ex. PW-37/K (Ex. D-84) dated 29th August, 1988. This document
was proved by PW-37 Ganesh Das Verma, retired Senior Stenographer, MCD. The
document is part of a common report in respect of 13 cinema halls that were inspected. The
report, as may be, noticed from the preceding Table-I above, lists out 11 points. It was
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 227
contended on behalf of accused No.1&2 that a comparison of Ex.PW-17/B and Ex.PW-37/K
would show that whereas the former listed 11 irregularities, the later inspection of 29.8.1998
showed that in August, 1998 itself the wooden plank flooring, (one of the main objections
relating to creation of additional floor between stilt floor and floor of the auditorium) had
been removed. The second report also showed that the Homeopathic Dispensary was not
seen as a fire hazard and that the printing press noticed in Ex.PW17-B as well as combustible
material stored in the basement had been removed. Thus the most serious objections about
use of the building or existence of structural deviations had been rectified and properly
addressed. It was urged that the subsequent report of the Delhi Fire Service dated
12.8.1994 (marked as C-95 by PW 37) had to be read with the previous reports as it
concerned itself with the points listed in the earlier documents. It had been contended that
those objections were in existence and did not relate to the fire service. However, this report
nowhere mentioned that a Homeopathic Dispensary existed or that wooden planks were
inserted or put back as contended by the prosecution. It was submitted that the other
objections pertaining to occupation of basement, blockage of other areas (excepts as regards
occupation of various agencies and offices forming part of staircase and loft) were not even
mentioned or even spelt out in this report by the Delhi Fire Service.
7.21 According to the accused Ex.17/D (dated 30.4.96) as well as Ex.16/E (dated 6.5.96)
showed that: -
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 228
(1) There were no unauthorized wooden planks forming an additional floor in
between the stilt floor and the first floor.
(2) M/s East Coast Breweries Ltd. had vacated their office from the basement.
(3) Certain partitions walls were in existence which according to the official agencies
needed rectification.
(4) The R.S. Joists (Steel structures) on which wooden planks were placed earlier
(but removed) were in existence and had not been removed.
(5) Third floor was let out to various organizations.
(6) The Homeopathic Dispensary said to be unauthorized and a fire hazard was in
existence.
(7) The Printing Press noticed in 1983 had been removed as far back as in 1988 and
did not find mention in the subsequent inspection of 1994 and two inspections in
1996.
(8) No part of the basement was used to store combustibles material. This had been
initially found in 1983 but subsequently rectified and so reflected as rectified in all
the four later reports.
(9) An office on a part of the additional floor on the wooden plank was in existence;
however, the fire service did not mention that this was a hazard in any report.
(10) The space used by Anil Chopra and Company found in the First Information
Report of 1983 had been vacated. This was reflected in all the subsequent reports
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 229
Ex. PW 37/K, Ex PW 17/D, Ex PW16/E and the report dated 12.8.94 (marked as
C-95 by PW 37).
(11) The space marked for restaurant was let out to a Bank.
7.22 The contentions here were that contemporaneous inspections reflected in the reports
produced by the prosecution had shown how progressively the cinema addressed the issue of
fire hazard. When it was pointed out that wooden plank based additional floor on R.S. Joists
had been created, the planks was immediately removed. So far as the Homeopathic
Dispensary was concerned even if it were to be considered a deviation, the prosecution was
unable to establish how it contributed to the accident or prevented egress or ingress of the
patrons from the cinema at the time of the accident. Similar arguments were made in respect
of R.S. Joists; the contention here was that the prosecution could not prove how its existence
at a height of above 8 feet from the floor (at ceiling level) in any manner hindered free
passage to the patrons. The other contention with regard to the letting out the third floor to
various organizations and existence of offices on the top floor for which no permission was
required, two arguments were made. It was firstly argued that the permission to let out
portions of the building was given as far back as on 12.7.1974 evident from Ex.102/D1.
Similarly the partitions of basement were itself not an unlawful act for the reason that it was
compoundable deviation if there was proper ventilation in the basement.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 230
7.23 The deposition of PW-39 was relied on in support of this contention. It was urged
that four partitions walls in the basement had not co-relationship with the incident and could
not have contributed either to the fire or to the spread of smoke which ultimately resulted in
death. The evidence of PW-39 was relied on to say that the wooden flooring in the
Homeopathic Dispensary per se could not be construed as a structural deviation and certainly
not a fire hazard. The evidence of the same witness as well as PW/18 was relied on to say
that the mere existence of R.S. Joists did not cause any hazard; nor was it unauthorized.
7.24 It was next contended that the Court should give credence to pre-1997 inspection
reports which had recorded faithfully what was found before the incident and not the contents
of the reports created after the event. The accused contended that there were several internal
inconsistencies and glaring contradictions between such reports relied upon by the
prosecution i.e. Ex.39/B dated 30.06.1997, Ex. PW-29A dated 2.8.1997 and Ex.PW2/A dated
11.8.1997. The first in the series was a report of PW/39 it listed only six so called
irregularities. The report prepared by fairly senior officer of the MCD nowhere reflected that
there were any structural deviations of the kind found by the Trial Court. He merely
reiterated the existence of partitions walls, R.S. Joists, Homeopathic Dispensary and
conversion of restaurant into a Bank. He also determined that the lift well from the ground
floor to the basement was converted into an office of Sehgal Carpets and that Manager Room
and W.C. on the ground floor had been converted into verandah. These surely could not be
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 231
considered structural deviations and certainly not deviations of such a serious nature as could
have contributed to the fire, spread of smoke or aggravated the accident and ultimately the
death so as to fasten any kind of liability on the accused.
7.25 As regards the other two reports, (Ex-29/A and Ex.2/A), the contention was that they
showed deviations incrementally. Ex.PW29/A showed about 24 deviations as a whole in the
building, whereas 2/A which was prepared barely ten days later, showed more deviations.
There were internal contradictions as between two documents. These clearly established that
the prosecution started to improve upon its case and ‗dig out' minor variations with a view to
project major structural deviations somehow to implicate the accused and ensnare them.
7.26 It would be relevant at this stage to deal with objections to the reports Ex.2/A and Ex.
PW-29/A and depositions of their authors. In relation to Ex. PW-2/A, it was contended that
PW-2 had not visited the site with an original sanctioned plan, but with a photocopy, and that
the other members of the team did not sign the report. The other objection was that the
witness did not speak about the deviations in his testimony and that the report could not be
considered one, since it did not furnish reasons in the opinion, to conform to the requirements
of Section 51 of the Evidence Act.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 232
7.27 As regards PW-29 and his report, Ex. PW-29/A are concerned, the argument was that
the report was not signed by police officers present on the spot; the report was not forwarded
to the SDM, and further that the report was not prepared on the spot. So far as objections to
PW-2/A are concerned, the contention that the witness went and inspected the site with a
copy, would not per se undermine it; however, being an opinion, the Court would have to see
whether it is corroborated in material particulars. The Court would have to satisfy itself as to
the credibility of what is stated, on its merits. As far as the question of other members of the
team not signing the document is concerned, PW-2/D contains the signature of other officials;
PW-2 has deposed about the report. The contention that the report is unreasoned, cannot be
accepted. The report adverts to specific provisions of byelaws [Byelaw 2(49); 54; 76(2) and
(3); 25; 98, of the 1959 Byelaws]; it also specifically states, wherever deviations were found
from the sanctioned plans. Thus, the contention has no force.
7.28 As regards PW-29, no doubt be admitted not having prepared the report at site. Yet,
that would not vitiate it. The document was included in the list of documents, and the
irregularity of the police in not signing at the time of inspection, cannot be such as to
undermine its credibility, since PW-29 was extensively cross-examined. Besides, the witness
is unconnected with the event, as he is an engineer from the Public Works Department
(PWD). For these reasons, the arguments of the accused, about Ex. PW-29/A are unfounded.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 233
7.29 It was submitted that a comparison of the three post 13.6.1997 reports shows that:
(1) according to PW-39/B four partitions existed in the basement up to the ceiling
height which was in consonance with the pre 13.6.1997 report. No such irregularity was
reflected in Ex.PW-2/A dated 11.8.97. On the other hand, Ex- PW -29/A dated 2.8.1997
showed four deviations, not reflected in Ex.2/A.
(2) the irregularity or deviation in respect of outer wall constructed beyond the
height of 3 feet, behind the area of the transformer was first mentioned in the Ex.29/A dated
2.8.1997 ; this portion of the wall was mentioned as unauthorized beyond the height of 12
feet in Ex.2/A. Reliance was placed on the plan Ex.102/C-16 to say that the original proposal
of a parapet wall at 3' was modified and shown to be fully constructed; the proposal was
approved by MCD. Reliance was also placed on Ex.PW17/DA completion certificate that
was preceded by scrutiny report Ex. 17/DX-9 (dated 10.04.1973).
(3) The conversion of spaces near the Manager room adjoining the ticket foyer
etc. into glazed verandah could not be construed as structural deviations so serious as to
endanger public safety or human life.
(4) While there was no dispute that the sizes of cubicles in the transformer room
had been varied, these were not structural deviations as they were permissible under the bye
laws being re-positioning of internal partitions.
(5) The observation that a mezzanine floor on the R.S. Joists with timber flooring
which had been completely burnt was without any evidence. Undoubtedly the mezzanine
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 234
floor had existed but as far back as in 1988, they were removed. Inspection Report Ex.PW-
37/K noticed that wooden flooring had been removed. Having regard to the evidence of PW-
27 and PW-49 who visited the site earliest in point of time and clearly mentioned that there
was no burnt wood at the spot as well as the evidence of PW-64 and the reports Ex.PW-24/A
and Ex.PW-64/D (which nowhere disclose any burnt wood, carbon or charcoal attributable to
such wood). These observations in Ex. PW-29/A and Ex.PW-22/F were blindly accepted
by the Trial Court.
(6) So far as use of a space converted as ticket foyer adjacent to the HT room was
concerned that could not be construed as a structural deviation. No evidence was led to show
that it hampered free egress or passage of patrons. This was not as clearly mentioned in
Ex.2/A.
(7) The use of space sanctioned for restaurant by the Syndicate Bank was
authorized as evident from Ex.102/D-1. The same document had permitted the cinema to use
top floor for commercial establishments. In these circumstances, the statements in Ex.PW-
29/A and 2/A as regards the so called structural deviations on the top floor were uncalled for
and the findings of the Trial Court, without any basis.
(8) The use of a stair case around the lift well by the Sehgal Carpets spoken to in
PW-29/A and PW 2/A were in no manner connected with the fire accident; even if they were
construed to be as deviation like the other observations which could at best be termed as
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 235
irregularities. They did not have any connection with the causa causan and certainly not with
the cause of death of or injury to the patrons.
(9) Positioning of the exhaust fans in the balcony area as well as 3rd floor rear stair
hall instead of opening into direct open space was a first time observation made in Ex.PW
2/A the report prepared on 11.8.1997. This was not even commented upon or found in any of
the previous six reports. Besides, it was not proved if it contributed to or aggravated the
smoke.
7.30 This Court proposes to analyze the documentary evidence in relation to each
deviation, commented upon and found by the Trial Court in the light of the arguments made
by the accused as follows: -
(a) One of the significant findings rendered by the Trial Court was as regards the
construction of the rear outer wall. The oral evidence relied upon in this regard is of PW-2.
The documentary evidence is in the form of plan Ex.15/X-9 (the stilt/ground floor plan
sanctioned by order dated 30.5.1972). This drawing (No.4) is in the series containing
proposed additions in red colour and deletions in yellow. The outer wall of the building is
de-noted in two parallel lines with small square blocks intercepted in between signifying
pillars. The legend at two places describe the wall as a ‗3 foot parapet wall'. This plan
significantly discloses that only pillars on the right in the middle side immediately behind the
L.T. Transformer were coloured in red. However, the outer 3' wall was shown. This is a
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 236
cloth bound plan. The corresponding plan recovered from the Ansal Bhawan is Ex.PW-
102/C-1. It is the copy of the same drawing (Ex.PW-15/X-9) containing the signatures of
the same MCD Officer and that of the owner. This, however, shows that the portion of the
outer wall (shown in this plan also consistently as 3 foot height wall, (but corresponding at
the back of the wall from the middle transformer room) was coloured in red. In both the
drawings, i.e. Ex. PW102/C-1 as also Ex.PW-15/X9, the rest of the outer wall is shown as
parapet wall.
7.31 The building parking plan relied upon by the prosecution and recovered from the
office of the MCD Ex.PW-15/X7 is similar to the Ground floor plan (Ex.PW-15/X9) except
that parking slots are clearly marked out. This MCD map, a cloth backed one does not show
that the parapet wall is covered; indeed it shows that the entire outer wall up to the end of the
back side of the transformer room was 3 foot height parapet wall. The corresponding map
recovered from the Ansal Bhawan Ex.PW102/C-2 (through Seizure Memo Ex.PW102/A) is a
copy of Ex.PW15/X7. This, however, shows a section of the parapet wall is built up. The
1973 Parking plan recovered from the office of the MCD, Ex.PW-15/Y3 was sanctioned by
order dated 22.3.1973. This shows a 3 foot height parapet wall. It is an original plan
recovered from the MCD office and is cloth backed one, according to the Bye laws. It also
contains the signature of Accused No.1. The alterations and deletions are marked in red and
yellow colour respectively. There is no indication that the concerned section parallel to the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 237
transformer section was to be fully built up. A copy of this document (Ex.PW-15/Y3) is
Ex.PW-102/C-16 seized through Ex.PW-102/A from the Ansals' office. It is the copy of
Ex.PW15/Y3. It also reflects the 3 foot height parapet wall. Unlike PW-102/C-1 or PW-
102/C2 this does not bears the original signatures of any MCD officials or the stamp
sanctioning the plan. No further comment can be made about this except that it corresponds
in all respects with Ex.PW-15/Y3 as regards the extent of 3 foot outer parapet wall in the
entirety of that section. The last in these series is Ex.PW-15/Y-11 recovered from the office
of the MCD. This is the Ground floor plan sanctioned in 1973. This too uniformly shows that
the outer wall at a height of 3 foot; it does not disclose that any portion of that outer wall
extended to the ceiling. This too is bound by cloth as required by the bye-laws.
7.32 The oral evidence in this regard may be summarized at this stage. PW-2 - Chief
Engineer of MCD went along with a team of officials on 11.8.1997. He stated that the wall
was not sanctioned up to ceiling height. He stated in the report Ex.PW-2/A that a parapet
wall was constructed in full height ―whereas this wall has been shown in sanctioned plan up
to the height of 12 feet i.e. without any enclosure except some portion which was provided
with parapet, railing etc. for safety reasons‖. This witness supported his report and deposed
that the full wall up to the ceiling height as found at site was unsanctioned. He denied
suggestions to the contrary in cross examination on behalf of Accused No.1. PW-29/A the
Assistant Engineer in his report dated 2.9.1997 clearly mentioned that the outer wall behind
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 238
HT & LT room, transformer room was constructed up to the first floor height instead of 3 feet
height. In cross-examination on 21.09.2002 he stated that the full height of the wall had been
sanctioned. However, three days later on 24.09.2002 he sought to state to the contrary,
further deposing that at the time when he had previously recorded his statement, there was
noise in the Court hall. His subsequent version was objected to on the ground that such
retraction could not be permitted since witness was not declared hostile.
7.33 A conspectus of evidence in this regard would show that Ex.29/A, the first report to
mention about this particular deviation is clear enough that a full height wall was not
sanctioned. The maps in question i.e. the Parking plan and the Ground floor plans recovered
from the office of the MCD as well as the Ansals show that: -
(1) All plans consistently reflected two parallel lines as the outer wall.
(2) This wall is described in more than one place as a 3 foot parapet wall.
(3) The sanctioned plan Ex.102/C-16 recovered from the Ansals by Ex.PW-102/A
and the corresponding cloth backed MCD plan Ex.PW-15/Y-3 also describes
the outer wall as a 3 foot parapet wall.
(4) The Ground floor plan recovered from MCD office (Ex.PW15/Y-11) also
shows that the outer wall has a uniform height at 3 feet and describes it as a
―parapet wall‖.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 239
(5) There is a variation between the two sets of plans relating to ground floor and
the parking respectively sanctioned on 30.5.1972, recovered from the office of
MCD on the one hand and from the offices of the Ansals on the other. The
Ground floor plans sets are PW-15/X9 (from the MCD office); the
corresponding copy recovered from the Ansals is PW-102/C-1. They coincide
in all details except that in respect of the outer wall described as 3 foot parapet
wall the plan Ex.15/X-9 does not contain any red colour (signifying addition)
for a section of the 3 foot parapet wall behind the LT and transformer room,
whereas the plan recovered from the Ansals PW-102/C-I does so.
The MCD Parking plan Ex.PW15/X9 does also not contain such proposed
additions; the Ansals' plan Ex.PW102/C-1 contains such additions in red. The
other set i.e. the parking plan similarly reflect the same variations. PW-15/X7,
the cloth backed MCD plan recovered from its office does not show a covered
parapet; there is no proposal to add anything on that section of the wall.
However, Ex.PW-102/C-2, recovered from the Ansals' office shows that
concerned section of the parapet wall is sought to be added or constructed
upon just as in the case of Ex.PW-102/C1.
7.34 The net result of all this is that there are definitely discernable differences between the
plans, i.e. the two sets of plan recovered, from the MCD office on the one hand and those of
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 240
Ansals on the other. So far as the accused's arguments on this aspect are concerned, the
evidence of PW-39, who first inspected the site after the accident suggests that he did not
visit the place with the copy of any sanctioned plan. He only went with the photocopy of the
plan which did not reflect any comments regarding additions or deletions in the sanctioned
plan. Therefore, the omission does not assume any significance. The first person to inspect
the building with the plans and report of this issue is PW-29. His report clearly reflects the
deviations i.e. construction of section of the outer wall up to ceiling height. Now, it is a
matter of record borne by evidence that the ground floor ceiling is 16 feet. If the originally
sanctioned plans permitted a 3 feet parapet wall, the open section had to be above 12 feet,
(since it has come in evidence, in more than one place that R.S. Joists were at a height of 8'
feet from the ceiling, about half the height of the stilt floor). In view of this, it is apparent
that when PW-2 talks of a 12 foot wall and at the same time speaks of a 3 foot parapet wall,
the implication is that the space for the outer wall (left open) is 12 feet. However, he is clear
enough in his oral evidence that the entire section could not have been built up. If these are
seen together with the fact that plans recovered from the MCD, kept in the normal course of
official business, as well as Ex.PW-29/A/A-14 & 29/A-3 (original certified copies of the
plans, parking plans and Stilt plan recovered from the PWD office with the seals, produced
along with PW 29/A in the report) it is clear that outer wall had to be a 3 foot parapet wall; no
more no less.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 241
7.35 So far as the evidence of PW-29 is concerned, the extracts of his deposition, the first
during his cross-examination on 21.09.2002 read as follows:-
―Parafit wall is upto 3ft. from the roof level. The wall upto first floor
was sanctioned and thereafter, parafit wall upto 3ft. is sanctioned and
thereafter, if there is any construction, that is not sanctioned. The symbols
shown as boxes in Ex. PW 2A/17 show the existence of ventilators and these
boxes are shown in rectangular shape. It is incorrect that the outside wall is
sanctioned upto the top level or that my reading of the plan is not correct.‖
The subsequent deposition, during cross examination on 24.09.2002 is as follows:
―Cross-examination by Sh. Butan counsel for accused No.2 Gopal
Ansal Nil (opp. given).
(at this stage the witness submits that he wants to submit that height of outer
wall behind HT, LT panel and transformer room had been raised upto first
floor height instead of three feet).
Cross examination by Sh. Naseem, counsel for Sushil Ansal:
My statement was recorded on 21.09.2002. I had given the correct
statement on that date. It is correct that question regarding this wall was put
to me on the last date of hearing thrice. Vol. there was interruption on both
the sides so there was mistake. It is correct that when the said statement was
read by me before signing, the CBI Prosecutor and Ms. Krishna Murti was
present. But I read it myself and correction was made by me. After reading the
statement I had signed the statement and left. I had signed the statement after
reading the same and finding it correct. Though I stated that I will clarify my
statement on next date. It is incorrect to suggest that under the pressure of
CBI I am giving the clarification of wall being raised upto first floor height
instead of three feet. Vol. it is mentioned in my report. It is incorrect to suggest
that I am deliberately making false statement in the court. ―
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 242
These extracts of depositions show that the witness was clear that the entire wall up to first
floor height was not sanctioned, even when he was cross-examined on the first day
(21.09.2002).
7.36 In the light of this discussion, this Court holds that there is no infirmity in the finding
of the Trial Court that the ceiling level of the outer wall was not in accordance with the
sanctioned plan, and amounted to a structural deviation.
7.37 So far as R.S. Joists are concerned, it is undeniable that a mezzanine floors on these
steel structures at a height of 8 feet from the ground floor, existed some time in 1983. This
was pointed out as a deficiency and the subsequent report Ex-37/K shows that the wooden
planks were removed. Later, pre-1997 reports (Ex.-PW/37K, 17/D and 16/E) all consistently
mentioned that wooden planks were removed from the mezzanine but the R.S. Joists did not
exist. The evidence of PW-27 Mr. B.R. Meena, one of the Fireman to first reach the site and
attend to the fire as per as PW-49 Mr. R.C. Sharma, Chief Fire Officer show that there were
no ash, coal or burnt wood seen by them. The prosecution has also not disclosed that any
wood ash recovered and sent for analysis by any expert to be so. It is, therefore, held that
Trial Court findings are not borne out by the evidence led by the prosecution in this regard.
7.38 So far as the observation in PW-2/A that the parking area on the Ground floor did not
contain demarcations, the Parking plans consistently reflected that clear markings had to exist
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 243
at the site. Besides, these parking plans also delineated a 16 foot passage on the ground floor
for easy passage of vehicles. The report of PW-2 that such markings for cars did not exist
and that such demarcation of 16 foot passage also did not exist has gone unchallenged.
Besides, PW-49 also deposed about this. The findings of the Trial Court are, therefore, borne
out by the record.
7.39 Neither Ex.PW15/X9 recovered from the MCD office nor the parking plans recovered
from the Ansals' office PW-102/CD and PW 102/C-16 (the 1973 plans) or even the parking
plans recovered from MCD office (PW-15/X7 and PW 15/Y3) reflect that any of the
following ground floor structures were approved: -
(i) Homeopathic Dispensary behind LT/HT/Transformer Rooms on a part of the
ramp.
(ii) Enclosure of space to create a glazed verandah next to the Manager's room.
(iii) Enclosure of an open space adjoining the HT room as a ticket counter.
(iv) Use of a small portion at the mid landing of the staircase of the stilt floor at a
height of 8 feet, for use as an office.
7.40 As far as the permissibility of R.S. Joists is concerned, the evidence of PW-18 reveals
that he was unable to say whether this was contrary to rules or bye laws. PW-39 who
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 244
prepared the report Ex.PW-39/A too could not say whether they violated any building bye-
laws. Therefore, the findings of the Trial Court in this regard are not sustainable.
7.41 The prosecution contention about a deviation in the height of the transformer room,
i.e. its being sanctioned at 3 feet 6 inches below the ramp level, is based on a reading of the
sanctioned plan (Ex.PW-15-Y/3) and the report of CBRI (Ex.PW-25/A) as well as testimony
of PW-25, who mentioned that the transformer room was at a higher level than the parking
ramp. The evidence of PW-2, PW-29 and PW-39 as well as the reports submitted by them,
Ex.PW-2/A, PW-29/A and PW-39/A, however, do not reflect these as deviations. The effect
of this state of affairs, its facilitation in the spread of spilt transformer oil, and the resulting
inferno, are an altogether different matter. But, in the light of the evidence led, it cannot be
held that the height of the transformer room was a deviation from the sanctioned plan; the
experts, (who included the Chief Engineer and Executive Engineer, MCD and Assistant
Engineer, PWD) having knowledge in the relevant field did not speak of this as a deviation.
7.42 The observation of PW-29 in PW 29/A and PW-2 in PW-2/A that the shifting of
internal partitions walls in the LT Room, transformer room and HT room was a deviation
even though the overall outer size was in accordance with the plan, sought to be countered by
the accused that such internal repositioning is permissible under the bye laws, appears to be
prima facie attractive. However, as observed in the previous section of this judgment, the
most important aspect in this regard was the lack of approval by the Licensing Department as
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 245
well as the MCD for installation of two transformers. If the Uphaar transformer alone had
existed and repositioning of partition walls had been made, the arguments on behalf of the
accused would have been more credible. However, the repositioning of the walls whereby
the HT equipment was placed alongside, the LT equipment making rooms for two
transformers, was a crucial deviation which could not have been deemed merely irregular.
Specific approval had to be obtained for this having regard to the nature of the building and
the dominant use for which it was to be put i.e. as Cinema Hall, which was to house or host
several hundred people and visitors during most part of any day. Clearly such permission
was lacking. The trial court's findings here, are based on the materials, and, therefore,
justified.
7.43 So far as the deviation in the first floor where two snack bar counters existed by the
side of the rear stall, near the exit gate and one near the stair case are concerned both PW-
29/A and PW-2/A speak about them. The positioning of a refreshment counter by itself not
amount to a deviation. However, what is of significance is that they caused obstruction in the
free movement of patrons which is a violation of bye law 76 (2) & (3) of the building bye
laws of 1959. The placement of such counters cannot be called structural deviations - they
were violations of bye laws, since they inhibited free passage of patrons and obstructed
smooth egress, so crucial in the case of an emergency. This also violated Para 10 (1) of the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 246
first Schedule to D.C.R., 1953 and thus constituted a violation of the condition of licenses as
well as Section 14 of Cinematography Act.
7.44 The evidence relied on in relation to the deviations of the Second Floor except within
the balcony are discussed below: -
(i) Both PW-2/A and 29/A speak about the sweeper room and adjoining
toilets being converted into an office room during their depositions. According to
PW-2/A report, this constituted violation of Building Bye Law 98 (4) (r). The first
two accused did not cross examine either PW/2 or PW/29 in this regard. The findings
on these deviation is upheld.
(ii) Both PW-2/A and PW-29/A speak of conversion of the Operator rest
room into an office-cum-bar room with drink counter. This conversion was described
by PW-2/A as retiring room along with office and attached toilet-cum-dress. PW-2
was not cross examined by accused No.1 & 2 and PW-29 during the cross
examination confirmed as to the existence of office-cum-bar room which had been
converted instead of Operator rest room and stated that there was no bottle of liquor in
the bar room. He deposed that there were chairs and sofas in the bar room and food
could be taken from the counter. This deviation, therefore, was proved.
(iii) According to Ex.PW-29/A in between the second floor and loft floor, a
full width door on the right side stair case landing had been positioned which caused
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 247
hindrance in excess to the terrace. This went unrebutted; this fact was, therefore,
proved.
(iv) According to PW-2/A, toilet block on the Second Floor was converted
into an office and it constituted violation of bye-law 98 (4) (o). This was not contested
during the course of PW-2's cross examination. This deviation too was, therefore,
proved.
(v) PW-29/A stated that a reception counter of M/s Sareen Associates, an
occupant in the top floor, having its office located on the staircase leading to the
terrace was an obstruction to the staircase passage. There was no challenge to this;
the fact was, therefore, proved.
(vi) Four exhaust fans were positioned to open in the front stair case hall
instead of opening to a direct open space. This was mentioned in both Ex.-PW-2/A
and PW-29/A. PW-2 was not cross examined; in cross examination PW/29 clearly
mentioned that the exhaust fans should have faced an open area. According to PW-
2/A this was in violation of bye law 32 of Building Bye Law, 1959. This fact too,
was, therefore, established.
7.55 Point No.3, 8 & 10 in very report Ex.PW-17/B dated 9.6.1983 mentioned about letting
out the Third floor to various organizations, creation of a part in staircase into an office plus
loft over it on a part of the staircase on the top floor and extending it to the portion above
toilets shown in the sanctioned plan and lack of permission in terms of condition 17 of license
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 248
for the offices. The subsequent reports PW-37/K dated 29.8.1988; PW-17/D dated
30.4.1997, the report dated 12.8.1994 and PW-16/E dated 6.5.1996, all reiterated these
objections. The post 13.6.1997 reports i.e. Ex.PW-2/A, Ex-39/B and Ex.29/A also referred to
four offices as well as conversion of stair case over the loft level at different levels into
office. PW-2/A in his report clearly mentioned that these offices amounted to violations of
bye laws 32 & 98 of Building Bye Laws, 1959. The Trial Court found that these amounted to
violations.
7.56 The appellants' contention is that permission to let out had been granted far back on
12.7.1974. They also rely on Ex.102/D-1. It is also contended that deviations were never
notified through any show cause notice or determined to be hazards by the concerned
Municipal office. Under these circumstances, determination by the very same agencies after
the event should be seen all such offices being contrary to bye-laws should be viewed
suspicion as an attempt to cover up the official omissions rather than pointing at any fault by
the Cinema or its Management.
7.57 The argument that the licensing department had given permission, for the letting out
of the third floor or for that matter any part of the premises through a letter dated 12.7.1974
(Ex PW 102/D and Ex PW 17/DC), has to be viewed in the context of the other facts and
circumstances. The relevant portion of the letter granting permission is extracted below: -
―With reference to your letter dated 19.6.74 on the subject noted above, you
are allowed to let out the portion of the cinema building i.e. top floor and
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 249
ground floor to commercial establishments u/r 45 (xi) of the Delhi
Cinematograph Rules, 1953‖
7.58 All the pre-tragedy inspection reports, such as, Ex PW 37/K, Ex PW 37/C, Ex PW
17/D and Ex PW 16/E mention about the third floor commercial establishments as well as the
homeopathic dispensary on the ground floor. No doubt, Ex.PW 37/K states that the existence
of the dispensary is not a fire hazard; yet, it is listed as a deviation or area of concern. Ex.PW
37/C, Ex PW 17/D and Ex PW 16/E also mention this. So far as the top floor offices and the
enclosure of a part of the staircase, as well as the creation of the lot are concerned, Ex PW
37/C, Ex PW 17/B and Ex PW 16/E mention that they have been removed. The letter of the
cinema management dated 30/8/1994 (Ex PW 49/F), claimed that the concerns have been
addressed in the following terms:
―Your Divisional Officer Mr. Pawar inspected the above premises as per the
Court Directives to ascertain whether we have complied with the conditions
issued by the Court or not to meet the fire fighting and fire safety measures in
the above complex.
We confirm the following:
1. Wooden planks have been removed. Steel members in the area are no
hazard and hence not removed. (parking)
2. Homeopathic Doctor's cabin has bgeen got vacated. (parking)
3&4 The basement is not being used for any other purposes except for parking
as sanctioned. Also proper fire arrangements are existing in the basement.
The entire basement has automatic sprinkling system.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 250
No combustible material are being stored in the basement. Incidental spares
for operating cinema are only being stored in a small store in the basement
room. The store is protected by fire extinguishers.
5. No office exists above the stair case as alleged.
6. Store room in the basement is being used as store of Cinema only and
not by any company.
7. Offices on the top floor have been provided with suitable fire
protection arrangements.
8. The restaurant sanctioned on ground floor is in the
possession/occupation of Syndicate Bank which is less hazardous than a
restaurant.
9. Denied.
Thanking and assuring you of our best co-operation at all times.
Yours faithfully
for GREEN PARK THEATRES ASSOCIATED PVT. LTD.‖
7.59 Ex PW 37/AC was the reply to the above letter, by the Fire Service Authorities, which
clearly stated that the offices near the staircase and on the top floor, were still matters of
concern from the point of view of fire safety, in the following terms:
―Please refer to your letter No.nil dated 30.8.94 on the matter cited as subject.
In this connection, it is to inform you that the inspection of Uphaar Cinema
was carried out by the Asstt. Divisional Officer P.K. Sharma accompanied by
Station Officer Surinder Dutt to verify the compliance of the shortcomings
pointed out earlier vide our letter dated 12.8.94. During the course of
inspection, following shortcomings were observed:
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 251
1. As regard to point at Sl.No.8, an office has been erected forming part
of the staircase on the top floor is still in existence.
2. At least three offices on the top floor having wooden partition are still
in existence and there is no fire extinguishers accept one DCP of non ISI mark
found kept.
In view of the above you are requested to rectify the above mentioned
shortcomings under intimation to the undersigned.‖
7.60 Cumulatively, these show that although permission to let out the top floor was given
on 12.7.74, yet, all the inspection by statutory agencies, particularly the fire safety authorities
unanimously determined them to be fire hazardous from the safety angle.
The Court cannot also be oblivious to the fact that the cinema had not been granted
permanent license on annual basis, ever since the first report after 1983. These deviations,
therefore, assumed an incrementally risky character, which the cinema occupier/licensee and
management were aware of. That no penal action was taken at that time, in the opinion of the
court, is no answer to the existence of these risks and the consciousness on the part of the
licensees/occupier of the cinema. More importantly, the aspect of structural deviations and
issue of the fire hazards, has to be viewed in the light of the following remarks made in Ex
PW 2/A:
―1. Conversion of cinema hall into cinema cum private office complex;
2. Shifting of cinema administration offices at various floors without
keeping in mind the aspect of proper ventilation and sanitary requirements;
3. Opening of exhaust fans in the stair-hall instead of opening into a
direct open space;
4. Erection of R.S. joists in between stilt & first floor to create extra
floor;
5. Enclosure of stilt area and construction of dispensary in the stilt area;
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 252
6. Storing and using of various combustible materials including provision
of wooden acoustic panels and wooden partitions in the building;
7. Considerable increase in number of seats in the auditorium and also
creation of boxes/dress circle; and
8. Closure of one of the exits and shifting of gangway from its proper
sanctioned plans and also reduction in width of one of the gangways thereby
increasing travel distance.‖
The position in the balcony of the cinema hall
7.61 The Trial Court found that, according to the original sanctioned plan, 250 seats were
allowed in the Balcony, which through a notification No.F2/45/75-Fi (G) dated 30.09.1976,
was increased to 293. The court found that in 1974, the inspection room was converted into a
14 seater private box for the use of the owners and subsequently, due to the increase in the
number of seats, the right side gangway was closed in lieu of which the middle gangway was
created. In 1979, the earlier notification (of 1976) allowing additional seats were withdrawn
and a show cause notice was issued for removal all 100 additional seats sanctioned at Uphaar
Cinema. The withdrawal/cancellation notification was challenged before this Court, which
directed the issue to be considered by the licensing authorities after inspection. In the
meanwhile, w.e.f. June 1978, an 8-seater additional box was installed where the right-side
exit from the balcony had originally been sanctioned (Ex.29/DL). In the year 1980, the
cinema hall sought for permission to install additional 15 seats in the balcony. After the
proposal was moved and fresh applications made, the additional seats were installed, after
04.10.1980 (Ex.29/DY & DZ).
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 253
7.62 The Trial Court found that changes made between the period 1974 and 1980 by
installation of 8-seater boxes on the right-side gangway, narrowing of passages (which
hindered free egress to the exits) and the closure of the right side exit violated several
provisions of the DCR, 1953 and DCR, 1981.
The arguments on behalf of the accused 1 & 2 broadly are as follows:-
(1) The relevant rules for determination of standards are the Delhi Cinematograph
Rules, 1953.
(2) Factually, there was no violation of any rule or law or any other building
norm.
(3) The placement of the 8-seater box, which led to closure of right-side exit,
repositioning/closure of gangway, installation of additional seats and other
changes in the balcony of the cinema hall was preceded by due sanction by
relevant authorities.
(4) The Trial Court findings that such sanction did not legitimize or render lawful
these changes, is contrary to the record and law.
7.63 At the outset, it would be relevant to notice the two sets of rules, DCR, 1953 and
DCR, 1981.
Delhi Cinematograph Rules, 1953 Delhi Cinematograph Rules, 1981
Procedure in granting license Procedure in granting license
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 254
3. (1) Licenses granted under Section 10 of 3.(1) Licenses granted under Section
the Act shall be either annual or temporary. 10 of the Act shall be either annual or
temporary, or casual.
(2) An annual license shall only be granted
in respect of a building which is permanently (1)(a) Any person desirous of erecting
equipped for cinematograph exhibitions and a Cinema House or converting an
in respect of which the requirements setforth existing building into a Cinema house
in the First Schedule to these rules are shall apply to the Licensing Authority
fulfilled. It shall be valid for one year from for a provisional clearance certificate
the date of issue and shall be renewable on the in respect of the building and the site
application of the licensee. plans. Such application shall be
accompanied by five copies of the site
(3) ―Notwithstanding anything in the and building plans giving details of
preceding sub-rule, an annual license may be the structure, location of exists,
granted or renewed in respect of building gangways, toilets, foyers, booking
already licensed for cinematograph windows, stair cases, lifts, projection
exhibitions. The cinema houses which come rewinding and switch rooms, parking
into existence after the issue of these rules, arrangements, etc. in the building
may be licensed only if all the provisions of plans and showing surrounding roads
the rules set forth in the First Schedule are and buildings in the site plans.
complied with.‖
Provided that the provisions of paragraphs The Licensing Authority after
1(1), (2) and (3), 4, 8(i), 9, 10(3), (4) and (5), scrutinizing the plans in consultation
13(2) and (3), 18(1), 19 and 29 in the First with the Executive Engineer, PWD or
Schedule may be relaxed by the Chief any other authority concerned if he
Commissioner in any particular case to such considers it necessary, shall, if the
extent and subject to such conditions as the plans are in conformity with these
Chief Commissioner may think fit. rules, grant a provisional clearance
certificate:
(4) Subject to the provisions of the rules
in Part V, a temporary license may be granted Provided that grant of such provisional
in respect of any place for exhibitions by clearance certificate shall not ipso
means of touring cinematograph only. A facto entitle the applicant for grant of
temporary license may be given in the first a regular cinema license on
instance by the licensing authority for a completion of the building or give any
period of two months. The validity of such a immunity from the application of any
temporary license may, however, be extended new provisions to these rules which
upto a maximum of six months by the State might be incorporated after the issue
Government. The aggregate period of touring of such certificate and before the grant
cinematograph at one place shall not be of a license under the Cinematograph
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 255
extended beyond the period of six months in Act.
any case. A fee of Rs.20/- will also be levied
for every extended period of two months or (2) An annual license shall only be
less. granted in respect of a building which
is permanently equipped for
cinematograph exhibitors and in
respect of which the requirements
setforth in the First Schedule to these
rules are fulfilled. It shall be valid for
one year from the date of issue and
shall be renewable by the application
of the Licensee.
and with the conditions of his license, for the conditions of his license, for the
maintenance of the licensed premises at all maintenance of the licensed premises
times and in all respects in conformity with at all times and in all respects in
the standards prescribed by these rules and for conformity with the standards
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 257
taking all necessary measures before any prescribed by these rules and for
cinematograph exhibition is commenced to taking all necessary measures before
ensure the safety of the public and his any cinematograph exhibition is
employees against fire and other accidents. commenced. The clearance from the
(2) The licensee or some responsible person Chief Fire Officer, Delhi Fire Service
nominated by him in writing for the purpose shall be obtained by the licensee to
shall be in general charge of the licensed ensure the safety of the public and his
premises and cinematograph during the whole employees against fire.
time where any exhibitions is in progress. (2) The licensee or some responsible
person nominated by him in writing
for the purpose shall be in general
charge of the licensed premises and
cinematograph during the whole time
where any exhibition is in progress.
examine the structural features of the building (a) call upon the Executive Engineer
and report whether the rules thereto have been to examine the structural features of
duly complied with; the building and report whether the
(b) call upon the Electric Inspector to examine rules thereto have been duly complied
the cinematograph and the electrical with;
equipment to be used in the building and to (b) call upon the Electric Inspector to
report, whether they comply with the examine the cinematograph and the
requirements both of these rules and of the electrical equipment to be used in the
Indian Electricity Act, 1910 and of such of the building and to report, whether they
rules made thereunder as are applicable, comply with the requirements both of
whether all reasonable precautions have been these rules and of the Indian
taken to protect spectators and employees Electricity Act, 1910 and of such of
from electric shock and to prevent the the rules made thereunder as are
introduction of fire into the building through applicable, whether all reasonable
the use of the electrical equipment, and precautions have been taken to protect
whether the prescribed fire extinguishing spectators and employees from
appliances have been provided, are in electric shock and to prevent the
working order and are suitable for the purpose introduction of fire into the building
for which they are intended. through the use of the electrical
(2) All defects revealed by such equipment.
inspections shall be brought to the notice of (c) call upon the Chief Fire Officer or
the applicant or licensee and of the licensing any officer authorized by him in this
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 258
authority, who may refuse to grant or renew behalf for the purpose of ensuring the
the license unless and until they are remedied proper means of escape and safety
to his satisfaction. against fire and to report whether the
prescribed fire extinguishing
appliances have been provided; are
fire working order and are suitable for
the purpose for which they are
intended.
(2) All defects revealed by such
inspections shall be brought to the
notice of the applicant or licensee and
of the licensing authority, who may
refuse to grant or renew the license
unless and until they are remedied to
his satisfaction.
2. No portion of the building shall be
occupied or used as factory,
workshops, or for storage purposes or
as a hotel. Licensing authority may
however, permit commercial block
provided safety requirements such as
independent means of escape are fully
ensured to his satisfaction. Only the
canteen for the preparation and sale of
food and drink alongwith sale counter,
within the premises of a theatre shall
be allowed with the permission in
writing of the licensing authority.
7.64 It would be first necessary to deal with the appellant's contention that DCR, 1981 did
not proprio vigore apply to this case. This submission is premised upon Rule 3(3) of the said
DCR, 1981.
7.65 Rule 3(1) prescribes the requirement that those desirous of erecting cinema halls or
converting an existing building into a cinema hall, have to apply to the licensing authority for
provisional Clearance Certificate. Rule 3(2) provides that an annual license shall only be
granted in respect of a building which is permanently equipped for cinematographic
exhibitors and in respect of the requirements set forth in the first schedule of the said rules
(DCR,1953 and DCR 1981), are fulfilled. Such annual license is to be valid for one year from
the date of its issue and is renewable through application by the licensee. Rule 3(3) provides
as follows:-
―Notwithstanding anything in the preceding sub rule, an annual
licence may be granted or renewed in respect of building already licensed for
cinematograph exhibitions. The cinema houses which come into existence
after the issue of these rules, may be licensed only if all the provisions of the
rules setforth in the First Schedule are complied with:
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 278
Provided that the specifications mentioned in the First Schedule may
be relaxed by the Administrator in any particular case to such extent and
subject to such conditions as the Administrator may think fit.‖
The mandate of Rule 3(3) DCR, 1981 cannot be viewed in isolation. It is part of a scheme
conceived by the rule-making authority under a continuing enactment, i.e. The
Cinematographic Act, 1952. That Act, by Section 10 enacts that ―no person‖ is entitled to
exhibit a cinematograph except through a license.
7.66 Section 12 enjoins the licensing authority (contemplated under Section 11) not to
grant a license unless it is satisfied that:
―(a) the rules made under this part (i.e. of the Act) (except) have been
substantially applied with and adequate precaution has been taken in the
place in respect of which the license is to be given, to provide for the safety of
the persons attending exhibitions thereon.‖
Section 16 empowers the Central Government to frame rules prescribing the terms and
conditions of the license providing for regulation of cinematographic exhibition, for securing
the public safety. Section 17 empowers the Central Government, subject to such conditions
and restrictions as it may impose to exempt cinematographic exhibitions or class of
cinematographic exhibition from any provisions of that part or any of the rules made under it.
7.67 The table containing an extract of the relevant rules reproduced in the preceding part
of judgment would show that, in material particulars, the concerns expressed in the DCR,
1953 are repeated in the corresponding provisions made in DCR, 1981 vis-à-vis safety
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 279
standards except in regard to a few details. These concerns require the licensee to conform to
standards meant for public safety in the case of emergencies. Rule 10(1) of DCR, 1953 and
DCR, 1981 are in para-materia except in regard to specific mention of the Chief Fire Officer,
Delhi in the latter rules. They cast absolute obligation on the licensee for due compliance
with its provisions, and conditions of licensee. Rule 12 (1) of DCR, 1953 corresponds to Rule
14 of DCR, 1981; both prescribe for pre-grant and pre-renewal (of licensee), inspection by
named authorities. Part-VI of DCR, 1953 (containing Rules 37-44) corresponds almost in all
particulars with Part-VI of DCR, 1981 (containing Rules 39-46). They deal with the
obligation to ensure safety that fire compliance intended for use in the enclosure are in
working order before the commencement of each schedule.
Para 2 of the schedule to both DCR, 1953 and DCR, 1981 are cast in the same terms.
However, DCR, 1981 prescribes that a commercial block may be permitted provided safety
requirements, such as independent means of escape are ensured, within the cinema hall
building. Para 3, 4 and 7(1) of First Schedule to DCR, 1953 are in para materia with Para
8(1), 8(3), 8(4) and 8(5) of First Schedule to DCR 1981. Para 7(2) and 7(5) of First Schedule
DCR, 1953 are similar to Para 8(2) and 8(5) of First Schedule to DCR, 1981. These are
concerned with the norms prescribed for seating. Similarly, the gangway norms are
prescribed in Para 8 (First Schedule) of DCR, 1953; they correspond with the gangway norms
prescribed in Para 9 (First Schedule) of DCR, 1981. Para 9 and 10 (of DCR, 1953) which
deal with entry and exit norms correspond with Para 11 and 12 of DCR, 1981.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 280
7.68 If a comparison of the relevant sets of regulations is made, it immediately becomes
apparent that the concerns sought to be addressed through DCR, 1981 are almost identical
with the concerns sought to be addressed in the DCR, 1953. So viewed, the enabling power
under Rule 3(3) has to be seen as the licensing authority's discretion (underscored by the use
of expression ―may‖] in that provision. The intention of the rule-making authority,
apparently, was to clothe the licensing authority with the discretion to renew licenses on a
case-to-case basis provided, it was satisfied that all the safety concerns, as deemed essential
under 1981 rules, were addressed. As discussed previously, these concerns - so far as the
present case is concerned, were closely similar, if not entirely identical. In any event, they
were not of such character as would have necessitated a drastic structural of the building. At
best, the strict application of DCR, 1981 would have resulted in repositioning or realignment
of certain seats within the balcony, a task or act not imposed in fact and certainly mandated
by law. Therefore, the Court cannot accept the appellant's contention that since the cinema
hall was built prior to DCR, 1981, the said rules did not apply to it. The adoption of such a
broad argument would lead to startling result whereby stricter standards made applicable for
public safety mandated by law makers, as essential for the use of public places, are relieved
to certain class of building. Standards, whenever spelt-out are uniform; there is no question of
a set of regulations working in a time wraps in relation to older owners of buildings or
establishments and another set of safety standards applying to establishments or buildings
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 281
constructed later. This conclusion is supported by the fact that the relevant part of Act
empowering licensing to such establishments begins with a mandate to the licensing
authorities to ensure that at all times, safety norms are satisfied (Section 12). The acceptance
by the Court, of the Appellant's contention would mean that at no given point of time, even
those standards - which are dynamic in nature, can be different having regard to the age of
the establishment. In matters of public safety, such an interpretation, though novel and
ingenuous, would spell disaster.
7.69 The first document relevant for consideration regarding the state of balcony would be
Ex.17/DA, a completion certificate issued by MCD on 10.04.1973. The license under the
Cinematograph Act, was issued on 24.04.1973 Ex.17/DB. The statement of conditions was
attached to the said licence in accordance with the Second schedule to DCR 1953. The
scrutiny report, which preceded the said completion certificate, inter alia deals with the
auditorium; the license is marked as Annexure PW17/DX-9. The auditorium, i.e. located on
the first floor measured 7839 square feet and was allotted 750 seats. The sanctioned area for
the balcony was 2691 sq. feet, 250 seats were sanctioned for balcony.
7.70 Ex.15/Y-1 to Y-16 is in the series of the first sanctioned plans dated 22.03.1973. It
deals with the balcony. The plans reveal that 250 seats were permitted. The plan provided
for an entry from the balcony foyer, and the exits could be accessed by two staircases one
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 282
from the right side of the building and the other from the left. Upon entrance the patrons
could move up to their seats. Two exits on either side of the balcony were provided for at the
same level. For movement, four vertical gangways were interspersed, they also led to a
horizontal gangway or a passage, facing the screen, described as ―Cross Gangway‖. This is
also reflected in the balcony plan exhibited through the trial and marked as Ex.PW-95/B-1.
The Cinema Management applied for provision of additional 14 seats, apparently by
converting the space sanctioned for an inspection room. They were permitted to do so by
letter dated 02.11.1974 issued by the Executive Engineer, PWD. This was marked as Ex.PW
29/DF.
7.71 On 30.09.1976, a notification, marked as PW 29/DC was issued by the Delhi
Government sanctioning extra seats, for various cinema halls in Delhi. The relevant portion
of that notification as far as it concerns Uphaar cinema distributed additional seats; 43 seats
were permitted in the balcony
―by adding seats in two vertical gangways and introducing new gangway in
the middle in lieu of this. This alteration is to be carried out in the right wing
of the balcony‖.
This resulted in a total of 293 seats in the balcony. The right side gangway was closed. A
gangway 111 CM wide between seat Nos. 8 & 9, in rows A to H was created; the other three
gangways remained unaffected. This shows that seats were added on the right side gangway
which was completely closed and a new middle gangway was created in the right side of the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 283
balcony. This resulted in obstruction to the right exit, which could be accessed only by
patrons sitting in the last row next to it and with some difficulty by the patrons sitting
elsewhere who had to turn back and walk a considerable distance. DCR 1953 did not
authorize this; the 1976 Notification did not say that the entire gangway could be closed.
7.72 On 24.05.1978, Accused-2 wrote the following letter (Ex.110/AA-20). The relevant
portion of the said letter is as follows :
―May 24, 1978
The Entertainment Tax Officer,
2, Battery Lane,
DELHI
Subject : Sanction of an additional box at Uphaar Cinema.
Dear Sir,
We are grateful to you for having sanctioned a family box for 14
persons at Uphaar Cinema quite some time back. You will appreciate that
with the passage of time, the family is growing; we would, therefore, be
grateful if you could kindly sanction us an additional private box comprising
of eight seats.
2. We wish to assure you that the same would be strictly for personal use.
The necessary drawings for the same are enclosed herewith.
3. Hope you would consider the case sympathetically and accord the
necessary sanction.
Thanking you in anticipation
Yours faithfully,
For GREEN PARK THEATRES ACCS (P) LTD.
SD/-
(DIRECTOR)
Encl : 3 sets of proposed drawings.‖
7.73 On 19.06.1978 (Ex. PW29/DK) the Entertainment Tax Officer to whom the request
for placement of additional eight seater box was made forwarded the application to the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 284
Licensing Branch with copies of the proposed plan seeking the latter's comments and
approval. On 28.06.1978, the Executive Engineer S.N. Dandona replied to the Entertainment
Tax Officer, a copy of this letter was also forwarded to the Uphaar Cinema. The said letter
reads as follows :
"The site has been inspected on 27.6.78 and the additional eight number seats
as a Private Box are in accordance with the Cinematograph Rules. The plan
received with your above referred letter showing the proposed additional box
is enclosed herewith in duplicate duly approved.‖
7.74 The Entertainment Tax officer expressed some reservation on 02.09.1978 (Ex.
29/DM). The reservation was in respect of the number of spectators who could be
accommodated within Clause VI of Firsst Schedule to DCR 1953. On 20.09.1978, Shri
Dandona wrote back (Ex. 29/DN) as follows:
―PUBLIC WORKS DEPTT (DA)
No.12 (62)/Uphaar/7879 Dated New Delhi the
20/9/78
To
The Entertain Tax Officer,
2-Battery Lane, Rajpur Road,
Delhi
Subject : Installation of 8 seats at Uphaar Cinema
Sir,
Kindly refer your letter No.F.2(48)/ETO/76/3260 dated 2.9.78. The
installation of 8 seats in the Properietor Box at Uphaar Cinema are within
clause 6 of the Ist Schedule of Delhi Cinematograph Rules, 1953.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 285
Yours faithfully,
Sd/-
(S.N. Dandona)
Executive Engineer,
PWD Divn. 2(DA)
New Delhi
Copy to the Licensee, Uphaar cinema Green Park, New Delhi for information
Executive Engineer.‖
The permission to place the additional eight seater box, which resulted in the blocking of the
right side exit was granted on 06.10.1978. The said letter is in Ex. PW 69/AA.
7.75 The result of this entire exercise was that the right side exit was rendered inaccessible
coupled with the complete closure of the right gangway. It is significant to notice at this
stage that :
(1) The notification dated 30.09.1976 (hereinafter referred to as `1976 notification')
allowed placement of seats and creation of a middle gangway. However, it did not authorize
the closure of the entire right side gangway, as that would have been violative of DCR 1953,
Para 10 of the Ist Schedule.
(2) The licensing authority as well as the Entertainment Tax Officer who authorized
closure of the right side gangway and blocking of exit on the right side, with the permission
to install eight seater additional family box, did not advert to any specific provisions of DCR
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 286
1953 which mandated existence of such gangway and the necessity of exits being positioned
on either side.
(3) On 27.07.1979, the Delhi Administration issued a notification (hereinafter referred to
as `the 1979 notification') withdrawing and canceling the 1976 notification. The result of
this 1979 notification was that the cinema hall had to restore the position exiting as on and
prior to 20.09.1976. This notification was exhibited during trial as Ex. PW 29/DP.
(4) This notification was challenged in writ proceedings before this Court. The court
passed an entire order requiring inspection of individual cinema halls. Later by the judgment
reported as Isherdas Sahni & Bros and another Vs. The Delhi Administration and Others,
AIR 1980 Delhi 147, the writ petition was disposed of requiring the various aspects to be
considered on a case to case basis, after inspection of each cinema hall, including Uphaar,
and examining whether the changes proposed to be retained by the management in the seating
capacity substantially complied with the DCR 1953 and other provisions of law. The
relevant portions of that judgment reads as follows:
―4. xxx xxx xxx xxx xxx
The authorities will also be guided by Sections 12 (1) (a) and 17 of the Act.
Section 12 (1) (a) of the Act is that the licensing authority shall not grant a
licence under part III of the Act unless it is satisfied that the Rules made under
Part III of the Act have been substantially complied with.........‖
―8. xxx xxx xxx xxx xxx
Therefore, the advice of the Fire and Health authorities had to be taken before
relaxation could at all be granted. We have seen at page 224 of the Paper
book the report of the Chief Fire Officer. A perusal of this report shows that
he was very reluctant to advise the making of relaxation in the Rules if the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 287
safety of the visitors to the theatres would be affected thereby. He has rightly
observed as follows:-
―Even under the normal circumstances the exit facilities are seriously
hampered by people rushing and it is felt that in case of panicky situation of a
minor nature, the people will be put to great difficulty which may even result
in stampede. In the circumstances, I feel that it would not be advisable to
allow extra seats required by the Managements. In a few theatres, however,
the difficulty may not be so acute. If at all any relaxation has to be considered
under unavoidable circumstances, our reaction to the proposals put forward
by the management of a few cinema houses may kindly be seen in the
enclosure.‖
xxx xxx xxx xxx xxx.‖
―9. xxx xxx xxx xxx xxx
In our view, a fair reading of the proviso to Rule 3(3) and the conditions under
which action thereunder is to be taken would show tht the relaxation granted
to the petitioners was not of such a nature that it could not be withdrawn at
all. As an ultimate consideration, we must point out that the petitioners have
come to this Court under Article 226 of the Constitution and the extraordinary
relief can be granted to them thereunder only to prevent injustice being done
to them. Their conduct also should be such as to deserve an equitable relief.
Since the main considerations underlying the grant of relaxation have now
disappeared, it is difficult to agree with the petitioners that the impugned
order of cancellation was such as could not be passed by the Government
under the proviso to Rule 3(3) read with Sections 14 and 21 of the General
Clauses Act.
xxx xxx xxx xxx xxx xxx‖
―17.The main order has been passed during the currency of the licences. But
this is inevitable. At any rate, in the light of the observations made above, the
dismantling of the seats on the ground that they do not substantially comply
with the Rules will be done I future after the Administration apply their mind
to the question. It cannot be expected as to exactly when this would occur. It
is not therefore, possible to ensure that any change in the sitting
accommodation would be enforced by the Administration only at the end of
any particular licensing period.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 288
18. For the above reasons, the writ petitions are disposed of in the light of
the finds given above and in the light of the observations as to the existing
additional seats and as to the changes which may have to be made in them in
future after the administration examine the question on merits and take steps.
No costs.‖
7.76 It is evident that the Court's observations and findings did not result in quashing of
1979 notification. The cinema management including Uphaar did not acquire any entitlement
to insist that benefits of the 1976 notification should be continued on a blanket basis. The
authorities were enjoined to consider whether retention of seats proposed by the 1976
notification or any part was in consonance with law and if there was substantial compliance,
permit such of the additions.
7.77 On 06.12.1979 the licensing department, through the DCP issued a show cause notice
asking the Uphaar cinema to remove all the 100 additional seats including 43 balcony seats.
This notice was exhibited and marked as part of Ex.69/AA- File. The relevant extract of the
said show cause notice is as follows:
―Balcony: 43 additional seats installed by adding seats in two vertical
gangways and introducing new gangway in the middle in lieu of this. This
alternation to be carried out on the right wing of balcony in contravention of
paras 8 (1) (b) and 6 91) of the Ist schedule of Delhi Cinema Rules 1953‖.
Hall : 57 additional seats installed by reducing the existing vertical gangways
from four to three and reshuffling of the seats in contravention of paras
5(1)(b) and 6 (1) of the Ist Schedule of DCT 1953.‖
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 289
7.78 On 13.12.1979 the cinema, through Gopal Ansal, second appellant, Director GPT,
replied to the show cause, the reply was exhibited as PW 100/AA2. It was contended that the
additional 43 sets installed were within the rules without prejudice it was contended that 85
additional seats in the balcony, in the auditorium were clearly within the rules and could not
be said to be violative thereof. The DCP (Licensing) Shri Amod Kant along with Shri S.N.
Dandona, Executive Engineer, PWD inspected the cinema hall. Their inspection report was
produced as Ex.69/CC (by order of Court dated 23.12.2004). The said inspection report reads
as follows:
"Of the 43 additional seats sanctioned in balcony, 6 additional seats (i.e Seat
No. 9 in rows A to F) and all the 56 additional seats in hall are blocking
vertical gangways causing obstruction to free egress of patrons from the hall.
These 62 additional seats are in gross contravention of Paras 7(1) and 8(1) of
the First Schedule of Delhi Cinematograph Rules. 1953 and must, therefore,
be removed. The original number of vertical gangways in the hall must be
restored. The remaining 37 additional seats in the balcony were found to be in
substantial compliance of the rules and may, therefore, be retained. Similarly,
one additional seat on the back row in hall (i.e Seat No. A-33) has also been
found to be insubstantial compliance of the rules and may, therefore, be
retained. This case has been examined in the light of the observations made in
the Judgment of Hon'ble High Court and it has been seen to that the
specifications laid down under the First Schedule of Delhi Cinematograph
Rules have been substantially complied with keeping in view the safety
requirements in the cinema hall ".
By order dated 24.12.1979, 37 seats (out of original 43) were permitted to be retained in
balcony by orders of Mr. A.K. Sinha, DCP (Licensing). That order was marked as Ex.PW
29/DR.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 290
7.79 On 29.07.1980 the cinema hall acting through the second accused Gopal Ansal wrote
the letter (marked as Ex. PW100/AA7) seeking permission to install 15 additional seats in the
balcony. The said letter is as follows:
" We now wish to bring to your kind notice that Seats No. 9 ( Rows A to F),
i.e., a total of six seats are causing lot of inconvenience to the patrons because
of the fact that the gangway after two rows i.e H and G, suddenly widens up to
an irregular size of about 64 ". The said six seats ( A9 to G9) were removed
under protest, although the same can be sanctioned under the heading of
'Substantial Compliance' of Cinematograph Rules. Keeping in view the
inconvenience caused to the public due to the sudden break in the gangway,
we would request if the same could kindly be approved. In addition to the
above, we wish to apply for an additional nine seats marked G-36 to G-38, H-
36 to H-38, and I-38 to I-40, since the corner as shown in red is lying vacant
in the Balcony of our above-mentioned Theatre. Hope you would find the
above in order and oblige us by giving the necessary sanction for a total of 15
additional seats ".
On 20.08.1980 DCP (Licensing) write a letter to the Executive Engineer marked and
produced as Ex. PW 29/DS. The said letter reads as follows :
The Licensee, Uphaar Cinema Green Park, New Delhi has submitted revised
plan to this office for the grant of permission to install 15 additional seats in
the Balcony i.e one seat each in rows A to F, three seats each in three rows at
left hand side of the Balcony, as shown in the enclosed plan which may please
be examined with reference to para 6,7,8,10,12,14,16 of First Scheme of Delhi
Cinematograph Rules, 1953 and a detailed report may be sent to this office, at
an early date with recommendations to consider the case ".
On 03.09.1980 the Executive Engineer Shri Dandona replied to the queries of DCP
(Licensing). His letter was marked as PW 29/DU. He rejected the proposal for installation of
additional 15 seats, as not conforming to the first Schedule, DCR 1953 in the following
terms:
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 291
"The proposal for installation of 15 additional seats in the balcony submitted
by the Licensee is not in accordance with the Ist Schedule of DCR, 1953. A
copy of the plan received vide your above referred letter duly rejected is
enclosed herewith with the following observations:
1. The addition of one seat each in row A to F makes the total number of seats
in a row as 9 Nos i.e from 9 to 17, therefore, it requires aisles on both sides
against one aisel shown on the plan and as well as at site.
2. After installation of three Nos of proposes rows with three seats each i.e 38
to 40, the space left between the last row and the exit will be less than 44 "
which is required under the rules.
3. The position of the exit shown between seat No. 37 and 38 to row I in the
back wall of balcony is not correct as per its original position at site. The
above observations were also brought to the notice of Licensee's
representative Shri Malhotra during the site inspection on 2.9.80 and who
also agreed for the same. The Licensee's representative after discussion has
informed that he would submit the revised plans with his new proposals
keeping in view the Ist Schedule of DCR 1953.
7.80 The cinema GPT Limited, through Mr. Gopal Ansal, submitted a revised proposal for
addition of 15 seats on 05.09.1980 (letter marked and exhibited as Ex. PW 29/DV). The
same reads as follows:
September 5, 1980
The Executive Engineer,
C.P.W.D. Division II
Maulana Azad Hospital Buildling
Subject :- 15 Additional Seats at our Uphaar Cinema
Dear Sir,
You must have been in receipt of our proposal addressed to the Deputy
Commissioner of Police (Licensing) vide our letter dated 29th July, 1980. In
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 292
continuation of the same, we are enclosing herewith revised plan for the said
15 additional seats as per your requirement.
Hope you would find the same in order and accord us the necessary
sanction.
Thanking you in anticipation.
Yours faithfully,
For GREEN PARK THEATRES ASSOCIATED PVT. LTD.
SD
(DIRECTOR)
Encl : As above
CC : The Deputy Commissioner of Police (Licensing)
MSO Building, 4th Floor, Indraprastha Estate, New Delhi
Fire Officer, New Delhi
Together with the plans.
In reply Mr. Dandona, Executive Engineer, PWD, after considering proposal submitted his
report through Ex. PW 29/DX after 10.09.1980 in the following terms:
"The total number of seats at present in the balcony are 287 and by adding
these 15 seats the total number of seats in the balcony would be 302. The
number of exits at site at present are three in number. As per First Schedule of
DCR, 1953, the number of exits should be one per 100 seats and on account of
which seats would be in excess, but at the time of removal of additional seats
in October, 1979 during a meeting held in your room where D.C.P and Chief
Fire Officer were also present, it was decided that keeping in view the High
Courts' orders for substantial compliance 1% excess number of seats over the
required number of exits should be allowed and accordingly so many cinemas
were allowed to retain one per cent excess number of seats than the
permissible limit of one exit per 100 number of seats. Keeping that decision in
view these two number of excess seats can also be allowed and the proposal of
15 additional seats will be in conformity of Delhi Cinematograph Rules, 1953
and therefore, it is approved. The approval is subject to the final inspection
after the completion of work ".
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 293
The Deputy Commissioner of Police (Licensing) on 04.10.1980 (marked and exhibited as
Ex.PW 29/DY) allowed installation of these proposed additional 15 seats in the balcony,
stating as follows:
" Permission is hereby accorded for the installation of 15 additional seats in
the Uphaar Cinema i.e. two additional rows each of three seats in front of exit
in the balcony, one seat against back wall adjacent to Seat No. 37 and 8
additional seats in the balcony by adding one seat in row A to H by making
readjustment of seats in these rows. The permission is provisional subject to
the final inspection by Public Works Department. The seats may be installed
strictly in accordance with the plans approved and these should be
inconformity with the First Scheme of Delhi Cinematograph Rules. "
Accordingly, 15 additional seats were installed as per the seating plan Ex. PW 95/B4. Prior to
issuance of the letter Ex. PW 29/DY, the Chief Fire Officer expressed his agreement with the
proposal on 08.09.1980. That letter was produced as Ex. PW 29/DZ, the relevant part of
which are extracted below:
―Kindly refer to your letter No.13811/DCP/Lie dated 27.8.80
regarding installation of proposed 15 additioal seats, as per revised plane
received from the cinema management. They have proposed two additional
rows, each of 3 seats in front of the exit in the balcony. One seat is proposed
against back wall adjacent to sent No.37. They have also proposed 8
additional seats in the balcony by adding one seat in row A to H this will be
done by making readjustment of the seats in these rows.
The proposed additional 15 seats are I conformity of First Scheme of
DCR - 1953 therefore this department has no objection to the grant of
proposed additional seats.‖
7.81 In 1983 two serious fire accidents took place in the city; one at Shakur Basti and
another was in Gopala Tower. Consequently the Lieutenant Governor of Delhi directed
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 294
inspection of all cinema houses. A joint team of officials inspected various cinema theaters
including Uphaar. Their report listed 11 irregularities which has been extracted in Table (1)
in the preceding part of this judgment.
7.82 On 29.06.1983 Uphaar license was suspended for four days by orders of DCP
(Licensing). He required that deviations listed in the report be removed within the said
period of four days or the license would be revoked. Similar orders were made against other
cinema houses. Uphaar cinema as well as the other cinema theaters approached this Court
questioning the orders suspending the license. This Court by its order dated 28thJune, 1983,
stayed the operation of the orders of suspending the license. By the order dated 25th March,
1986, the Court confirmed the interim order. While doing so it noticed the concern expressed
on behalf of the Delhi Administration, by its counsel and recorded as follows:
―If there is any Fire hazard or no proper fire fighting equipments, the
respondent will be at liberty to call upon the petitioner to remove the fire
hazard or to use proper adequate fire fighting equipments and also call upon
the petitioner to remove serious irregularities, if any. If the petitioner fails to
comply with the same, the respondent will be at liberty to move the Court for
variation of the said order and for obtaining appropriate directions in this
behalf.‖
The material part of the above order has been extracted in the inspection report dated
02.05.1980, marked and exhibited as Ex. PW 37/K.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 295
7.83 After the developments noted above, concerning the inspection of the cinema house in
1983, suspension of its license and the interim order of the court, the material on record
shows that no annual license was issued to the cinema house. It continued to function on the
strength of two months duration temporary permits issued between 1983 and 1997.
7.84 PW 2, PW 29 and PW 39 spoke about the deviations in relation to the balcony. The
relevant extracts of their reports have been collected in the form of Table (2), in the preceding
part of the judgment.
The deviations in the balcony, from their reports are listed below:
incident one of them had been reduced to 1 feet & 10.5 inches.
the numerological requirement of 2 exists. However, this was not in conformity
with DCR 1953 and 1981, since two exists were to be provided on either side of
the balcony leading to independent stair case.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 296
(f) Placement of six seats in front of the newly created exit, which caused
obstruction.
(g) Operator rest room and a single room tenement for sweeper were converted into a
retiring room along with office and attached toilet.
(h) Four exhausts fans opened in front of the stair case instead of opening outside to
an open space.
(i) Obstruction by a reception of M/s Sarin Associations on the stair case leading to
terrace.
7.85 The materials on record in the form of the inspection reports Ex. PW 2/A, 29/A and
39/A, as well as the sitting plan sanctioned produced before the court Ex. PW 95/B4 would
disclose the following:
(1) As against the original 250 seats proposed, 302 seats (excluding 22 seats,
which were part of two additional blocks) were discovered in the balcony. Para -
DCR 1953 and Para - DCR 1981 required that one exit had to be provided for every
100 seats. The increase of 15 additional seats proposed on 05.09.1980 by the cinema
should have also resulted in increase in the number of exists. However, the cinema
management did not provide for an additional exit. It sought to rely upon the letter
Ex. PW29/DX, which stated that if the increase was less than 1% and therefore, in
substantial compliance of the Rules. The judgment of this Court in Isherdas Sahni
case (supra), as the extracted portions disclosed, clearly preserved, fire safety
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 297
concern, expressed by the authorities. Section 17 enables only the Central
Government to exempt the operation of any norm specified in rules. There was no
rule or regulation in existence in 1980 or even thereafter which authorized the
suspension of Para. In so far as it insisted upon provision for an additional exit, after
the number of seats increased to 300. Equally there is no similar provision enacting
that a deviation which is less than 1% could be waived or condoned or exempted by
the licensing authority or even recommended by the Executive Engineer. If viewed
from the context of the observations of the Division Bench, this omission was a clear
violation unsupportable by law, and, therefore, an illegal omission.
(2) One exit i.e. right exit was closed by installation of a family box in 1978.
Although the accused rely upon a permission accorded in this behalf, there is no
escape from the fact that this clearly contravened Para 10 (4) of DCR 1953, which
was similarly enacted in Para 12 (4) of Ist Schedule to DCT 1981. These
unequivocally mandated that exits from the auditorium were
(a) to be suitably placed;
placement or installation of the additional 8 seater family box violated these norms in
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 298
both respects. Firstly, it completely shut out means of rapid dispersal from the right
side, at that side i.e. providing access to the right side stair case. Secondly, it also
blocked the back side exit on the right side. The provision for a separate exit on the
left side, at the same level where the right side exit was blocked, did not alleviate or
relieve the serious concern which para 10 (4) sought to redress i.e. rapid dispersal in
both directions, through independent stair way leading to outside the building. This
blockage resulted in exits being concentrated in one direction thus driving patrons to
what the Chief Fire Officer had apprehended while reporting to this Court in the
proceedings leading to the decision of the Division Bench.
(4) The provision for an additional left side entrance in the opinion of the court
did not relieve the cinema hall of its primary obligation to ensure due compliance with
Para 10 (4) and 12 (4) of DCR 1953 and 1981 at all times nor did it amount to
substantial compliance with the rules.
(5) The complete blockage of right side gangway, also added to the hindrance of
patrons who could not get down from different levels. This also violated Para 10 (1),
DCR 1953 which mandated that exits would be provided to afford audience ample
means of safe and speedy egress.
(6) The provision of a gangway which was less than 44‖ (3 feet or 8‖) and was 1
ft X 10.5‖ amounted to contravention of Para 8 (1) of DCR 1953. This norm provided
that gangways of not less than 44‖ width to be provided each side of auditorium. The
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 299
reduction of this gangway reduced the number of proper gangways to three, which
was contrary to DCR 1953/1981.
(7) The provision of 7 seats, due to the proposal by the cinema management on
05.09.1980, which was eventually granted on 04.10.1980, resulted in 7 seats
obstructing the left side exist and causing hindrance to free movement. If one
considers that this exit was newly created in lieu of the blocked right side exit, it was
incumbent on all to ensure that it was kept completely unobstructed, at all times. The
placement of these 7 seats narrowed the passage and inevitably constricted free
movement of the patrons in the event of an emergency. This violated Para 8 (4) DCR
1953.
(8) The blockage of the right side exit from the balcony by installation of an 8
seater box rendered substantially ineffective the mandate of Para 9 (1) DCR 1953
which prescribes that at least two stair ways of each not less than 4 Feet had to be
provided for the access in gallery or upper floor in the building which is intended for
use by the public.
7.86 In view of the above discussion, this Court is of the opinion that the seating in the
balcony, changed from time to time i.e. in 1976 by closure of the right side gangway;
placement of 8 seater family box for the owners in 1978, installation of 37 seats and
additional 15 seats in 1979/1980, contravened several important provisions of DCR 1953 &
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 300
1981. So far as applying standards of DCR 1981 are concerned, the contraventions had
already taken place by October 1980, therefore, it would really not be of much consequence.
What is however significant is each deviation had the effect of substantially increasing the
risk to such a point that in the event of an emergency - be it by fire or otherwise,
necessitating rapid egress or dispersal of those within the balcony, these deviations and
placements of additional seats would invariably and almost certainly have resulted in
obstruction to such a free passage. In this sense, it would be necessary here to emphasis that
regulations concerning exits which have been discussed in this part of the judgment are
generic in nature and do not concern themselves with only fire emergency, but all kinds of
eventualities requiring rapid dispersal of patrons and others within the balcony. Even the use
of expression ―fire‖ has to be understood in this context to mean an emergency, no more, no
less.
7.87 In view of the above discussion, the trial court's findings that the arrangements of the
seats and placement of additional 8 seater family box and other deviations, amounted to
contravention of several provisions of DCR and Cinematograph Act are sound and supported
by the facts on record.
Condition of the DVB transformer and the 1989 fire incident
7.88 The prosecution case against two sets of accused, i.e., accused No.1&2 and accused
employees of DVB, was of gross negligence in relation to location and maintenance of the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 301
transformer. The materials on record were held sufficient to return a finding of guilt against
both sets of accused. The former were convicted of having committed an offence under
Section 304-A read with Section 14 of the Cinematograph Act, 1952 and also Sections 337,
338 and Section 36 of IPC. DVB employees, on the other hand, were convicted under
Section 304 IPC read with Sections 337 & 338 as well as 36 IPC.
7.89 Before discussing the relevant findings under arguments made, it would be necessary
to briefly notice the standards spelt out by law in this regard. In the first part of this
judgment, this Court had analyzed the evidence and held that the positioning of the
transformer and permitting it to be installed was a voluntary action, without any element of
coercion, and without authority of law since no permission was obtained in that regard from
the MCD or the licensing authority.
7.90 Chapter 4 of Indian Electricity Rules, 1956 (hereinafter referred to as Electricity
Rules) deals with the general safety requirements Rule 29 prescribes that all electric supply
lines and apparatus shall be of sufficient ratings for power, insulation and estimated fault
current and of sufficient mechanical strength, for the duty which they may be required to
perform under the environmental conditions of installation, and shall be constructed,
installed, protected worked and maintained in such a manner as to ensure safety of human
beings, animals and property. Rule 29 (2) states that unless and otherwise provided the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 302
relevant code of practice of the Bureau of Indian Standards including National Electrical
Code had to be followed; Rule 29 (3) provides that the material and apparatus used shall
conform to the relevant specifications of the BIS. Rule 30 reads as follows: -
―30. Service lines and apparatus on consumer's premises-
(1) The supplier shall ensure that all electric supply lines, wires, fittings and
apparatus belonging to him or under his control, which are on a consumer's
premises, are in a safe condition and in all respects fit for supplying energy
and the supplier shall take due precautions to avoid danger arising on such
premises from such supply lines, wires, fittings and apparatus.
(2) Service-lines placed by the supplier on the premises of a consumer which
are underground or which are accessible shall be so insulated and protected
by the supplier as to be secured under all ordinary conditions against
electrical, mechanical, chemical or other injury to the insulation.
(3) The consumer shall, as far as circumstances permit, take precautions for
the safe custody of the equipment on his premises belonging to the supplier.
Rule 43 prescribes that fire buckets containing dry sand and ready for immediate use for
extinguishing fires, in addition to fire extinguishers suitable for dealing with electric fires,
should be conspicuously marked and kept in all generating stations, enclosed sub-stations and
switch stations in convenient situations.Rule 46 provides that where an installation is already
connected to the supply system, it shall be periodically inspected and tested at intervals not
exceeding 5 years by the Inspector or someone authorized in his behalf. Rule 50 prescribes as
follows: -
―50. Supply and use of energy
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 303
(1) The energy shall not be supplied, transformed, converted or used or
continued to be supplied, transformed, converted or used unless provisions as
set out below are observed:-
(a) The following controls of requisite capacity to carry and break the current
[are placed] after the point of commencement of supply as defined in rule 58
so as to be readily accessible and capable of being easily operated to
completely isolate the supply to the installation such equipment being in
addition to any equipment installed for controlling individual circuits or
apparatus: -
(i) A linked switch with fuse(s) or a circuit breaker by low and medium voltage
consumers.
(ii) A linked switch with fuse(s) or a circuit breaker by HV consumers having
aggregate installed transformer/apparatus capacity up to 1000 KVA to be
supplied at voltage upto 11 KV and 2500 KVA at higher -voltages (above 11
KV and not exceeding 33 KV).
(iii) A circuit breaker by HV consumers having an aggregate installed
transformer/ apparatus capacity above 1000 KVA and supplied at 11 KV and
above 2500 KVA supplied at higher voltages (above 11 KV and not exceeding
33 KV).
(iv) A circuit breaker by EHV consumer:
Provided that where the point of commencement of supply and the consumer
apparatus are near each other one linked switch with fuse(s) or circuit
breaker near the point of commencement of supply as required by this clause
shall be considered sufficient for the purpose of this rule;
..... ....... ...... ........
[Provided further that for all transformers-
(A) having a capacity of 5000 KVA and above and installed before the
commencement of the Indian Electricity (Amendment) Rules, 2000 and
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 304
(B) having a capacity of 1000 KVA and above and installed on or after the
commencement of the Indian Electricity (Amendment-1) Rules, 2000 a circuit
breaker shall be provided].
....... ........ .......... .........
(2) Where energy is being supplied, transformed, converted or used the
[consumer, supplier or the owner] of the concerned installation shall be
responsible for the continuous observance of the provisions of sub-rule (1) in
respect of his installations.
(3) Every consumer shall use all reasonable mean to ensure that where energy
is supplied by a supplier no person other than the supplier shall interfere with
the service lines and apparatus placed by the supplier on the premises of the
consumer.]‖
Under Rule 63, inspection by the Electrical Inspector is necessary before even an application
for permission to commence or re-commence supply energy is made. Rule 64 (2) and Rule 69
(a) provide as follows: -
―64. Use of energy at high and extra-high voltage- ............
(2) The following provisions shall be observed where energy at high or extra-
high
voltage is supplied, converted, transformed or used: -
[(a) (i) clearances as per Indian Standard Code shall be provided for
electrical apparatus so that sufficient space is available for easy operation
and maintenance without any hazard to the operating and maintenance
personnel working near the equipment and for ensuring adequate ventilation.
(ii) The following minimum clearances shall be maintained for bare
conductors or live parts of any apparatus in out-door substations, excluding
overhead lines, of HV and EHV installations: -
(1) The above values are valid for altitude not exceeding 1000 Metres (m.). A
correction factor of 1.25 per cent per 100 m. is to be applied for increasing
the clearance for altitudes more than 1000 m. and upto 3000 m.
(2) The above safety working clearances are based on an insulation height of 2.44
m. which is the height of lowest point on the insulator (where it meets the
earthed metal) from the ground.,
(3) ―Safety Working Clearance‖ is the minimum clearance to be maintained in
air between the live part of the equipment on one hand and earth or another
piece of equipment or conduct on which it is necessary to carry out the work,
on the other.
(4) The ―Highest System Voltage‖ is defined as the highest rms phae to phase
voltage which occurs under normal operating conditions at any time and at
any point of the system. It excludes voltage transients (such as those due to
system switching) and temporary voltage variations due to abnormal system
conditions (such as those due to frault conditions or the sudden disconnection
of large loads).]
(b) The windings of motors or other apparatus within reach from any position
in which a person may require to be shall be suitably protected so as to
prevent danger.
(c) Where transformer or transformers are used, suitable provision shall be
made, either by connecting with earth a point of the circuit at the lower
voltage or otherwise, to guard against danger by reason of the said circuit
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 306
becoming accidentally charged above its normal voltage by leakage from or
contact with the circuit at the higher voltage.
(d) A sub-station or a switch station with apparatus having more than 2000
litres of oil shall not be located in the basement where proper oil draining
arrangement cannot be provided.
(e) Where a sub-station or a switch station with apparatus having more than
2000 litres of oil is installed, whether indoor or out-doors, the following
measures shall be taken, namely: -
(i) The baffle walls [of 4 hour fire rating] shall be provided between the
apparatus in the following cases: -
(a) Single phase banks in the switch-yards of generating stations and
substations;
(b) On the consumer premises;
(c) Where adequate clearance between the units is not available.
(ii) Provisions shall be made for suitable oil soakpit and where use of more
than 9000 litres of oil in any one oil tank, receptacle or chamber is involved,
provision shall be made for the draining away or removal of any oil which
may leak or escape from the tanks receptacles or chambers containing the
same, special precautions shall be taken to prevent the spread of any fire
resulting from the ignition of the oil from any cause and adequate provision
shall be made for extinguishing any fire which may occur. Spare oil shall not
be stored in an such sub-station or switch station.
[(f) (i) Without prejudice to the above measures, adequate fire protection
arrangement shall be provided for quenching the fire in the apparatus;
(ii) Where it is necessary to locate the sub-station/switch station in the
basement following measures shall be taken:-
(a) The room shall necessarily be in the first basement at the periphery of the
basement;
(b) The entrances to the room shall be provided with fire resisting doors of 2
hours fire rating. A curb (sill) of a suitable height shall be provided at the
entrance in order to prevent the flow of oil from a ruptured transformer into
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 307
other parts of the basement. Direct access to the transformer room shall be
provided from outside.
(c) The transformer shall be protected by an automatic high velocity water
spray system or by carbon dioxide or BCF (Bromochlorodifeuromethane) or
BTM (Bromotrifluromethane) fixed installation system; and
(iii) Oil filled transformers installed indoors shall not be on any floor above
the ground or below the first basement.]
(g) Cable trenches inside the sub-stations and switch stations containing
cables shall be filled with sand, pebbles or similar non-inflammable materials
or completely cover with non-inflammable slabs.
(h) Unless the conditions are such that all the conductors and apparatus may
be made dead at the same time for the purpose of cleaning or for other work,
the said conductors and apparatus shall be so arranged that these may be
made dead in sections, and that work on any such section may be carried on
by an authorized person without danger.
(i) Only persons authorized under sub-rule (1) of rule 3, shall carry out the
work on live lines and apparatus.]
[(3) All EHV apparatus shall be protected against lightning as well as against
switching over voltages. The equipment used for protection and switching
shall be adequately coordinated with the protected apparatus to ensure safe
operation as well as to maintain the stability of the inter-connected units of the
power system.]
64A. Additional provisions for use of energy at high and extra-high voltage-
The following additional provisions shall be observed where energy at high or
extra high
voltage is supplied, converted, transferred or used, namely: -
(1) Inter-locks- Suitable inter-locks shall be provided in the following cases: -
(a) Isolators and the controlling circuit breakers shall be interlocked so that
the isolators cannot be operated unless the corresponding breaker is in open
position;
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 308
(b) Isolators and the corresponding earthing switches shall be interlocked so
that no earthing switch can be closed unless and until the corresponding
isolator is in open position;
(c) Where two or more supplies are not intended to be operated in parallel,
the respective circuit breakers or linked switches controlling the supplies shall
be interlocked to prevent possibility of any inadvertent paralleling or
feedback;
(d) When two or more transformers are operated in parallel, the system shall
be so arranged as to trip the secondary breaker of a transformer in case the
primary breaker of that transformer trips;
(e) All gates or doors which give access to live parts of an installation shall be
inter-locked in such a way that these cannot be opened unless the live parts
are made dead. Proper discharging and earthing of these parts should be
ensured before any person comes in close proximity of such parts;
(f) Where two or more generators operate in parallel and neutral switching is
adopted, inter-lock shall be provided to ensure that generator breaker cannot
be closed unless one of the neutrals is connected to the earthing system.
(2) Protection- All systems and circuits shall be so protected as to
automatically disconnect the supply under abnormal conditions. The following
protection shall be provided, namely: -
(a) Over current protection to disconnect the supply automatically if the rated
current of the equipment, cable or supply line is exceeded for a time which the
equipment, cable or supply line is not designed to withstand;
(b) Earth-fault/earth leakage protection to disconnect the supply automatically
if the earth fault current exceeds the limit of current for keeping the contact
potential within the reasonable values;
(c) Gas pressure type protection to given alarm and tripping shall be provided
on all transformers of ratings 1000 KVA and above;
(d) Transformers of capacity 10 MVA and above shall be protected against
incipient faults by differential protection; and
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 309
(e) All generators with rating of 100 KVA and above shall be protected
against earth fault/leakage. All generators of rating 1000KVA and above shall
be protected against faults within the generator winding using restricted earth
fault protection or differential protection or by both.]‖
7.91 In the preceding section of this judgment it was concluded that the permission to
install or allowing DVB to install an additional transformer which ultimately was the cause of
fire, did not confirm to the sanctioned plan and was, therefore, unauthorized. The Court had
taken into consideration the sanctioned plans for this purpose. The state of the transformers
either of Uphaar or that of DVB before 1989 and the relative maintenance reviewed are very
clear from the record.
7.92 The earliest material relied upon by the prosecution in this respect is a fire accident
that occurred on 6.7.1989. According to ___, during the late evening show at 11:45 PM, the
fire occurred which extensively damaged the Uphaar transformer as well as the then existing
750 KVA DVB transformer. The Prosecution relied upon Ex.PW-88/A, recovered from the
Fire Department; it is a note sheet. Ex.PW-88/B is a letter dated 7.7.1989, written by the
Uphaar Cinema to the Chief Fire Officer intimating about the fire in the Cinema Hall. The
fire report dated 13.7.1989 by the Chief Fire Officer records the nature of the incident. It
states that the fire occurred at 11:40 hrs. in the Uphaar cinema transformer at ground floor
level, also tripping the D.C. Battery of the DESU transformer. The HT panel board, cable
shaft and A.C.Duct of the cinema were affected. The report noted that smoke and hot gases
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 310
affected the main hall, balcony, projection and rewinding room, the screen, furniture and
various offices located in the cinema complex. A report (Ex.PW-88/D) describing ―serious
fire‖ on 6.7.89 is also on record as is another report giving details of the fire and estimated
loss. This document Ex.PW-88/E repeats the contents the value of estimated loss is about
Rs.30 Lacs. Ex.88/F is the Seizure Memo evidencing recovery of the file containing the note
sheets and papers from the Fire Department.
7.93 PW-88, Surender Kumar, Dy. Chief Fire Officer who deposed in support of the
exhibits produced in the Ex.PW-88 series, stated that he was working in the Department since
1978. He was not crossed-examined by any of the accused about the fire incident of 1989.
PW-48 the Additional Chief Engineer, DVB who deposed in support of the prosecution, sent
his replies to queries furnished to him on 25.6.97. The covering letter and the annexure
which contains specific replies dated 2.7.97 were produced as Ex.PW-48/A. The relevant
part of his report 48/A reads as follows: -
―2. The file in question containing the relevant details with regard
to HT connection alongwith provisions of erstwhile DESU transformer at
Uphaar Cinema has already been sent to Deputy Commissioner, South,
Enquiry Magistrate.
3. As per our understanding and information obtained so far,
none of the transformers actually caught fire. However, there appears to have
been sparking, earthing of LT leads at the terminals of the transformer owned
by DVB. This transformer (having a life of approximately 25 years under
normal conditions of use) was installed on 09.07.1989.
4. As per information/records traced so far, on 09.07.1989, i.e.
the date of installation of the concerned transformer, Shri S.K. Choudhary was
the Executive Engineer S/Stn. South Circle and Sh. V.K. Singhal was Asstt.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 311
Engineer S/Stn. (R.K. Puram District). However, we are ascertaining the
name of the supervisors and this will be made available shortly.
5. As per the record available, on the night of 6th July, 1989, and
th
morning of 7 July, 1989 both the transformers i.e. one placed by Green Park
Theatres Associated Pvt. Ltd. (500 KVA) and by DESU (750 KVA) were burnt
due to short-circuiting. The DESU transformer was replaced by another new
transformer of 1000 KVA. The other transformer belonging to Green Park
Theatres Associated Pvt. Ltd. was also replaced during July, 1989. The
officers mentioned in reply to para 4 above were concerned only with the
installation of DESU transformer (1000 KVA).‖
Later on 4.9.97, PW-48 answered another questionnaire sent to him by the CBI on 28.8.97.
Relevant portion of these replies, forming part of PW-49/G which reads as follows: -
―A perusal of old record indicates that the relays provided initially in the HT
panels got damaged on 6/7.7.89 when fire occurred at the sub station.
However, back-up protection was available both at K-84, Green Park S/Stn.
And also at Grid S/Stn. at AIIMS. No record is available regarding
replacement of relays after the above date.
It has already been indicated above, that the relays existing in HT panels at
Uphaar Cinema S/Stn. got damaged on 6/7.7.89. Needless to mention that
relays from unattended S/Stn. have been getting stolen from different sub
stations all over Delhi and this activity by unscrupulous elements is causing a
dent on the maintenance of the S/Stn. equipment.‖
7.94 The evidence on record, in the form of Ex. PW-40/B, the maintenance register seized
from the DVB office, reveals that upon inspection of the DVB transformer on 22-1-1997, it
was found that protection relays were missing. This was confirmed by PW-40, the Assistant
Engineer for the concerned region. The relays were also missing on the date of the incident,
as is evident from the following observations of the CFSL expert, PW-64, in his report PW-
64/D (dated 11-8-1997):
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 312
―The transformer in question i.e DVB transformer did not have following
safety measures at the time of inspection.
1. The LT side cables from the bus bar did not have clamping system or any
support to the cables.
2. The earth cable of the transformer has been found temporarily fitted with
the earth strip i.e twisting of earth cable.
3. There was no cable trench to conceal the cable.
4. HT panel board of transformer did not had any relay system to trip the
transformer in case of any fault.
5. The Buchholtz relay system was not fitted on the transformer
6. Temperature meter was not found fitted on the transformer...‖
7.95 On 25-6-1997, PW-24, the Electrical Inspector, Shri K.L. Grover, too had mentioned
the absence of this equipment, in his report PW-24/A:
―8.No protection relays/system were found installed on any of the HT
Breakers of the said HT Four Panel Board from where the HT supply to 1000
KVA transformer in question was fed.........''
7.96 PW-24 supports his report, in the deposition. PW-26, Shri A.K. Agarwal too
corroborates this evidence, about lack of protection and the Buchholtz relay system, in the
transformer. PW-35 too deposed about the absence of relays; this opinion was given in Ex.
PW-35/A, (dated 29-6-97) a report given after the incident. This report was supported by
Professor Kothari, another expert, from the IIT, Delhi, in PW-36/A (dated 2-7-1997). The
importance of these relays is apparent from the fact that in the event of a fault, they would
have ―tripped‖ and disconnected electricity supply.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 313
7.97 On the morning of 13-6-1997, a fire broke out in the DVB transformer. This was
immediately reported to the DVB; Deep Chand, Attendant, DVB, PW-41, deposes having
received this information at about 6:55 AM. He claims to have sent Munna Lal (PW-47) who
came back to the R K Puram Sub-station and passed on the information that one lead in LT
side of DVB transformer has burnt due to which electric supply has been disrupted; he passed
on information to C J Singh, the Superintendent. He proved the entry as Ex. PW 41/A, in the
―No Current Complaint Register‖ maintained by the DVB. PW -42, CJ Singh corroborated
having received information at about 7.20 hours, from the Green Park Complaint Centre and
also from Munna Lal about the fire having taken place in Uphaar transformer and he along
with his team reaching the Uphaar Cinema at 7.40am. On inspecting the DVB transformer he
found that three leads out of 11 leads were partly burnt on the LT side of the transformer. The
fault was not repairable at his level. He proved Ex. PW-42/A, the relevant part of the General
Diary Break down, maintained by the DVB at RK Puram. PW-46, Junior Lineman Munna
Lal, deposed having gone to the Uphaar cinema in the morning of 13-6-1997, found some fire
and that insulation of one lead upto one feet and second lead upto six inches were burning
and melting. He deposed to switching off the HT panel of the adjoining room, putting sand on
fire and reporting the matter to his office. He went back to his office and reported to Deep
Chand who passed on the information to the Break Down division. These facts are also
corroborated by PW-45 Jagpal.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 314
7.98 PW-40, Mr. P.C. Bhardwaj deposed that he received information about the morning
incident at 08.00 am, and that he instructed Mr. B.M. Satija, Inspector to attend to the
complaint. The Prosecution relied on the depositions of PW-40 and PW-44 in support of the
case that such repairs were carried out by Mr. Bir Singh, Senior Fitter under supervision of
Mr. B.M. Satija and Mr. A.K. Gera, Inspectors.
7.99 The Trial Court held that these repairs were in the form of replacements of
Blue (B) Phase Cables with the aid of dye and hammer, and that the said three accused left
the Uphaar premises at 11.30 am after repairing the DVB transformer. Further findings by the
Trial Court in this regard were that, between 03.55 pm and 04.55 pm that day, there was a
power cut/load shedding. Soon after resumption of power, there was a loud bang in the
transformer room which led to the B-Phase Cable detaching itself from the Bus Bar, its
subsequent de-coiling and settling on one of the transformer fins. It was found that this was
preceded and followed by intense sparking and that the heat generated by the incident at that
stage led to continuous sparking/arching, which resulted in a slit in the transformer radiator;
in turn this led to spillage of more than 900 litres of transformer oil, which caught fire due to
the sparking. The Trial Court held that transformer oil flowed out of the transformer room,
setting ablaze many vehicles parked near the transformer room. The smoke from this
conflagration went into the theatre resulting in death of 59 persons and grievous injury to 100
others.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 315
7.100 The Trial Court relied upon the reports of Mr. K.L. Grover's (Electrical
Inspector) report (Ex.PW-24/A) as well as his depositions. He visited the spot on
25.06.1997. The facts relating to load shedding were corroborated by Ex.24/DA. It was held
that the sparking/arching most probably continued for about ten minutes (till 05.05 pm) when
the AIIMS Grid Station tripped and was shut down. The Trial Court also relied upon the
other reports, such as that of Mr. K.V. Singh, Executive Engineer (Electrical), PWD (Ex.PW
35/A dated 29.06.1997) deposition of the said Mr. K.V. Singh as PW-35; the report of Prof.
Kothari, PW-36/A (dated 02.07.1997) and his deposition as PW-36. The Trial Court further
relied upon the report of PW-64 (Dr. Rajender Singh, Director and Scientist from CFSL),
being Ex.PW-64/D. This report was submitted on 27.06.1997. Dr. Rajender Singh deposed as
PW-64 before the Trial Court.The Prosecution relied upon PW-40/B, a photocopy of the
report of Mr. A.K. Gera regarding the repairs conducted on DVB transformer; it was sought
to be proved as Ex. 108/AA.
7.101 The common argument advanced by the accused, Mr. Bir Singh and Mr. B.M.
Satija, and implicitly endorsed by accused, Mr. A.K. Gera was that the prosecution could not
prove the charges leveled against them. Certain contentions were raised, casting doubts on
the findings of the Trial Court on the basis of evidence in regard to:
1. The nature of the repairs carried out.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 316
2. Time of the accident.
3. Absence of any fault or negligence on the part of the said accused, since the risks
of fire had been increased by negligence in regard to parking of vehicles; whether
the repairs carried out could be the cause having regard to an intervening incident
reported to have taken place in the building around 02.00 pm.
4. The appropriateness of the use of dye and hammer to fix the cables while
attending to the complaint.
5. Whether the transformer itself was a cause for the fire or something else.
7.102 Sequentially, the first aspect in this regard would be the manner in which the
complaint was attended. PW-40 deposed that he asked the three accused at 09.15 am to attend
to the complaint. He proved Ex.40/A, a General Diary Register for the period from
14.05.1996 to 13.06.1997, which contained an entry Ex.PW-40/C to the effect that two 630
mm. aluminum sockets were replaced in the DVB Uphaar Cinema local transformer. He
deposed that the entry was made by accused, Mr. A.K. Gera and that it contained the name of
Mr. Bir Singh. PW-40 also stated that upon previous inspection of the transformer on
22.01.1997 (when it was noted that protection relays were missing), everything, including
nuts, bolts, transformer oil and connections were checked.
7.103 The version of PW-40 about the three DESU employee/accused attending to
the complaint was corroborated by an eyewitness, PW-44, Mr. Bhagwan Din. He was
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 317
working as Mazdoor on that day. He deposed to having accompanied Mr. B.M. Satija, Mr.
A.K. Gera and Mr. Bir Singh to Uphaar Cinema at about 10.00-10.30 am. He had carried the
tool box with him. According to the deposition, Mr. Bir Singh opened the shutter of the DVB
transformer room in the Uphaar Cinema complex. The socket was changed with the help of
dye and hammer as the crimping machine was out of order. He deposed that the entire repair
work was finished within 45 minutes and after replacing the socket and connecting it to the
bus bar, the transformer was switched on and electricity supply restored. He stated, in the
course of cross examination on behalf of Mr. B.M. Satija, that he was not aware whether the
R-phase, B-phase or Y-phase was changed. He deposed that they were working in the middle
phase of the transformer and that two sockets were replaced. According to PW-44, when the
transformer was switched on, there was no sparking.
7.104 It is evident from the depositions of PW-40 and PW-44 as well as Ex. PW-
40/C that two 630 mm. Sockets were changed. Counsel for the accused had argued that there
was no evidence to show that the B-phase sockets had in fact been replaced and that the
deposition of PW-44 was explicit that the middle phase was the one concerned with repairs. It
was, therefore, contended that the Y-phase socket was attended to in the morning and not the
B-phase, which was the alleged cause of the accident. The said accused also relied upon the
Ex.24/A, report of Mr. K.L. Grover, which had spoken about the Y-phase repair. The relevant
part of Ex. PW-24/A relied upon on behalf of the accused in this regard reads as follows:-
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 318
―It was told by the representative of Uphaar Cinema present at the site
that they had lodged a complained with DVB Complaint Centre regarding
sparking in DVB transformer on 13.06.1997. The DVB staff attended to the
complaint on the noon of that day and stated that they had switched ‗ON' the
transformer after replacing 2 NOS. of burnt cable and sockets of Y-phase of
L.T. Supply Cables.‖
In the observations part of the report, it was stated as follows:-
―One of L.T. supply cable, socket N of B-phase through which the L.T. supply
from transformer to L.T. ACB had been taken, was found detached from the
transformer L.T. bus bar (Blue phase) and was lying by the side of the
transformer radiator..........‖
―........the opinion of the Ex.PW-24, after noting the observations as well as
the facts reported by the Uphaar's representative - whose name was not
disclosed - was clear enough, i.e. :
2. The cable end sockets of B-phase of L.T. supply cables had not been fixed
properly as they appeared to have been fixed by hammer and not by crimping
machine or by any other proper system. Necessary tests such as testing of
protecting system as specified in specification no. 13 (B) Table-2 of IES Code
1886-1967 had not been carried out from time to time..........‖
PW-64, the Director, CFSL was asked specific queries as regard the accident. Query no. 8,
forwarded by Ex.64/A dated 01.08.1997 was as follows:-
―8. Please examine the transformer and other electric
connections/appliances and articles, items seized from transformer room and
other places and sent to CFSL for examination and opine on the condition of
nuts and bolts of the transformer in question in the morning of 13.06.1997
when there was spark in the said transformer at about 07.00 am which was
reported to have been repaired at 11.30 am that day and also in the evening
before the fire incident.‖
PW-64/D, the report of Director, CFSL dated 11.08.1997 as regards to query no. 8 was as
follows:-
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 319
―A physical examination of DVB transformer reveals that the cables of
bus bars of L.T. side did not have check nuts except one lower terminal of
phase-Y and neutral terminal. The check nut of neutral terminal was found in
loose condition. The blue phase single cable at the top along with cable and
socket (detached cable fell down on radiator fin due to constant
arching/sparking at nut, bolt portion on bus bar de-coiling effect of the cable
due to weight of cable. All coupled together to eating away of metal of cable
and socket resulting in U-shaped cable socket end.‖
PW-44 was a Mazdoor. Concededly, he did not attend to the complaint but was standing
outside. His job appears to have been only to carry the tool box for the others who attended to
the transformer repair. No doubt, the witness mentioned that the officers were working in the
middle phase of the transformer. Further he clarified immediately that he could not see
whether it was the R-phase, B-phase or Y-phase.
7.105 The totality of the evidence in this regard would, therefore, show that the
repairs were carried out on the DVB transformer around 10.45 am-11.00 am on 13.06.1997
with the aid of dye and hammer. The attempt by the said accused to cast a doubt about the
phase upon which such repairs were carried-out, is unfounded. Both experts, i.e. PW-24 and
PW-64, who examined the transformer consistently spoke about the B-phase being detached.
The evidence of PW-44 only was that he was unaware as to which phase was repaired,
presumably because he stood at a distance. He clearly mentions that Mr. Bir Singh carried out
repairs under the supervision of Mr. B.M. Satija. If he was within reasonable distance from
the transformer room, there is no reason to assume why he would not have said that the
repairs were not carried-out at B-phase or put differently, were carried out at Y-phase. The
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 320
Trial Court findings about the morning repairs being carried-out upon the B-phase are,
therefore, are based on materials placed on the record and cannot be interfered.
7.106 The next question is whether use of dye and hammer, instead of a crimping
machine by the accused was improper and led to defective repairs, which ultimately led to
sparking and subsequent fire in the transformer. At this stage, it would be necessary to extract
the reports of the three experts examined by the Prosecution.
7.107 Ex. PW 24/A, the report of Mr. K.L. Grover, the Electrical Inspector who
visited the site on 14.06.1997 and submitted the report on 25.06.1997 is as follows:-
―The premises from where the fire started, as reported by the witnesses, is a
Sub-station located on the raised ground floor (stilt floor), Uphaar Cinema
Complex, Green Park, New Delhi. This sub-station comprises of three rooms
which are adjacent to each other and there is rampway leading to the
basement on the rear portion of these rooms & the space in front of these
rooms was being used as a car parking lot, where number of cars in burnt
condition still had been found parked.
In the extreme left room (nearer to balcony exit stair-case) a 500 KVA,
11/0.43 KV transformer belonging to consumer i.e. Uphaar Cinema was
installed and the same was being used to feed electricity to the Uphaar
Cinema complex. In the middle room, a 1000 KVA,11/0.43 KV transformer of
DVB was installed and had been feeding electricity to the adjoining Green
Park locality exclusively and not the Uphaar Cinema Complex. In the third
room, adjacent to DVB room, Low Tension (L.T.) Panel, Metering Cubicle,
Battery Charger, High Tension (H.T.) four Panel Board of DVB was found
installed.
On physical examination, we found that the 600 KVA transformer of consumer
was almost intact, whereas the 1000 KVA transformer and H.T./L.T. Panel
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 321
Boards and Battery Charter of DVB were affected by the fire. On inspection
of the DVB transformer, it was observed that there were two L.T. Bushings for
each phase of the transformer and the Bushings of each phase had been found
shorted with a common metal bar (known as Bus-Bar). There were four holes
in each of the Bus-Bar mounted on the transformer L.T. Bushing. Out of these
four holes, two holes were used for fixing the Bus-Bar on the L.T. Bushing
Terminals and the remaining two holes were used for jointing the L.T. Cable-
end-sockets with the Bus-Bar. On each phase three Nos. of single core
aluminium cables of size 630 Sq.mm. had been connected for carrying electric
supply from the transformer to the Air Circuit Breaker installed on the L.T.
Panel Board.
On detailed examination/inspection of the 1000 KVA transformer and
H.T./L.T. Panel Boards of DVB, the following observations were made: -
1. Two H.T. Bushings of the transformer were broken and the third one
cracked. There were no flash marks on H.T. supply leads and H.T. Bushings of
the transformer.
2. One of the L.T. supply cable-end-socket of B-Phase through which the L.T.
supply from transformer to L.T. ACB had been taken, was found detached
from the transformer L.T. Bus Bar (Blue-Phase) and was lying by the side of
the transformer radiator.
3. There was a cavity in the B-Phase Bus-bar (around the hole from where
cable got detached) of the transformer and the upper portion of the cable-end-
socket which was lying by the side of the radiator also melted/burnt in a way
that the centre hole of the socket took a U-shape.
4. The earth conductors connected to neutral terminal of the transformer were
found disconnected near the neutral terminal. There were short-circuit marks
on these earth conductors (indicating beads formation at the end of these
earth conductors).
5. The neutral Bus-Bar was loose and the check nut used for tightening the
Bus-Bar was also loose.
6. The P.V.C. insulation of the L.T. Cables connected to the transformer Bus-
Bar were found damaged/burnt. The insulation of the cable, which was lying
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 322
by the side of the radiator, was also found almost burnt out from transformer
up to L.T. Switch Room.
7. Battery Charger & L.T. Panel Board were found almost damaged with fire.
8. No protection relays/system were found installed on any of the HT
Breakers of the said H.T. Four Panel Board, from where the HT supply to
1000 KVA transformer in question had been fed.
It was told by the representative of Uphaar Cinema present at the site that
they had lodged a complaint with DVB Complaint Centre regarding sparking
in DVB transformer on 13.6.97, the DVB staff attended to the complaint on the
noon of that day and stated that they had switched ‗ON' the transformer after
replacing the two nos. of burnt cable-end-sockets of Y-phase of L.T. supply
cables.
From the above it is evident that due to loose connection of the cable- end-
socket of the B-phase Bus-Bar of transformer, there was sparking at the said
connection. At that time, the transformer was 'on load' and the current
supplied from the 1000 KVA transformer was passing through these Bus-Bars
and at the same time, sparking was there on the B-phase Bus-Bar, thus the
magnitude of the current supplied through B-phase could be large which had
caused excessive heating of the transformer B-phase Bus-Bar and cable-end-
socket. The excessive heating and sparking formed a cavity on the B-phase
Bus-Bar and also melted the upper portion of the cable-end-socket. Due to
weight of cable and decoiling effect of the cable, it might have exerted pull on
the Bolt (used for fixing the cable-end-socket at transformer Bus-Bar), as a
result cable-end-socket came out with a flick from the bolt portion, after
formation of an opening in the cable-end-socket (U-formation of socket) and
hit the transformer radiator's fin. Due to over-heating of the cable, its
insulation gave-way and conductor became naked/exposed. The live conductor
of this cable, which hitted the radiator-fin, formed an opening in the radiator-
fin (due to short circuiting) from where transformer oil gushed out and spilled
over the floor. It appeared that the short circuiting of cable with the radiator
fin continued for a sufficient time, since there was no protection system
provided for the transformer at the said sub-station, as a result the
transformer's oil caught fire due to arcing/sparking caused by short
circuiting.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 323
At the time of inspection the following provisions of the Indian
Electricity Rules, 1956 had not been found complied with by DVB: -
(1) No protection system against Over-Current, Earth Fault and excessive
Gas Pressure had been found provided for the said 1000 KVA transformer of
DVB installed at Uphaar Cinema Complex, so as to automatically disconnect
the supply under abnormal conditions as required under the provisions of
Rule 64A (2) of the said rules.
(2) The cable-end-socket of B-phase of L.T. supply cables had not been
fixed properly as the same appeared to have been fixed by hammering & not
by the crimping machine or any other proper system. Necessary tests such as
testing of protection system etc. as specified in the specification No.13.3
(Table-2) of I.S. Code No.1886-1967 had not been carried out from time to
time and as such the said transformer had not been found maintained in
healthy condition as required under the provisions of Rule 65 (5) of the said
rules.
The effect of short circuiting of L.T. supply cable with the transformer
and subsequently catching of fire by the transformer's oil, could have been
avoided, had the fault (may be loose connection etc.) in the transformer which
was detected in the morning of 13.6.97, been repaired properly & also the
protection relays/system which were missing, been there (on the H.T. Breaker
controlling the supply to transformer in question) to protect the transformer
against Over-Current, Earth Fault & excessive Gas Pressure (Buchholts-
Relay)‖
7.108 The report of Mr. K.V. Singh, Executive Engineer (Electrical), PWD dated
29.06.1997, i.e. Ex. PW.35/A is also corroborative. It reads as follows:-
―It was found that the transformer etc are installed on the ground floor level
where the vehicle (car) parking is also in the same floor. It was noticed that
HT panel installed in the sub station consist of 4 panels of which 2 panels
were incoming panels & 2 panels were outgoing panels. 11 KV supply was
further connected with two different transformers installed in two separate
adjacent rooms. One transformer capacity is 500 KVA which belongs to
Uphaar Cinema Management & Caters to their Electricity needs. The other
transformer is of 1000KVA and connected from second outgoing panel of the
above said HT panel. This 1000KVA transformer belongs to DVB and it was
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 324
feeding electricity to nearby area from LT panel installed in adjacent room
which is same as HT room.
On the visual inspection it was found that 500 KVA transformer which belongs
to Uphaar Cinema was undamaged. It is felt that the transformer was not
cause of fire at least.
On the inspection of 1000KVA transformer, it was found that the transformer
cover was open (it was stated to be opened by other officers who visited before
us). The one part of radiator was also not available and it was stated to be
taken away for further investigation by some other investigating agency. It
was seen that the LT terminal box of the transformer was having 2 bushings
on each phase. These 2 bushings were connected through copper bus bar.
From the each phase 3 single core cables of the size 630 sq. mm was
connected. The bus bar of the ‗B' phase was not available and it was seen that
one of the cable leads along with the socket was also not available. It was told
that bus bar and part of cable lead was taken away along with radiator for
further enquiry. It was noticed that the transformer tank inside was clean and
as such there were no sign of smoking inside. There was no oil except a little
bit of oil at bottom in the transformer tank. Apparently, it was no electrical
fault inside the transformer. It was also seen that all the cable connected to
the LT terminal box of the transformer were damaged and insulation of cables
was heavily burnt up to the wall of LT room. The transformer room was fully
dark with black smoke particle deposited on its all walls and roof.
It was noticed that earth strips were lying in the transformer room but the
joint in the earth stripped was not proper. It was also noticed that the earth
connection to the neutral was also broken.
INSPECTION OF LT & LT PANELS
The cubical LT panel was heavily burnt. The main incoming switch to
the LT panel was in the form of 1600 ampere air circuit breaker. It was
noticed that all the out going switches from the LT panel were without fuses.
There was no sign of HRC fuses. It was not correct to use wire in place of
proper use. The HT panel as has already been described above that HT panel
consist of 2 incoming oil circuit breakers & 2 out going oil circuit breakers.
Out of the two incoming circuit breakers one is connected to receive HT
supply from nearby Ashirwad building sub station. The other incoming feeder
was only for making use of standby/duplicate HT supply in case of failure of
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 325
one HT supply connection. It was seen that all these 4 oil circuits breaker
were without any kind of protection against earth fault and over current. It
was also found that potential transformer was in disconnected condition of
OCB operation mechanism which includes the battery charger etc appeared to
be defective and they were heavily damaged due to the fire. There was one
metering cubical was also available.
POSSIBLE CAUSE OF FIRE
As we have seen in the photographs that one of the LT cables got
disconnected from the cables from 'B' phase. It was evident from the
photographs that the cable was touching the radiator fin. There was a hole in
the radiator fin. There was also mark of sparking on the other fins. It is
apparent after seeing the various photographs of the transformer room, cable
leads and cable sockets, that one of the cable sockets got away from the nut &
bolts after getting melted due to severe heat. When it disconnected from the
bus bar terminal it came sliding from the fins of the radiator and caused
sparking marks on the radiator fins & finally it struck one radiator fin, since
heavy current was flowing due to earth fault and the temperature of the lead
was very high. The radiator sheet got damaged and the hole was created in
the fin because of continued arc. The transformer oil coming out from this
hole must have caught fire either from the existing arc which was there due to
touching of the current carrying conductor with the body of the transformer of
possible burning of PVC cable insulation. This arc must have continue for
some time as there was no immediate in tripping system available in the HT
panel. Once the oil got fire and oil continued to come out from the radiator it
was must have caused spread of fire. When oil was spreading it must have
taken the fire outside the transformer room also. The fire was aggravated
further by the presence of the petrol/diesel carrying vehicles parked in front of
transformer room. It is concluded that this unfortunate incident of fire
occurred due to possible over heating of one of the LT connections which may
be due to loose connections or over current. It was further aggravated
because there were no protection system was available in the HT panels
installed at Uphaar cinema. It was ultimately found that the only tripping took
place at 33 KV and sub station at behind AIIMS.
The fire could have been controlled, had there been any fire fighting
equipment installed inside the car parking area and substation building itself.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 326
POSSIBILITY OF SPREAD OF FIRE/SMOKE THROUGH AIR
CONDITIONING SYSTEM
On the preliminary inspection at the site, it was evident that most of the
fire took place only in the parking area & sub station area of Uphaar cinema
and the question of possibility of spread of fire/smoke through air conditioning
conduct was examined. We were told that electric supply to the Uphaar sub
station was not there from 3.55 p.m. to 4.55 p.m. Electric supply to Uphaar
Cinema sub station was restored at 4.55 p.m. As per the information, the
tripping in the 33 KV grid at AIIMS took place at 5.05 p.m. which means that
main power supply was available for a period of 10 minutes between 4.55p.m.
to 5.05 p.m. On the inspection of AC plant room it was noticed that switches of
the AC blower were in 'ON' position. It was also quite possible during these
10 minutes the blowers were started. To check this possibility the AHU room
was inspected. The wire mash filters of the one of the AHU installed near the
door were covered with black smoke. When the filters were removed the sign
of smoke were also seen on the cooling coil face. Therefore, it can be said that
blower might be working during those 10 minutes. The possibility of working
of the blower after the tripping of supply was also examined. It was found that
the main switch from generator supply which was going to the blower was
without fuses and fuses of that particular switch were found inside the body of
switch. The condition of fuses was such that it looked as if that the particular
switch was not being used for quite a long time as fuses were covered with the
dust. Hence, it can be said that blower did not work on generator supply.
7.109 PW-64, Dr. Rajender Singh was asked certain queries by the CBI and he
submitted two reports Ex PW-64/B (dated 27.6.1997 and Ex-PW 64/D (dated 11.8.1997,
relevant parts of which are reproduced below:
PW-64/B
―The inspection of scene of crime carried out by undersigned from 13th
th
to 15 June, 1997 in the premises of Uphaar Grand Cinema and subsequent
detailed Laboratory scientific examinations of exhibits marked 1, 2a, 2b, 3 and
5 revealed the following: -
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 327
1. The physical inspection of the scene of fire revealed two transformers in two
rooms in one of the corner of the hall in the ground floor of the cinema
complex. The smaller transformer situated at one of the corner room stated to
be of Uphaar cinema was found intact. The other bigger transformer of
1000KV installed in the adjacent room stated to be of DVB have maximum
burning effect of fire. The one electric phase cable of LT side mounted on bus-
bar of this transformer has been found to be detached and fallen on ground
due to constant sparking as electric sparking effects were detected on the nut
and bolts bus-bar and fastener end. In the process of falling down of the
detached phase cable the same has apparently come in contact with fins of
radiator at many places leading to intense sparking and creating U Shape
hole in one end fin of the radiator resulting in oil spill. This U-shape hole is of
same dimensions as that of cable fastener. Approximately 10-12 liters of
transformer oil was found in transformer.
On the basis of the fact stated above and laboratory findings it is concluded
that the constant intense sparking between detached phase cable and radiator
has initiated the fire and thus spreading along the oil spill.
2. The flash point of transformer oil (minimum temperature at which
transformer oil catches fire) marked exhibit 1 is 158 degree Celsius.
3. The aluminum cable marked exhibit 5 reveal signs of short circuiting.
4. Facilities do not exist to find out the contents of transformer oil
(exhibit1) in control earth sample marked exhibit 4.‖
Ex PW 64/D
The inspection of scene of occurrence of fire at Uphaar Cinema
Complex by the undersigned reveal the following: -
1. The fire has started from DVB transformer which is situated in the
western portion of the car parking hall situated in ground floor of cinema
complex. The shutter of the transformer room opens towards the car parking
lot. Thereafter, the smoke appears to have traveled in two directions i.e.
northward and southward. The northward bound smoke encountered
collapsible gate and a staircase adjacent to it. The smoke has gushed through
stairwell due to chimney effect. The doors next to the screen on either side has
severe smoke effect. The doors on either side of screen are two plank doors.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 328
Both portions shown effect of smoke. One door opposite to this staircase was
closed at the time of incident as smoke effect was observed only staircase side
of the door. Another door was to the right of the above door and one plank of
the door was open at the time of fire. This way the smoke had entered the
auditorium through right door as one plank of the door was opened at the time
of fire incident.
The southward bound smoke traveled through ariel route towards the
staircase situated to the south of the DVB transformer. The ariel route is
exhibited by the fact that the concrete pillars of the building do not show any
signs of smoke at the bottom portion and cable hanging overhead of Uphaar
Cinema complex shows signs of heat and smoke. The smoke gushed through
the stairwell due to chimney effect. The rear stall foyer canteen was not
effected by smoke as well as fire as the connecting door from this staircase
was closed. This connecting door has strong blisters i.e. effect of smoke and
temperature (heat) on staircase side of door. Hence, the smoke has gone
further up the stair case and reached the foot/lower portion of balcony of
auditorium. The balcony has three entrances, they are one entrance is next to
this particular stairwell and one entrance is through foyer/canteen lobby and
third entrance is one floor above. The smoke effect had been seen on the
outside as well inside of on one plank portion of door next to this stairwell,
leading to foot of the balcony. The smoke has entered the balcony through this
half open door. The connecting door to the foyer/canteen from this staircase
was closed. Hence, this door had effect of smoke and heat on outside portion.
Further the smoke has gone up and effect of smoke was detected on entry door
to the rear portion of balcony. The doors from the foyer canteen side to the
auditorium and balcony were closed at the time of incident. Out of four doors
from rear stall side, three doors of double planks have been forcibly opened
from the inner side of Cinema Hall.
Regarding query 3: The transformer in question i.e. DVB Transformer do
not have following safety measures at the time of inspection.
1. The L.T. Side cables from the bus bar do not have clamping system or any
support to the cables.
2. The earth cable of the transformer has been found temporarily fitted with
the earth strip i.e. twisting of earth cable.
3. There was no cable trench to conceal the cable.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 329
4. H.T. Panel Board of transformer do not have any relay system to trip the
transformer in case of any fault.
5. The Buchholtz Relay system was not fitted on the transformer
6. Temperature meter was not found fitted on the transformer.
Regarding query 4: The sequence of event of fire has already been reported
vide report No.CFSL-97/P-337 dated 27.6.97.
Regarding query 6: The inspection of scene of occurrence i.e Uphaar Cinema
Complex reveal that the ground floor basement i.e. car parking lot has been
effected by fire and rest of the cinema complex is effected by smoke.
Regarding query 7: No emergency light system could be detected in the
auditorium and balcony of Cinema Hall at the time of inspection.
Regarding query 8: The physical examination of DVB transformer reveal that
the cables on bus bars on L.T. side did not have check nuts. Except one lower
terminal of phase Y and neutral terminal. The check nut of neutral terminal
was found in loose condition. The blue phase single cable at the top along
with cable-end-socket (detached cable) fell down on radiator fin due to
constant arching/sparking at nut bolt portion on bus bar, decoiling effect of
cable and weight of cable. All coupled together led to eating away of metal of
cable end socket resulting in U shape cable socket end.
Regarding query 4: (Chemistry portion) The Laboratory examination of fire
extinguishers reveal the following: -
a crimping machine and the dominant cause of the electrical fire being the defective crimping
through the aid of dye and hammer. PW-26, Mr. A.K. Aggarwal, Assistant Electrical
Inspector also deposed that the cables and socket were not fixed by crimping but with dye
and hammer. He further deposed that according to the rules, all conductors of XLPE
terminators are to be terminated either by crimping, compression or by welding methods.
7.111 The relevant IS Code 1255 of 1983 reads as follows:
―Clause 12.6 Aluminum Conductor Connection
12.6.1: There are number of methods of jointing Aluminum Conductors. Four
Standard methods which are commonly used are:
a) Fluxless Friction solder method
b) Soft Soldering method using organic fluxes
c) Welding method
d) Crimped or compressed connection
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 331
12.6.2 Fluxless Friction Solder Method- In this method each strand of the
conductor is carefully cleared and scraped with scraper tongs to remove oxide
film. Then all the strands are tinned by rubbing a special friction solder stick
over the heated strands. This is known as metalizing. Aluminium conductor
thus prepared may be soldered on to copper cable lugs, ferrule, terminal studs
using 60 percent solder. No flux is used in any of the operation. This method is
not recommended for jointing conductors in XLPE cables.
12.6.3 Soldering Method using organic Flux
12.6.4Welding Method Welding Method gives the best possible results. Welded
conductor joints have lesser resistance and equal or better mechanical
strength than the conductor itself. Welding, therefore, should be given
preference for all larger cross sections. For smaller cross section welding may
not always be feasible or economical. In this method the end of the stranded
conductor are first welded to the cable lug, terminal stud or to each other, in
openor closed mould using aluminium welding rods or strands taken from
conductor. After cooling welded connections are filed smoothened and
cleaned.
12.6.5Crimped or Compressed Connections- In this method conductor and lug
ferrules are pressed together firmly by means of tools and dies to form a joint.
The methods normally used are indent compression, hexagonal compression
or circular compression. Tools and accessories should meet the requirement
of relevant Indian Standards where available.‖
7.112 It had been contended by the accused that Clause 12.6.1 and 12.6.5 only speak
of crimping cables; what was done here was to join cables with the transformer. Counsel
submitted that the materials and evidence led before the trial court fell far below the standard
required for it to conclude, beyond reasonable doubt, that there was defective fixing of
cables, by reason of a crimping machine not being used, and also that there was insufficient
evidence to prove that a crimping machine was available, but was not used.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 332
7.113 As far as the standards for fixing cables, are concerned, all experts on the
subject, i.e PW-24, PW-35, PW-36 and PW-64 consistently spoke that the cables were not
fixed or ―crimped‖ by using crimping machines. In the course of cross examination, the
consequence of such ―improper‖ fixing was spelt out by PW-24, who said that it would result
in lack of uniformity in the fixing the socket with the cable. He specifically mentioned that
his inspection showed that two sockets were loose, and fixed by hammering on the B-Phase
and the detached socket was one of them. These witnesses are independent; in fact PW-24
had visited the site at the earliest opportunity. There is no reason to disbelieve their
testimony. It was open to the accused to cross examine them, and suggest that crimping was
not the only method, and to have pointed out to other norms, in support of the argument that
such cables could have been joined with sockets, and fixed to the transformer bus bar, with
the aid of dye and hammer. They could have suggested that use of such dye and hammer
were not prohibited, or were standard practices. Such a suggestion was made only to one
witness, i.e PW-67, but not to any expert; certainly not to PW-24 and PW-64. Similarly, the
lack of awareness of the standard, or its description by PW-73, does not discount the
testimony of the experts, who speak of the accident, and the cables having been joined
improperly and being a major cause of the accident, leading to the fire.
7.114 PW-40, PW-48 and PW-73, all speak about existence of crimping machines
with the DVB. An argument was made by accused that PW-40's evidence cannot be
accepted, since he was under a scanner. Reliance is placed on the circumstance that PW-40
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 333
was suspended; that he had inspected the same transformer on 22-1-1997, and was, according
to the evidence of PW-48 responsible for its maintenance. Therefore, the court, it was argued,
could not have relied on his testimony in this regard. Reliance was placed on State of UP-vs-
Harban Sahai, (1998) 6 SCC 550 to say that overdependence on opinion evidence, even if
the witness is an expert in the field, to checkmate the direct testimony given by an eyewitness
is not a safe modus adoptable in criminal cases
7.115 As held by the trial court and observed earlier, the cable socket was not
crimped with a crimping machine; it was joined with the help of a dye and hammer. The
charge against accused was that they used this method, instead of using a crimping machine,
which resulted in the accident, and led to the death of several people. Several experts spoke
about adoption of this alternative method of joining the cable end, with the socket, which was
fastened to the transformer bus bar. They also deposed that this cable had detached, and due
to improper joining or its not being crimped, it melted into a U shape, and settled on a
transformer fin. The availability of crimping machines has been spoken to by witnesses. Even
if the contention regarding unreliability of PW-40 were to be accepted, at face value, the
other officials, i.e PW 48 and PW-73 speak about crimping machines being available. It is
therefore, held that the cables had not been joined properly, with the aid of a crimping
machine. The court is also of the opinion that there is no variation between the testimony of
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 334
eyewitnesses and opinion of the experts, or any conflicting nature of evidence of the kind
cautioned against by the Supreme Court in Harban Sahai (supra).
7.116 The accused had sought to propound an alternative theory that fire was not
caused at the transformer end, but for unknown reasons, in the parking area. For this purpose,
they urged that the timing of the accident was not 4-55 PM or thereafter, but earlier. The fire,
it was urged, engulfed the vehicles negligently parked, and led to the transformer catching
fire. It was also urged that the prosecution version about the fire emanating from the
transformer is beset with other inherent improbabilities, borne out of the record, which
undermine its case against the DVB accused, entitling them to an acquittal.
7.117 It was contended that the prosecution failed to prove conclusively, whether the
fire actually started due to the alleged faulty repair of the transformer. Learned counsel
suggested that overheating of the transformer and the cables could have been the source of
the fire. He stated that though the upper portion of the radiator and the edges were examined
by the experts for signs of short circuit, the cable core and the conductor were never
examined. He relied on the deposition of PW 35, who opined that the fire could also have
been caused due to over current, due to an earth fault, in which case too the wire could have
got detached and recoiled on the transformer fin. Further he had deposed that the tripping at
the AIIMS grid took place due to over current. He also deposed as to how insulation material
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 335
on the wire could have burned or some other material in the transformer room could have
caught fire. The expert witness further stated that the fire could have started in the parking lot
and later spread to the transformer room. Reliance was also placed in his observation as to
how if there were protection relays, the accident could have been avoided as there would
have been immediate tripping. Further, he sought to place reliance on the observations of
PW 64, that fire could have been caused due to external sources also.
7.118 Counsel relied on the statements given by PW 24, that there was sand in the
transformer room floor, which is also affirmed by PW 48. He stated since there was sand, the
oil would have soaked in it. PW 48 also states that the transformer room level was lower than
the parking lot; therefore, counsel contends that no oil could have flowed out. Moreover, the
temperature at which the transformer oil vaporizes is 140 degree Celsius, whereas the actual
temperature in the transformer room at that time was far higher and consequently it should
have vaporized instead of spilling out of the room.
7.119 Central to the DVB employees'alternative theory of source of fire
propounded, is the argument that its timing was earlier than one found by the trial court. For
this purpose, the testimony of PW-14 (who talked about the fire breaking out at around 4-
30PM or 4-45 PM); the deposition of PW-54, a tenant at Upahaar complex, who stated that
he saw the fire at about 4-45 PM, and the statement of PW-59, that he heard a loud bang at 5-
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 336
00 PM, are relied. The argument also was that the fire would have started much earlier than
4-55 PM, since it spread into the cinema hall by 5-00 PM and that if the prosecution version
is correct, according to PW-64, it would have taken at least 10-15 minutes of sparking for the
socket to detach from the transformer. If so, it is surmised, the transformer oil spillage would
have occurred much later, and smoke could not have entered into the cinema hall by 5-00 or
5-05 PM, as held by the court.
7.120 Now, the evidence relied on by the trial court, about the occurrence of the
incident, was the General Diary Register of DVB, PW-43/A, which recorded about the
incident at 5-00 PM, the log sheet of DVB 33MV Grid Station at AIIMS, Ex. 24/DA and
document Ex. PW-96/E, which records that the fire brigade office was intimated at 5-10 PM
that day. The note sheet in the office of the Chief Fire Officer, marked as Ex. PW-49/E is also
to this effect. PW-1 and 3 mentioned about the fire having occurred about 10 minutes after
the interval; PW-52 deposed having informed Shri K.L. Malhotra at 4-55 PM. PW 47 Baljit
Singh, a DVB Junior Engineer deposed about load shedding in the Green Park feeder from
15.55 hours to 16.55 hours; the relevant entry, made in the Log Sheet dated 13.6.97, was
marked as Ex. PW 24/DA. PW-47 stated that the electric supply to Green Park feeder tripped
off at 17.05 hours, and that he passed on that information to the South Circle, endorsement
was made on it, and signed by other officers who were present there.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 337
7.121 The argument of the DVB accused about the alternative possibility of fire
having occurred due to another cause, and not in the transformer, largely premised on
surmises and deductions sought to be made from depositions of certain witnesses, is sought to
be supported by the testimony of PW-64, who stated that it would have taken 10-15 minutes
for the cable to detach and fall on the transformer. Apart from the argument questioning the
timing of the fire, it was urged that fire could have resulted in the transformer, for a variety of
reasons, such as earth fault, overheating or over-current.
As observed earlier, the documentary evidence establishes that there was a power cut for one
hour, between 3-55 and 4-55 PM. Only two witnesses speak about a fire before 4-55; they
state having noticed it around 4-45. It is a matter of record that the AIIMs grid recorded
tripping, (due to absence of protection relay in the transformer) at 5-05PM. It is also a matter
of record that the incident was reported to the DVB office at 5-00 PM. PW-24, in his
deposition, to a specific query, states that the melting of socket and falling of a cable would
depend on variable factors, and it might have occurred in 5 or 10 minutes. These show that:
iii) Due to tripping at the grid, at 5-05, there was power shut down at the Upahaar
cinema complex and DVB transformer.
transformer, specifically due to the cable falling on the transformer fin. PW-
36's opinion, (recorded in Ex PW-36/A) is that:
―2) A line to ground fault has occurred on LT side due to one of the lead
having fallen on the radiator fin. This fault has been cleared by the protection
relays located at grid sub-station at AIIMS. During the conversation I came to
know that the plug setting of the relays were 5 A and time multiplier setting
(TMS) = 0.05. With these settings the fault must have been cleared in a very
short time of the order of a fraction of a second. During this period the heavy
short-circuit current must have caused damaged to the radiator fin leading to
creation of a hole. The oil leaked out through this hole. Since there was no
damage to the winding of the transformer , one can confidently say that the
duration of the fault must have been very short.
3) The leaking oil must have caught fire either due to the arcing or some
unknown cause.‖
vi) The report of PW-64, ie. Ex. PW-64/D says that:
― The physical examination of DVB transformer reveal that the cables on bus
bars on LT side did not have checked nuts. Except one lower terminal of phase
Y and neutral terminal. The check nut of neutral terminal was found in loose
condition. The blue phase single cable at the top alongwith cable end socket
(detached cable) fell down on radiator fin due to constant arching/sparking at
nut bolt portion on bus bar, decoiling effect of cable and weight of cable. All
coupled together led to eating away of metal of cable end socket resulting in
U-shape cable socket end.‖
vi) According to PW-35/A, one LT cable of the transformer of 1000KVA
transformer had broken away from the terminal and had fallen on the radiator
which caused line to ground fault and also caused heavy flow of the current
which caused hole in their radiator and resulted in spilling of transformer oil
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 339
and the transformer oil which spilled on the ground, due to hole in the radiator.
Fire had taken place because of arching which had taken place in the cable
which had fallen down and this was the cause of fire. There was heavy smoke
in LT and HT rooms and carbon deposits were there, LT and HT panels had
no fuses.
vii) PW-35, in his deposition, states that creation of a hole on the transformer
could occur due to a variety of factors, and that it could take place even within
one second.
viii) PW-35 clearly says that if there were an earth fault, even that would have
resulted in the earthing tripping at the Grid section, at AIIMs. However, the
tripping indicated an over-current, which was due to lack of protection relay.
If such safety measure were present, there would have been a shut down,
instead of an over current.
7.122 A cumulative reading of the evidence would reveal that according to DVB and
the fire department records, the fire incident was reported at around 5-00 PM. Though there
are some variations in the versions of witnesses, this court is of opinion that the findings of
the court about the nature of the accident cannot be held to be without basis. All experts have
uniformly spoken about the manner in which fire started and spread. The attempt of the
accused to say that fire started somewhere else, or for some other reasons, is purely
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 340
conjectural; they do not seem to have put it in the cross examination of any witness.
Similarly, though an attempt was made to elicit facts relating to the flash point of the
transformer oil (140 degrees Celsius) no suggestion was put to any witness, or expert who
deposed in the trial, that the fire did not take place in the manner opined by them, as such
melting of the transformer fin or body would have taken a long time. The line of questioning
of witnesses was not to suggest that the source of fire was something other than a
transformer, or that it was due to over-current. If the alternative theory about the fire were a
reasonable one, the least that the defense could have done was to lead evidence of experts, in
that regard, or produce materials, in support. They chose to do neither. The experts evidence
on the other hand, is categorical that the faulty joining of cable led to intense sparking,
resulting in the blue phase cable detaching itself and falling, after sliding down, on the
transformer fin. The intense sparking, according to them, resulted in melting of the cable
insulation as well as the socket end, resultant constant sparking and arching. Both PW-64 and
PW-35 say that such intense sparking and arching can lead to slit (rupture) of the transformer.
PW-35 even says that such melting, due to arching can take place within a few seconds. In
the light of these statements, and the state of the transformer, as seen by these experts at the
relevant time, (which was also photographed by PW-61) it is concluded that the cause of fire
was, as found by the trial court, namely the blue phase cable at the top along with cable end
socket falling down on the radiator fin due to constant sparking at nut bolt portion on the bus
bar; the de-coiling effect of cable its weight of cable, together led to ―eating away‖ (corrosion
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 341
or melting) of metal of cable end socket, resulting in U shape cable socket end. This in turn
caused a slit in the radiator fin through which transformer oil gushed out in the form of spray,
caught fire and spilled on to the transformer room floor. This flowed outside the transformer
room. The argument about the fire being the result of earth fault was refuted by PW-35. On
the face of these materials, the contention by DVB accused about the fire having emanated
due to some other cause, or due to other electrical causes, unrelated to the repairs of the
transformer in the morning of 13-6-1997, cannot be accepted; the trial court's findings are
held to be based on materials and evidence on record.
ACCIDENT AND SPREAD OF SMOKE:
7.123 The Trial Court found that the fire in the transformer room soon engulfed
several cars parked nearby, which in turn led to thick black smoke. The Court held that this
smoke, being hot and light moved upwards; the movement was accelerated by the ―Chimney
Effect‖, caused by low pressure in one part of the building and high pressure in other. The
Court further held that the smoke travelled from the first floor, into the auditorium from the
back of the screen and through the staircase, blistering the doors on the first floor and finally
entering the second floor, into the balcony from the left side. It was also held that this smoke
which eventually took the lives of 59 people and grievously injured 100 others, composed
mainly of transformer oil and other combustible material, including petrol, were so toxic, that
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 342
sustained and continued exposure for about 20-30 minutes could have naturally caused death
and in fact did so.
7.124 As discussed in the previous part of the judgment dealing with transformer and
accident, PW-24, in his report Ex.PW-24/A, stated that loose connection of cable-end-socket
of the B-phase transformer bus-bar led to intense sparking, causing its detachment. The
transformer was on load at that time and current supply from the 100 KVA transformer was
passing through bus-bar. The magnitude of the current supply through the B-phase could be
large causing excessive heating of the B-phase and the cable-end-socket. This led to a cavity
on the B-phase bus-bar, melting the upper portion of the socket. The weight of the cable and
its decoiling effect might have exerted pull on the bolt; as a result, the cable-end-socket
detached with a flick from the bolt portion after forming an opening and hit transformer
radiator's fin. Due to cable overheating, its insulation gave away and the conductor was
exposed. The live conductor which hit the radiator fin, found an opening due to short-
circuiting from where the transformer oil gushed and spilled-out on the floor. The short-
circuiting appeared to have continued for sufficient time. The transformer oil thus caught fire
due to arching/sparking.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 343
7.125 PW-35 who prepared his report Ex.PW-35/A, after inspecting the cinema hall
on 19.06.1997 supported the findings of PW-24. PW-36, as noticed earlier, also said much
the same thing. As to the cause of spread of fire and smoke, PW-35, in his report PW-35/A,
after inspecting the site stated much the same conclusions as PW-24. Further, the spread of
fire was described in Ex.PW-35/A where it states that the spillage of transformer oil
continued; it went outside the transformer room. The fire was aggravated, according to PW-
35/A, by presence of petrol, diesel oil parked in vessels of transformer room. The reason for
spread of fire, according to PW-35/A, through the air conditioning system was that between
the period when electricity supply was restored at 04.55 pm and at 05.05 pm, when it was
shut down as a result of tripping in AIIMS grid, there was a possibility of the air conditioning
blowers having started. On inspection of the AHU (Air Handling Unit), it was found that the
filters installed there near the door were covered with black smoke. After removal of filters, it
was found that the ‗cooling coil' face also showed traces of smoke. Ex.PW-35/A, the report,
states that the blower might have been working for ten minutes. It further states that the AC
blower was in ON position and concluded that the condition of the generator room was such
that there was lot of dust indicating its disuse and that the blower was not working on the
generator at the relevant time. The next witness was PW-25, who inspected the site. He
noticed black smoke from the transformer room going to the staircase area. He also
mentioned in cross-examination that cars were parked in the parking area which too showed
traces of smoke. He deposed that wind must have come through the grill gate to the parking
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 344
area and then through the staircase and it led to smoke prevailing in that direction due to
‗Chimney Effect'. According to PW-25, when a fire occurs, it results in high pressure in a
slightly high area and low pressure at a lower height. Wind blows from higher to lower
levels. He deposed that part of the smoke had travelled through AC ducts. He mentioned that
there was a small opening of 45 cm. dia at the roof of the ground floor responsible for the
spread of smoke to the first floor through AC tunnels. This was also mentioned in his report,
Ex. PW-25/A.
7.126 PW-64, in his report had given the opinion that fire started from the
transformer room situated in the western side of car parking area on the ground floor. He
stated that smoke appears to have traveled in northward and southward direction. The
northward bound smoke encountered a collapsible gate and staircase adjacent to it. The
smoke gushed to staircase due to ‗Chimney Effect'. Two plank doors on either side of the
screen showed severe smoke effects. The door opposite the staircase was closed; it also
showed smoke effects. The smoke entered according to him, into the auditorium through the
right door as one plank was open. Southward air traveled through the aerial route towards the
staircase south of the DVB transformer room. This, according to PW-64 was due to concrete
pillars not showing any sign of smoke in the lower portion and the cables hanging overhead
showing signs of heat and smoke. Rear stall canteen was not affected by smoke or fire, since
it disclosed strong blisters. The smoke, therefore, had gone up and reached the lower portion
of auditorium balcony. The smoke effect had been seen on the outside as well as inside one
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 345
plank portion of the door next to the stairwell leading in to the lower portion of the balcony.
The smoke entered through this half-opened door. The door connecting fire canteen from the
staircase was closed. This showed smoke and heat effect from the outside portion. Smoke
went up and its effect was detected on the entry door to the rear portion of the balcony. The
doors from the fire canteen to the auditorium were closed at the time of the incident.
7.127 Among the eye-witnesses, PW-3, Mr. Raman Kumar deposed having noticed
smoke emerging from the air-conditioner duct. He managed to leave the theatre but could not
enter the hall due to dense smoke. Mr. Rishi Arora, PW-7 felt gases in the rear stall after
interval and felt suffocation due to smoke and gases. PW-11 also noticed lot of smoke and
gas after the interval. He also deposed having encountered smoke in the lobby and having lost
consciousness. According to the witness, nothing was visible due to smoke. PW-8, Amit
deposed having noticed that after lights went out, some smoke arose before the screen.
7.128 PW-63 also deposed noticing fire in the DVB transformer. He noticed smoke
in the stairs and lot of gases on the top floor. Similarly, PW-27, 49 and 52, all mentioned
about fire and smoke in the parking area of the building. PW-49, the Chief Fire Officer
deposed having reached the cinema hall complex at 05.45 pm, and entered the balcony area.
According to his deposition, there was thick black smoke and lot of heat. The balcony fire
door could not be opened and had to be forced open by his officers.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 346
7.129 Ex.PW-49/E is a fire report prepared by PW-49. According to the document, a
call reporting fire was received at 05.10 hours in the Delhi Fire Control Room from PCO.
Four fire tenders were requisitioned from nearby places. The earliest tenders, with one
ambulance reached the fire scene at 05.16 hours. The first unit reached at 05.21 hours and
started fire-fighting operations. On receiving a message, four motor tenders, two motor
pumps along with two hydraulic platforms were sent at 05.27 hours. The fire was declared to
be of medium category due to the number of persons trapped in the hall, at 05.31 hours, by
the officer incharge of the scene. Fire fighting operations were strengthened by the
responding seven water tenders, two light vans, hose tender, water pump and two mini buses
with manual power, at 05.32 hours. The Dy. Chief Fire Officer and Asst. Divisional Officer
also rushed to the scene. The fire was declared as of serious category at 05.50 hours with
eight water tenders, one Bronto, one ambulance, two motor pumps and one hose tender. The
Chief Fire Officer also rushed to the scene. The report stated that there was heavy traffic in
the road leading to considerable delay in the fire engines reaching the site of the accident; the
fire was brought under control at 06.20 pm and rescue of the last person completed at about
07.45 pm.
7.130 The prosecution had, for the purpose of proving composition of substances
seized soil samples through Ex.PW-70/X on 29.07.1997. These included soil samples beneath
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 347
leakage point of the DVB transformer; middle-point distance of about 3 ft. from the starting
point where oil was said to have leaked from the radiator, from outside the transformer room
about two-and-half feet away from the shutter base. Again, another sample, four feet away
from the shutter base and right side of the bottom of the wall near a car which was in
completely burnt condition, was recovered. One soil sample was collected 7 ft. away from the
transformer room in the right direction underneath a burnt car and one sample was collected
from a burnt scooter near the staircase. These samples were sent as Ex.S(1) to S(15), to the
CFSL. The report of Director, CFSL, Ex.PW-64/D adverted to a chemical analysis report
forthcoming on a later date. Ex.PW-83/A was the report prepared by K.S. Chabra, Senior
Scientific Officer-cum-Assistant Examiner, CFSL, relating to the samples. He deposed
having examined parcel nos. 4, 5, 7 and 8 containing transformer oil, Ex.P-6, petrol, Ex.P-7
and soil samples taken from the site. In his deposition and the report, the witness stated that
there was presence of petrol in Ex.P(2). Ex.62/A, the report of forensic science experts
headed by PW-62, Dr. T.D. Dogra mentioned about the 41 persons being brought dead to
AIIMS. Specifically, the report, Ex. 62/C, prepared by a panel of doctors, mentioned about
the death of two persons, namely Srishti, on 19.06.1997, due to carbon monoxide poisoning
and Amarpal, on 29.06.1997, due to smoke inhalation injury chest infection, Septicemia,
acute renal failure, acute liver necrosis and Leptospirosis.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 348
7.131 The report, Ex.62/C, which was in answer to query nos. 2 and 3 through letter
dated 05.09.1997, read as follows:
Q.2. The copy of the postmortem examination report enclosed and
the report of the CFSL may please be examined and opinion be given about
the smoke and the gas which had caused the death of the persons who were
affected by the fire in Uphaar Cinema on 13.06.1997.
Q.3 Opinion may please be given on the contents of the smoke and
the type of gas which could have emerged from the fire as mentioned above
and effect of the same on the human body.
Ans. 2&3. After considering the postmortem examination report in respect
of deceased M.S. Bhinder conducted at Army Hospital, CFSL report and the
report of the scene of occurrence, the Board is of considered opinion that the
gases produced in such a fire shall depend upon the nature of items burned.
The possible items which may have been burnt were likely to be made of
rubber, polyurethane, polyvinylchloride, acrylonitrile-butadiene styrene,
petrol, diesel & nylon. The product of combustion of such items may contain
carbon soot, hydrocarbons (saturated+unsaturated), carbon-monoxide,
carbon dioxide, sulphur dioxide, hydrogen sulphide, nitrous oxide,
hydrocyanic acid, hydrochloride, vinylchloride, phosgene, ammonia,
aldehydes etc. The photo copies of relevant literature from the Text Book of
Medical Toxicology and Goldfrank's Toxicologic Emergencies are attached
herewith as Annexure.III & IV for ready reference. All these gases are toxic
gases having either systemic toxic effect and/or pulmonary irritant effect. The
item wise products of combustion are given below:
Among them, the most common cause of smoke inhalation related
deaths is carbon monoxide, which is a systemic toxin with no irritant
properties. In the postmortem report of deceased Shri M.S. Bhinder, lungs are
described to be exuding ‗pinkish fluid' on sectioning and compressing of
lungs. Such a finding can be seen in Carbonmonoxide poisoning.‖
The report also stated that there were no burn injury or other cause of suffocation.
7.132 Ex. PW 25/A is the report of Shri T.P. Sharma. It stated that:
―Since the fire load, which is responsible to the growth and spread of fire was
in the form of cushion seats, tyres, petrol/diesel, transformer oil and cable
besides other materials like wood etc. The nature of the flammable material
and their amount with low ventilation has resulted in the burning which can
be categorised as partial burning or burning as a result of defficient oxygen
supply. This has resulted in the high smoke generation evolving the toxic gases
(alongwith carbon dioxide gases ) like carbon monoxide, hydrocloric, (HCL)
gas, cynogen gas (HCN), Sulphur dioxide etc. The later these gases may be in
very low concentration but they are highly toxic to cause fatal injury.‖
The report further outlined toxicants, their sources, their effects and the estimate of their short
term lethal concentrant. They included hydrogen chloride, other Halogen acid gases, sulfur
dioxide, (SO2) Hydrogen cyanide (HCN), Nitrogen dioxide, and other dioxides of nitrogen,
ammonia. It further says that:
SO2 results in damage of mucos, is extremely pungent and leads to death due
to 1) asphyxiation 2) cardio respiratory disorder.
H2S is extremely dangerous to mucos membrane.
NH3 is extremely dangerous to mucos membrane. Inhalation of strong
concentration may lead to immediate death from direct vagal inhibition.
Irritant(gases) may be chloride, aldehydes phosgene, vinyl monomers etc.
They result in deaths due to pulmonary complications & respiratory tract
damage. Presence of particulate further enhances these effects.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 350
Particulates. They carry toxic products on them(absorbed) and penetrate
deeper in lungs.
In reply to another question, PW-25, in his report, stated as follows:
―9. How did the people die and what could be the effect of the gas/smoke on
them. May please see the copy of the post mortem report in respect of Capt. M
S Bhinder and please comment on the nature of gas which had caused the
death. A:People might have died
due to :
Lack of oxygen
Carbon monoxide(CO) inhalation in large quantity resulting in impaired
cardiovascular function, high COHb percentage.
CO2 increases respiration rate thus resulting in increased inhalation of toxic
products of combustion.
HCN- due to histotoxic anoxia in which normal cellular
metabolishm is prevented from occurring due to the enzyme inhibition.
Asphyxia results as oxygen is not effectively utilized.
( Documented cases in which HCN alone is considered to be primarily toxic in
fire are rare)‖
7.133 The appellants' contended that the toxicity of gases and the fatality caused by
them was not proved; they termed the trial court's findings ―conjectural‖. The discussion of
the above material would disclose that medical experts' evidence, in the form of Ex. PW-
62/C was clear as to cause of death of two victims, who were brought in on that day, though
who died later. The board, which gave its opinion, also examined the autopsy report of Capt.
Bhinder. Ex PW 77/A, the autopsy report, says that the cause of death was declared as
Asphyxia. The relevant extract of that report, prepared by the Command Hospital, and seized
by Ex. PW-77/B, is as follows:
―... 3. Pupils fixed and dilated. Cornea hazy.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 351
C. INTERNAL EXAMINATION
a) ALIMENTARY SYSTEM
Mouth, pharynx and esophagus.
Frothy blood mixed fluid with blacking particles preSent. Mucosa
of pharnyx congested
2(a)
...
(d) RESPIRATORY SYSTEM
e1. Nose, nasopharnyx, larnyx, trachea, and bronchi mucosa of
nasopharnyx, larnyx, trachea and brochi parched and congested.
Frothy blood mixed fluid with black particles present in the
lumen.
(F). SALIENT AUTOPSY FINDINGS
1. Congestion and oedema of larnyx trachea and bronchi
2. Evidence of pulmonary oedema
3. Foreign particles in respiratory tract
(G). CAUSE OF DEATH
Asphyxia ......''
7.134 The AIIMS constituted a medical board, consisting of Prof. T D Dogra, Dept.
of Forensic Medicines, (PW-62) Prof. S K Sharma, Dept. of Medicines, Prof. R.K Khazanchi,
Dept. of Surgery, Dr. Praveen Aggarwal, Associate Professor, Dept. of Emergency Medicine,
Associate Prof. L R Murmu, Dept. of Emergency Medicine, Associate Prof. Dr. Shakti
Gupta, Dept. of Hosp. Admn. Dr. Shakti Gupta, member secretary, Dr. Arun Sahu, the then
Deputy Director. The experts arrived at a unanimous report, and answered the questions
posed by CBI. The relevant part of the report, in relation to Questions 2 and 3 has been
noticed above; it unambiguously states that the post mortem report of Capt. Bhinder showed
that lungs were described as exuding 'pinkish fluid' on sectioning and compressing of lungs
and that such finding could be seen in carbon monoxide poisoning. Ex. PW-108/N is a test
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 352
report of the CPRI, pursuant to submission of the samples, by CBI, to it, on 29th October,
1997. The sample was of transformer oil; it mentioned that the flash point of the sample was
O
149 C, with methane content @ 2 PPM (parts per million); ethane @ less than 1 PPM;
ethylene @ 2 PPM; acetylene @
establish the manner whereby the smoke sped and spread on to the upper floors (first floor,
second floor-including balcony- and top floor) of the cinema building. The reports PW-83/A
and 108/N mentioned about composition of transformer oil and petrol. The report PW-25
detailed, on the basis of observations - including the burnt cars at the site, the composition
and toxicity of various substances, which were burnt by the fire. Soil samples had been taken
near cars and other vehicles; more than one witness spoke about several cars having been lit
up by fire. The substances mentioned in PW-25/A, and described above, were highly toxic.
PW-62, who headed the medical board, that submitted the report Ex. PW-62/C clearly
mentioned the cause of death of two patrons. It was said that Shristi, a victim, died on 19th
June, 1997 due to carbon monoxide poisoning; the causes of death of Amarpal (who died on
29-6-97) were several, including smoke inhalation injury, chest infection, septicemia, acute
renal failure. Examination of PW-77/C, the autopsy report of Capt. Bhinder, according to the
medical Board, showed that the cause of death was due to carbon monoxide poisoning. The
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 354
board also wrote about the effect of the gases burnt, due to the transformer and vehicles
catching fire; according to it, the effect of these gases is rapid as the fatal period for carbon
monoxide with ten percent concentration is within 20-30 minutes; the fatal period of hydro-
cyanic acid is 2 to 10 minutes, sometimes immediately. Therefore, combined effect of various
toxic gases produced during combustion of the above-said material could have caused rapid
death of the victims.
7.137 One argument made by the accused appellants was that there was no evidence
to support the conclusion that smoke entered the balcony, through air conditioning ducts. It
was urged that the experts' reports did not support this theory; on the contrary, Ex. PW-35/A
expressly stated that the air-conditioning system was not using the generator.
7.138 According to PW-35/A smoke went through the air conditioning duct. He
however, found that air conditioning blowers were not connected through generator supply.
He, therefore, blowers were not working and the smoke did not travel through air
conditioning duct, after the fire, the blower should have stopped working but it did not. The
supply was restored between 4.55 to 5.05 and during that period, the blowers were on which
enhanced the speed of smoke inside the cinema hall. These observations were premised on
his seeing that the blower was in the ―ON‖ position when the A/C unit was inspected by him.
PW-25, in his report Ex. PW-25/A states this:
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 355
......The smoke, travel through staircase NO. 3, was again responsible for the
faster spread in the first floor auditorium area through the door provided at
the base of the podium of the screen. Similarly the small opening of about 45
cm dia at the roof of the ground floor was also responsible for the spread of
the smoke at the first floor through A.C. Tunnels......
7.139 PW-3 mentioned about smoke entering the balcony, through the air
conditioning ducts. The evidence of PW-35, PW-25 and PW-3, therefore, is to the effect that
the air-conditioning was not linked with the generator system. However, the blowers were in
the ―ON‖ position; they started immediately after the electricity supply was restored at 4-55
PM, and continued to blow, till shut down consequent to tripping, at 5-05. In the meanwhile,
the smoke caused by fire in the ground floor, spread through the staircase, into the cinema
hall and balcony; it also entered the balcony, through the air-conditioning tunnels.
7.140 The findings of the trial court, therefore, about the cause of fire in the
transformer room, vehicles catching fire, spread of smoke into various parts of the building
and the manner of spread of smoke, choking of patrons due to hot smoke, their sustained
exposure, for 30-45 minutes, to such smoke, are based on sufficient materials; the prosecution
has been able to establish its case on this score. The doubts sought to be expressed are not of
such a character as to undermine the findings.
Statutory clearances/approvals and position of inspection concerning fire safety
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 356
7.141 Cinema theatres in Delhi were being licensed after inspection by various
authorities. These included inspection by the Public Works Department (PWD), the No
Objection issued by the MCD and clearance by the Fire Department. After these clearances
the appropriate authority i.e. the SDM used to issue the annual or temporary licenses as the
case may be. With the coming into force the Delhi Police Act, 1978, the responsibility of
issuing licenses became that of the Police Commissioner; he designated the Deputy
Commissioner of Police (DCP) in that regard. The procedure adopted by the DCP
(Licensing) was to call for clearances by the PWD, MCD and the Fire Department and
thereafter proceed to pass necessary orders. In this section it is proposed to examine the role
of various statutory/licensing agencies and the individuals working in such agencies, arrayed
as accused, while granting the clearances.
7.142 The first agency in this regard would be the Licensing Department. While
considering the nature of deviations, particular those in the balcony, various letters and
correspondences exchanged between the PWD through Mr. S.N. Dandona and the concerned
DCP (Licensing) Mr. Amod Kanth were discussed. It would be relevant at this stage to
notice the evidence and materials adduced by the prosecution with regard to the role of the
Licensing Department. The prosecution relied upon inspection reports dated 8.4.1977;
16.11.1977, 22.5.1978, 28.3.1979, 7.3.1980, 25.3.1981, 10.3.1983, 26.4.1985, 20.5.1987 and
19.5.1990, among other inspection reports. These were all parts of Ex.PW-69/AA, the file
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 357
seized from the office of the PWD. These inspection reports are stereo typed and have
repeated year after year the same observations. Interestingly the reports for inspection dated
23.2.1978 and 28.3.1979 specifically say that no side gangway was provided in the balcony
due to new seating arrangements. However, those observations do not find mention in the
later reports. Two other irregularities noticed in relation to gangway is that instead of 1.20
metres, mentioned in the inspection report, the width of 3 gangway is mentioned as 1.15
meters. The inspection report also speaks about one existing water tank. The inspections are
completely silent about existence of two transformers in the ground floor and that they were
located near the parking lot.
7.143 The above evidence would show that Licensing Department continued to issue
clearances periodically in a mechanically manner. In the part concerning deviations found in
the balcony, this Court had held that there were several breaches of DCR 1953 such as Para 8
(1), First Schedule; para 8 (4), First Schedule DCR 1953 which mandated that exits and
gangways leading to exits shall be kept clear of obstructions as well as Paras 10 (1), 10 (2),
10 (4) & 10 (a). Besides, the Court noticed several other violations. The closure of the exit
from the right side by permitting installation of 8 seater box, obstruction of the additional exit
permitted on the left side by allowing several seats to be placed, narrowing of a gangway, all
amounted to serious contraventions of DCR 1953 and DCR 1981 which compromised the
safety norms. The Licensing Inspectors/PWD officers did not apparently even deem it
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 358
appropriate to consider the fire safety angle having regard to the location and capacity of the
second DVB transformer and its proximity to the parking lot.
7.144 In the circumstances, it is held that the Licensing Department, which
authorized issuances of approvals and NOCs did so mechanically; they also acted contrary to
the DCR 1953 while permitting and continued approval for closure on right side gangway;
closure of the right side exit; narrowing of a gangway and the other violations discussed in
the earlier part of the judgment.
7.145 The second aspect concerning safety of the building and the DVB transformer
located within it. Here it becomes necessary to examine, to scrutinize the inspection reports
by the Electrical Inspectors. Three such inspection reports, namely, PW-24/DB (dt.6.6.95);
PW-24/DC (dt.21.5.96) and PW-24/DW (dt.6.5.97) are material. Each of these was issued by
the office of the Electrical Inspector, under the Electricity Act. They all clearly mentioned
that there was no objection if the license of the Cinema were renewed.
7.146 Now, it is a matter of record that in July, 1989, a fire had occurred in the
Cinema Hall. The facts relating to that incident were discussed in a separate part of this
judgment. Record discloses that approval had been granted by the Electrical Inspector for
installation of the Uphaar Cinema 500 KVA transformer in substitution of the burnt
transformer. However, no such corresponding permission was granted in respect of the DVB
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 359
transformer; the DVB in fact increased its capacity from the existing 750 KVA transformer
(which caused damage due to the fire) to 1000 KVA transformer.
7.147 In his report PW-24/A listed several norms which were flouted in regard to the
installation of the second transformer. They included absence of protection relays in the
DVB transformer to guard against over current, earth fault and excessive gas pressure. He
state that this violated Rule 64-A (2) of the Electricity Rules. Ex.64/D by Director, CFSL
observed that the DVB transformer also showed other deficiencies such as absence of cable
trench to conceal the cable; no temperature meter fitted on the transformer; lack of Bush
Holtz relay system, no clamping system or support to the cable.
The above would shows indifference by both the DVB in regard to the maintenance of the
transformer as well as omission by the Electrical Inspector's representatives who visited the
Cinema Theatres for annual inspection. Although the inspections were of the Uphaar Cinema
Transformer, Court cannot lose sight of the fact that the inspection was to be in terms of the
DCR 1953 & DCR 1981. The paramount consideration of the Cinematograph Act and the
norms stipulated by DCR 1953 and 1981 were fire safety of the building being used as a
cinema hall. The officials and employees who inspected the Cinema did so for the ostensible
reason of considering the fire safety and security of the Cinema Halls in the context of the
equipment, construction and manner of use of the building. The location and use of the
second transformer even if unauthorized surely did call for comment. That the Electrical
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 360
Inspector's representatives did not deign even to comment on the existence of the transformer
much less inspect it from the fire safety angle points at their colossal failure in this regard.
7.148 The third agency which issued no objections at the relevant time was MCD. It
has been held in the previous part of this judgment that ever since 1983 when the Licensing
Department stopped issuing annual licenses, the Cinema was issued temporary two months'
licenses. The Trial Court after considering the evidence of the prosecution in the form of
testimony of PW-22 Veerbhan Sethia and documentary evidence such as Ex.PW-69/AA,
69/BB, 69/CC & 69/DD concluded that temporary permits were issued for the period
1.2.1995 to 31.3.1995, 1.4.1995 to 31.5.1995, 1.6.1995 to 31.7.1995 and 1.8.1995 to
30.9.1995. The Trial Court also held that though NOC by the MCD was not of any
relevance, it was issued on 20.9.1995, six months after the previous license had expired on
31.3.1995. Similarly it was held o n the basis of PW-23's evidence (who spoke about the
NOC for the period 1.4.1996 to 31.3.1997) and upon consideration of Ex.PW-23/A and Ex-
PW-2/AA-27 (that Department had no objection in renewing the license for the period
1.4.1996 to 31.3.1997), that for both these periods, there was no inspection by the MCD and
the concerned employees approached the matter in a mechanical manner recommending
issuance of NOC. The Court also held that Ex.PW-2/AA-27 NOC was handed over directly
to Mr. K.L. Malhotra instead of being routed through the Licensing Department.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 361
7.149 Ex. PW 39/DA is a letter dated 20.4.1995 to the Zonal Engineer Building,
MCD from the DCP (Licensing). The letter was marked to one Jr. Engineer Mr. Sherawat. It
was subsequently marked to the Administrative Officer Mr. Shyam Sunder Sharma on
4.5.1995. The noting of Jr. Engineer on the letter was that the matter pertained to the
Licensing Department; on 28.9.1995, the said accused merely stated that if aggeed MCD
could issue NOC for the renewal of licenses. In the circumstances, NOC Ex.PW-2/AA-26
was issued on 28.9.95. The original NOC was handed over directly to accused K.L. Malhotra
on 28.9.95 by Shyam Sunder Sharma. Neither the noting, nor any other document on the
record discloses that the NOC was preceded by any inspection or enquiry. It appears to have
been issued merely for the asking. The entire sequence of facts leading to issuance of this
NOC was narrated by PW-22.
7.150 Ex PW-23/PA is a letter dated 11.3.1996 by the DCP (Licensing) to the MCD
concerning the NOC to be issued by the latter. The MCD received a letter dated 19.9.96
(Ex.PW-23/DB) seeking no objection from the annual renewal of license for the year 1996-
97. The said letter itself contained a noting by Mr. N.D. Tiwari recommending issuance of
NOC. Pursuant to this, Mr. Bharat Bhushan, PW-23 made a noting on 23.9.97 and Ex.PW-
2/AA-27 NOC was issued by M.D. Tiwari, Administrative Officer to the DCP (Licensing) till
period 31.3.1997. The sequence of events was corroborated by the testimony of PW-23. On
the basis of the above material, the Court held that the concerned authorities had violated
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 362
Rule 14 of DCR 1981. The allusion here appears to be to Rule 14 (1) (a) which concerns
itself with examination on structural features of the building for the purpose of reporting
whether rules ―thereto‖ have been duly complied with.
7.151 The last aspect to be considered by the Court is the nature of fire safety
inspections carried out by the concerned authorities i.e. the Fire Department. Before the
factual discussion on this score, it will be necessary to briefly summarize and wherever
necessary extract the relevant norms. DCR 1953 by Para 16 of the First Schedule required
provisions for fire extinguishing appliances suitable to the character of the building and of a
pattern, class and capacity approved by the licensing authority. It also prescribed that such
appliances were to be readily available for use in case of fire in any part of the building. Para
16 (2) set out that sufficient means for dealing with the fire should always be readily
available within the enclosure including a damp blanket and portable chemical fire
extinguishers and two buckets of dry sand. Para 16 (3) enjoined that all fire extinguishing
appliances were to be maintained in proper working order at all times and available for
instant use and that chemical fire extinguishers were to be capable of withstanding a pressure
of not less than 250 lbs. Square inch. Para 16 (4) prescribed that all fire extinguishing
appliances were to be in charge of some person or persons specially appointed for that
purpose ―who were not to do any other work during an exhibition which would take them
away from the building or otherwise prevent them from being immediately available in case
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 363
of danger or alarm of fire.‖ DCR 1981 by Rule 39 prescribed that the Cinematograph
Operator had to satisfy himself before commencement of every performance that fire
appliances intended for use within the enclosure were in working order; it also mandated that
such appliances were to be in the charge of some person specially appointed for that purpose.
The duty of such person was to ensure that the appliances were kept constantly available for
use. Rule 40 prescribed that the enclosure would be in charge of a qualified operator holding
a certificate granted by the Electric Inspector and not being less than 18 years of age. Rule
42 mandated the operator incharge to satisfy himself that all cables, leads, connections and
resistances and fire extinguishing appliances in the enclosure are in proper working order.
Paras 8 & 10 of DCR 1953 as well as the paras 9 & 12 of DCR 1981, discussed previously
elaborately with the issues concerning nature of gangways, size exits, their locations and
numbers etc. These are also material and as held in this judgment are crucial for
understanding the vital concern express by the rule making authorities that in the case of an
unforeseen emergency - fire or any other serious emergency, threatening the safety of the
patrons, or personal safety of the patrons, speedy and easy evacuation could be facilitated.
Additionally DCR 1981 para 18 of the First Schedule outlines the precautions against fire;
every permanent cinema was directed to store two cisterns connected with fire service in the
Cinema, each of 1,135 liters of water capacity for every 100 individuals of the public to be
accommodated in the cinema. Para 18 (2) prescribed that all cinemas shall be provided with
requisite number of hydrants/hose reels (not less than two) to be fixed by the licensing
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 364
authority. Para 18 (3) prescribed that fire buckets would be housed and the manner of its use.
Para 18 (4) mandated that portable fire extinguishers of an approved type as required by the
Licensing Authority were to be placed on brackets 1.20 m. from the ground. Such
extinguishers were to be refilled, well cleaned or re-charged every 12 months; records of the
same were to be kept for inspection. Para 18 (5) stated that two pressures type fire
extinguishers, two buckets of water, one bucket of sand and blanket were to be always placed
inside the enclosure. A large sponge was also to be kept in one of the bucket of water and one
fire extinguisher was to be kept immediately outside the enclosure. Para 18 (6) provided that
portable fire extinguishers and fire buckets of approved type shall be provided as directed by
the Chief Fire Officer in respect of air-conditioning plant room, electrical sub-stations,
rectifier room etc. Para 74 of the First Schedule to DCR 1981 mandated that where the supply
of current is derived from the special plant on the premises, such plant must in all cases be
approved by the Electrical Inspector. Para 76 stated that electrical accumulators unless
installed in rooms of compartments specially reserved were to be completely enclosed
together with terminals in substantial casings constructed of or lined with insulating and fire
resisting material. Para 77 stated that transforming and converting machinery with
controlling switches and cut-outs were to be placed in a fire proof and water proof structure,
adequately ventilated to the outside air properly and accessible to the management and to be
used for no other purposes. Para 77 (2) stated that
―No transformer which under normal conditions of total heats to above 130
degree F shall be used and the transformer circuits shall be so arranged that
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 365
in no circumstances may a contact between the primary and secondary coils
be established.‖
7.152 The MCD Bye Laws of 1959 through Bye Law 75 prescribed standard for
ventilation in staircases; Bye Law 76 regulated means of egress from building. Bye Law 98
elaborated the standards which certain public buildings including theatre hall were to follow.
Bye Law 98 (4) (i) stated that every such building was to be constructed of fire resisting
materials throughout. It prescribes standards of ventilation through Bye-Law 98 (4) (l) as
1000 cubic feet of fresh air per seat per hour. The 1959 Bye Laws were repealed and in 1983
new set of Building Bye Laws were enacted and brought into force. Bye Law 17.1 of the
1983 Bye Laws provided that buildings were to be planned, designed and constructed to
ensure fire safety in accordance with part-IV of fire protection of National Building Code of
India. It also provided that in case of certain specified kind of buildings mentioned in Bye
Law 6.2.4.1 (i.e. those with the height of more than 15 meters), the Chief Fire Officer had to
clear the building scheme. Bye Law 17.2 mandated that additional provisions relating to fire
protection of building more than 15 meters in height were to be followed; those additional
provisions were prescribed in Appendix ‗K'. Appendix ‗K' - 8.4 prescribed the standards for
which transformers were to comply to. In case transformers were housed in the building,
separate fire resisting room of 4 hours rating had to be built; the entrance of the room was to
be provided with a steel door of 2 hours fire rating with a curve of suitable height to prevent
the flow of oil from raptured transformer into other parts of the basement. K-8.4 (b) stated
that transformer were to be protected by an automatic high pressure water spray or a foam
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 366
sprinkler system. If housed at ground floor level, it/they were to be cut off from the other
portion of premises by fire resisting walls of 4 hours fire resistance. Bye Law K-8.4 (c)
mandated that a tank of RCC construction of adequate capacity was to be provided at lower
basement level to collect the oil from the catch-pit to the tank and was to be of non-
combustible construction. K-9 prescribed the provisions of first aid and fire fighting
appliances. It reads as follows: -
―K-9.1 The First Aid Fire Fighting equipments shall be provided on all floors
including basements, occupied terrace, lift rooms in accordance with IS 2217-
1963 Recommendations for providing First Aid Fire Fighting Arrangements in
Public Buildings in consultation with the Chief Fire Officer.
K-9.2 The Fire Fighting Appliances shall be distributed over the
building in accordance with IS 2190 Code of practice for selection,
installation and maintenance of portable First Aid Fire Appliances.‖
Bye Law K-11 prescribed the standards for fire alarm systems. The relevant portion thereof
reads as follows: -
―K-11.1 All buildings above 15 m. in height shall be equipped with fire
alarm system as given in Bye-laws No.K-11.1.1 and K-11.1.2.
Bye-law No.K-11.1.1 shall, in addition to the manually operated electrical fire
alarm system, be equipped with an automatic fire alarm system. The letter
shall be in addition to the alarm which may be sounded by the actuation of
any automatic fire extinguishing system which may be installed in any
particular occupancy in accordance with these bye-laws. Unless otherwise
decided by the Chief Fire Officer, Delhi Fire Service, the detectors for the
automatic fire alarm system shall confirm to IS:2175-1962 Heat Sensitive Fire
Detectors and the system shall be installed in accordance with IS-2189-1962
Code of Practice for Automatic Fire Alarm system, or any other relevant
Indian Standards prepared from time to time.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 367
Note: - Several types of fire detectors are available in the marked but the
application of each type is limited and has to be carefully considered in
relation to the type of risk and the structural features of the building where
they are to be installed.
7.153 The Delhi Fire Prevention and Fire Safety Act, 1986 was enacted by the
Parliament in 1986 and brought into force on 27.2.1987. It provided by Section 3 for
inspection of building premises etc. by the nominated authority for ascertaining adequacy or
contravention of fire prevention and fire safety measures. Consequently, powers to deal with
and if necessary seal any building or premises, determined to be non-compliant with fire
safety measures, were conferred by sections 4 & 5. section 6 reads as follows: -
"6. Provision regarding certain buildings and premises.
(1) Notwithstanding anything contained in any other law for the time
being in force, the Chief Fire Officer may enter and inspect any building, the
construction of which was completed on or before the 6th day of June, 1983
(being the date on which the current building bye-laws had come into force)
or any building which was under construction on such date if such inspection
appears necessary for ascertaining the adequacy of fire prevention and fire
safety measures in such building.
(2) The entry and inspection under sub-section (1) shall be done by the
Chief Fire Officer in the manner laid down in Section3.
(3) The Chief Fire Officer shall, after inspection of the building or
premises under sub-section 91), and after taking into consideration -
(i) the provisions of the building bye-laws in accordance with
which the plan of the said building or premises was sanctioned;
(ii) the conditions imposed, if any, by the local authority at the time
of the sanction of the plan of the said building or premises; and
(iii) the minimum standards for fire prevention and fire safety
measures specified for such building or premises as may be specified by rules
framed under this Act.
issue a notice to the owner or occupier of such building or premises stating
therein the inadequacy in regard to the fire prevention and fire safety
measures in it and direct the owner or occupier to undertake measures for
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 368
rectifying the said inadequacy within such period as he may consider just and
reasonable.‖
7.154 In exercise of the rule making power conferred under Section 16 of the said
1986 Act, the Delhi Fire Prevention and Fire Safety Rules were framed and brought into
force w.e.f. 31.3.1987. Rule 5 imperatively prescribed that minimum standards for fire
prevention and fire safety measures specified for building or premises shall be as are
provided in Building Bye-Laws notified in 1983. The said Rule reads as follows: -
"5. Minimum Standards - The minimum standards for fire prevention and
fire safety measures specified for building or premises shall be as are
provided in building bye laws notified in 1983 or as may be amended from
time to time thereafter, relating to the following matters: -
major fires in the city of Delhi in 1983, the Uphaar Cinema building's license was directed to
be suspended and 11 notified deviations were ordered to be rectified. The order of the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 369
licensing authority was challenged in the writ proceedings; this Court granted an interim
order. The interim order was later made absolute but upon condition that in the event the
authorities felt that building was not complying with the provision of law vis-à-vis fire safety,
they could seek vacation of the stay order. The materials on record show that in the
successive inspections which took place in 1988, 1994 and 1996, several deviations were
noticed, including those in the top floor. The applications for grant of annual licenses under
the Cinematograph Act were not granted; instead two month's temporary licenses were
issued - apparently because the matter was pending and had not been resolved by the Court.
In the meanwhile, with advent of the 1986 act and the rules framed under it, the standards of
fire safety, both as regards structural aspects as well as availability of appliances, were
prescribed under Rule 5 of the 1987 Rules. These assumed mandatory character and being
specific as regards the question of fire safety, acquired primacy over bye-law 3.7of 1983 bye-
laws. The said bye-law-3 had exempted application of certain bye-laws in its operation to
building authorized under the previous 1959 bye-laws. As a consequence of the combined
operation of the non obstante clause under Section 6 of the 1986 Act as well as Rule 5, the
fire safety measures prescribed in 1983 became universally applicable to all buildings. In
addition Rule 5 of the 1987 Rules also prescribed the standards which were to be complied
with by all buildings, towards fire safety. In a Division Bench judgment of this Court
reported as B.L. Vadhera v. Govt. of NCT of Delhi (105 (2003) DLT 1), it was held that all
buildings constructed after 6.6.1983 had to strictly conform to the bye laws framed in 1983.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 370
As far as buildings constructed prior to that date were concerned, the Court held that Chief
Fire Officer had a duty to inspect every such building and ensure that adequate fire safety
measures were taken. This Court is to, therefore, consider the duty cast upon the Chief Fire
Officer (hereinafter referred to as CFO) acting though his officers, and the matter in which it
was discharged.
7.156 It was urged on behalf of accused H.S. Panwar that all the equipment
prescribed by the norms, including fire extinguishers, were present, at the time of inspection.
Counsel pointed out that the utility or existence of such equipment, as well as other
appliances such as exit lights, gangway lights and emergency lights, had to be ensured, by the
licensee and owner at the time of operation of each show. That these appliances were missing
at the time, or that emergency lights or exit lights did not function, was something not within
the control of any official of the fire department, or the accused. He also relied on the
depositions of defence witnesses, DW-1 and DW-3, to say that an inspection was conducted
on 6th July, 1997, when the operability of the fire extinguishers were demonstrated.
7.157 It had been urged, additionally, on behalf of the other accused, such as Sushil
Ansal and Gopal Ansal, that the fire department was satisfied about the existence of fire
extinguishers, and all other equipment; the building was certified as compliant with the
norms. In the absence of any inspection at the relevant time, the observations about missing
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 371
exit lights, emergency lights not being operational, or inadequacy of fire extinguishers, etc
could not be sustained. The prosecution, they contend, was unable to establish any negligence
or illegal omission in this regard.
7.158 The prosecution had adduced evidence in the form of request letters by the
DCP (Licensing) to the Fire Department (i.e. the CFO) for the period 1982-83 to 1988-89 as
Ex.PW-37/H. Some of the inspection reports Ex.PW-37/J (dated 10.8.1988), Ex.PW-37/M
(dated 20.5.1989); PW-37/O (dated 25.4.1990) being a request for CFO to inspect the
premises; inspection report Ex.PW-37/P (dated 14.6.1990); Ex.PW-37/R (dated 28.4.1991)
being inspection report in regard to the renewal of the license for the period 1.4.1991 to
31.3.1992 have been relied upon. After inspection of the premises on 28.4.1991(Ex.PW-
37/R) the Divisional Officer in the Fire Department wrote on 29.4.1991 (Ex.PW-37/S),
outlining deficiencies in the fire equipment, noticed in the Uphaar Cinema. This included the
observations regarding two broken fire extinguisher nozzles; installation of improper fire
extinguishers in the main hall; a direction to refill the water tank fire extinguishers in the
main hall and balcony; provision for rubber mat etc. After these deficiencies were pointed, a
letter (Ex.PW-37/T) was written to the DCP (Licensing) on 6.6.1991 by the Fire Department
stating that the deficiencies had been rectified. This was preceded by a letter written on
behalf of the Uphaar Cinema.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 372
7.159 The DCP (Licensing) received an inspection report dated 26.3.1992,
concerning the period 1.4.1992 to 31.3.1993. This report, was in standard format, 15 rows
and 11 columns. The rows concerned the placement of equipment such as hose reels, water
bucket drum, blankets, exit lights, emergency lights, trained fireman, fire protection/safety
arrangement including placement of extinguishers etc. The columns interestingly dealt with
the various places in the cinema such as the hall, balcony box, pantry, projection room,
rectifier room, rewinding room, AC plant/blower, generator room, electrical sub-
station/distribution panel and covered parking. The inspection reports only mention about the
presence of certain fire safety equipment but did not indicate in any other detail the
deficiency or compliance with the standards. This is a common feature noticeable with all
the inspection reports right up to the last one issued before the fire.
7.160 Ex.PW-37/X is the NOC issued on 27.3.1992 by the office of the CFO
concerning the period 1992-93. The Ex.PW-37/Y is the letter of request by the DCP
(Licensing) to the office of the CFO asking it to inspect the premises. Ex.PW-37/Z is the
inspection report dated 29.4.93 recording compliance with the norms.Ex.PW-37/AB is a
letter issued by the DCP (Licensing) to the CFO requesting the latter to inspect the premises
and intimate the position of fire safety and if necessary to bring to the notice of the licensee
any comments in that regard.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 373
7.161 Pursuant to an inspection, adverted to in the previous part of the judgment, the
licensee of the cinema was intimated on 12.8.1994 of certain deficiencies. This referred to
the points mentioned in the first inspection which had taken place, of the building in 1983.
The cinema management wrote back on 12.10.1994 saying that deficiencies had been
rectified. Ex.PW-33/G is a letter dated 19.4.1994 written to the DCP (Licensing) recording
no objection pursuant to a report made on 14.4.1994. The report was exhibited as PW-33/H.
After the inspection, a letter (Ex.PW-33/A) dated 17.4.1995 was written to the G.P.T. Ltd i.e.
the Cinema. This recorded that six fire extinguishers of CO-2 type were installed in the top
floor.
7.162 An inspection of the cinema was conducted on 29-4-1995 by Divisional
Officer Shri PK Sharma and Station officer accused Surender Dutt (now expired) in the
presence of accused KL Malhotra (now expired) by inspection report Ex.PW37/AH. The
inspection report sent by the Chief Fire officer reads as under:
―.....During the course of inspection, fire fighting arrangements already
provided by the cinema management were seen. Some of the fire extinguishers
and hose reels were operated to adjudge the performance and the same was
found satisfactory at the time of inspection and must always be maintained in
similar efficient working condition at all time and at least two trained persons
must be available during exhibition of the films and then in the end , it is very
specifically mentioned that in view of the above, the department has no
objection to the renewal of license of the above mentioned cinema from fire
safety and means of escape point of view......‖ _
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 374
The fire department apparently treated the matter as a formality by sending the above report.
This fact is fortified when the report prepared by the Chief Fire officer's office, for the
previous years are seen. The report of the Chief Fire officer's office, for 1994-95, Ex.
PW37/AC had pointed out following shortcomings in the cinema hall building.
―1) An office has been erected forming part of the staircase on thetop floor.
2) Atleast three offices on the top floor having wooden partition were in
existence and there was no fire extinguisher present except one of non ISI
mark.‖
It is significant to note on 08.03.95 vide Ex. PW 37/AD Dy. Chief Fire Officer wrote to the
management of Uphaar cinema:
―.....during the inspection it has been seen that Point 1 has been rectified. As
already held herein before that the said office existed on the top floor forming
part of the staircase on the day of the occurence of the incident. It is also very
significant to note the reply was sent by the management of Uphaar Cinema to
the Chief Fire Officer on 31.03.95 vide Ex. PW 37/AF. The relevant portion of
the reply reads as under :
.....We have treated the wooden partition in the offices with fire retardant
paint to increase the fire rating of wood and these partitions are in existence
for the last 20 years as per normal practice to sub-divide larger offices by
wooden partition......‖
7.163 In the inspection proforma pertaining to year 1995-96, there is no mention
whether the shortcomings still existed. The said shortcomings were found to exist in the
cinema hall building after inspections were conducted after the occurrence of the incident.
Combustible material continued in the cinema hall building, despite previous warnings.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 375
7.164 An inspection by the Fire Department was carried out on 09.4.96 by Ex. PW
32/A by Divisional Officer HS Panwar Station officer Surender Dutt (now expired) in the
presence of KL Malhotra (now expired). After the inspection 'No Objection Certificate'
Ex.PW32/B dated 18.4.96 was issued by HS Panwar, for DFS. The relevant portion of the
said 'No Objection Certificate' reads as under :
―....During the course of inspection , fire fighting arrangements already
provided by the cinema management were seen. Some of the fire extinguishers
and hose reels were operated to adjudge the performance and the same was
found satisfactory at the time of inspection and must always be maintained in
similar efficient working condition at all time and atleast two trained persons
must be available during exhibition of the films and then in the end , it is very
specifically a mentioned that in view of the above, the department has no
objection to the renewal of license of the above mentioned cinema from fire
safety and means of escape point of view..... _
Thereafter a letter dated 20.09.06 Ex.PW37/AL was sent to CFO by DCP (Licensing)
requesting comments from the CFO. The letter says that the report had not been received,
and requests it, at the earliest,
― to enable this office to renew the license of cinema as licensee is pressing
hard for the same.....''
The tone is suggestive of the authorities anxiety to accommodate the licensee, rather than
being satisfied that all safety norms were complied with. The inspection was carried out in
the presence of K. L. Malhotra and accused Shri Sharma, of Uphaar cinema. The following
deficiencies were found and were intimated to the Manager, Uphaar Cinema on 18/11/96 by
letter Ex.PW33/C:
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 376
―1) The fire extinguisher required refilling i.e water, CO2, DCP and foam
type
2) The sprinkler system in the basement is not operating and
the gauge bell is not provided
3) The wooden planks are stored in the basement. It requires to be totally
removed from there.
4) First aid box shall be provided in the projector room which is not available.
5) Fire safety measures shall be provided in the visitor lounge on each floor,
director office and guest room and on the ground floor parking
6) Foot lights in the balcony shall be provided In view of the above 'No
Objection Certificate' shall only be considered after compliance of the
aforesaid shortcomings and re-inspection by the department... .‖
7.165 On 28.11.96, by letter Ex.PW33/F information was sent on the letter head of
the Ansal Properties & Industries Ltd. by Shri Vimal Nagpal of Uphaar Cinema informing
the Divisional officer, Delhi Fire service that the short comings pointed out were rectified and
a request was made to issue 'No Objection Certificate'. On 22.12.96 re-inspection was carried
out by accused H. S. Panwar and Station House Officer Surender Dutt and thereafter,
inspection report/No Objection Certificate Ex. PW 33/D was sent on 24.12.1996 to DCP
(Licensing ); it reads as follows:
―......During the course of inspection , fire fighting arrangements already
provided by the cinema management were seen. Some of the fire extinguishers
and hose reels were operated to adjudge the performance and the same was
found satisfactory at the time of inspection and must always be maintained in
similar efficient working condition at all time and atleast two trained persons
must be available during exhibition of the films and then in the end , it is very
specifically a mentioned that in view of the above, the department has no
objection to the renewal of license of the above mentioned cinema from fire
safety and means of escape point of view....‖
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 377
There is no report by the Chief Fire officer or the accused stating whether the shortcomings
pointed out in the letter 18.11.1996 were actually rectified or not. The 'No Objection
Certificate' was again issued by the accused on the standard form proforma, described
previously in the judgment.
7.166 After the expiry of the license(on 31.03.96), the DCP asked, through letter Ex.
PW37/AM, the CFO, on 21-4-1997 for inspection report /comments for renewal of annual
license for the period 1.4.97 to 31.3.1998. This inspection was carried out by accused HS
Panwar and Station Officer Surender Dutt (since expired) on 12.5.97 by Ex.PW31/DB. The
'No Objection Certificate' was sent on 15.5.97, through Ex.PW31/DC which reads as
follows:-
―During the course of inspection, fire fighting arrangements already provided
by the cinema management were seen. Some of the fire extinguishers and hose
reels were operated to adjudge the performance and the same was found
satisfactory at the time of inspection and must always be maintained in similar
efficient working condition at all time and at least two trained persons must be
available during exhibition of films and then, in the end, it is very specifically
mentioned that in view of the above, the department has no objection to the
renewal of license of the above mentioned cinema from fire safety and means
of escape point of view...‖
7.167 On PW-60, a tenant in the building, stated in his deposition that there were no
fire extinguishers in his premises. PW-78 deposed that after the accident, he seized 22 fire
extinguishers from various places in the cinema hall. PW-49, the CFO deposed that the
proforma for inspection from the fire safety angle had been changed; it incorporated
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 378
particulars such as fire extinguishers in specific areas, provision for rubber mats, public
announcement system, emergency exits, signage, standby power supply, first aid box,
asbestos blankets, hose reels, water tanks and trained personnel. This witness also deposed
that after the accident, he operated two or three fire extinguishers, which were functioning.
He stated that though there was a hose reel, water was not available, due to lack of electricity.
PW-48 deposed about the state of inspection, on 5-7-1997, and his report Ex. PW-48/D. In
the report, he observed that during inspection, no fire fighting material, viz. buckets or fire
extinguishers were found, placed inside the transformer room. According to DVB's practice,
such equipments were placed in HT switchgear room; however, in this case, they were
missing from the HT room. PW-64, who had tested the fire extinguishers, annexed a table in
his report PW-64/D, which was extracted in the previous part of this judgment.
7.168 PW-85 deposed to being untrained for operating fire extinguishers. He also
deposed that the mike for the public address system in the theatre was not operational.
According to him, emergency lights were not controlled from the operator room; they were
also not connected to the projector room. He admitted that two fire extinguishers were there
in the operator room, that were operated during inspection by the Naresh Kumar committee
inspection.
by the licensee, of the cinema hall. The inspection reports which preceded these exercises
were in proforma or standard form; the inspections carried out lackadaisically granted the
permission to renew licenses.
(2) The concerns required to be addressed in DCR 1953 and DCR 1981, regarding fire
safety as well as means of escape and exit, (or rapid dispersal) in the event of fire or other
emergency, were not even considered. In fact, on the contrary, Ex. PW 33/D on 24.12.1996 to
DCP (Licensing ) records that
―the department has no objection to the renewal of license of the above mentioned
cinema from fire safety and means of escape point of view....‖
(3) The last inspection report, dated 12-5-1997, does not show any application of mind to
the compliance with the gangway, exit rules or other vital aspects which the fire department
had to necessarily consider as part of its obligation, under Section 6 of the 1986 Act, read
with Rule 5;
(4) All the reports, preceding the fire incident of 13-6-1997, talk of existence of
equipments mandated by the rules. However, significantly, they omit any mention whether
these equipment were tested, and found in order. Similarly, it is not known whether the report
of 12-5-1997 was preceded by testing of the emergency, and other lights.
(5) The evidence of PW-85 that the emergency lights were not controlled from the
operator or projector room, assumes significance. According to the contention of accused
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 380
Gopal Ansal, the lack of electricity, due to tripping at 5-05 possibly meant that the lights went
off. Here, it is to be remembered that during such emergencies, the emergency lights have to
be automatically switched on; they should not depend on the general supply; or even on the
generator supply.
(6) The depositions of PWs 1, 3, 7, 10 and 11 establish that no public address system,
emergency lights or exit lights were operational at the time when smoke entered the cinema
balcony.
(7) None of the inspection reports even notices that two transformers, one of 1000 KVA
capacity, (installed by DVB) existed on the ground floor, near the parking area. There was no
advertence or assessment of fire hazard of that equipment, or in the transformers' proximity,
or its condition, in relation to the parked vehicles. No advisory in that regard was even
mentioned; perhaps not even thought of. These concerns were essential, and had to be
addressed by virtue of provisions of the DCR 1953 and DCR 1981.
(8) There was no fire extinguisher, of any type in the DVB transformer room;
(9) The report of the fire department dated 18-11-1996 PW-33/C had noted inadequacies
in the existing transformer. However, the subsequent report stated that the deficiencies were
rectified. This inspection was supposedly carried out- as the evidence points out- when the
accused H.S. Panwar was on leave. The subsequent report mechanically gave clearance, vis-
à-vis fire safety.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 381
7.170 In view of the above discussion, it is held that the clearance or approval and
the no-objection certificates issued by the fire department, were contrary to DCR 1953, and
contrary to vital fire safety norms. They were issued mechanically, in a routine manner. The
cinema hall was also ill equipped with appliances, and several fire extinguishers were not
operable, according to the report Ex. PW-64/D. These establish beyond a doubt that the
clearances by the fire department, preceded by inspections were unreliable; the cinema
management did not comply with safety norms, both in regard to fire emergencies, as well as
other emergencies, to facilitate rapid evacuation of patrons. The appliances and extinguishers
were neither sufficient nor adequate to quell the fire.
Position in the balcony
7.171 The trial court found that the balcony was unmanned at the time of the
accident; there was no gatekeeper or torch-man, the public announcement system did not
function, the emergency lights did not operate, and the balcony doors were shut. This, it was
held, resulted in delaying the patrons' exit, leading to fatalities and serious injuries, due to
smoke exposure.
7.172 PW-1 deposed about commotion in the balcony and other patrons saying that
balcony doors were closed. According to PW-3, in the balcony, at when the smoke entered,
no exit lights were on, there was no alarm and nobody from management was there. He
deposed that patrons were trying to push the main door but it was locked. He watched people
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 382
bringing their babies, children and other persons dead out of the cinema building. PW-7
deposed that at that time, (i.e when smoke entered the balcony) lights went off and it was
pitch dark. He, with his sister tried to come out of balcony but were unable to do so. Both felt
suffocated due to smoke and gases; it was difficult to breathe and they got stuck in the
balcony, for 10 to 15 minutes. He deposed that there was no gate keeper, no torch man, no
emergency announcement system, or any emergency light. PW 8 Amit, deposed that while
the show was on, the lights went off and some smoke arose before the screen. Noise was
heard from the auditorium and people started going out. There was lot of smoke. They tried
to come out. All doors were closed and he could not open them. They were able to break
open. There was lot of smoke and nobody was there to help. PW-11 stated about absence of
announcement systems, and lights. The public (patrons) near the balcony door pushed it open.
He was in the last row in the middle of the balcony; he mentions about commotion and that
balcony doors were shut. Half the people were standing and half were sitting, a situation
which continued for 5-7 minutes. He deposes about lot of pushing and people trying to go
out, without a care for others. He did not know the number of exits, but deposes about one
separate exit and one entry. He denied the suggestion that there was light, in the balcony.
PW-63, the security guard, after noticing the fire and smoke, rushed up; he went to the
staircase which led on to the fourth floor and where a door was located. He pushed that door
open. He asked the people to go upstairs, but at the end the staircase was locked. He broke
open the door and tried to use another staircase leading to top floor which was at some
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 383
distance from there. The door was found bolted; he tried to open it. A lot of smoke and gas
was there. He immediately closed the door. He entered inside the office on the fourth floor,
when members of the public followed him. PW-49, the Chief Fire Officer, reached the
cinema hall at 5-45 PM and found that some people were trapped in the balcony area. There
was smoke and a lot of heat; he could not open the balcony foyer door, which was forced
open by his officers. He helped rescuing 3 persons, who were not responsive or moving, as
well as a girl.
7.173 The prosecution had relied on a letter (part of Ex. PW-69/AA) dated 28-5-
1982, issuing a show cause notice under Rule 12(8) DCR 1981, to the cinema management,
stating that when an inspection was carried out, it was discovered that the doors had been
bolted. In its reply, (written by accused Gopal Ansal) on 4-6-1982 (Ex. PW-110/AA-24) the
licensing department was assured that such practice could have been due to constant opening
of the doors or due to pressure of air conditioning. It was stated that:
― We assure you that utmost precaution would be taken in future...‖
7.174 The discussion of oral evidence, seen in the background of the deviations
noticed earlier in the balcony, would show that the patrons were exposed to smoke for a long
time; many patrons, and certainly the eyewitnesses who spoke in that regard, were unable to
leave the place swiftly. The Chief Fire Officer (PW-49) who went to the balcony at around 5-
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 384
45, had to ensure that the foyer door was forced open; he witnessed at least 3 people being
taken out of, or rescued from, the balcony. Several eyewitnesses have corroborated each other
in saying that the doors were bolted. It has come on the evidence that the right side exit, from
the balcony was completely blocked by the eight seater box, placed in 1978. It has also been
found earlier that several changes in the balcony seating, resulted in narrowing of a gangway
and blockage of one gangway on the right side. These, coupled with absence of any lighting,
and absence of help by employees at the vital time, both exposed these patrons to the thick
dense smoke for a long period, and also hindered free movement. Many patrons, who
managed to exit from the balcony, were still trapped; they tried to flee the hall, and broke
open some windows This exposure to smoke, and lack of easy access outside, resulted in
death of several persons and serious injury to many others.
VIII. The Law on criminal negligence section 304-a, ipc - rashness, negligence,
foresight and causation; consideration of Section 36, IPC
All our work, our whole life is a matter of semantics, because words are the
tools with which we work, the material out of which laws are made, out of
which the Constitution was written. Everything depends on our understanding
of them.
- Felix Frankfurter
8.1 Before a discussion of the case law, cited by counsel for parties, it would be necessary
to notice the relevant provisions, of the Indian Penal Code (IPC). They are extracted below:
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 385
―Section 32. Words referring to acts include illegal omissions
In every part of this Code, except where a contrary intention appears from the
context, words which refer to acts done extend also to illegal omissions.
Section 33. Act Omission
The word "act" denotes as well a series of acts as a single act: the word
"omission" denotes as well as series of omissions as a single omission.
Section 36. Effect caused partly by act and partly by omission
Wherever the causing of a certain effect, or an attempt to cause that effect, by
an act or by an omission, is an offence, it is to be understood that the causing
of that effect partly by an act and partly by an omission is the same offence.
Section 43. Illegal, Legally bound to do
The word "illegal" is applicable to everything which is an offence or which is
prohibited by law, or which furnishes ground for a civil action; and a person
is said to be "legally bound to do" whatever it is illegal in him to omit.
Section 299. Culpable homicide
Who ever causes death by doing an act with the intention of causing death, or
with the intention of causing such bodily injury as is likely to cause death, or
with the knowledge that he is likely by such act to cause death, commits the
offence of culpable homicide.
Section 304. Punishment for culpable homicide not amounting to murder
Whoever commits culpable homicide not amounting to murder shall be
punished with imprisonment for life, or imprisonment of either description for
a term which may extend to ten years, and shall also be liable to fine, if the act
by which the death is caused is done with the intention of causing death, or of
causing such bodily injury as is likely to cause death,
Or with imprisonment of either description for a term which may extend to ten
years, or with fine, or with both, if the act is done with the knowledge that it is
likely to cause death, but without any intention to cause death, or to cause
such bodily injury as is likely to cause death.
304A. Causing death by negligence.
Whoever causes the death of any person by doing any rash or negligent act
not amounting to culpable homicide, shall be punished with imprisonment of
either description for a term which may extend to two years, or with fine, or
with both.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 386
Section 336. Act endangering life or personal safety of others
Whoever does any act so rashly or negligently as to endanger human life or
the personal safety of others, shall be punished with imprisonment of either
description for term which may extend to three months, or with fine which may
extend to two hundred and fifty rupees, or with both.
Section 337. Causing hurt by act endangering life or personal safety of
others
Whoever causes hurt to any person by doing any act so rashly or negligently
as to endanger human life, or the personal safety of others, shall be punished
with imprisonment of either description for term which may extend to six
months, or with fine which may extend to five hundred rupees, or with both.
Section 338. Causing grievous hurt by act endangering life or personal
safety of others
Whoever causes grievous hurt to any person to doing any act so rashly or
negligently as to endanger human life, or the personal safety of others, shall
be punished with imprisonment of either description for a term which may
extend to two years, or with fine which may extend to one thousand rupees, or
with both.‖
8.2 The distinction between the three offences of murder and culpable homicide on the
one hand and causing death by criminal negligence may be summarized now. Murder and
culpable homicide involve the mens rea element or state of mind of the offender. These
offences are separated from each other not by the consequences, but the intention of the
offender to the particular result. The other class of culpable homicide is where the accused
causes an injury without intention of causing death, but with knowledge that death would be
likely. In the case of criminal negligence what has to be proved is the act, amounting to
breach of duty of care, which causes death. There, the perpetrator does not have knowledge
or intention of the result, but acts rashly, or negligently with disregard to the consequences of
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 387
his action. In such intentionless or ―knowledge-less‖ offences, the rash or negligence
standards are the same; it is only the consequence that determines the offences. So, if the
rash and negligent act results in death, the accused is guilty of Section 304-A; if the
consequence is grievous hurt, the offence proved is Section 338 IPC.
8.3 The all-important question upon which both the appellants and the prosecution led
considerable arguments were the precise import of what constitutes criminal negligence. On
behalf of the appellants various decisions, such as Emperor v. Omkar Rampratap, (1902) 4
Bom LR 679, Kurban Hussein Mohamedalli Rangawalla v. State Of Maharashtra., AIR 1965
SC 1616, Ambalal Bhat v. State of Gujarat, (1972) 3 SCC 525 and Jacob Mathew, Petitioner
V. State Of Punjab & Anr 2005 (6) SCC 1 were cited. It was principally urged that to
constitute criminal negligence, it should be proved beyond reasonable doubt that (1) the
accused owed duty of care to the victim (2) such duty was breached (3) the breach or the
consequence of such breach was reasonably foreseeable and (4) the cause of the accident
which led to the death or bodily injury and in the case of section 336/337 of ipc was the
most efficient and proximate cause and not a remote one. The appellants, particularly
accused 1 and 2 relied upon several English decisions to bring home the question of what
constitutes the reasonable foresight. These were John Oni Akerele Vs. The King, AIR 1943
PC 72; Overseas Tankship UK Ltd v. Morts Dock Engineering Co. Ltd. (―the Wagon Mound
No. 1‖) [1961] 1 All ER 404, Corporation of Glasgow v. Muir, [1943] 2 All ER 44, Bolton v.
Stone [1951] 1 All ER 1078, Lord v. Pacific Steam Navigation Co. (The Oropesa) [1943] 1
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 388
All ER 211, Doughty v. Turner Manufacturing Co., [1964] 1 All ER 98, Rajkot Municipal
Corporation v. Manjul Ben Jayanti Lal Nakum, (1997) 9 SCC 552.
8.4 It was argued that awareness of the consequence of the breach of duty should be of a
very high order to constitute the offence. All the appellants had emphasized that mere
negligence resulting in a consequence, howsoever harsh and also resulting in several deaths
alone should not impel the Court to conclude the nature of the risk and its forseeability was of
such order that the offender must reasonably be expected to have been aware of it. The
cause, and not the dimensions of the consequences, (which would cloud the issue) should
determine the guilt or innocence. Anything short of such requirement, it was submitted,
would be applying a civil or tortious norms for convicting those accused for the offence
criminal negligence which would be impermissible. It was also submitted that the Court
cannot fall back upon doctrine such as res ipsa locquitor, a rule of evidence rooted in civil
law in case of tortious liability. For this purpose reliance was placed on Syad Akbar Vs. State
of Karnataka, (1980) 1 SCC 30. It was also argued that the intervening actions of others,
which could not reasonably foreseen by the accused and which were the cause of accident
lead to death, (termed as novas actus intervieneus i.e. a new act intervening, breaking the
chain of causation set in to motion by the accused) absolving such accused. In support of this
reliance was placed upon the decision reported as Mutual Life and Citizens Assurance
Company Ltd. Vs. Evatee [1971] 1 All ER 150 and Lamb v. London Borough of Camden
[1981] 2 All ER 408.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 389
8.5 The CBI on the other hand had relied upon the decision reported as Bhalchandra
Waman Pathe v. State of Maharashtra, [1968] ACJ 622, Bhalchandra alias Bapu and Anr v.
State of Maharashtra, AIR 1968 SC 1319, Rustom Sheriar Irani v. State Of Maharashtra.,
[1969] ACJ 70; Cherubin Gregory Vs. State of Bihar, 1964 (4) SCR 199, and Suresh Gupta
Vs. NCT of Delhi, AIR 2004 SC 4091.
8.6 It was urged that Rustam Irani's case underlines that the forseeability standard need
not necessarily mean that the accused should be present when the accident occurs leading to
death or grievous injury, nor that the cause must be one, and establishes that it is sufficient
that the court is convinced about his role in the cause which led to accident and consequent
death. Reliance was similarly placed on Woodward v. Crown AIR 1925 Sind 233, State of
M.P. Vs. Ranjit Kumar, AIR 1959 MP 284; Tulsi Sita Ram Vs. State, 1963 (1) Criminal Law
Journal 44, Ganesh Gir Vs. State of M.P., AIR 1966 MP 311. To indicate what should be
the standard for judging criminal negligence, CBI relied on R. v. Bateman (1925) 19 Cri App
Rep 8, R. v. Lawrence, [1981] 1 All ER 974; Andrews v. Director of Public Prosecutions
(1937) 2 All ER 552, and R v Adomako, [1994] 3 All ER 79.
8.7 The locus classicus on section 304-A is Emperor v. Omkar Rampratap, (1902) 4 Bom
LR 679, where, certain women were working in a half roofed building, temporarily hired by
and in the possession of the appellant. The premises were used for grinding sulphur for
manufacturing gun-powder. The premises caught fire, as a result of which three women died
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 390
and others were injured. The prosecution argued that the fire was caused by the rash and
negligent acts of the appellants, since they stored gun powder in gunny bags in a temporary
shelter. Rejecting the prosecution's case the court acquitted the appellant and held as follows:
―To impose criminal liability under Section 304-A, Indian Penal Code, it is
necessary that the death should have been the direct result of a rash and
negligent act of the accused, and that act must be proximate and efficient
cause without the intervention of another's negligence. It must be the causa
causans; it is not enough that it may have been the cause sine qua non‖
Thus the court held that the act in question must be the direct, proximate and efficient cause
for the death, without the intervention of another's negligence. This postulate was followed in
a number of later decisions.
8.8 In John Oni Akerele (supra), the doctor was charged and convicted with criminal
negligence. He had mixed a strong dose of sobita and injected it. This over dose resulted in
death of several young children. The Court, reversing the concurrent conviction of the
appellant held that the negligence, to be culpable depends upon the probable and not the
actual result. In the facts of the case the Doctor could not be held responsible as the probable
result of such over dose was not known to him. The Court commented that it is impossible to
define culpable or criminal negligence or make it intelligible except by means of illustrations,
drawn from judicial opinions. Concluding that the distinction between civil and criminal
liability had been inexactly drawn- in that case, and instances of negligence, were found
having regard to the many deaths, the Court concluded that conviction was fallacious.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 391
8.9 In Kurban Hussein Mohamedalli Rangawalla v. State Of Maharashtra., AIR 1965 SC
1616, the accused was the owner of a factory engaged in manufacturing paints and varnish.
Though he was only authorized to manufacture dry paints by a cold process, he had started
manufacturing wet paints through heating. Burners were used in the process, for melting resin
and then adding turpentine to it. On April 20, 1962, the melted resin overflowed from the
barrel in which it was being heated and set alight the turpentine stored nearby. As a
consequence of this fire, 7 men working in a loft nearby were charred to death. The reason
for the overflow was that a worker, in charge of the operation, had added turpentine to the
melting rosin but was unable to stir the mixture, as a result of which it kept frothing and
overflowed. The accused was charged under Sections 304-A and 285 of the Indian Penal
Code for having caused death through a rash or negligent act. His main contention was that
he was not present at the time the fire broke out and therefore it could not be said that he had
caused the death of the seven persons through any rash or negligent act. The Magistrate, as
well as the High Court, who had convicted the accused, held that the very fact of storing
turpentine in the same room as the burners would amount to a rash or negligent act and make
the accused responsible for the deaths. Applying the test laid out in Omkar (supra) the
Supreme Court held:
―[T]he mere fact that the appellant allowed the burners to be used in the same
room in which varnish and turpentine were stored, even though it might be a
negligent act, would not be enough to make the appellant responsible for the
fire which broke out. The cause of the fire was not merely the presence of
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 392
burners in the room in which varnish and turpentine were stored, though this
circumstance was indirectly responsible for the fire which broke out. But what
S. 304-A requires is causing of death by doing any rash or negligent act, and
this means that death must be the direct or proximate results of the rash or
negligent act. It appears that the direct or proximate cause of the fire which
resulted in the seven deaths was the act of Hatim‖
8.10 The case of Bhalchandra Waman Pathe v. State of Maharashtra, [1968] ACJ 622
involved the case of the appellant running over a pedestrian, at a crossing, while he was
speeding at 40 miles per hour, when the permitted speed was only 35 miles per hour. The
Magistrate found him guilty under section 304-A, and imposed a fine of Rs. 2000. The High
Court not only confirmed the conviction but also enhanced the sentence to six months simple
imprisonment and a fine of Rs. 200, against which he appealed to the Supreme Court.
Disagreeing with the enhancement, and differentiating the terms ‗rash' and ‗negligent', the
Supreme Court held that:
"An offence under Section 304-A Indian Penal Code may be committed either
by doing a rash act or a negligent act. There is a distinction between a rash
act and a negligent act. In the case of a rash act as observed by Straight, J. in
Idu Beg's case. (ILR 3 All 776) the criminality lies in running the risk of doing
such an act with recklessness or indifference as to the consequences. Criminal
negligence is the gross and culpable neglect or failure to exercise that
reasonable and proper care and precaution to guard against injury either to
the public generally or to an individual in particular, which having regard to
all the circumstances out of which the charge has arisen, it was the imperative
duty of the accused person to have adopted. Negligence is an omission to do
something which a reasonable man guided upon those considerations which
ordinarily regulate the conduct of human affairs would do, or doing something
which a prudent and reasonable man would not do. Again as explained in
Nidamarti Nagabhushanam's case. (1872) 7 Mad H.C.R. 119 a culpable
rashness is acting with the consciousness that the mischievous and illegal
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 393
consequences may follow but with the hope that they will not, and often with
the belief that the actor has taken sufficient precautions to prevent their
happening. The imputability arises from acting despite the consciousness.
Culpable negligence is acting without the consciousness that the illegal and
mischievous effect will follow, but in circumstances which show that the actor
has not exercised the caution incumbent upon him and if he had he would have
had the consciousness. The imputability arises from the neglect of the civic
duty of circumspection."
The Court further held that as between rashness and negligence, rashness is undoubtedly a
graver offence. It held that appellant could not have been said to be rash or reckless, but
definitely negligent because he had the duty to look ahead and see whether there was any
pedestrian in the pedestrian crossing. Therefore, the enhancement was unjustified.
8.11 In Rustom Sheriar Irani v. State Of Maharashtra., [1969] ACJ 70, the court held that if
a person who is not an engineer chooses to decide for himself the width of the pipe of the
chimney of a bakery, and entrusts the work of alteration of the chimney to a mason who had
not designed chimneys before, and does not completely stop the functioning of the ovens
during the construction of the chimney, he should be held guilty of negligent acts under
section 304-A, irrespective of the fact that the chimney collapsed on account of the
negligence of the mason. It held:
―But on the facts of this case it seems to us that the proximate and efficient
cause of the deaths was the negligence of the appellant in choosing a pipe of
six inches diameter and asking PW 8 to carry out the alterations, and also
continuing working at least one oven during the period while alterations to the
chimney were being made. Even if Gunaji Lad was negligent in actually fixing
the pipe on the brick masonry, the proximate and efficient cause of the
accident was the acts of the appellant mentioned above.'
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 394
8.12 In Bhalchandra alias Bapu and Anr v. State of Maharashtra, AIR 1968 SC 1319, the
appellants were the owners of a factory which manufactured crackers. An explosion in the
factory led to death of some working in it. It was discovered that the appellants had stored
chemicals and explosives for which they had no authorization, and had also committed a
number of breaches of the conditions contained in the licenses issued to them. The appellants
taking cue from Omkar (supra) argued that their act of storing such explosive material,
despite them being in contravention of law, was not the direct cause of the explosion. The
Court held that, even though the exact cause of the explosion could not be determined, the
appellants had undoubtedly displayed a high degree of negligence by allowing or causing to
be used dangerous and prohibited substances which must be held to have been the efficient
cause of the explosion.
8.13 The case of S N Hussain v. State of AP, (1972) 3 SCC 18 involved a bus driver who
was convicted under section 304-A for causing the death of people while he drove through a
railway crossing gate and a goods train hit the bus. Acquitting the driver, the Court held that
the he was not negligent under section 304-A since he could not have reasonable foreseen
that a manned gate would be left open when the train came, especially when no whistles were
blown and the bus was being driven slowly. The Supreme Court in Ambalal Bhat v. State of
Gujarat, (1972) 3 SCC 525 had to determine whether a chemist, who negligently used a
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 395
unknown source of sodium chloride of different potencies and assigned the same batch
number for all four lots of injections manufactured on that day, was responsible under section
304-A for the death of 12 people who were injected. The Court found that the accused was
merely carrying on the routine practice, and that such practice was not even objected to by
the Drug Analyst or any other authority. It held that in order to be liable under section 304-A,
the act causing the deaths must be the causa causans; it is not enough that it may have been
the sine qua non. It will have to be determined that there is not causa interveniens which has
broken the chain of causation and that the act accused of is the direct and immediate cause.
The Court also observed that the fact that twelve lives were lost, however shocking and
regrettable it may be, ought not to allow the mind boggle while appreciating the evidence.
8.14 Tusliram Sitaram v. State (supra) was a case where a ferry contractor, who had not
taken out a license to ferry passengers across the river, after expiry of the previous license,
took the risk of putting the boat to water and ferrying the passengers and transporting them,
as floods were receding, and there was a heavy wave which dashed against the boat and
capsized it resulting in the loss of lives; the court concluded that he was guilty of criminal
negligence. Woodward v. Crown (supra) was a case where the accused, a boiler inspector,
was under a duty to periodically inspect certain boilers to see that they were in fit condition.
These boilers were in use in locomotives; some pressure plates failed and the boiler exploded.
It was held that the failure of the accused's duty to carry out his duty of inspecting the
boilers, resulted in the boiler explosion and caused loss of life and injury to some persons, he
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 396
was held guilty. In Cherubin Gregory (supra), the placement of naked electrical wire, without
warning, resulting in death of persons who came into contact with it, were held to be acts of
rashness and criminal negligence.
8.15 Syad Akbar (supra) involved the driver of vehicle, charged with criminal negligence
for rash driving. It had been found that a young child was run over by him even though he
was driving below the speed limit prescribed. The child, accompanied by her mother was
crossing the road; when the mother had crossed over, the child suddenly dashed across the
road and was caught under the left wheel of the accused bus, which crushed her to death. The
Supreme Court held that ordinarily, proof that an event occurred resulting in an accident the
cause of which was unknown, is not evidence of negligence. However, the peculiar
circumstance constituting the event in a particular case may proclaim in clear and
unambiguous terms, the negligence of someone as it has caused/happened. After exploring
the nature of presumptions which courts can try in the course of criminal trial i.e. permissive
presumption or presumptions of fact (Section 114); compelling presumptions or
presumptions of law (Sections 113, 113-A & 113-B) and irrebuttable presumptions of law or
conclusive proof (Section 112), the Court held that in an action in tort it is possible for the
Court to rely upon and apply the maxim res ipsa locquitor, but since it gives a larger effect
than that of a merely permissive inference, it cannot be applied universally in criminal cases.
The court posited a high degree of proof, i.e. beyond reasonable doubt. After considering the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 397
evidence, the Court upset the conviction and set aside the sentence imposed upon the
appellant. It was held that the maxim was useful only to a limited extent:
―However, shorn of its doctrinaire features, understood in the broad, general
sense, as by the other line of decisions, only as a convenient ratiocinative aid
in assessment of evidence, in drawing permissive inferences under S. 114,
Evidence Act, from the circumstances of the particular case, including the
constituent circumstances of the accident, established in evidence, with a view
to come to a conclusion at the time of judgment, whether or not, in favour of
the alleged negligence (among other ingredients of the offence with which the
accused stands charged), such a high degree of probability, as distinguished
from a mere possibility has been established which will convince reasonable
men with regard to the existence of that fact beyond reasonable doubt.‖
8.16 Jacob Mathew's case (supra), reviewed several judgments of Indian and English
decisions on criminal negligence. It was rendered by a Bench of three Judges of the Supreme
Court, upon a reference as to the applicable standard in cases of medical negligence. In that
context, the Court approved the formulation in Andrews Vs. Director of Public Prosecution,
[1937] 2 All ER 552 that a simple lack of care which constitutes negligence in civil law is
insufficient to prove criminal negligence. A very high degree of negligence has to be proved
before culpability is established. This view was echoed in Riddle Vs. Reid, [1942] 2 All ER
161. The Court held that :
―while negligence is a omission to do some which a reasonable man, guided
upon those considerations which ordinarily regulate the conduct of human
affairs would do, or doing something which a prudent and reasonable man
would not do; criminal negligence is the gross and culpable neglect or
criminal failure to exercise that reasonable and proper care and precaution to
guard against injury either to the public generally or an individual in
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 398
particular which having regard to circumstances out of which the charge has
arisen. It was the imperative duty of the accused person to have adopted‖.
The Court in its summing up emphasized that in all cases of negligence there are three
essential components, i.e., duty, breach and resulting damage. What delineates civil
negligence from criminal negligence is the degree of breach of duty, which results in the
consequence.
8.17 The prosecution had placed reliance on English decisions that the threshold proving
criminal negligence is not an impossibly high one. In this context, the decisions reported as
R. v. Bateman, (1925) 19 Cri App Rep 8, R. v. Lawrence, [1981] 1 All ER 974 and Andrews
v. Director of Public Prosecutions [1937] 2 All ER 552, and R v Adomako, [1994] 3 All ER
79 were relied on. In Bateman, the court, while considering the issue, stated that:
―whatever epithet be used and whether an epithet be used or not, in order to
establish criminal liability the facts must be such that, in the opinion of the
jury, the negligence of the accused went beyond a mere matter of
compensation between subjects and showed such disregard for the life and
safety of others as to amount to a crime against the State and conduct
deserving punishment. ........... It is desirable that as far as possible, the
explanation of criminal negligence to a jury should not be a mere question of
epithets. It is, in a sense, a question of degree and it is for the jury to draw the
line, but there is a difference in kind between the negligence which gives a
right to compensation and the negligence which is a crime."
8.18 In the next decision, Andrews v. Director of Public Prosecutions [1937] 2 All ER 552,
the court reiterated that for liability under criminal law, (for negligence):
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 399
"simple lack of care such as will constitute civil liability is not enough...a very
high degree of negligence is required to be proved. Probably, of all the
epithets that can be applied 'reckless' most nearly covers the case."
In R. v. Lawrence, [1981] 1 All ER 974, speaking of ―recklessness‖ in the context of criminal
negligence, the court observed that:
"Recklessness on the part of the doer of an act does presuppose that there is
something in the circumstances that would have drawn the attention of an
ordinary prudent individual to the possibility that his act was capable of
causing the kind of serious harmful consequences that the section which
creates the offence was intended to prevent, and that the risk of those harmful
consequences occurring was not so slight that an ordinary prudent individual
would feel justified in treating them as negligible. It is only when this is so that
the doer of the act is acting 'recklessly' if, before doing the act, he either fails
to give any thought to the possibility of there being any such risk or, having
recognized that there was such risk, he nevertheless goes on to do it."
8.19 In Adomako, the House of Lords sought to resolve a discontinuity in the reasoning,
which was a result R v. Caldwell [1981] 1 All ER 961, as to what would constitute criminal
negligence. The Court held that:
―the ordinary principles of the law of negligence apply to ascertain whether or
not the defendant has been in breach of a duty of care towards the victim who
has died. If such breach of duty is established the next question is whether that
breach of duty caused the death of the victim. If so, the jury must go on to
consider whether that breach of duty should be characterized as gross
negligence and therefore as a crime. This will depend on the seriousness of the
breach of duty committed by the defendant in all the circumstances in which
the defendant was placed when it occurred. The jury will have to consider
whether the extent to which the defendant's conduct departed from the proper
standard of care incumbent upon him, involving as it must have done a risk of
death to the patient, was such that it should be judged criminal.
It is true that to a certain extent this involves an element of circularity,
but in this branch of the law I do not believe that is fatal to its being correct as
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 400
a test of how far conduct must depart from accepted standards to be
characterized as criminal. This is necessarily a question of degree and an
attempt to specify that degree more closely is I think likely to achieve only a
spurious precision. The essence of the matter which is supremely a jury
question is whether having regard to the risk of death involved, the conduct of
the defendant was so bad in all the circumstances as to amount in their
judgment to a criminal act or omission.
My Lords, the view which I have stated of the correct basis in law for
the crime of involuntary manslaughter accords I consider with the criteria
stated by counsel although I have not reached the degree of precision in
definition which he required, but in my opinion it has been reached so far as
practicable and with a result which leaves the matter properly stated for a
jury's determination.‖
8.20 It would be useful to sum up this part, with the following quotation from Naresh
Giri v. State Of M. P, where many of the above English decisions were cited and applied:
―Negligence and rashness to be punishable in terms of Section 304-A must be
attributable to a state of mind wherein the criminality arises because of no
error in judgment but of a deliberation in the mind risking the crime as well as
the life of the person who may lose his life as a result of the crime. Section
304-A discloses that criminality may be that apart from any mens rea, there
may be no motive or intention still a person may venture or practice such
rashness or negligence which may cause the death of other. The death so
caused is not the determining factor.‖
8.21 From the above decisions, certain broad propositions may usefully be outlined, for
application in this case. Thus in determining whether an act constitutes criminal negligence,
the Court has to be satisfied of:
(1) a duty of care, owed by the accused, and its consequent breach;
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 401
(2) Forseeability of the likely consequence of such breach;
(3) the nature and degree of risk of causing death or bodily harm;
(4) The co-relationship between the degree of risk and the culpability of the accused is
directly proportionate. In other words higher the degree of risk, the greater
blameworthiness of the acts for the consequence.
(5) the consequence i.e. death, bodily harm or simple hurt, determines the criminality of
the action. In case the consequence being death the accused would be guilty under
Section 304-A IPC. In other cases he would be guilty under Section 337/338 IPC.
8.22 Summation of the legal position, especially in such cases would be an obviously
limiting exercise. ‗negligence', ‗rashness' and ‗forseeability' are all well developed concepts.
Yet, as John Oni Okerele (supra) stated 65 years ago, it is impossible to define criminal
negligence and distinguish it from actionable (Civil) negligence except by means of
illustrations drawn from actual judicial opinions. Use of words like ―gross‖, ―reckless‖,
―grave‖ borrowed from English decisions, rendered in the era of common law offences,
would confuse the issue. One cannot be unmindful of the fact that Section 304-A uses the
terms ―rash‖ or ―negligent‖ act, each expression coloring the meaning of the other. As stated
in Roscoe's Law of Evidence (15th Edn), - quoted in Jacob Mathew (supra):
―.....In explaining to juries the test which they should apply to
determine whether the negligence in the particular case amounted or did not
amount to a crime, Judges have used many epithets, such as ―culpable‖,
―criminal‖, ―gross‖, ―wicked‖, ―clear‖, ―complete‖. But whatever epithet be
used and whether an epithet be used or not, in order to establish criminal
liability the facts must be such that, in the opinion of the jury, the negligence
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 402
of the accused went beyond a mere matter of compensation between subjects
and showed such disregard for the life and safety of others as to amount to a
crime against the State and conduct deserving punishment.‖
The Court, therefore, has to consider whether the extent to which the accused'S conduct:
―departed from the standard of care incumbent upon him, involving as it must
have done, a risk of death, to the patient (read victim) was such that it should
be judged criminal.‖
It is true that to a certain extent this involves an element of circularity, but in
this branch of law I do not believe that is fatal to its being correct as a test of
how far conduct must depart from accepted standards to be characterized as
criminal. This is necessarily a question of degree and an attempt to specify
that degree more closely is I think likely to achieve spurious precision. The
essence of the matter -----is whether, having regard to the risk of death
involved, the conduct of the defendant was so bad in all the circumstances as
to amount in their judgment to a criminal act or omission,‖ (Adomako, supra)
Forseeability
8.23 It would now be necessary to discuss what constitutes forseeability in the context of
criminal negligence. It is a principle of civil liability that the liability for the damage caused
by a wrongful act will be determined by the remoteness of the damage from the act in
question. If the damage is too remote, then liability shall not be affixed. The test for
determining whether the damage is too remote has been a subject of debate. For long, the
classic case was Re Polemis [1921] All ER 40. The claimants' ship was being unloaded in
Casablanca when a quantity of benzene leaked into the hold. As a result of the negligence of
certain stevedores who were carrying planks, one of the planks fell into the hold causing a
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 403
spark which ignited the benzene. The resultant fire destroyed the ship. The Court of Appeal
held the owners liable for the destruction of the ship. The test applied by them was the test of
directness which pins responsibility for all direct consequences of the negligent act. The
destruction in this case was held to be a direct consequence of the stevedores' negligence.
8.24 However, this test was severely criticized and was overturned in Overseas Tankship
UK Ltd v. Morts Dock Engineering Co. Ltd. (―the Wagon Mound No. 1‖) [1961] 1 All ER
404. The claim in this arose after the defendants negligently discharged bunkering oil from a
ship onto water about two hundred yards away from the claimants' wharf. The oil was carried
by the tide onto the claimants' wharf and damaged the slipways. Welding operations carried
out by the claimants caused the oil to ignite and the wharf was damaged. The Privy Council,
rejecting the Polemis ―direct consequence‖ test, devised the test of ―reasonable foresight‖ and
held that although the damage caused to the slipways was reasonably foreseeable, the damage
caused by the fire was not. In the words of Viscount Simonds,
―Enough has been said to show that the authority of the Polemis has been
severely shaken though lip service has from time to time been paid to it. In
their Lordships' opinion it should no longer be regarded as good law. It is not
probably that many cases will for that reason have a different result, though it
is hoped that the law will be thereby simplified and that in some cases, at
least, palpable injustice will be avoided. For it does not seem consonant with
current ideas of justice or morality that for an act of negligence, however
slight or venial, which result in some trivial foreseeable damage the actor
should be liable for all consequences however unforeseeable and however
grave, so long as they can be said to be ‗direct'. It is a principle of civil
liability, subject only to qualifications which have no present relevance, that a
man must be considered to be responsible for the probable consequences of
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 404
his act. To demand more of him is too harsh a rule, to demand less is to ignore
that civilised order requires the observance of a minimum standard of
behaviour‖
8.25 In Phillips Vs. William Whitley [1938] All ER 566, was an action for damages by the
plaintiff who arranged to have her ear pierced by someone contracted by a jeweler to do it in
their premises. The operation resulted in plaintiff having to undergo medical treatment for
pain in the neck and abscess. The Court, rejecting civil action for damages against the
jeweler held that in such a situation a jeweller who holds himself out as a surgeon or
professes his ability to conduct the operation by piercing lady's ear by a septic operation
about which he knows nothing, cannot be held responsible. In Grant Vs. Sun Shipping
Company Limited, 1948 AC 549, a ship owner was sued by stevedore who was injured, while
he fell into a uncovered hatch which had been left open without any indication and without
lighting. The repairers, who were responsible for the uncovered hatch, argued that ship
owners owed a duty to inspect the vessel and that the act happened within the bounds of their
foresight. The Court while dismissing the repairers appeal held as follows :
―My Lords, I regard it as a well settled principle and when separate
and independent acts of negligence on the apart of two or more persons have
directly contributed to cause injury and damage to another, the person inured
may recover damages from any one of the wrong doers or from all of them.‖
It was also held that :
―I have no doubt (leaving aside for the moment the question whether
fault can be attributed to the pursuer) that the negligence and breach of
statutory duty attributable to each of the defenders ―partly‖ and ―directly‖
caused the pursuer's injuries. Whether or not a cause is a ―direct‖ cause is
sometimes a difficult question, but here the precautions which the regulations
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 405
prescribed and ordinary prudence should have dictated have for their object
the prevention of accidents of the very nature of that which befell the pursuer.
8.26 In Doughty v. Turner Manufacturing Co., [1964] 1 All ER 98 the defendants had two
cauldrons in their factory's treatment room, in which they subjected metal parts to heat by
immersing them in a hot molten solution. They provided suitable covers for the cauldrons in
order to conserve the heat. One of these covers was accidentally knocked into the cauldron, so
as to cause the hot liquid to erupt violently, resulting in burns to the claimant. The Court of
Appeal applied the test of reasonable foresight and held that it was reasonably foreseeable that
the claimant might have suffered burns as a result of splashing of the liquid from the cauldron.
However, it was not reasonably foreseeable that slipping of the cover into the cauldron would
cause the liquid to explode. Thus the harm caused to the claimant was too remote. According
to Lord Diplock:
―There is no room today for mystique in the law of negligence. It is the
application of common morality and common sense to the activities of the
common man. He must take reasonable care to avoid acts or omissions which
he can reasonably foresee would be likely to injure his neighbours; but he
need not do more than this. If the act which he does is not one which he could,
if he thought about it, reasonably foresee would injure his neighbour it
matters not whether he does it intentionally or inadvertently‖
8.27 In Corporation of Glasgow v. Muir, 1943 (2) All ER 44 members of a picnic party
had obtained permission from a lady manager employed by the Corporation of Glasgow to
have their tea in the tea room. For this, it was necessary to carry the tea urn through a narrow
passage on one side of which there was a counter where several children were buying sweets.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 406
The urn was being carried by a church officer and a boy when the officer let go of the handle
and the scalding tea escaped from the urn injuring 6 children. It was urged that the manager
was responsible as she should have anticipated that there was a risk of the contents of the urn
being spilt and scalding the children in the passage. However, the House of Lords, applying
the test of reasonable foresight, unanimously held that the spilling of tea from the urn was not
one that was reasonably foreseeable as there was no element of danger to be reasonably
anticipated from the careful carrying of the urn. As the accident arose because of an
unexplainable mistake by the church officer, the Lordships held the manageress to be free of
liability. Their views on the test of reasonable foresight may be pithily expressed in the words
of Lord MacMillan:
―The standard of foresight of the reasonable man is in one sense an
impersonal test. It eliminates the personal question and is independent of the
idiosyncrasies of the particular person whose conduct is in question. Some
persons are by nature unduly timorous and imagine every path beset with
lions; others, of more robust temperament, fail to foresee or nonchalantly
disregard even the most obvious dangers. The reasonable man is presumed to
be free both from over-apprehension and from over-confidence.‖
8.28 In Bolton v. Stone [1951] 1 All ER 1078 the respondent standing on a highway
adjoining a cricket ground was struck by a ball hit by a batsman during a match. She brought
suit against the occupiers of the ground for negligence. The House of Lords again applied the
test of reasonable foresight and, on consideration of the fact that the cricket pitch was
protected by a fence, the top of which was seventeen feet above the cricket pitch, that the
distance from the striker to the fence was seventy-eight yards and that the ball had gone
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 407
outside the stadium just 6 times in the last 30 years, held that it was not reasonably
foreseeable that the ball would strike someone standing on the adjoining highway. It was held
that:
―[t]he standard of care in the law of negligence is the standard of an ordinary
careful man, but, in my opinion, an ordinarily careful man does not take
precautions against every foreseeable risk. He can, of course, foresee the
possibility of many risks, but life would be almost impossible if he were to
attempt to take precautions against every risk which he can foresee. He takes
precautions against risks that are reasonably likely to happen...It may very
well be that after this accident, the ordinary prudent committee man of a
similar cricket ground would take some further precaution, but that is not to
say that he would have taken a similar precaution before the accident.‖
8.29 In Lord v. Pacific Steam Navigation Co. (The Oropesa) [1943] 1 All ER 211 two
vessels collided at sea, i.e the Oropesa and the Manchester Regiment. The latter incurred
serious damage. Its crew were therefore ordered to take lifeboats, whereas the captain along
with 14 of his crew decided to go in a separate lifeboat to the Oropesa to request them to take
the Manchester Regiment in tow or to offer assistance of any sort. This lifeboat capsized and
resulted in the death of 9 of the crew members. It was contended that the Oropesa had been
negligent in running down the Manchester Regiment and the owners of it were therefore
responsible for the 9 deaths. The question, before the House of Lords was whether the death
of the crew members was a direct consequence of the collision which took place owing to the
negligence of the Oropesa. To answer this, it had to be first answered whether the action of
the captain in deciding to take a lifeboat towards the Oropesa would constitute an intervening
circumstance and thus break the chain of causation. The House held that the action of the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 408
captain in those circumstances was reasonable; and reasonable human action does not sever
the connected sequence of acts. Thus, reasonable human conduct forms part of the ordinary
course of things. In the words of Lord Wright:
―The mere fact that human action intervenes does not prevent the sufferer
from saying that damages for injury due to that human action, as one of the
elements in the sequence, is recoverable from the original wrongdoer‖
Therefore, it was held that the chain of causation was not broken and that the owners of the
Oropesa would be responsible for the death of the crew.
8.30 In Lamb v. London Borough of Camden [1981] 2 All ER 408 the plaintiff had let her
house while she was away in America in 1972. In 1973, a sewer pipe in a road outside the
plaintiff's house was being repaired. The contractors engaged by the local council for this
purpose had breached a water main causing the foundations of the house to be undermined.
As a result the house became unsafe causing the tenant to move out. Thus the house was left
unoccupied to await repair. In 1975, squatters moved in but were evicted by the plaintiff. In
1975, squatters moved in again and caused substantial damage to the house. The plaintiff then
filed suit against the Council claiming damages in nuisance and negligence, for the damage
caused by the squatters. However, the Court of Appeal held that a reasonable man could not
have foreseen that by breaking a water pipe when working on the road he would cause the
plaintiff's house to be invaded by squatters. Therefore, the damage was too remote to affix
liability on the Council.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 409
8.31 In Public Prosecutor Vs. Pitchaiah Moppanar, AIR 1970 Mad 198, the accused,
Manager of a School, had a building constructed by employing masons who used excess sand
in the mortar. This resulted in building collapse and death of several inmates. The Court held
that improper work executed by the masons, whereby the sand was mixed in larger
proportion and the consequent building collapse could not be basis for holding the accused
guilty of criminal negligence since he had contracted out the task of construction those who
were supposed to be skilled in that regard.
8.32 In Rajkot Municipal Corporation's case (supra) tortious liability was fastened upon a
corporation because a road side tree fell on a pedestrian walking on the footpath, causing
death to him. The suit was decreed and the Corporation's appeal was dismissed. The
Supreme Court even while rejecting the arguments that statutory bodies could not be sued for
damages and tort, proceeded to hold in that case, the forseeability of the damage could not
attributed to the corporation. The Supreme Court held that:
―the concept of forseeability i.e. what the hypothetical reasonable man would
have foreseen in the circumstances is ubiquitous in the tort of negligence. It is
the foundation of the neighbour principle but it is also used as a test of breach
of duty and remoteness of damage. The fact that particular consequences
were unforeseeable may lead to the conclusion that the defendant's behaviour
was not careless and even when negligence is patent, damage of an
unforeseeable kind will be regarded as too remote and therefore not
actionable...... One man's reasonable foresight is another man's flight of
fancy and so the bounds of what foreseeable can be stretched or the narrowed
as the case may be. The likelihood that a particular event may occur in a
given set of circumstances may range from almost certainty to virtual
impossibility, and in deciding whether it was foreseeable involves a choice.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 410
There is no fixed point on the graph at which the law requires people to take
account of a possibility. It is not a totally unprincipled choice since the
degree of forseeability required may be varied with the kind and extent of the
damage, and the nature of the relationship between the parties. The loss must
be reasonably foreseeable which may mean that it must be foreseeable as a
possibility or probable or more probable than not or likely or very likely‖.
(Emphasis supplied)
8.33 The preceding discussion of case law on forseeability shows that every case would
turn on the subjective factors brought before the court. Thus in Muir (supra), it was held that
the spilling of hot tea in a narrow passage where six children were scalded was an
unforeseeable instance since such an occurrence could not reasonably have been anticipated,
at the place where the tea urn was being carried. Similarly Bolton (supra) was literally a
―bolt from the blue‖, a cricket ball lustily hit by batsman striking someone standing in the
highway. The Oropessa (supra) concerned the death of nine crew members of a capsized
vessel who went in a separate life boat after the vessel was severely damaged, by another
vessel. The owners of the vessel Oropessa, which caused the damage to the other vessel,
whose crew had used the capsized lifeboat, were held responsible for the death of crew.
8.34 The above analysis would disclose that there cannot be any cast iron rule as to what
would constitute foresight. Reasonable forseeability should be judged by itself having regard
to the circumstances rather than the disputed action of the accused or the actors. In other
words the question inevitably which the Court has to direct itself is to what would be
reasonably foreseeable in a given set of circumstances, having regard to the proof before it.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 411
As held by the Supreme Court there cannot be any fixed point on the graph at which the law
requires people to take account of the possibility. The action resulting in damage or death or
injury, the latter two categories being concerned with criminal negligence must be
foreseeable as a possibility or probable consequence. Negligence, to be called criminal
therefore, must always reach the stage of such failure to exercise the requisite, reasonable and
proper care and precaution to guard against injury either to the public generally or to an
individual, which is required to be judged having regard to all the circumstances out of which
the charge has arisen, that it was the imperative duty of the accused to have adopted the
course which he neglected or failed to adopt; such failure should be of such magnitude as to
be regarded as a crime, and not merely a matter of liability, capable of redressal through
damages.
Causation
8.35 The next important aspect to be discussed is causation, as extensive arguments were
made by all appellants. Before taking up the discussion it would be necessary to note that the
facts of this case have thrown up complexities in the understanding of criminal negligence
crimes, perhaps without parallel in this country. Such crimes are uniquely intentionless,
preclude mens rea, and punishment is based on consequence. Overwhelmingly, courts in
India, in the decided cases cited before this court, were concerned with offenders who may be
termed ―direct actors‖ whose acts or omissions could be scrutinized in a fairly simple,
straightforward and in a ―linear‖ manner. This case, perhaps uniquely - presents the
operation of more than one cause, or set of causes which culminated in the tragedy, on 13 th
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 412
June, 1997. If the court were to accept the argument of one or the other group of accused (i.e
the cinema management set of appellants, the DVB set of appellants, the statutory authorities'
employees, accused in the case) the act of one would absolve the other of any responsibility.
In other words, according to DVB employees, the causa causans for the deaths and injuries
was the blockage of exits, bolting of balcony doors, shrinkage of gangways and blockage of a
gangway, which were also in contravention of DCR 1953 and DCR 1981, that led to the
horrific consequences. On the other hand, according to the cinema management and
employee set of appellants, the causa causans was the negligent manner of repairs carried out
on the DVB transformer, which led to a cable detaching, settling on the transformer fin,
resulting in a slit, oil catching fire, and the consequent smoke, which choked those seated in
the balcony. And yet, the fragmentation of the accident, detracts its inherent indivisibility. It
has been proved that the sparking led to detachment of a cable, its falling down, causing a slit
on the transformer, oil gushing out, and catching fire; the fire engulfing vehicles, and leading
to hot smoke and toxic gases which rapidly sped upwards, due to a chimney effect, and the
smoke entering the cinema hall from various points. The patrons in the balcony, unlike those
in the first floor, were most affected; out of 302, 159 were affected by the smoke; 59 died.
All this happened rapidly, within half an hour; there were hinderances in the means of speedy
evacuation of viewers and patrons in the balcony, due to the deviations from prescribed
norms. In effect, the causation theory propounded by each set of appellant, if accepted by the
court, would, according to each of them result in being held blameless. The court, however,
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 413
while evaluating such contentions, has to keep in mind, two factors: firstly, the duty of care
owed by each set of appellants in this case; and two the nature of duty and the standard of
care, having regard to the fact that:
(i) two transformers were located in the cinema's parking area;
(ii) one, the DVB's transformer had caught fire in the morning of the accident;
(iii) the cinema hall had to follow a set of several regulations, which mandated
more than a dozen safety precautions, that were to be in place or complied with, at the
time of and during each cinema show;
(iv) all sets of appellants could be expected to know that a large number of patrons
(to be precise, 1050) could be seated in each show, in darkness during the show,
unaware of their surroundings, as they would be engrossed in the performance for
which they were in the cinema hall. This heightened the risk to those patrons.
8.36 Causation is the "causal relationship between conduct and result." This means that
causation provides a means of connecting conduct, complete with actus reus, with the
resulting harm or result element. Causation applies only where a result is achieved.
Determination of causation involves a two step exercise; one, establishing cause in fact, and
two, legal causation. A method of establishing factual causation is the ―but-for‖ test. The ‗but
for test' inquires ‗But for the accused's act, would the death or injury occurred?' A shoots
and wounds B. The inquiry then is ‗But for A's act, would B have been wounded?' The
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 414
answer is ‗No.' The answer then is that A caused the harm to B. The ―but for‖ test is one of
necessity. It asks was it ‗necessary' for the accused's act to have occurred for the resultant
harm to have occurred. The ―but-for‖ test very often gives the right answers to causal
problems, but at times it does not give the right answers. The first problem is that almost
anything can be a cause. But for the victim of a crime missing the bus, he or she would not
have been at the site of the crime and hence the crime would not have occurred. Yet in such
instance, the victim's missing the bus is not intuitively causes of the resulting harm. This
often does not matter in the case where cause is only one element of liability, as the remote
actor will most likely not have committed the other elements of the test. Inspite of such
limitations, the ―but for‖ test has been applied in determining causal responsibility. Courts
have qualified it by saying that causation is to be understood ―as the man in the street‖ would
(Yorkshire Dale Steamship Co v Minister of War Transport [1942] AC 691). The High Court
of Australia supplemented this with a ―common sense‖ approach, in March v Stramare
(1991) 171 CLR 506. In the US, in United States in State v. Tally, 15 So. 722, 738 (Ala.
1894), the court ruled that:
―The assistance given ... need not contribute to criminal result in the sense
that but for it the result would not have ensued. It is quite sufficient if it
facilitated a result that would have transpired without it.‖
8.37 Legal scholars too have grappled with the question of causation. HLA Hart and Tony
Honore in their seminal work Causation in the Law proposed the test of sufficiency.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 415
According to them something is a cause of that if it is a ‗Necessary Element of a Set of
conditions jointly Sufficient for the result'. This is known as the ―NESS‖ test. A component
of this NESS set is a "causally relevant condition". This becomes a "cause" where it is a
deliberate human intervention, or an abnormal act in the context. An example is an
accomplice to a murder who drives the principal to the scene of the crime. Clearly the
principal's act in committing the murder is a "cause" (on the but for or NESS test). So is the
accomplice's act in driving the principal to the scene of the crime. However the causal
contribution is not of the same level (and, this provides some basis for treating principals and
accomplices differently under criminal law).
8.38 The law intervenes in certain situations, and predicates that even if the accused is
guilty for the cause, he nevertheless cannot be held responsible liable because in the
circumstances he is not to be understood, in a legal sense, as having caused the death or
injury. This is the effect of novus actus interveniens, which means a ‗new intervening act'
which may ‗cut the chain of causation'. The effect of the principle may be stated that if a new
event, either through human agency or natural causes, does not break the chain, the original
actor is liable for all the consequences flowing naturally from the initial circumstances. If the
new act breaks the chain, the liability of the initial actor (the man responsible for the ―cause‖)
stops at that point, and the new actor, if human, will be liable for all that flows from his or her
contribution. ―Proximate cause‖ which is associated with ―causation‖ as a concept is beset
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 416
with its own share of problems. Prosser and Keeton are forthcoming in their dislike for the
term ―proximate‖. They say, (in Prosser & Keeton on Torts, § 42, at p. 273) (Quoted in
James Mitchell Et Al., v. Jose L. Gonzales Et Al 54 Cal. 3d 1041; 819 P.2d 872), that :
"The word 'proximate' is a legacy of Lord Chancellor Bacon, who in his time
committed other sins. The word means nothing more than near or immediate;
and when it was first taken up by the courts it had connotations of proximity in
time and space which have long since disappeared. It is an unfortunate word,
which places an entirely wrong emphasis upon the factor of physical or
mechanical closeness."
8.39 In a similar vein, United States v. Roosevelt Cooke, 18 MJ No. 44387, CM 441428,
(US Court of Military Appeals) quoted LaFave and Scott in Handbook on Criminal Law:
―In the criminal law too the situation sometimes arises where two causes,
each alone sufficient to bring about the harmful result, operate together to
cause it. Thus A stabs B, inflicting a fatal wound; while at the same moment X,
acting independently, shoots B in the head with a gun, also inflicting such a
wound; and B dies from the combined effects of the two wounds. It is held that
A has caused B's death (so he is guilty of murder if his conduct included an
intent to kill B, manslaughter if his conduct constituted recklessness). (X, of
course, being in exactly the same position as A, has equally caused B's death.)
So the test for causation-in-fact is more accurately worded, not in terms of
but-for cause, but rather: Was the defendant's conduct a substantial factor in
bringing about the forbidden result? Of course, if the result would not have
occurred but for his conduct, his conduct is a substantial factor in bringing
about the result; but his conduct will sometimes be a substantial factor even
though not a but-for cause.‖
It also quoted R. Perkins's Criminal Law, 698-701 (2d ed. 1969):
―It must not be assumed that negligence of the deceased or of another is to be
entirely disregarded. Even though the defendant was criminally negligent in
his conduct it is possible for negligence of the deceased or another to
intervene between his conduct and the fatal result in such a manner as to
constitute a susperseding cause, completely eliminating the defendant from the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 417
field of proximate causation. This is true only in situations in which the second
act of negligence looms so large in comparison with the first, that the first is
not to be regarded as a substantial factor in the final result. In one case, for
example, the defendant by his criminal negligence had created a risk of
explosion in a building. The deceased, after being fully warned of the danger
and urgently requested to stay out, went in and was killed. This death was
held to be imputable solely to the negligence of the deceased and not at all to
the negligent conduct of the defendant. In another case, while the driver of a
horse-drawn vehicle did not even have the reins in his hands, a child suddenly
ran in front and was killed. Erle, J., charged the jury that if by the utmost care
on his part the driver could not have prevented the accident, he must be
acquitted.
In like manner the negligence of a third person may intervene in such a
way as to be the sole cause of resulting death within the legal view. For
example, a starter was criminally negligent in starting a second train too soon
after the first had departed and the second train crashed into the first, killing
a passenger. But this homicide was imputed solely to the negligence of a
flagman who got confused in his signals and held up the first train until it was
struck by the second.‖
8.40 G. Williams in his celebrated Textbook of Criminal Law (2nd ed. 1983), at pp. 381-82
says that:
―When one has settled the question of but-for causation, the further test to be
applied to the but-for cause in order to qualify it for legal recognition is not a
test of causation but a moral reaction. The question is whether the result can
fairly be said to be imputable to the defendant. . . . If the term ―cause‖ must
be used, it can best be distinguished in this meaning as the ―imputable‖ or
―responsible‖ or ―blamable‖ cause, to indicate the value-judgment involved.
The word ―imputable‖ is here chosen as best representing the idea. Whereas
the but-for cause can generally be demonstrated scientifically, no experiment
can be devised to show that one of a number of concurring but-for causes is
more substantial or important than another, or that one person who is
involved in the causal chain is more blameworthy than another...‖
8.41 The courts have not hesitated to look beyond the ―but for‖ or ―proximate‖ cause
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 418
doctrine, wherever the circumstances demanded. Thus, in Aggregate Limestone Company v.
Robison 276 ALA.338, 161 SO. 2d 820 (1964) the Alabama Supreme Court held that:
―Proximate means next in relation to the cause and effect, and, together with
the word ―remote‖ is used to distinguish between actionable and non-
actionable negligence...Proximate cause is not the act necessarily nearest to
the injury, but is an act which actively aided in producing injury as a direct
and existing cause...‖
This understanding was approved in Maxwell v. Southern Christian Leadership Conference
414 F.2d 1065 US Federal Fifth Circuit Court (1969). In Milwaukee and Saint Paul Rly Co-v.
Kellogg, 94 US 469 (1877) it was opined that:
―The true rule is, that what is the proximate cause of an injury is ordinarily a
question for the jury. It is not a question of science or of legal knowledge. It is
to be determined as a fact, in view of the circumstances of fact attending it.
The primary cause may be the proximate cause of a disaster, though it may
operate through successive instruments, as an article at the end of a chain
may be moved by a force applied to the other end, that force being the
proximate cause of the movement, or as in the oft-cited case of the squib
thrown in the market-place. The question always is, Was there an unbroken
connection between the wrongful act and the injury, a continuous operation?
Did the facts constitute a continuous succession of events, so linked together
as to make a natural whole, or was there some new and independent cause
intervening between the wrong and the injury? (Emphasis supplied)
8.42 In R v. Hallett [1969] SASR 141 the Full Court of the South Australia Supreme Court
held that:
―The question to be asked is whether an act or a series of acts (in exceptional
cases an omission or series of omissions).... by the accused is or are so
connected with the event that it or they must be regarded as having a
sufficiently substantial causal effect which subsisted up to the happening of the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 419
event, without being spent or without being in the eyes of the law sufficiently
interrupted by some other act or event.‖
8.43 In R v Smith [1959] 2 All ER 193 the appellant had been convicted at a court-martial
of the murder of another soldier by stabbing him. The victim had been dropped twice while
being taken to the medical reception station and was subsequently given treatment which was
said to be incorrect and harmful. Lord Parker CJ, giving the judgment of the Court-Martial
Appeal Court, rejected a contention that his death did not result from the stab wound. It was
held that:
'It seems to the court that, if at the time of death the original wound is still an
operating cause and a substantial cause, then the death can properly be said
to be the result of the wound, albeit that some other cause of death is also
operating. Only if it can be said that the original wounding is merely the
setting in which another cause operates can it be said that the death does not
result from the wound. Putting it in another way, only if the second cause is so
overwhelming as to make the original wound merely part of the history can it
be said that the death does not flow from the wound.' (Emphasis supplied)
8.44 In R v Malcherek, R v Steel [1981] 2 All ER 422, it was argued that the act of a doctor
in disconnecting a life support machine had intervened to cause the death of the victim to the
exclusion of injuries inflicted by the appellants. In rejecting this submission Lord Lane CJ,
after considering R v Smith, said:
'There may be occasions, although they will be rare, when the original injury
has ceased to operate as a cause at all, but in the ordinary case if the
treatment is given bona fide by competent and careful medical practitioners,
then evidence will not be admissible to show that the treatment would not have
been administered in the same way by other medical practitioners. In other
words, the fact that the victim has died, despite or because of medical
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 420
treatment for the initial injury given by careful and skilled medical
practitioners, will not exonerate the original assailant from responsibility for
the death.'
8.45 Some of these decisions were considered in R v. Cheshire [1991] 3 All ER 670. In
that case, in the course of an argument in a fish and chip shop the appellant shot the deceased
in the leg and stomach seriously wounding him. The victim was taken to hospital where he
was operated on and placed in intensive care. While in hospital he developed respiratory
problems and a tracheotomy tube was placed in his windpipe to assist his breathing. The tube
remained in place for four weeks. The deceased suffered further chest infections and other
complications and complained of difficulty in breathing. More than two months after the
shooting, while still in hospital, the deceased died of cardio-respiratory arrest because his
windpipe had become obstructed due to narrowing where the tracheotomy had been
performed, such a condition being a rare but not unknown complication arising out of a
tracheotomy. The appellant was charged with murder. At his trial, evidence for the defence
was given by a consultant surgeon that the deceased's leg and stomach wounds no longer
threatened his life at the time of his death and that his death was caused by the negligent
failure of the medical staff at the hospital to diagnose and treat the deceased's respiratory
condition. He was convicted, on the basis of responsibility for the death even if the treatment
given by the hospital medical staff was incompetent and negligent. The House of Lords, in
the course of its judgment, after discussing the two previous judgments and a judgment of the
Victorian Supreme Court, held that:
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 421
―It seems to us that these two passages demonstrate the difficulties in
formulating and explaining a general concept of causation but what we think
does emerge from this and the other cases is that when the victim of a criminal
attack is treated for wounds or injuries by doctors or other medical staff
attempting to repair the harm done, it will only be in the most extraordinary
and unusual case that such treatment can be said to be so independent of the
acts of the accused that it could be regarded in law as the cause of the victim's
death to the exclusion of the accused's acts.
Where the law requires proof of the relationship between an act and its
consequences as an element of responsibility, a simple and sufficient
explanation of the basis of such relationship has proved notoriously elusive.
In a case in which the jury have to consider whether negligence in the
treatment of injuries inflicted by the accused was the cause of death we think it
is sufficient for the judge to tell the jury that they must be satisfied that the
Crown have proved that the acts of the accused caused the death of the
deceased, adding that the accused's acts need not be the sole cause or even the
main cause of death, it being sufficient that his acts contributed significantly
to that result. Even though negligence in the treatment of the victim was the
immediate cause of his death, the jury should not regard it as excluding the
responsibility of the accused unless the negligent treatment was so
independent of his acts, and in itself so potent in causing death, that they
regard the contribution made by his acts as insignificant.‖
8.46 In Empress Car Co v. National Rivers Authority [1998] 1 All ER 481, the
appellant company, E Ltd, maintained a diesel oil tank in a yard on its premises that
drained directly into a river. Although the tank was surrounded by a bund to contain
spillage, E Ltd had overridden that protection by fixing an extension pipe to the outlet
of the tank so as to connect it with a smaller drum standing outside the bund. The
outlet from the tank was governed by a tap, which had no lock. An unknown person
opened the tap and as a result the entire contents of the tank ran into the drum,
overflowed into the yard and passed down a storm drain into the river. The National
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 422
Rivers Authority preferred an information against E Ltd, charging it with 'causing'
polluting matter to enter controlled waters from its premises contrary to s 85(1) of the
Water Resources Act 1991. The justices convicted E Ltd. On appeal, the Crown Court
upheld the conviction, holding that the escape had been caused by the way E Ltd had
maintained its tank of diesel fuel and that it should have foreseen interference with its
plant and equipment in view of the history of local opposition to its business. E Ltd
appealed to the Divisional Court, contending that if the evidence was consistent with
the tap having been opened by a stranger, the escape would have been caused by the
stranger and it should have been acquitted. The Divisional Court rejected that
submission and dismissed the appeal. E Ltd appealed to the House of Lords,
contending, further, that 'causing' for the purposes of s 85(1) required some positive
act and that the escape could not have been caused by any such act by the company. It
was held:
―The first point to emphasise is that commonsense answers to
questions of causation will differ according to the purpose for which the
question is asked. Questions of causation often arise for the purpose of
attributing responsibility to someone, for example, so as to blame him for
something which has happened or to make him guilty of an offence or liable in
damages. In such cases, the answer will depend upon the rule by which
responsibility is being attributed...In answering questions of causation for the
purposes of holding someone responsible, both the law and common sense
normally attach great significance to deliberate human acts and extraordinary
natural events. A factory owner carelessly leaves a drum containing highly
inflammable vapour in a place where it could easily be accidentally ignited. If
a workman, thinking it is only an empty drum, throws in a cigarette butt and
causes an explosion, one would have no difficulty in saying that the negligence
of the owner caused the explosion. On the other hand, if the workman,
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 423
knowing exactly what the drum contains, lights a match and ignites it, one
would have equally little difficulty in saying that he had caused the explosion
and that the carelessness of the owner had merely provided him with an
occasion for what he did. One would probably say the same if the drum was
struck by lightning. In both cases one would say that although the vapour-
filled drum was a necessary condition for the explosion to happen, it was not
caused by the owner's negligence. One might add by way of further
explanation that the presence of an arsonist workman or lightning happening
to strike at that time and place was a coincidence.‖
8.47 It was stated, rather pithily, in Winfield and Jolowicz on Tort, (13th Edition (1989)
138 that:
―The rather unscientific way in which lawyers are apt to approach the
problem (referring to causation) is shown in their use of metaphors about
causation, such as chain, rivers, transmission gears, conduit pipes, nets,
insulators of phrases expressive of it, such as ―causa causans and causa sine
qua non‖, ―direct cause and intervening cause‖, ―effective cause and
ineffective cause‖, ―nova cause interveniens‖; but all these merely conceal
the puzzle and do not solve it. In fact, neither metaphor nor catchword will
release judges from the effort or agony of deciding each case on its merits
with such held as they can get from some very general principles. This may
not be systematic, but what is often forgotten by critics is that judges would no
better if they tried to be more exact‖
8.48 Intractable though the problem may seem, the question of what constitutes cause,
where a continuous, unbroken chain of events is involved, has to be addressed by the court,
by adopting a common sense approach. Of course, the court has to be satisfied that the act
sought to be intervening is not so significant that it breaks the original chain, of causation, set
into motion by the first act. The question always is, whether there was an unbroken
connection between the wrongful act and the injury, a continuous operation, and if the facts
constituted a continuous succession of events, so linked together as to make a natural whole,
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 424
or was there a new and independent cause intervening between the wrong and the injury. That
this approach is also consistent with the law in India, is evident from the decisions in
Bhalachandra Pathe (supra) and Rustom Irani (supra) that the duty of care, breached by an
actor, having a sufficient or significant connection with the accident, resulting in death,
constitutes rash and negligent act, and an offence under Section 304-A IPC. The Supreme
Court's approach in both these judgments was not doctrinaire; a commonsense view was
applied to what is ―proximate‖.
8.49 Section 32 IPC defines an ―act‖ as including an illegal omission; Section 33 says that
"act" denotes as well a series of acts as a single act: the word "omission" denotes as well as
series of omissions as a single omission. Section 36, in a sense takes the thought underlying
both Sections 32 and 33 further, by saying that wherever the causing of a certain effect, or an
attempt to cause that effect, by an act or by an omission, is an offence, it is to be understood
that the causing of that effect partly by an act and partly by an omission is the same offence.
Unlike sections 34 and section 35, which imply application of a conscious and active mind,
Section 36 allows for offences to be ―caused‖ by acts, combinations of acts and combination
of omissions, or combination of acts and omissions, in the absence of a mental element. It
also extends to attempts.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 425
8.50 Counsel for accused had urged that Section 36 was inappropriately applied by the trial
court, since it can be pressed into service only if the part act, part omission or two separate
acts, are performed or perpetrated by one single actor. Sections 32 and 33 concern themselves
with what are acts, and clarify that series of acts also include series of omissions. They do not
refer to anyone. However, Section 36 starts with the expression ―Whoever‖ that is not limited
to the singular, having regard to Section 13(2) of the General Clauses Act, 1897. Also, it,
unlike Sections 32 and 33, adverts to ―offence‖ thus signifying that it is, at once, clarificatory
as well as independent of those two provisions. Clarificatory, to the extent that series of acts
or omissions, if they cause an effect, amounting to offence, by part acts or part omissions or
part act and part omissions, which are different from each other, nevertheless they are
considered to be integral to each other, if they result in the same consequence. The fact that
the illustration to Section 36 refers to acts and omissions by the same person, does not mean
that it should control the provision itself; at best, it seeks to illustrate. The plain words of
Section 36 are capable of a wider application.
8.51 It is therefore, held that where more than one cause operate independently to
lead to the same result, the acts or omissions involved, so long as they are significant and
―operative‖ to cause the event which is the offence, even if done by different persons would
attract Section 36, IPC. It is therefore held that the combined operation of several causes,
some acts, some omissions, including part acts and part omissions, can be considered in the
context of the a charge under Section 304-A IPC, by reason of Section 36, regardless that
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 426
more than one person was responsible for them. However, each such act or part act or
omissionor part omission must be proved as a significant factor in such ―chain‖ or series of
causes, as to be part of the whole. The role of each such act or omission must be integral to
the entire incident, for it to complete the offence punishable under Section 304-A, 337/338
IPC.
IX CRIMINAL APPEAL NO. 794/2007: SUSHIL ANSAL & CR. APPEAL NO.
846/2007: GOPAL ANSAL
9.1 The question of control and management of Uphaar Cinema in the light of the
unauthorized installation of transformer, structural deviations noticed and glaring
inadequacies in the balcony, all of which played a prominent and significant part in the cause
of death of 59 persons and grievous injury to 100 others has to be examined. This would
become relevant in the background of the over-lapping and supplementary arguments made
on behalf of accused Sushil Ansal and Gopal Ansal.
9.2 Counsel on behalf of accused Nos. 1 & 2 argued that both the brothers were not
directors in the company nor were in any manner in charge of the affairs of the company at
the time of the incident in 1996. While Sushil Ansal had resigned on 17.10.1988, Gopal
Ansal served another brief period from 24.12.1994 to 30.06.1995. The cinema was licensed
in favour of GPT ltd and thereafter in favour of Ansal Theatre and Clubotels (P) Ltd.;
accused No. 1 was merely a representative licensee. Therefore, merely because they played a
role in1973 in the installation of the DESU transformer and were found to have sought
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 427
permission for modification in the balcony, they cannot be personally held responsible for the
fire and the subsequent death.
9.3 The trial court found that the appellants Sushil Ansal and Gopal Ansal although not
designated as Directors on the relevant date i.e. 13.06.1997, were in real and effective control
of the theatre and management of the company which owned it. To arrive at this conclusion
the trial court examined and took into consideration several documents and circumstances,
spanning about 25 years. The evidence and findings in this regard would be analysed
hereafter.
9.4 It has been conceded by both Sushil Ansal and Gopal Ansal, in reply to their queries
under Section 313 that they were Directors of the company continuously till 17.10.1988. In
the case of Gopal Ansal, it is also not denied that he was a Director for another period
between 24.12.1994 and 30.06.1995.
9.5 The Board of Directors in its meeting of GPT, held on 15.07,1972, resolved that
(Exhibit as PW-103/XX), which reads as under :
―.........Resolved unanimously that Shri Gopal Ansal be and is hereby
authorised to sign all the document, drawings and other connected papers
regarding submission of revised plans, applications for water and electric
connections, licences, permission from time to time regarding Uphaar
Cinema, Green Park Extension Market, New Delhi to all concerned
authorities.......‖
9.6 An application was made to the erstwhile DESU, (DVB) for the electricity connection
of the cinema which is produced as part of file Ex. PW 100/M. On 02.02.1973 Sushil Ansal
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 428
as Managing Director of GPT, wrote to DESU agreeing to give two rooms for the DESU
transformer. The said letter inter alia reads as follows :
―..... This is to confirm the discussions the undersigned had with you yesterday
when we agreed to give you two rooms measuring 10'-6'' x 30' and 10'-g'' x 15'
for your transformer and HT and LT panels. This accommodation we will give
you at a nominal rent of Rs. 11 per year. We further undertake to execute the
civil maintenance work.....
It is therefore, requested to kindly get the transformer and HT and LT Panels and
laying of necessary cables expedited so that the necessary connection can be given in
time.
For Green Park Theaters Associated (P) Ltd.
Sd. Sushil Ansal
(Managing Director)‖
9.7 On 20.02.1973 Sushil Ansal again wrote to DESU regarding its transformer (Part of
Ex. PW 100/M). The said portion of the letter reads as follows :
.....Though we are installing our own transformer for our requirements, but
during emergency you will give us current from your transformer on L.T.
Supply for the sub-station to be installed at Uphaar cinema. We are giving you
the space on the above undertaking.....
For Green Park Theaters Associated (P) Ltd.
Sd. Sushil Ansal
(Managing Director)‖
9.8 License No.51, produced as Ex. PW 17/DB dated 24.04.1973 was issued through
Sushil Ansal as Managing Director. At this stage it may be noticed that all subsequent
renewals adverted to this license and also referred to licensee in this document. The material
portion of the license reads as follows :
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 429
''..... FORM-A
The building/place known as Uphaar Cinema situated at Green Park Extension, New
Delhi............. is hereby licensed under section 10 of the Cinematograph Act, 1952 as
a place where exhibitions by means of a cinematograph may be given.
This license has been granted to M/s Green Park Theaters Associated ( Pvt.) Ltd. (
Rep. Licensee Shri Sushil Ansal, Managing Director), Green Park, New Delhi. and
shall remain in force from 24.4.1973 to 23.4.1974 provided that the said M/s Green
Park Theaters Associated ( Pvt.) Ltd. ( Rep. License, Shri Sushil Ansal,Managing
Director ) Green Park, New Delhi or any person to whom, with consent of the
licensing the license is transferred continues to own or manage the cinematograph
used in the said
Uphaar Cinema.........‖
9.9 On 19.06.1974 Sushil Ansal, Managing Director of GPT Limited (Ex. PW 69/BB)
sought permission from the Entertainment Tax Officer to lease out premises on the ground
floor of the cinema building for commercial establishments stating the place has already been
sanctioned for a restaurant.
9.10 In the affidavit dated 21.03.1975 (part of Ex. PW 69/BB), it was stated by Sushil
Ansal that :
''....I, Sushil Ansal Managing Director, Green Park Theatres Associated (P)
Ltd. New Delhi and licensee of Uphaar Cinema, Green Park Extn. Market for
the year 1975-76 have not without without the permission transferred the
license or the licensed place or the Cinematograph not allowed any other
person during the year 1974-75 to exhibit film in the licensed place. I am still
the occupier of the licensed premises and owner of cinematograph .....''.
9.11 Sushil Ansal likewise sought for renewal of licence on 02.04.1979 - a part of Ex. PW
69/CC. This document states that the original license No.51 dated 24.04.1993, due for
renewal with effect from 24.04.1979 had been misplaced from the Head Office at Ansal
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 430
Bhawan, and requested for issuance of a duplicate license along with the annual renewal.
Significantly, Sushil Ansal described himself as licensee in the said document.
9.12 By Ex. PW 15/I, Sushil Ansal authorized V.K. Bedi, Architect to discuss the issues
with the authorities. The relevant part of the document is extracted below :
― LETTER OF AUTHORITY
I/We the undersigned hereby authorize Mr. V K Bedi (Architect) to deal,
discuss and explain in connection of Building Plan on Plot/House
No:.......Ward No./Block No: Green Park Theaters situated at New Delhi. I/We
also authorize him to make necessary corrections in the above stated plan as
required under the Building Bye Laws and to collect the sanctioned plan on
my/our behalf.
For Green Park Theaters Associated Pvt. Ltd.
-Sd Sushil Ansal
Signature of Owner.......‖
9.13 Accused Gopal Ansal, acting as Director, GPT, wrote a letter on 24.05.1978 to the
Entertainment Tax Officer, for permission to install an eight seater box. The letter is Ex. PW
110/AA 20 which reads as follows :
".... We are grateful to you for having sanctioned a family box for 14 persons
at Uphaar Cinema quite some time back. You will appreciate that with the
passage of time, the family is growing; we would , therefore, be grateful if you
could kindly sanction us an additional private box comprising of eight seats.
We wish to assure you that the same would be strictly for personal use. The
necessary drawings for the same are enclosed herewith.
Hope you would consider the case sympathetically and accord the necessary
sanction......"
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 431
9.14 On 06.12.1979 a show cause notice being part of Ex. PW 69 was issued for removal
of 100 additional seats, permitted by 1976 notification. Gopal Ansal as a Director of GPT
replied on 13.12.1979 (PW 100/AA-2), taking the following position:
".....It is surprising to note that the Administration without applying it's mind
as directed by the Hon'ble High Court seems to have formed its view on the
basis of some earlier inspection that all the additional seats installed by us
would require removal. We will request you to please consider the case of our
additional seats on merits. If the guidelines furnished by the Cinematograph
Act, 1952 and reiterated by the Hon'ble Delhi High Court are kept in view,
you will appreciate that the additional seats installed by us are within the
Rules and accordingly not liable to be removed merely because the relaxation
has been withdrawn. Without prejudice to the aforesaid contention, in any
event, we submit that all the 85 number of additional seats in the Balcony and
Auditorium are clearly within the Rules and cannot be said to be violative of
any of the rules. We would request that after due intimation to us, you may
kindly inspect the Cinema in the light of the High Court's order.
We request you to give us a personal hearing before you take any
final decision in the matter .....".
9.15 On 29.07.1980 Gopal Ansal wrote a letter Ex. PW 110/AA 7 for permission to install
15 additional seats. This document has been discussed in the preceding portion of this
judgment, dealing with deviations and changes in the balcony. Though this letter is sought to
be objected to, its existence and genuineness receives corroboration by reference to it in
subsequent, undisputed documents i.e. Ex. PW 29/S, PW 29/DS and Ex. PW 29/DV.
9.17 Ex. Pw 29/DV, the letter dated 05.09.1980 enclosing revised plan for installation of
15 additional seats which was finally granted on 04.10.1980.
9.18 On 11.05.1981, the DCP (Licensing) has issued a show cause notice to the licensee
asking why the cinema license should not be suspended. Sushil Ansal sought for intervention
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 432
to ensure that patrons interests did not suffer, in the following terms, describing himself as
licensee.
―In view of the above, it is requested that the operation of the suspension
order may please be postponed by seven days and may become enforceable
from Friday, the 17th July, 1981, beyond which no advance booking has been
done nor would be done by us. As discussed with your, we agree that the order
of suspension is acceptable to us and that we shall not appeal against this to
the court of law. We would , however, leave it to you to review the matter.
We shall be grateful for your co-operation at this juncture which will be in the
larger interests of the public.
For Green Park Theaters Associated Pvt.Ltd.
(SUSHIL ANSAL )
LICENSEE......''
9.19 A show cause notice was issued on 28.05.1982 when five doors/gate in the cinema
hall were bolted inside during film exhibition violating Rule 12 (8) of DCR, 1981. Gopal
Ansal as Director of GPT replied on 04.06.1982 (PW Ex.110/AA-24). He mentioned the
possibilities of such doors being bolted due to pressure from patrons or pressure from air
conditioning. The said letter has been discussed in the previous section of this judgment
dealing with ―Safety Precautions in the Balcony‖. The above mentioned letter assures ―that
utmost precautions would be taken in future‖.
9.20 The car parking contract Ex. PW 56/A was signed by Gopal Ansal on 01.04.1988.
This was proved by PW 56, the parking contractor.
9.21 According to the records, concededly, Sushil Ansal and Gopal Ansal also resigned
from the Directorship of the company through a Board Resolution (PW 103/XX-1), yet,
through letter dated 20.02.1989 (Ex.PW 98/C) Gopal Ansal intimated the names of three
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 433
persons as nominees, describing himself as Director. This letter when sought to be produced
was objected to. The witness Mr. Phartyal mentioned that he seized the file and the signature
of one Mr. Avtar Singh were obtained on the original. PW 107 Avtar Singh confirmed
having signed the memo Ex. Pw 98/A. The said letter reads as follows :
―22 February 1989
The Entertainment Tax Officer
Office of the Entertainment Tax Commissioner
2 Battery Lane, Rajpur Road
Delhi
Sub : Nominee for Uphaar Cinema
Dear Sir,
Further to our earlier letters giving the names of our Nominees for
Uphaar Cinema, we request you to kindly cancel the nomination of Mr. S.K.
Bhatnagar as he is no longer working with us.
Also we would like to have the following person as an additional
nominee for Uphaar Cinema.
Mr. Krishan Gopal Arora
Booking Clerk
The signature of Mr. Krishan Gopal Arora is attested hereunder.
Also we already have the following Nominees. Their signatures are also
attested hereunder for your records:
Mr. K.L. Malhotra, Dy General Manager
Mr. R K Shrma, Manager
Mr. N S Chopra, Assistant Manager
Yours faithfully,
For GREEN PARK THEATRES ASSOCIATED (P) LTD
SD
(GOPAL ANSAL)
DIRECTOR
9.22 By Ex. PW 50/B a letter dated 03.03.1992, Sushil Ansal (who by then had resigned as
Director of the company) sought for renewal of the annual license for the period 24.04.1992
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 434
to 23.04.1993 in describing himself as licensee of the Uphaar cinema. He also filed an
affidavit. The same are as follows :
―We wish to apply for renewal of our license under section 10 of the
Cinematograph Act 1952 for Uphaar Cinema situated at Green Park
Extension , New Delhi, for the period from 24.4.1992 to 23.4.1993. In this
connection we are sending herewith the following documents:
1. Existing License no.51 dated 24.4.1973 (already lying with you)
2. Affidavit
We shall be grateful if you can renew our license for the period 24.4.1992 to
23.4.1993....''
Affidavit :-
'....I, Sushil Ansal s/o Late Shri Charanji Lal R/o N-148, _ Panchshila Park,
New Delhi Chairman of Green Park Theatres Associated (P) Ltd 115, Ansal
Bhawan, 16 Kasturba Gandhi Marg, New Delhi 110001, am applying for
renewal of License for the year 1992-93. I have not without permission,
transferred the License or the Licensed place or the Cinematograph to any
person during the year 1991-92 to exhibit films in the Licensed place. I am
still the occupier of the licensed premises and owner of the
Cinematograph.....''.
9.23 The accused Sushil Ansal, in response to the query under Section 313 (Question
No.381) only stated that he could have been authorised to sign the letter, by the Board of
Directors. He did not deny the letter; he did not also give any explanation why he was
authorised to sign it. He described himself as licensee in the application and affirmed the
affidavit in such capacity.
9.24 The Minutes of Board of Directors meeting dated 24.12.1994 disclosed that Gopal
Ansal was Director and Sushil Ansal was a special invitee. The minutes resolved for
appointment of Gopal Ansal as an Additional Director till the next annual general meeting.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 435
9.25 A cheque being No.955725 dated 26.06.1995, for an amount of Rs.50 lakhs was
drawn from the account of M/s Green Park Theatre Associated Pvt. Ltd. in favour of Mr.
Sushil Ansal. The account being current account No.4129 was maintained with the Punjab
National Bank. The said cheque was proved as Ex. 31/B.
9.26 According to the Board of Directors meeting held on 25.03.1996 Ex. PW 103/XX-3,
Gopal Ansal was appointed as authorized to operate bank account of the company upto any
amount. Three others were granted power to operate bank accounts for a sum not exceeding
Rs.7,50,000/-. Six persons were conferred power to jointly operate account with any two of
each of four upto an amount not exceeding Rs.2,50,000/-. Similar powers were conferred on
the said persons, including unlimited power in relation to the opening and operation of a new
current account.
9.27 Shri Gopal Ansal issued a cheque Ex. Pw 93/B for Rs.9711/- from the bank account
of GPT, this was seized by memo Ex. 93/A. By this time the name of GPT has been changed
to Ansal Theatres and Clubotels (P) Ltd., a fact recorded in the minutes of meeting held on
25.031996 adverted to earlier. The resolution of 30.06.1995, however, had recorded
that Gopal Ansal resigned from the Board of Directors (Ex. PW 103/XX-3).
9.28 By two resolutions dated 04.09.1996 Sushil Ansal and Gopal Ansal were authorized
and empowered to deposit title deeds of the company with the intent to create an acquitable
mortgage to secure a term loan of Rs.40 crores. The second Board resolution authorized
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 436
Gopal Ansal and Sushil Ansal inter alia to operate various bank accounts of the company
upto any amounts.
9.29 A cheque dated 30.11.1996 (Ex. PW 90/B) was issued by Gopal Ansal for a sum of
Rs.1,50,000/- from the account of Ansal Theatre and Clubotels Limited.
9.30 By two office memos (Ex. PW 102/D-54 and PW 102/D-56) dated 18.12.1996, day
to day activities of Uphaar cinema were sought to be delegated. The memo stated that erring
officials would be dealt with severely if necessary by dismissal from service. These memo
were also marked to ―MD (APIL) for his information....‖. Significantly there was no
Managing Director of Ansal's Theatres and Clubotels Limited and reference of AIPL appears
to be Ansal's Properties and Industries Limited.
9.30 By Board of Directors resolution dated 31.12.1995 Sushil Ansal and Gopal Ansal
were appointed and constituted as authorized signatory upto any amount, for operating the
current accounts with the companies banks. This resolution is also contained in Ex. PW
103/XX-3.
9.31 By cheque Ex. PW 90/C dated 12.02.1997 Gopal Ansal sought to withdraw a sum of
Rs.2,96,550/- from the account of Ansal Theatres and Clubotels (P) Ltd, payable to
Chancellor Club.
9.32 By the minutes recorded at the meeting of Board of Directors dated 28.03.1997, inter
alia, Sushil Ansal and Gopal Ansal were authorized to operate the bank accounts of the
company upto any amount. The banks were authorized to honour and accept all cheques,
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 437
drafts, bills of exchange and negotiable instruments correspondingly. Other authorisation
arrangements were made in respect of Canara Bank account at Hazrat Ganj, Lucknow,
authorisation to open bank account with the Corporation Bank at Sushant Lok was separately
made. Resolution No. 16 further stated that for the purpose of security of a loan sanctioned
to Ansal Properties and Industries Limited to the extent of Rs.40 crores, equitable mortgage
of the properties of Ansal Theatres and Clubotels Pvt. Limited could be created. Sushil Ansal
and Gopal Ansal inter alia were authorized to sign documents including giving corporate
guarantees and other necessary documents. This loan was to be disbursed to the said Ansal
Properties and Industries Limited by Punjab National Bank, Tolstoy Marg, New Delhi.
9.33 The trial court had relied upon certain other documents, such as minutes of MD
conference dated 27.02.1997 (Ex PW 98/X-4), 02.04.1997 (Ex PW 98/X-2), 02.04.1997 (Ex.
PW98/C - File. Minutes dated 01.05.1997 contain in Ex. PW 98/C and 09.05.1997 contain
Ex. PW/X-3.
9.34 The record shows that Ex. PW 98/C was seized under Memo Ex. PW 98/A. The
seizure memo Ex. PW 98/A was signed by Mr. Avtar Singh, PW 107. He deposed to this
effect. Ex. PW 98/C file contains the other documents which were relied upon by the trial
court to underline the active involvement of Gopal Ansal. A brief discussion about these is
necessary. It would also be essential to deal with the contention of the appellants in this
regard.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 438
9.35 Ex. PW 98/X-4, a letter written by accused Ajit Chaudhary, forwarded to the DGM
(Uphaar). It encloses what is termed as MD's minutes, which are part of Ex. PW 98/C. This
minutes/document list out various points discussed during the meeting held on 27.01.1997.
The said minutes/document itself does not bear the signature of anyone and is not dated too.
The covering letter dated 03.03.1997 describes the meeting as one held on 27.02.1997. The
minutes record a variety of issues having been discussed including ones relating to fixing of
responsibility upon various officials by the MD for furnishing a feasibility report, for advance
booking counter; the fixing of responsibility for maintenance and repairs within the building,
placed upon the GM (Construction), installation of improved version of sound system and
financial application, advertisement and publicity, covering of empty show windows, etc.,
indicating the involvement of the M.D. Likewise Ex. PW 98/X 2 was signed by Ajit
Chaudhary. It encloses the minutes of ―MD Conference‖ held on 02.04.1997. This also lists
out 11 matters which were discussed in the meeting and for which responsibility was fixed on
various officials. The matter discussed included a photograph taken during the night
placement of rope light, neon light, emphasis on maintenance of cleanliness of auditorium,
proper display of items in the canteen, beautification, proper parking place in front of the
cinema hall, scheme for installation of EPABX and so on. A list of 11 points discussed is
recorded in the said minutes which are again undated and unsigned. They are part of Ex. PW
98/C. The third in this series is Ex. PW 98/X-3 dated 02.05.1997, it encloses the minutes of
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 439
meeting held on 01.05.1997. The letter Ex. PW 98/X-3 describes Mr. Gopal Ansal as MD in
the Chair.
9.36 By letter dated 16.12.1996 (part of Ex. Pw 69 K), the Ansal Theatres and Clubotels
(P) Ltd. intimated that the name of the erstwhile GPT has been changed with effect from
11.03.1996 and the Uphaar Cinema would be controlled by M/s Ansal Theatres and Clubotels
(P) Ltd. A copy of the certificate of incorporation issued by the Registrar of Companies,
NCT of Delhi and Haryana was enclosed. The letter adverted to the original license issued
since 1973 and stated ―you may however, please note that there will be no change in the
name of licensee of the cinema.‖
9.37 Ex. PW 9/D-15 is the diary of the Ansal Group for the year 1997. It described a
common corporate management which included Sushil Ansal and Gopal Ansal. The diary
was seized by PW 78 Rajbir Singh by seizure memo Ex. Pw 78/F, which lists Ansal Theatres
and Clubotels (P) Ltd., as part of the group company. Shri Sushil Ansal shown as Corporate
Chairman. Apart from Uphar cinema, Charanjeev Charitable Trust is also shown as running
Homeopathy dispensary in the Uphaar Cinema. That trust is also shown as part of the group.
9.38 The argument made on behalf of the accused Sushil Ansal is that company GPT
owned the land as well as the cinema. The license issued for the cinema was also in favour of
the company. It is only for the sake of convenience that Shri Sushil Ansal was described as a
representative licensee. However, at all material times, the licensee continued to be in the
name of the company. With effect from 1994, the company explicitly nominated Shri R.M.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 440
Puri as its authorised person, which amounted to nominating someone under Rule 10, DCR
1953. In the circumstances, the trial court could not have concluded that the first two accused
had any manner of connection with the company.
9.39 It was urged in addition that both the said accused had severed their connections with
the company, the first accused Sushil Ansal as far back as in October 1988 and Gopal Ansal
in 1995. The mere circumstance of their being authorised to operate accounts of the company
was to do other specific acts did not clothe them with any real or effective power or invest
effective decision making attributes upon them. In these circumstances the said two accused
could not, by any strength of imagination be held culpable for the omissions found by the
trial court. To the extent that the said accused had engaged in correspondence with the
statutory authorities which were considered by the Court, they had done so in the capacity of
the directors. That did not, in any manner, disturb the reality of the company being the
licensee and owner of the premises. It was urged that the materials on record did not measure
up to proof beyond reasonable doubt, the only standard applicable for a sustainable
conviction, to implicate the said two accused for the offence of criminal negligence, and
sustain a finding that the two accused were the directing mind or alter ego of the company.
9.40 It was urged that the said two accused could not also have been charged with the
offences under Section 14 of the Cinematograph Act because their so called involvement had
occurred, more than two decades prior to the incident. The cinema was under the effective
control and management of all others which included a nominated Director. It was also
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 441
managed by a Board of Director, which had no connection with them. The materials,
therefore, could not sustain a finding that the first two accused were the real directing or
operating mind of the company. In other words, the trial court could not have held appellants
guilty of the alleged acts which were clearly those of the company or at the highest
attributable to others incharge and in control at the relevant time.
9.41 The arguments made on behalf of the appellants have to be dealt with at two levels:
(1) Whether the acts and omissions, which the trial court found to be culpable, are
attributable to accused 1 and 2 or were only attributable to the company as a separate entity?
(2) If they were indeed attributable to these appeallants, whether such acts and omissions
amounted to criminal acts inasmuch as they infracted Section 14 of the Cinematograph Act
and also were of such nature and character, so as to breach the duty of care, attracting
culpability under Section 304 A IPC?
9.42 No doubt in this case the land and the building in which the cinema is located was
transferred to GPT. The evidence and materials indicated above disclosed that between 1973
- 1988 at all material times effective decision making within the company was with the first
two accused. These decisions included the following :
(1) Installation of the DVB transformer, which was not authorised either by MCD or the
licensing department;
(2) The closure of the right side gangway after the first notification of 1976
(3) Closure of the right side exit in the balcony, in 1978. Their request for this change
was made by accused Gopal Ansal. This was ultimately granted as discussed in detail
in the Section dealing with balcony deviations.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 442
(4) The decision and request for re-arrangement of 37 seats which were directed to be
withdrawn after the second notification of 1979.
(5) The request for installation of 15 additional seats, made through letter dated
29.07.1980 Ex. PW 29/DX. A modified request for placement of the said additional
seats which was ultimately granted on 04.10.1980, Ex. PW 29/DV.
(6) Various letters/ replies were written in response to show cause notices, listing out
deficiencies noticed by the statutory authorities at the time of inspection, such as the
effect that the cinema doors were bolted from inside even during the time of show and
other related matters;
(7) Applications for renewal of license made by accused Sushil Ansal described himself
as licensee and also supporting such requests with an affidavit containing solemn
declaration.
(8) The case of both accused Sushil Ansal and Gopal Ansal is that they ceased to be
Directors with effect from 17.10.1988. Barring a brief stint as a Director during
1994-1995 as far as Gopal Ansal was concerned, this position continued till the fateful
day i.e. 13.06.1997. It would be, therefore, necessary to examine more closely this
contention in order to scrutinize whether the trial court findings are well founded.
9.43 As discussed earlier the trial court relied on certain circumstances such as the fact that
in several minutes of Board of Directors for the period 1994-1995 to 1996-1997, both Gopal
Ansal and Sushil Ansal were authorised to
(a) operate bank accounts of the company upto any amount
(b) deposit the title deeds of the company to crate acquitable mortgage,
securing loans raised by other companies of the Ansal's group i.e. AIPL.
(c) Ex. PW 103/XX-3 contains the minutes of meeting of the Board of
Directors of GPT dated 30.06.1995. Item 12 records the resignation of Gopal
Ansal and but at the same time it authorizes him to open a current account
with the Bank of Baroda under the name and style of Ansal Theatres and
Clubotels (P) Ltd., describing it as a division of Green Park Theatre
Associated Pvt Ltd. The resolution authorizes Gopal Ansal to operate that
account upto any amount.
(d) The resolution dated 02.09.1995 (Ex. PW 103/XX-3) authorised Shri
R.M. Puri all time Director of the company to perform, acts of management of
the Uphaar cinema. These extended to appointing and dealing with personnel;
correspondence on behalf of the company with labour authorities including,
institute, conduct, defend, compromise and attending legal or quasi legal
proceedings.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 443
9.44 All the cinema licenses through issued temporarily for two months period continuously
from 1986 onwards, referred Sushil Ansal as the licensee. All these are part of Ex PW
69/AA, Ex. PW 69/BB, Ex. Pw 69/CC.
9.45 Significantly the resolution sought to be relied on, by the accused, did not nominate Shri
R.M. Puri as a licensee nor authorize him to act on behalf of the company as licensee under
the Delhi Cinematograph Act nor authorizing him to act on behalf of the representative
licensee to deal with the statutory authorities under the said Act. This aspect is of extreme
importance in the letter written by Shri R.M. Puri. The letter nominating Shri R.M Puri
issued on behalf of the company only described him as an authorised signatory. The letter
also does not mention that he was being nominated in terms of Rule 10 of DCR, 1953/DCR
1981.
9.46 The application for renewal made on 03.03.1992 (Ex. PW 50/B) was signed by Sushil
Ansal. This was accompanied by an affidavit executed by him describing himself as the
occupier of the premises and owner of the cinema. Though Shri Sushil Ansal ostensibly
divorced himself from the company by resigning from it with effect from 17.10.1988, he
issued a cheque favouring himself from the company account, on 20.06.1995, for the sum of
Rs.50,00,000/- . This circumstance was proved by the deposition of PW 91 and the letter, Ex.
PW 91/B enclosing a copy of the cheque, issued by the Punjab National Bank.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 444
9.47 Similarly Gopal Ansal after his resignation from the company issued two cheques (1)
cheque dated 23.5.1996, for Rs.9,711/- (PW 93/B) and the other for Rs.2,96,550/-, Ex. 90/C.
9.48 Though having no interest or involvement in the company both Sushil Ansal and Gopal
Ansal were authorized to operate all bank accounts except two specified bank accounts of
Ansal Theatres and Clubotels (P)Ltd., by its board resolution 28.03.1996 (Ex. PW 69/C). By
the same resolution they were further authorized to create corporate guarantees for securing
loan of another concern, a sister company, i.e. Ansals Properties and Industries Limited to
the extent of Rs.40 crores as well as create equitable mortgage for loan in favour of that
concern.
9.49 In addition to the above circumstances, the trial court relied upon the inspection
reports of the Delhi Fire Service for the period 1989-1997 (Ex. PW 31/DB, PW 33/E , PW
33/H, PW 37/M, PW 37/P, PW 37/U, PW 37/W, PW 37/Z. The Court relied upon the
minutes of MD meeting produced along with Ex. PW-98/X-1, PW 98/X-2, PW 98/X-3, PW
98/X-4.
9.50 Before referring the effect of all these documents and conclusions that can be
legitimately drawn, it would be necessary to deal with Ex. PW 98/X-1, PW 98/X-4 set of
documents.
9.51 At the relevant stage the defence i.e. appellants 1 and 2 objected to their being marked
as exhibits. It has also been noticed during the evidence that some originals of those
documents went missing during the trial. The prosecution sought to substitute the missing
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 445
documents with photocopies. PW 107 testified to having signed upon the seizure memo PW
98/A. The objection to these documents is that to the extent they contain material deemed
incriminating by the prosecution, there should be formal proof. Emphasizing this aspect,
counsel contended that when one of other functionaries of the company, PW 114 deposed
during the trial, none of these documents were put to him for corroboration. Furthermore it
was urged also that the signatures of A.K. Chaudhary who is supposed to have signed on the
covering letters exhibits PW 98/X-1, PW 98/X-2, 98/X-4, the documents were not proved,
nor was any opinion taken by hand writing expert such as PW -92 led during the trial. In
these circumstances neither the evidence of PW 98 nor of PW 107 were sufficient to prove
the contents of the MD's document, it was unsigned and undated.
9.52 In a preceding part of the discussion relating to the mode of proof adopted by the CBI
and accepted by the trial Court, this court had affirmed the marking of the files as collective
exhibits. Such files were recovered from the statutory and official agency, empowered by
law to maintain them in their official course of business.
9.53 The Court had relied upon the provisions in Sections 35, 74, and 76 of the Evidence
Act to justify the production and admissibility of such documents as well as their relevance
by the trial court. However, the same reasoning cannot be applied to Ex. PW 98/X-1, PW
98/X-4 series of documents and their enclosures. The enclosures to these documents which
are critical as far as the accuse are concerned, bear no date and they are also unsigned. They
were rnot ecovered from the custody of an official agency or a statutory authority
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 446
empowered to maintain such documents and someone had spoken about such documents
being maintained in the normal course of official business, undoubtedly they too could have
been considered and their contents, been taken into consideration by the Court. However, if
the prosecution wanted to implicate the accused to the extent these documents seek to portray
the involvement of Sushil Ansal and Gopal Ansal it was incumbent upon it to produce
witnesses who could speak about those documents.
9.54 PW 114 was such a natural witness. For reasons best known to prosecution, these
documents were not put to the said witness. In these circumstances, the Court is of the
opinion that the said document ex. PW 98/X-1, PW 98/X-4 and its enclosures were
inadmissible and their contents not proved in accordance with law.
9.55 That brings this Court to a discussion on the liability cast upon the Accused Nos 1 and
2 for the acts leading to their conviction under Section 304 A, for what they term to be acts
of the company. Firstly they argued that since cinema and the building is owned by
company, which has not been charged and that they were Directors at some remote point of
time liability cannot be fastened on them for something which happened in 1997.
9.56 Speaking about the juristic or artificial personality of a company or corporation,
while considering its relationship with a sister company or dependent concern, Justice
Benjamin Cardozo in Barkey Vs. Third Avenue Railway, 244 N.Y. 84, (1926)
―The whole problem of the relation between parent and subsidiary
corporations is one that is still enveloped in the mists of metaphor. Metaphors
in law are to be narrowly watched, for starting as devices to liberate thought,
they end often by enslaving it. We say at times that the corporate entity will be
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 447
ignored when the parent corporation operates a business through a subsidiary
which is characterized as an 'alias' or a 'dummy.'... Dominion may be so
complete, interference so obtrusive, that by the general rules of agency the
parent will be a principal and the subsidiary an agent.‖
9.57 The problem of fixing responsibility for an offence by corporations or companies has
been grappled with, and has been confronted by Courts for long. In this context in 1972 the
House of Lords in Tesco Supermarkets Ltd. v. Nattrass [1971] 2 All ER 127, Lord Reid,
while considering the question of commission of an offence by a company, ruled as under :
"I must start by considering the nature of the personality which by a fiction the
law attributes to a corporation. A living person has a mind which can have
knowledge or intention or be negligent and he has hands to carry out his
intentions. A corporation has none of these; it must act through living persons,
though not always one or the same person. Then the person who acts is not
speaking or acting for the company. He is acting as the company and his mind
which directs his acts is the mind of the company. There is no question of the
company being vicariously liable. He is not acting as a servant,
representative, agent or delegate. He is an embodiment of the company or,
one could say, he hears and speaks through the persona of the company,
within his appropriate sphere, and his mind is the mind of the company. If it is
guilty mind then that guilt is the guilt of the company. It must be a question of
law whether, once the facts have been ascertained, a person in doing
particular things is to be regarded as the company or merely as the company's
servant or agent. In that case any liability of the company can only be a
statutory or vicarious liability."
9.58 This formulation was approved by our Supreme Court in J K Industries limited Vs.
Chief Inspector of Factories and Boilers, 1996 (6) SCC 665. The Court also cited another
decision, Lennard's Carrying Company Ltd. Vs.Asiatic Petroleum Company Ltd, [1915] AC
705, where the House of Lords held that
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 448
― A corporation is an abstraction. It has no mind of its own anymore than it
has a body of its own; its active and directing will must consequently be
sought in the presence of somebody, who for some purpose may be called an
agent but it is really the directing mind and will of the corporation, the very
ego and centre of the personality of the corporation. That person may be
under the director of the shareholders in general meeting; that person may be
the Board of Directors itself or it may be, and in some companies it is so, that
the person is an authority to coordinate with the Board of Directors given to
him under the Articles of Association.‖
9.59 The Supreme Court in J K Industries was called upon in an analogous situation to
decide whether any director designated as an occupier in terms of the Factories Act, absolved
the directors of any role and whether they could legitimately claim immunity from
prosecution. The Court expressly negatived such a claim. The court also took note of the
decision in the Oleum Gas leak case (M.C. Mehta Vs. Union of India, 1986 2 SCC 325)
whereby the Supreme Court had ruled that
―hazardous or dangerous activities posing a threat to the health or life of
members of the public, Chairman/Managing Director of the company should
be compelled to furnish undertakings, to deal with eventuality of disaster
mitigation through compensation‖.
9.60 The Canadian courts have used ―alter ego‖ doctrine to attribute mens rea offences to
corporations. It was established by a decision of the Canadian Supreme Court in Canadian
Dredge and Dock Co. v. R [1985] 11 RCSC 662 that not only the board of directors would be
seen as the directing mind of a company but also the managing director or any other person to
whom authority has been delegated by the board and that it is sufficient that the act is
committed by a person on behalf of and within the capacity of the corporation.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 449
9.61 Although not directly apt, yet it would be noteworthy to remember that our Supreme
Court, in the five judge decision reported as Standard Chartered Bank v. Directorate of
Enforcement,(2005) 4 SCC 530, rejected the theory of blanket corporate immunity from
serious offences punishable with imprisonment. The argument was that such non-human
actor cannot be sentenced to a prison term, in the case of a non-discretionary sentencing
provision. The court held that:
―We do not think that there is a blanket immunity for any company from
any prosecution for serious offences merely because the prosecution would
ultimately entail a sentence of mandatory imprisonment. The corporate
bodies, such as a firm or company undertake a series of activities that affect
the life, liberty and property of the citizens. Large-scale financial
irregularities are done by various corporations. The corporate vehicle now
occupies such a large portion of the industrial, commercial and sociological
sectors that amenability of the corporation to a criminal law is essential to
have a peaceful society with stable economy.‖
9.62 The factual material discussed above would show that the following decisions are
attributable to the first two accused:-
1) The decision relating to installation of the DVB transformer
2) All decisions relating to re-arrangement of the seating in the balcony, which were held
in an earlier part of the judgment to violate several mandatory provisions of DCR.
3) Closure or blockage of right side exit which effectively blocked the access to the
right side stair case from the balcony;
4) Placement of additional seats
5) Parking contracts
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 450
6) Unlimited financial powers on behalf of the company, to bind it and create
encumberance on its assets;
7) Decisions concerning commercial use of the building;
8) Decisions about the working of the cinema, on day to day basis,
9.63 The first two accused were concededly directors of the company and had engaged
themselves on day to day functioning. Their involvement in the company continued even
thereafter. If one were to take their argument on its face value there was no occasion for
Sushil Ansal to continue being described as a licensee even in 1992 or hold himself out as
such. He not only did so but permitted the company to do so, as well as the statutory
authorities issuing no objections as well as approvals who described the licensee of the
original license No.51 i.e. Sushil Ansal as the licensee or occupier of the cinema hall.
Significantly enough he withdrew a large amount of Rs.50 lakhs in 1995 from the account of
the company. As held by the trial court he was called as a special invitee to attend the
meeting of Board of Directors. He along with Gopal Ansal continued to enjoy unlimited
power to withdraw the amounts and operate the accounts of the company. Both of them were
also authorized right up to the date of incident to operate such accounts and also create
liabilities upon the company's property.
9.64 The position so far as Gopal Ansal is concerned is identical. According to the
Minutes/Board Resolution Book produced in Court Ex. PW 103/XX3, he resigned from the
company on 30.06.1995. He continued to enjoy same powers and almost unlimited powers to
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 451
withdraw amounts and operate accounts of the company. He was not fettered in terms of
accountability to the company for the moneys withdrawn and utilized by him. Further to this,
in at least two instances the bank accounts were operated ostensibly for the personal use of
the Gopal Ansal have been placed on record.
9.65 The licenses even after the name of GPT changed in 1996 continued to remain that of
the original license i.e. Sushil Ansal as is evident from Ex. PW 69/CC dated 16.12.1996. The
letter dated 06.03.1997 by the licensing authority merely records that Shri R.M. Puri and Shri
K.L. Malhotra would be authorised signatory for the company for operating the cinema and
for dealing with the licensing authority. These cannot led to an inference that a specific
nomination, in terms of Section 10 (2) was ever made.
9.66 The shareholding pattern of the company, disclosed through the Ex. PW 87/53 A, set
of documents showed that the major/pre-dominant shareholding of the company continued to
remain with the Ansal's family. Sometime Sushil Ansal and his family members were shown
majority shareholders and another time other members of the family such as brothers were
shown as shareholders. However, at no time any outsider was shown to hold any of the 5000
shares. These clearly pointed out that the company was closely owned and completely
controlled by the Ansal's family. The change of name of the company from GPT to Ansal's
Theatres and Clubotels (P) Ltd., likewise seems to be very fluid because since the licenses
renewed and substituting (25.03.1996, 27.06.1996, 13.09.1996, 26.11.1996) till the date of
the incident was in the name of GPT as is evident by Ex. PW 69/CC. Furthermore crucially
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 452
the evidence of PW 109 Pranav Ansal, one of the directors of the company as on the date of
the incident as well as PW 113 V.K. Aggarwal, another director discloses their complete
innocence about the affairs of the concern or the cinema enterprise. The minutes of the
company reports filed with the Registrar and produced by him (Ex. PW 87/D-54), the said
Pranav Ansal and V.K. Aggarwal were shown as Directors.
9.67 The depositions of Pranav Ansal (PW 109), according to the records of the company,
was its director from 29.06.1996 till 28.03.1997, Subhash Verma (PW 114) who was a
Director of the company as on the date of the incident, V.K. Aggarwal (PW 113) was the
Director of the Company till 28.03.1997 and Dr. (Mrs.) Kusum Ansal (PW 115) was the
director of the company till 25.03.1996, would show that though these Directors were shown
as having attended the meetings on various dates, according to the minutes book Ex. 103/XX-
3, they were unaware as to the decisions taken empowering some of them such as Shri V.K.
Aggarwal to do certain acts on behalf of the company. PW 109, who according to the
minutes of meeting of Board of Directors was conferred with powers was even in doubt as to
whether he was actually a director in the company. In any event, PW 109 had no idea even
any financial powers were delegated to him and was not aware what were the functions and
duties of a Director. He even claimed being unaware whether Uphaar cinema was being run
by Ansal Theatres and Clubotels (P) Ltd. Viewed from the context of such evidence even on
the date of incident becomes very relevant, as the powers were conferred on these Directors
by Board Resolution on behalf of Ansal's brothers.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 453
9.68 The above analysis would show that the cinema enterprise was established, managed
and controlled by the first two accused, for their benefit and their family. The appointment of
Directors, whose nomination were carefully worded to avoid any reference to Rule 10 (2) of
DCR 1953, and the corresponding rule in DCR 1981, is, in this context, not without
significance. The intention of both first two accused was to remain in control of the company
and the cinema property at all material times. The Court is therefore, satisfied that the
findings of the trial court about the control, management and ownership of the Uphaar
cinema vesting in reality with the first two accused is well founded. They cannot in the
circumstances of this case hide behind the façade or mask of GPT or Ansal Theatres. Thus
the decision of the corporate entity be it GPT or Ansal Theatres Pvt. Ltd., that situation
continued as on the date of the incident.
Whether Section 313, Cr. PC. was complied with as regards Accused No. 1 and 2
9.69 This Court proposes to deal with a contention that the accused Nos. 1 and 2 were not
questioned under Section 313 Cr.P.C. properly and that incriminating circumstances were not
put to them fairly, to elicit their response. The trial court put as many as 846 questions
separately to both the said accused. These ranged from the correspondence pertaining to
initial installation of the transformer, various sanctions obtained for constructing the cinema
hall, change in the plans; permissions obtained from various authorities by the cinema
management from time to time, the change in the seating pattern in the balcony; the
inspection reports by authorities who visited the cinema hall on various occasions; details
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 454
about 1989 fire incident; affairs pertaining to the management of the company; minutes book
of the company reflecting decisions by its Board of Directors; shareholding pattern of the
company; involvement of the Accused Nos. 1 & 2 in the affairs of the company, their letters,
signing of cheques by them, powers conferred upon them; the material gathered during the
investigation and produced by the prosecution, concerning the fire incident t in the morning
of 13th June, 1997, the manner of parking of vehicles; spread of fire from the transformer
room into various parts of the building; the structural deviations noticed and sought to be
proved within the building, which aided the spread of smoke upwards and also obstructed
free egress outside the building. Postmortem reports and expert reports were also brought to
the notice of these accused.
9.70 By Question Nos. 617 and 618 the trial court put the seized file Ex. 100/M that
contained the corresponding leading to installation of the DVB transformer in 1974 to the
accused; by Question Nos. 725 and 726, the building plans 15/Y 1 to 15/Y 16 and 102/C 1 to
102/C 6 were put to the accused. The question Nos 124 to 129 specifically related to
compliance with norms spelt out in Indian Standards of 1967 and 1981, read with Rules 62
and 67 of DCR 1981 and the circumstances as to how there were deficiencies in the DSVB
transformer room. All the expert reports i.e. PW 24/A, 25/A, 35/A, 36/A, 48/A, 64/D and
83/A were put to all the accused. The details of what these experts stated in their reports
were also put to the accused; similarly details of seized matter, described in these reports
were specifically put to the accused (Question Nos. 104 to 112, 138 to 149, 204 to 214, 277
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 455
to 304). By question Nos. 8 to 13, 265 to 276, 166 to 170, 65 to 69, 56 to 62, 79 to 83 and
171 to 179, all concerned to structural deviations within the cinema building and the various
unauthorized built up areas, including obstruction noticed during the inspection in the various
reports Ex. 2/A, 17/B, 29/A, 39/A, 16/E, 17/G including maps and sketches prepared during
the inspection carried out after the accident were all put to the accused Nos. 1 and 2.
Questions 415 to 418 related to the car parking arrangements, the cinema had with PW 56, it
also included parking contract. Question 680 was the parking contract dated 01.04.1988
seized by memo PW 56/C. By question 803 to 834 and 551, 580, 604, 648, 649, 656, 657,
757, 760, 775, 764, 767, 796 to 802 related to the ownership and the management of M/s
GPT (which was later re-named as Ansal Theatres and Clubotles Pvt. Ltd.) Question No.486
puts Ex. 69/A the file containing 427 pages was put to both accused, this document was later
marked as Ex. 69/AA. Question Nos. 379 to 381 and 382 to 385 related to the application for
renewal of cinema license submitted on behalf of GPT; Question Nos. 737 to 739 pertained to
the concerned provisions of the Cinematograph Act Sections 12, 14 and 16 and the
circumstance that closure of gangways violated the norms. Question Nos. 740 to 749 related
to various developments that led to changes in the seating pattern in the balcony including the
installation of eight seater box, closure of one gangway, installation of additional seats,
closure of right side exit and violation of DCR 1953. Question Nos. 361 to 369 related to fire
safety norms, which the cinema was bound to follow.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 456
9.71 As noticed in the discussion on the preliminary legal issues and objections raised by
the accused, the object of Section 313 is to afford a fair opportunity to the accused to set forth
his position and furnish an explanation to any incriminating material put to him. The law
enunciated by the Courts is that every incriminating circumstance, discerned by the Court
should be put to the accused in a comprehensible manner. The standard indicated is as if the
accused is an illiterate and an unlettered man. In other words the Courts obligation is to put
all circumstances, and indicate them in a simple and understandable manner. Any complaint
about failure of the Court will have to be seen from stand point of prejudice, in the
circumstances of each case, in the light of these principles. The terminology used in Section
313 ―generally‖, has been construed as one meaning that all incriminating aspects have to be
generally put to the accused.
9.72 When examining the arguments of accused about non-compliance with Section 313,
the Courts have to see and be satisfied that the examining court put all incriminating and all
relevant material to the accused. If any material not put to the accused, is used for arriving at
a finding, that would be vitiating factor. In this case the extensive questioning under Section
313 adopted by the Court was doubtless cumbersome; no doubt the accused were asked to
respond to several bulky documents. Apparently such questioning consumed a lot of time.
However, the appellants in the opinion of the court have not been able to pin point how this
method of questioning affected them or resulted in the trial court's finding suspect. One
cannot be unmindful of the fact that the accused are well educated and successful
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 457
businessmen, they are also fairly conversant in English. The responses given by them in
answer to several queries show that they understood the Court's line of questioning; they
even claimed knowledge about Delhi Cinematograph Rules 1953 and Delhi Cinematograph
Rules 1981. If for any reason they were under any misapprehension, surely they could be
well sought clarification as to the meaning of the question from the Court. The queries
recorded nowhere disclose any doubt in the mind of the accused or that the method of
question was incomprehensible to them.
9.73 In these circumstances although the procedure adopted by the trial court may be
considered cumbersome, that itself in the opinion of this Court is insufficient to render the
line of question under Section 313 Cr.P.C. suspect or hold that finding and conviction of the
accused Nos. 1 and 2 were for such reasons vitiated. The contentions of the accused Nos. 1
and 2 on this score are, therefore, devoid of merits.
9.74 The most crucial decisions of the company which had direct link with the deaths of 59
patrons and grievous injury to 100 others, are beyond any question or doubt, attributable to
the first two accused. Thus:
(1) the decision to install a DVB transformer contrary to sanctioned plan and
without permission or approval of the licensing authority and the MCD;
(2) absence of fire safety measures within the transformer room again contrary to
regulations;
that reduced the number of gangways, correspondingly increase the seats and
also crucially blocked the right exit
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 458
(7) failure to ensure proper supervision within the cinema at the time of the show,
contrary to the mandate of DCR 1953 and DCR 1981
(8) failure to ensure functioning fire safety equipment that would have at the time
same warned the patrons to leave the cinema hall immediately upon the
outbreak of fire or an emergency and also facilitate their escape through
proper lighting;
were directly attributable to the first two accused as owners and occupiers of this cinema hall.
Their duty of care towards patrons and visitors did not end with any approval granted by one
or the other statutory authority either upon a request or in a routine manner. The duty of care
both in terms of the Cinematograph Act, Section 12 and in terms of DCR 1953 and DCR
1981 continued, for the duration of each show. That duty did not decrease or vanish merely
because some employee was expected to be present, at the relevant points. When a large
body of persons such as cinema viewers are closeted in a fully enclosed space having limited
exits and who were virtually entrusting their life and well being to owners of the cinema, who
effectively managed it, the duty of such owners is a very high one, even in the normal
circumstances. In this case the risk factors kept increasing with each departure from the
norms. Thus, the installation of the second transformer without authorization, an illegal act
itself, increased the risk so far as patrons were concerned. Similarly outsourcing the parking
to someone without any operational control or no direction created a further hazard. The
closure of right side gangway, decrease in the number of gangways, increase in the number of
seats, all in the balcony and the blockage of the right side exit, ―stacked‖ these risks to
unacceptable proportions.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 459
9.75 Being prudent entrepreneurs, the first two accused should have ensured that there was
no compromise, with any safety measures that would have imperiled the lives or health of
any member of public. Instead the installation of seats blocked the right side exit and the
consequent decrease in the number of gangways, were all at their insistence. Similarly the
decision to place the eight seater box and permanently block the right side exit, increased the
risk enormously. If one viewed one decision in isolation from other it could arguably be said
that there was no danger. Yet each decision had to be seen in its aggregate or cumulative
form. Thus, the most important decision to block the right side exit, which rendered the right
stairwell inaccessible, was inherently dangerous. It also, in the facts of this case, constituted
the foundation for stalking of all subsequent risk factors, which aggravated the danger. All
these cumulatively amounted to rash acts which given the outbreak of an emergency - be it a
fire incident or something else needing immediate and speedy evacuation of patrons, would
have in all probability resulted in casualties. That such an accident did not take place for a
long period of time is no excuse for the danger from the cumulative effect of these
deviations. Likewise the fact that someone on the fateful day had bolted one or the other
door may be another act of negligence on his part. This, however, did not deflect from the
inherent dangerousness of the situation that existed within the balcony on that day. The
Accused 1 and 2 could not under any circumstance have claimed ignorance of these
established facts, or that this should not have reasonably occurred to them also because the
two family boxes were placed in the cinema hall for their families exclusive case. The
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 460
second box was installed in 1978; it blocked the right side exit, of the viewers. These boxes,
interestingly, had independent exit/entry points - the appellants were at pains to contend that
they were not part of the balcony. The omission to maintain fire safety equipments in proper
order or its unworkability at that time similarly might have contributed as another act of
omissions. But the evidence clearly shows that patrons experienced difficulty in leaving the
balcony; it was pitch dark, dense and thick smoke choked them. Many of them were
exposed to this for as many as 15 minutes before they could leave the balcony. Some of them
who did, came out and deposed. That there is no direct or primary evidence to say that the
blockage of the right side hindered movement or that existence of less than prescribed
number of gangways and placement of additional seats hindered or obstructed the patrons,
again is no consideration. If one visualizes the situation which existed then, and keeps in
mind the evidence of witnesses such PW 49 who deposed that three dead bodies were taken
out of the balcony around 5.45 PM, the inherent and unacceptable nature of the danger posed
by these deviations stands fully established.
9.76 The accused Gopal Ansal and Sushil Ansal undoubtedly were not present in the
scene. The question, however, is not of the presence of actor at the scene of occurrence. In
such cases the Court invariably sees the role played by the accused who caused the event.
Thus in Bhalchandra's case and Rustam Irani's case (supra), the Supreme Court did not feel
any hesitation in convicting the owner who was not present at the site when the fatal accident
occurred.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 461
9.77 The lack of effective safety measures and the omission by the first two accused to put
in any means of rapid evacuation is further heightened by the fact that an almost identical
accident had occurred at the very same place i.e. transformer room in July 1989. A reading
of the fire report recorded then which is part of the prosecution chargesheet and documents
proved in this case. Ex. PW 88/B establishes that the hot gases escaped and spread up into the
cinema hall which had to be evacuated. Then as in the instance of June 1997 the fire brigade
had to rush in as many as 40 fire tenders and it took nearly two hours to control the fire. This
incident should have served as a warning bell and the Accused Nos. 1 and 2, unfortunately it
did not.
9.78 Apart from the decisions of the Supreme Court, mentioned above and discussed in the
preceding part of this judgment, the duty of owners and occupiers of lodging houses and
establishments have been discussed in two English judgments. Thus in R.Vs. Gurphal Singh,
1999 Crim LR 582, one Foster, a lodger who stayed in the accused's lodging house died on
account of carbon monoxide poisoning. The poisoning was caused by room fire. A chimney
in the room should have acted as a flew, it did not, since it was blocked. The chimney in the
neighbouring room too had been blocked. Resultantly the carbon monoxide, instead of
escaping of the chimney remained inside and killed the lodger. It was argued that on behalf
of the lodging house owner, the appellant that his acts or omission if one assuming there to be
one was not proximate one which led to the death of the lodger. Citing Caparo Industries Vs.
Dickman, 1990 (2) AC 605, the Court held that the greater the awareness of potential for
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 462
harm the more likely it is that proximity test would be satisfied. It went on to hold that the
proximity test focuses on broader relationship between the parties. After proceeding to hold
that what had to be looked at
―is the totality of the situation and when considering whether or not a duty of
care existed, it is not appropriate to stay out each part of that situation and
then to consider, absent all the other parts there would be a duty of care. Nor
is it useful in this context to concentrate on the phrase ―assumption of
responsibility‖.
―....... In substance this is a case where those living in the room in which Mr.
Foster died in a lodging house managed by Singh family. They were led to
believe that the appellant and his father would take care that they were not
poisoned by equipments provided by the family. The appellant was possessed
of sufficient information to make him aware of danger of death from gas. He
may not have had sufficient skill to be able to discover how the danger arose
but he was responsible for reasonable space to deal with that danger if need
by calling an expert help.‖
9.79 The other decision H & N Emanual Ltd.Vs. Greater London Council and another,
[1971] 2 All ER 835, was a case where one King and his employees lit a bonfire to get rid of
rubbish, when, they were removing two pre-fabricated bungalows. That job had been
contracted by them from the London County Council, owner of the site. Sparks from the fire
flew over to the adjacent premises belonging to Emanual and burned them down. The latter
sued the Council, which had contracted the job since the contractor was not possessed of
means to satisfy the claim. After tracing the law from 1401 onwards Lord Denning held that
Council could not escape liability and could be sued since it was the occupier. It was held
that an occupier or owner in law is liable for escape of fire due to his negligence not only his
servants but also his guests or anyone there with his leave or license. The only exception
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 463
drawn for immunity from negligence is whether the escape is caused by a stranger. The
Court in the course of its judgment described an occupier, for the purpose of fire as follows :
―Any person was an occupier for the purposes of fire if he had a sufficient
degree of control over the premises and could say with authority to anyone
who came there, ―Do or do not light a fire,‖ or ―Put out that fire‖. If he
could, he was liable for negligence on the part of any person who came
there.‖
9.80 In this context of what is reasonably foreseeable, Justice Cardozo in ―Palsgraf v. Long
Island Railroad, 248 NY 339 stated that:
―If no hazard was apparent to the eye of ordinary vigilance, an act innocent
and harmless, at least to outward seeming with reference to her, did not take
to itself the quality of a tort because it happened to be a wrong, though
apparently not one involving the risk of bodily insecurity, with reference to
some else..., Even then, the orbit of the danger as disclosed to the eye of
reasonable vigilance would be the orbit of the duty.‖
9.81 The duty owed by theater owners to patrons, was spelt out in Rosston Vs. Sullivan,
278 Mass 31 (1931), where it was held as follows :
―the general duty to use ordinary care and diligence to put and keep this
theatre in a reasonably safe condition, having regard to the construction of
the place, character of the entertainment given and the customary conduct of
person attending‖.
9.82 This was affirmed in Helen Upham Vs. Chateau De Ville Theatre Inc 380 Mass 350
(1980). In Mostert V. CBL & Associates, et. Al., 741 P.2d 1090 (Wyo. 1987), the court had
the opportunity to determine the nature and scope of the duty of care owned by a theater
owner to its patron, against the factual backdrop of a 1985 severe thunderstorm and ensuing
100 year flood which hit the City of Cheyenne. The court held that the theatre owner as
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 464
business ―invitor‖ owed its patron as ―business-invitee‖ an affirmative duty to exercise
ordinary case for the patron's safety not just inside the theatre but also including an
obligation to advise the patron of off-premises danger that might reasonably be foreseeable.
The Supreme Court of Canada too in Brown V. B & F Theatres Ltd., (1947) S.C.R. 486,
recognized that a theatre owner owed a duty of care to the patrons, and was obliged to take
reasonable measures to ensure their safety. Though some of these decisions were rendered in
the context of civil action, yet they are useful guides in discerning the nature of duty owed
and the extent of reasonable foresight that can be attributable to the concerned actor. Our
Supreme Court too has recognized situations where the standard of duty of care cast upon one
entrusted with safety of others, is higher than in normal circumstances. This was so stated in
M.S. Grewal Vs. Deep Chand Sood 2001 (8) SCC 151 where the dutyof care towards pupils,
off premises was held to be greater than normal whn they were taken on picnic by the school
establishment.
9.83 The first two accused who were instrumental in increasing by each decision taken
over a period of time, the risk elements which ultimately caused several deaths and grievous
injury, owed several duties that was spelt out by specific rules. That they are culpable for the
breach of such Rules and Regulations, in another enactment does not in any manner preclude
the examination by the Court, the consequence of such action. Section 26 of the General
Clauses Act, 1897 provides that where an act or omission constitutes an offence under two or
more enactments, offenders can be prosecuted and punished under any one of those but not
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 465
punished twice for the same offence. Therefore the act which constitutes an offence under
two separate laws can be proceeded with together but not separately.
9.84 If the consequence of breach of the Cinematograph Act is spelt out by Section 14, that
does not end the matter because the resultant breach of duty may be of such magnitude as to
constitute a grave offence dealt with under the general Penal Law. As long as the necessary
elements that constitute such general offence are satisfied, the Court will be unconstrained for
the prosecution of a lower penalty by the particular law which in this case is Section 14.
9.85 Thus the duty element in this case is spelt out in unambiguous terms by various norms
contained in Ist Schedule of DCR 1953 and DCR 1981. The duty as occupier to ensure fire
safety was also clearly discernible under Section 12, which enacts an over-riding statutory
concern in such matters. The decision to take measures that ultimately hindered escape of
patrons exposing them to hot noxious gases which resulted in death was both a rash and
negligent. The appellants contention of lack of reasonable foresight in such circumstances,
cannot be accepted. In this context, although the legislature and rule making authority have
used the expression ―fire safety‖ nevertheless the concern is for the safety and security of the
patrons. That the fire did not reach the balcony is irrelevant. What is relevant is that all fire
safety measures which would have assisted in rapid evacuation and dispersal, utterly and
miserably failed. More than half the people in the balcony were affected; 59 died; 3 bodies
were recovered from the balcony by the fire officials.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 466
9.86 As far as argument that the cause of deaths were not attributable to the accused since
they could not have foreseen fire in the transformer which were made to be maintained and
kept in proper repair by DVB's concern, that does not in any manner lessen or eliminate the
role of the appellants. The appellants were instrumental in allowing the DVB to install the
transformer; they also knew about its potential for harm when fire broke out in 1989. Then
also hot gases entered the cinema hall and patrons were evacuated. Miraculously there was
no harm. However, this warning was not heeded and instead the DVB proceeded to install a
transformer of higher capacity. As men with reasonable foresight having regard to the
propensity of such transformers to create harm, the first two accused could have taken
appropriate steps and prevented the installation of the DVB transformer. After all, the
cinema hall had proceeded to challenge the license suspended in 1983, due to concerns of fire
safety. This fire outbreak should have underlined that concern. No doubt, the authorities do
not seem to have approached the Court for variation of the interim order. However, the
accused 1 and 2, as men of foresight, could have approached the Court and resisted the move
to install the DVB transformer of a higher capacity. This omission to take any steps was
crucial. Rule 23, DCR 1981 (which corresponded to Rule 21, DCR 1953) mandated that after
the outbreak of any fire, before any alteration, intimation about the change had to be given to
the licensing authority - about the change, and approval sought. This incident of 1989
afforded an opportunity to inform and seek evaluation of all authorities, about fire safety,
specifically in the context of the DVB transformer which had caused the fire. Rule 23(4)
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 467
mandated evaluation of all electrical equipment, and change. There is none, forthcoming,
about the DVB transformer. All acts - at least letters written to the fire department suggests
that the cinema management were more concerned with the recovery of their monetary
damages to their transformer and were content with that. This instance shows that there was
a real and live danger in the parking lot which the appellants were aware of; they could also
be reasonably expected to know about similar dangers. The appellants also knew that the
entire parking lot had been given to a contractor, two transformers were located in the ground
floor area where vehicles used to be parked. Both these were in their premises and some parts
of it (crucially those areas where the transformers were located in the parking area) were not
within their effective control. They had a greater responsibility, therefore, to ensure that such
areas were managed effectively and efficiently so as not to pose any danger or threat to the
patrons. Their failure on that score is also an act of rashness and negligence.
9.87 In another preceding part of this judgment the Court has held that these accused could
not have banked upon the certificates and approvals issued periodically by the statutory
authorities as they could not be taken in face value. The inspections, by the licensing
department and the fire authorities as also the electrical inspector, completely glossed over
the inherent danger which the patrons were exposed to on account of various factors.
Therefore, in keeping with the decision in Raj Kapur's case (supra) and Barik's case (supra)
those certificates are of no use to the appellants, in their submission that Section 79 intercedes
to their benefit. Their acts of blocking the right side balcony exit, blocking the right side
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 468
gangway and the decrease in the number of gangways in the placing additional seats, all
cannot be termed as acts of good faith.
9.88 As far as the argument regarding acts or omissions by the employees of Uphaar such
as Uniyal or managers are concerned, attractive through such contention is, they do not
detract from the magnitude or significance of the acts and omissions of the accused 1 and 2.
The bolting of doors, and absence of a gatekeeper caused greater hindrances. However, in
the larger context of causation it did not eliminate the essential cause for which accused 1 and
2 were squarely responsible, which they have ample time to eliminate.
9.89 It was argued that sustaining the conviction of accused Nos. 1 and 2 would be a
travesty of justice, and the Court would be setting impossibly high standards for men with
reasonable prudence and foresight, who carry on their enterprise through employees and
managers. It had been urged that such high degree of responsibility, based on an extremely
low threshold or standard of liability would be inappropriate in criminal law, since invariably
courts would be unable to draw the line. It was stressed that the ―reasonable foresight‖ and
―proximate and efficient‖ standards are settled and time tested, and any variation to suit the
facts of this case would be doing violence to the law.
9.90 This court has given its most anxious consideration to the submission of the accused.
It is often said that decisions are dictated by the facts proved and the attendant circumstances.
As noted earlier, the facts here have highlighted complexities which have perhaps not
confronted Indian courts, or at least have not been dealt with in reported cases. While the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 469
judgments cited by the appellants on proximity and forseeability are undoubtedly binding on
this count, yet the reported decisions do not limit the meaning of these concepts. Section
304 A IPC speaks of a ―cause‖. It conveys the concept of causation. Proximity can be seen
as an important factor directing the mind of the Court, and conveying that not all possible
causes, but those which are substantial or significant to the event, have to be considered. The
preceding section discussing the law has elaborately explored decisions from India, and other
jurisdictions on the issue. As held by the Supreme Court, there is no fixed point on the graph
at which the law requires people to take account of a possibility. The law in India -
discernible from the judgments discussed earlier, does factor for such liability of owners, or
occupiers of buildings, who might in a sense not be ―directly‖ involved with the incident.
Nevertheless casual responsibility has been fastened for breach of duty of care, and
consequent conviction for criminal negligence, if the act or omission is significant or
operational.
9.91 In the complexities of the modern world, where enterprises and large operations are
carried out at different levels and simultaneous acts, by different sets of people leading to one
or series of connected acts take place, the proximity test as suggested by the appellants would
only limit the law, where the text itself does not. This Court, by upholding the findings of the
trial court is for these reasons, in no manner diluting the standards for judging criminal
negligence liability.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 470
9.92 Causation and proximity as considered in this judgment are not inflexible points
capable of only the meanings suggested by the appellants. This Court is also satisfied apart
from their being no dilution of standards that entrepreneurial responsibility for purpose of
criminal liability has not been elevated to impossible or unreasonable levels. So far as the
question of being unable to draw the line is concerned each decision cited in this case points
to the inherent elusiveness and imprecision in defining what constitutes criminal negligence.
Every term is but an indicator and the courts have to be alive and keen of the different
elements that combine to fasten criminal negligence liability in a given case. As long as
there is awareness of these elements and the Court is conscious about the standard of proof to
be met with by the prosecution i.e. beyond reasonable doubt, there is no question of any
confusion about norm or blurring of lines. Each case, through its set of facts and
circumstances uniquely presents its own ―lines‖; this one is no exception. As held in Mayor
of Civil Court Vs. Moressa [1893] 1 QB 359,
―the Attorney - General has asked where we are to draw the line. The
answer is that it is not necessary to draw it any precise point. It is enough for
us to say that the present case is on the right side of any line that could
reasonably be drawn.‖
9.93 In the circumstances the trial court's finding about the conviction of Sushil Ansal and
Gopal Ansal under Section 304 A read with Section 337, 338 and 36 of IPC and Section 14
of Cinematograph are justified. The conviction is, accordingly affirmed.
X CRIMINAL APPEAL NOS. 45 & 46/2008 N.S. CHOPRA AND R.K. SHARMA
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 471
10.1 The charge against accused/ Appellants R.K. Sharma and N.S. Chopra (as well as A.K
Chaudhary since dead) was that they, on 13.6.97 at Uphaar cinema, committed culpable
homicide not amounting to murder by causing death of 59 persons/p atrons beside
simple and grievous hurt to about 100 persons/patrons who went to view the movie '
BORDER ' during the matinee show; that by their acts and omissions fire took place inside
the transformer installed in the cinema building and highly toxic gases generated inside the
cinema and spread inside the theatre. They were also charged with failure to inform, alert and
facilitate the patrons seated inside the theatre to escape from inside the building and it was
alleged that their act was in violation of rules; knowing that their acts was likely to cause
death or such bodily injury which was likely to cause death and they, committed an offence
punishable U/s 304 r/w 36 IPC.
10.2 As evident, the prosecution charged several acts against these set of accused. The first
was that their acts and omissions led to fire in the transformer room, and resulted in spread of
smoke and toxic gases, in the balcony. Two, they were charged failure to inform, alert and
facilitate the patrons seated inside the theatre to escape from the building. The court charged
them with knowing that their acts and omissions was likely to cause death or bodily harm
likely to result in death. The trial court found the two accused guilty as charged.
10.3 The common argument of both appellants is that the prosecution was unable to prove
how they had knowledge that any act or omission of theirs would lead to death, or cause such
injury as would have inevitably resulted in death of patrons. It was also urged that the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 472
prosecution failed to prove that they had fled from the scene immediately after the
occurrence, as charged. The findings, therefore, were challenged as unfounded in fact.
10.4 The evidence relied upon by the trial court to convict these set of accused was Ex.
PW-98/B, an Attendance Register for the months of May and June, 1997. This records the
name of R.K. Sharma as reporting at 8-00 AM, on 13-6-97. The remuneration register Ex.
PW.108/DB corroborates this position. However, Ex. PW-98/B does not show that N.S.
Chopra had attended his duties on 13th June, 1997.
10.5 PW-63, the Security Guard, PW-85 Bagde, the Operator, PW-97, a Gatekeeper and
PW-52, Sumer Singh, a police constable, all mention that both Chopra and Sharma were
working as Managers, at the relevant time. The letter 22-2-1989 (in file Ex. PW-98/C)
addressed to the licensing authority, by the GPT Ltd, says that Chopra and Sharma were
Manager nominees of the company.
10.6 The above discussion would show that what the prosecution could prove was that
Chopra and Sharma were Managers of the cinema hall. They were also shown to be
managers, in the letter written by the company, to the licensing department. Witnesses spoke
about their position as Managers. The documentary evidence pointed to the presence of
accused Sharma, from 8-00 AM in the morning. However, N.S. Chopra's presence is not
established, through any material, or witness.
10.7 The prosecution, however, has not been able to prove that either Sharma or Chopra
fled the spot, after learning or coming to know that a fire had broken out, and smoke entered
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 473
in the cinema hall, with the knowledge that a large number of patrons were in the balcony and
the hall. No one has spoken about these accused leaving the premises. PW-70 Azad Singh
mentions that after inquiry, on the evening of the incident, these two persons, as well as
others were arrested. No doubt, the eyewitnesses who deposed during the trial did mention
about absence of anyone from the management, in the balcony to help or guide the trapped
persons leave the premises. Yet, in order to prove the charge of culpable homicide, based on
knowledge of one's conduct, the prosecution had to prove that these accused were present;
that their duty was to be in the balcony at that time, and that they fled that place after
becoming aware of the smoke in the balcony, with the further knowledge that patrons were
trapped inside, and that their conduct would lead to death of others, or grievous injury which
would result in death.
10.8 The Attendance Register shows that the concerned employees, whose presence for the
day was marked, were present. That these two accused were managers is also spoken to by
witnesses. However, these facts do not establish that they were absent from the site, and had
fled it, after knowing about smoke having entered in the balcony. The prosecution thus, has
not been able to prove-
(1) That the said accused fled the balcony,
(2) The approximate time when they left the balcony, or fled the theatre;
(3) The accused fled the balcony after the smoke entered it;
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 474
(4) Knowledge of the accused that their act would result in death of many patrons and injury to
many others, which would result in their death.
(5) The nature of duties of the two accused.
10.9 To convict an accused of culpable homicide, under Section 304 Part II, the
prosecution has to prove that the act complained of was done with the knowledge, with
awareness - of the accused, about the consequence, i.e death or grievous injury of such kind
as would result in death. Even if the accused were found to have been in the cinema hall at
the time of the accident, their role in the transformer fire has not been disclosed, by any
evidence. Further, as noticed earlier, their act or omission and their absence, if assumed, has
not been proved to be coupled with the knowledge, as would inevitably result in death or
grievous injury leading to death.
10.10 The distinction between murder, which is but a species of homicide, under the Indian
Penal Code, and culpable homicide, is described by the Supreme Court in the following
manner, in State of A.P. v. Rayavarapu Punnayya, (1976) 4 SCC 382:
―12. In the scheme of the Penal Code, ―culpable homicide‖ is genus and
―murder‖ its specie. All ―murder‖ is ―culpable homicide‖ but not vice-versa.
Speaking generally, ―culpable homicide‖ sans ―special characteristics of
murder‖, is ―culpable homicide not amounting to murder‖. For the purpose
of fixing punishment, proportionate to the gravity of this generic offence, the
Code practically recognises three degrees of culpable homicide. The first is,
what may be called, ―culpable homicide of the first degree‖. This is the
greatest form of culpable homicide, which is defined in Section 300 as
―murder‖. The second may be termed as ―culpable homicide of the second
degree‖. This is punishable under the first part of Section 304. Then, there is
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 475
―culpable homicide of the third degree‖. This is the lowest type of culpable
homicide and the punishment provided for it is, also, the lowest among the
punishments provided for the three grades. Culpable homicide of this degree
is punishable under the second part of Section 304.‖
10.11 Section 304, first part requires proof of intention to cause death or such bodily harm
as would cause death; the second part requires proof that knowledge existed that such injury
would result in death, or grievous injury likely to result in death. The crucial aspect in both
cases, is the state of mind, i.e ―intention‖ or ―knowledge‖ of the consequence. Proof of such
intention or knowledge has to be necessarily, of a high order; all other hypotheses of
innocence of the accused, have to be ruled out. The prosecution here, glaringly has not
proved when these two accused fled the cinema hall; there is no eyewitness testifying to their
having been in the balcony when the smoke entered the hall, and having left it, which could
have proved knowledge of the likely deaths and grievous bodily injuries. Thus, this court is
of the opinion that proof of these appellants, i.e N.S. Chopra and K.K. Sharma, having
committed the offence under Section 304, is not forthcoming. Their conviction under that
provision cannot, therefore, be sustained.
10.12 The next question is whether the evidence on record is sufficient to sustain conviction
of these accused under Section 304-A IPC. Here, the prosecution has to prove that the acts
complained of were rash or negligent as to have caused deaths, and, in the case of Section
337/338, caused grievous injury to others.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 476
10.13 As far as R. K. Sharma is concerned, the evidence establishes that he had reported for
duty. The attendance register also discloses that he was in the cinema hall, when the DVB
repairs took place at 11-30 AM, since he reported for duty at 8-00 PM. Azad Singh, PW-70
deposed having arresting him late night on 13-6-1997. In his statement under Section 313,
Cr.PC, he contended having left the cinema hall at 4-30 PM. N.S. Chopra, on the other hand,
according to the documentary evidence (Ex. PW-108/DB-1, found in Ex.PW97/C) had not
reported for duty. In his statement under Section 313, he mentioned having reached the
cinema hall at 5-30 PM, and not being allowed inside, since the fire was raging in the
building.
10.14 R.K. Sharma was a manager; he is also adverted to in Ex. PW-98/C file containing the
letter to the licensing department, dated 22-2-1989, whereby his name as a manager was
intimated to the authorities. PW-63 mentions that after the repairs a decision was taken by the
manager to resume the show. As a manager, he could be attributed with awareness about the
fire risk in the cinema, particularly in the light of the 1989 fire incident. However, that by
itself would be insufficient to prove his negligence, for a sustainable conviction under Section
304-A. The duty of care, since he was not owner, licensee or occupier, should have been
clearly proved. There is no charge, under Section 14, Cinematograph Act, against this
accused. The endeavour of the prosecution was to show that they were deemed to be aware of
the dangers that lurked in the cinema hall, particularly the balcony, due to the deviations, and
as manager should have taken reasonable care, supervised the cinema hall and balcony, and
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 477
have been present to guide the patrons to evacuate from the building, when the smoke entered
the balcony.
10.15 The prosecution made no attempt to show the duties of either Sharma or Chopra. The
evidence adduced showed that besides them, there were other managers- this is apparent from
the register Ex. PW-98/B and Ex. PW-97/C. These other Managers, as on 13th June, 1997,
were M/s Rohit Sharma and D.D. Sharma- they were present on the fateful day. The other
two were K.L. Malhotra, and Ajit Chowdhury, both of whom were accused, but died later.
R.K. Sharma is shown to have reported to the cinema hall at 8-00 AM; PW-97 no doubt says
that he was a manager. Apart from that, nothing was elicited from him, or even PW-114
suggestive of whether either of these accused had the duty of supervising personnel deployed
in the gates and exit points. In the statement under Section 313, Cr.PC Sharma contended
that he left the cinema hall at 4-30 PM and that his duties were to ensure that collections (i.e
money collected during shows) were deposited; he claimed to be a Marketing Manager,
unconnected with the operations in the cinema. So far as N.C. Chopra is concerned, the
documentary evidence does not reflect his presence in the cinema hall during the fateful day.
His explanation in the statement under Section 313 Cr.PC. was that he reported for duty at 5-
30 PM, but was not allowed to go in, due to the raging fire.
10.16 The established facts of this case leave no room for doubt that there was a systemic
failure, of colossal proportions, in the management of the cinema. No doubt, there was
supervisory breakdown, without which the gates could not have been left unmanned, and
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 478
bolted, in the manner the events unfolded. Yet, to fasten criminal negligence liability on
anyone, on the basis of his facilitating such acts, due to omissions, or supervisory failure, the
duty element has to be proved; equally the magnitude of breach and forseeability of the
accused have to be established beyond reasonable doubt, through credible and clinching
evidence. No doubt, cinema managers and personnel were not present, according to
eyewitness accounts. Yet, that cannot be the sole basis for convicting either Sharma or
Chopra - in the case of the latter, there is no evidence of his presence and breach of duty. In
the case of the former, even the excluded evidence - Ex.PW-98/X-1 to Ex. PW98/X- 12,
characterized as Minutes of MD's meeting do not refer to either of these accused; they refer
to others specifically by name. PW-97 also does not say that these two accused had the
responsibility of overseeing or supervising what went inside the cinema hall, before, and
during each show or that they had the duty to oversee security measures. The hierarchy
within the cinema hall, crucial in this case, to show whether Uniyal the gatekeeper had to
report to both or either of them, has not been proved. PW-63, who deposed about the morning
incident, merely mentioned that Shri Sharma was present; however, he specifically deposed
about the role of K.L. Malhotra in connection with the decision to start the morning show,
after the DVB transformer had been repaired around 11-30 to 12-00 AM.
10.17 The totality of the above circumstances no doubt points to complete managerial and
supervisory failure in the cinema. Such inaction is certainly culpable, and points to grave
lapses. This undoubtedly was an important and significant part of the causation chain. Yet, to
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 479
convict the accused R.K. Sharma and N.C. Chopra, there should be more convincing proof of
involvement. At best, there is evidence of suspicion of their involvement. Yet, no attempt to
prove that they were present, and did not take any effective measures to evacuate the patrons,
which they were bound to do, in the normal course of their duty, has been made. Mere proof
that these accused were Assistant Manager, and Manager, as on the date of the accident, and
that one of them had reported earlier, during the day, is not adequate to prove that they
caused death by criminally negligent, or rash act. There was failure on the part of the trial
court to notice that the two vital aspects, i.e duty and breach of that duty of such scale, as to
amount to an offence. Their appeals are entitled to succeed. These appellants have to,
therefore, be acquitted of the charges. Their conviction is consequently set aside.
XI. CRIMINAL APPEAL 66/2008 : MANMOHAN UNIYAL
11.1 The Trial Court had convicted the Manmohan Uniyal, the gate keeper of the offences
punishable under section 304 part-ii i.e. knowingly committing an act that would have
caused death. It had reasoned that being a gate keeper, Uniyal was bound to stay at his post
and was duty bound to help the patrons escape and to facilitate their exit from the balcony.
On the basis of oral testimony of certain witnesses, the Trial Court concluded, firstly, that the
doors in the balcony were bolted, secondly, that Uniyal, the gate keeper was not present there
to assist the patrons to safety or indicate at least the means of escape and thirdly that he fled
the scene.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 480
11.2 PW-97, Bharat Singh was a gate keeper in 1997 in Uphaar Cinema. He deposed that
routinely, gate keepers, who were about 14, were on duty from 9 A.M. to 5 P.M. and the
second shift was from 5 P.M. till the end of the show. He identified Uniyal who was in the
Court as a gate keeper. According to the witness, a duty list was prepared and gate keepers
used to depute themselves as to who would be working in the balcony and who would be on
duty in the hall. He identified the signatures of Manmohan Uniyal and his own signatures, at
points A & B in Ex.PW-97/A. Ex.PW--97/B-1-B-20 were also proved by this witness. They
were duty rosters signed by their respective staff. In addition Ex.PW-97/C, an attendance
register maintained by the cinema hall was also proved.
11.3 A look at Ex.-PW-97/B-1 to B-20 reveals that duty slips/rosters for different parts of
the cinema halls had been printed. There were two slips for each day - one for the morning
shift and the other, for the evening shift. Ex.PW-97/A is the duty roster for 13.6.97; this was
seized along with the other duty rosters, on 19.6.97. The other duty rosters Ex.PW-97/B-1 to
B-20 also seized on the same date, are for the preceding 11 days i.e. 2.6.97 to 12.6.97. A co-
relation between these duty slips and Ex. PW-97/C, the attendance register disclose that
Manmohan Uniyal attended on all the 11 days; he consistently worked as the gate keeper in
the balcony in the morning shift. The rosters Ex. PW-97/B-1 to B-20 show that the evening
gate keeper in the balcony was Pitamber Jha. The attendance register would show that
12.6.1997 was the Pitamber Jha's day off. There is no entry on his having returned to duty
on the 13.6.97. The most contemporary document seized at the earliest point of investigation
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 481
thus established that at the relevant point of time, Uniyal was working as gate keeper in the
balcony and that Pitamber Jha who in the normal course should have relieved him on the
13.6.1997 had not yet reported for duty.
11.4 The earlier discussion and findings of this Court have showed that everything was
normal till about the interval and that an explosion was heard ten minutes later after which
smoke entered the balcony. It was urged on behalf of Uniyal that even eye witness accounts
did not pin pointedly state that there were no staff members of the cinema hall and that the
prosecution was unable to establish whether he was a gateman or torchman and further that
he was never identified by anyone. It was lastly argued that Pitamber Jha, his reliever had in
fact reported and that his withholding from the trial, amounted to unfairness since relevant
evidence was kept away from the Court.
11.5 PW-3, PW-7, PW-8 & PW-11, all eye witnesses who experienced the effects of hot
gases and smoke in the balcony, deposed about the exit gates being locked or shut. PW-49
corroborated this when he said that the foyer door had to be forced open by his officers and
that there was lot of heat and smoke. The eye witnesses also deposed that there was no help
in the balcony at that time to assist people escape or at least facilitate or guide them to easily
exit from the staircases.
11.6 Rishi Arora PW-7 deposed that he and his sister were trapped in the balcony for 10-15
minutes and it was difficult to breathe. He also clearly deposed that there was no gate keeper
or torchman, though he admitted lack of awareness as to who were from the management.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 482
He confirmed his version about absence of any help from gate keeper or torchman in the
balcony when the smoke was present. PW-11 also confirmed this and stated that the patrons
near the balcony door had to push it open. The doors were locked or bolted. This witness
also mentioned about efforts by people to get out which resulted in their pushing each other.
11.7 From these eye witness accounts and the evidence of PW/97 who was not cross
examined by Uniyal, as well as the documents PW-97/B-1 to B-20 and 97/C, the prosecution
was undoubtedly able to establish that Uniyal had reported for duty on the 13th of June, 1997;
his duty was in the balcony and that neither he nor others expected to be in the balcony were
present when the smoke was detected there. It has also established that the balcony doors
were bolted and had to be broken open by the patrons; the foyer entry door was broken open
by the Fire Brigade employees.
11.8 The question which arises is whether these established or proved facts amount to the
crime punishable under section 304 part-ii. In order to, for any Court, conclude that such
case has been proved beyond reasonable doubt, it is necessary for it to be convinced that the
accused did that act with the knowledge that it would in all likelihood, result in death or cause
such bodily injury as would be likely to cause death. It is, therefore, crucial that the accused
must be aware or conscious that his act is of such a nature as would in all probability cause
death or such bodily injury which would in all probability lead to death. Undoubtedly the
knowledge of the act on the part of the offender and likely result would not only depend on
what he did but also on the other circumstances.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 483
11.9 The knowledge standard required of Section 304 IPC to lead to conviction should be
of a high order. The accused Uniyal was nowhere proved to know that his absence, or
locking the doors would inevitably lead to death or injury to patrons. The judgments, cited,
i.e. Shamsher Khan, Keshub Mahindra, etc. require such proof of knowledge on his part.
What is proved here is absence, bolting of exit doors, leading to obstruction. That Uniyal
knew that smoke had entered, and yet fled the scene, and that he knew that smoke would
enter the balcony despite which he bolted the doors and left the balcony has not been proved.
11.10 In the present case, the prosecution has been able to (as held earlier) prove that Uniyal
reported for duty; the duty was from the morning; his reliever Pitamber Jha who used to
report for the evening shift was not recorded as having reported. The evidence pointed to this
pattern of shifts for the previous ten days whereby Uniyal worked in the morning shift and
Pitamber Jha in the evening shift. It also proved, through several eye witness accounts that
the exit gates as well as foyer entry gate were bolted or shut and that no gate keeper was at
hand when the smoke entered and the patrons had to be evacuated.
11.11 However, these facts are the opinion of the Court, insufficient to return a finding that
Uniyal abandoned his post knowing fully well that such act would result in death of grievous
bodily injury that would result in death. The charge framed by the Trial Court was that
Uniyal fled from the cinema hall building after getting to know about the fire, without
unbolting the door. This significant leap from the reckless or rash act of bolting the door
(when as many as 300 patrons were present) to knowledge that such act would almost
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 484
inevitably result in death, underlined by the accused' fleeing the site is unsupported by any
manner of evidence.
11.12 No witness testified the precise point when Uniyal left the scene. It is possible that he
left immediately upon seeing the smoke; it is equally possible that he had left the balcony
before the accident and had gone elsewhere. This point is crucial for a finding of guilt under
section 304 part-ii because nature of the crime is dependent on the action or omission
alleged. The prosecution has not even shown when Uniyal was arrested; and whether he was
arrested from the scene. These crucial omissions or gaps in the prosecution, in the opinion of
the Court, have to enure to the benefit of the accused who cannot be convicted of the offences
under section 304 part-ii.
11.13 The above finding in respect of Uniyal is, however, not dispositive of the issue. The
facts as found point a grave dereliction of his duties. His reliever Pitamber Jha had not
reported. Whether Pitamber Jha was himself negligent or whether his evidence was crucial
or not, cannot obscure the fact that Uniyal as the gate keeper was expected to be present at all
times during the show. The prosecution has established that the gates could not be opened as
they were bolted. The foyer gate was in fact broken open by the Fire department officials.
These two i.e. the action in bolting the door (when 300 patrons were watching the show) and
the omission i.e. absence from duty compounded the woes and miseries of the patrons who
found it extremely difficult to escape.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 485
11.14 Section 222 of the Criminal Procedure Code enacts that where a person is charged
with an offence consisting of several particulars, a combination of some only of which
constitutes a complete minor offence and such combination is proved, but the remaining
particulars are not proved, he may be convicted of the minor offence though he was not
charged with it. Section 222 (2) says that :
―when a person is charged with an offence and facts are proved which
reduced it to a minor offence, he may be convicted of a minor offence although
he is not charged with it‖
11.15 The question of legality of conviction by a Court of accused to a charge not made
against him was first discussed in Willie (William) Slaney v. The State Of Madhya Pradesh , 1955
(2) SCR 1140 in the backdrop of Section 535 and 537 of the Code of Criminal Procedure
1898 which corresponds to Section 464 and 465 of the present Code. The Court underlined
that in cases where accused are convicted of offences they are not charged with, the Courts
primary concern should be whether the accused had a fair trial; whether he was aware as to
what he was being tried for and whether the main facts sought to be established against him
were explained fairly and clearly and whether he was given a full and fair chance to defend
himself. If these considerations are fulfilled, the Court may convict the accused of an offence
under Section 222 (2). This was again emphasized in Bhoor Singh v. State of Punjab 1974
(4) SCC 754 where quoting Nanak Chand v. State of Punjab AIR (1955) SC 274, it was held
that the essence of the matter was that the law is not a technically formulae of words but
whether in such cases the substance of the matter was explained to the accused and whether
he understood what he was being tried for. This view has also been followed in other cases,
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 486
such as Kammary Brahmaiah v. Public Prosecutor AIR 1999 SC 775. Therefore, the
Court's enquiry should be ascertained whether the facts which may prove the ingredients of
another minor offence in relation to that which the accused was charged with at the trial have
been proved. While doing so, care has to be taken by the Court to satisfy itself that the
essential facts which constituted the offence must have been put to the accused in his
explanation, during the trial proceedings.
11.16 In this case, it has been held in the preceding part of the discussion that prosecution
was able to establish that a short while after the interval, an explosion took place and smoke
entered the balcony. At that time when patrons tried to escape, they faced obstructions
because the doors were bolted/locked. It is also established that according to the duty roster
for that day as well as the previous 11 days, Uniyal was the gateman. More crucial Uniyal
was not in the balcony at the relevant time when the smoke entered. The prosecution could
not, however, prove that he had left the balcony with the knowledge that smoke had entered it
and the conviction under section 304 part-ii cannot be sustained. However, being a
gatekeeper, it can be reasonably expected that he ought to have remained at his post during
the show, to help the patrons ordinarily and also to attend to them in precisely kind of
emergency that actually arose on that fateful day. Uniyal in answer to question No.3 under
Section 313 did not deny his presence and the show commenced. He, however, stated that
he had handed over charge to Pitamber at 5 PM and that all lights were on and foot lights
were also on. He also admitted in response to question No.14 that 2 or 3 times light went off
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 487
but added that his reliever had joined the duty after which he left the duty at 5 ‗O' clock. He
maintained the same position in answer to question No.27. The other incriminating
circumstances relating to seizure of attendance register, duty roster, slips etc. were all put to
Uniyal. He was thus given full and fair opportunity to answer to the charges.
11.17 The question which has to be considered is whether Uniyal's absence from the
balcony was a rash and negligent act. Being a gatekeeper, he was duty bound to be present at
all times. The ocular evidence establishes that there was no gateman when the time arose for
assistance of patrons. The duty roster slips and attendance register do not corroborate
Uniyal's version of being relieved by Pitamber. Although Pitamber was cited as a witness,
his non-examination in the opinion of the Court did not detract from the petitioner's illegal
omissions. If indeed the appellant felt prejudice it was open to him to move the Court for
examination of such witness. The absence of Uniyal resulted in the doors which had been
bolted being unmanned at a crucial time. All eye witnesses who deposed at the trial and who
had attended the performance, consistently testified to the difficulties in getting out of the
cinema and being exposed to the hot noxious gases. As gateman Uniyal had a duty to care
towards the patrons to ensure the safety in the event of a fire incident or any other untoward
emergency requiring swift evacuation. That duty is a common sense legal duty owed by him
to all the patrons who were watching the cinema performance. Being entrusted with the job
of gatekeeper he could reasonably foresee that in his absence having regard to the conditions
which existed i.e. blockage of right side exit and bolting of doors from within, would have
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 488
gravely hindered the smooth and easy exit of at least 300 patrons watching the cinema
performance. In the event of an emergency, such absence amounted to an illegal omission;
his act in bolting the door and leaving the place was also an illegal act, endangering the safety
and public health of several persons. Both cumulatively endangered public safety and were
rash acts.
11.18 Being a gate keeper Uniyal was expected to act responsibly. His action in bolting the
door was a rash act. He was under a duty not to do anything at any time during the show
which impeded easy access or obstructed the exits. His further absence from the site was also
reckless act being a gate keeper. He could have reasonably foreseen, that in the event of
some emergency, (whether it was through fire or smoke or anything else) which needed rapid
or immediate evacuation of the patrons watching the move in the balcony, it would have been
extremely difficult for them to escape. Equally he could have foreseen that being a
gatekeeper, he was best informed about the exits in the cinema hall. This assumed great
importance because the right side exit was blocked. He could have, were he present, opened
the doors, and guided the patrons to leave through the staircases, for speedy evacuation. This
breach of his duty which hindered the movement of patrons, caused several deaths. It clearly
amounted to criminal negligence punishable under Section 304A; he is also guilty of Section
337/338 read with Section 36 IPC.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 489
11.19 In view of the above discussion, the Court is of opinion that even though Uniyal
conviction under section 304 part-ii cannot be sustained, the materials on record are
sufficient to convict him under Section 304-A read with Sections 337/338 and 36 IPC.
XII. CRIMINAL APPEAL NO. 4/2008: MR.H.S. PANWAR
12.1 The appellant, Mr. H.S. Panwar was charged with causing death of 59 persons and
injury to 100 persons, who were watching the movie in the cinema hall, on account of fire
and the toxic gases through his act and omission in issuing the ‗No Objection Certificate'
without ensuring the provisions for fire safety and means of escape in the cinema hall,
enabling renewal of cinema hall in contravention of the Acts and Rules, which were
negligence not amounting to culpable homicide and thereby having committed offences
punishable under sections 304a read with section 36 ipc. He was also charged with
committing offences punishable under Sections 337/338 IPC. Mr. Surender Dutt, who was
charged along with Mr. H.S. Panwar, died during the pendency of the proceeding. As
discussed in the preceding portions relating to structural deviations, installation of
transformer and inspections, there were several building deviations noticed by the licensing
authority as well as the Fire Department. The earliest deviation noticed was in 1983
(Ex.17/B), which included offices in the top floor. They were again noticed in 1994 and in
the official inspection before the fire, i.e. 06.05.1996 (Ex. PW-16/E). These reports
consistently said that from the fire safety angle, the obstructions in the top floor were
hazardous.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 490
12.2 It has been also discussed that on 09.04.1996, an inspection was carried out; the report
was exhibited as Ex.PW-32/A. A ‗No Objection Certificate' (Ex.PW-32/B) was issued on
18.04.1996 by Mr. H.S. Panwar. A letter (Ex.PW-37/AL) was sent on 20.09.1996 to the
Chief Fire Officer by the DCP (Licensing) requiring an inspection report. This letter stated
that the requisite report from the fire office had not been received by the licensing office.
12.3 Further to the licensing authorities request, an inspection was carried out on
18.11.1996; the report is PW-33/C. It listed deficiencies which included fire extinguishers
requiring refilling; sprinkler system in the basement not operating; storage of wooden planks
in the basement under warning that they should be removed; direction to provide fire safety
measures in the visitor's lounge on each floor, Director office and guest room on the ground
floor parking and directed that footlights in the balcony should be provided. The ‗No
Objection Certificate' was withheld on the ground that the matter would be re-considered
only after removal of listed deficiencies and shortcomings. By a letter dated 28.11.1996, the
Ansals informed fire office that shortcomings had been cured. A re-inspection was carried out
on 22.11.1996. Thereafter, a ‗No Objection Certificate' (Ex.33/B) was sent on 24.11.1997 to
the DCP (Licensing). The re-inspection report stated that fire-fighting arrangements by the
cinema management were seen and some of the fire extinguishers and some hoses were
operated and found satisfactory. Barring this, the ‗No Objection Certificate' did not mention
that all the other deficiencies mentioned in the previous objections dated 08.11.1996
(Ex.33/C) had been cured or rectified. There was no mention of the provision of footlights in
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 491
the balcony or their proper functioning; no mention of sprinkler system in the basement and
that fire safety measures had been provided in the visitor's lounge in each floor.
12.4 The next document is fire inspection note and report of May 1997. The inspection
report/proforma (Ex.31/DD), according to PW-32, Mr. Ashok Kumar, P.A. to Mr. H.S.
Panwar, was filled by him. That report recorded that the various equipments and sections of
the cinema hall were in order from the fire safety angle and latter recommended grant of ‗No
Objection Certificate'.
12.5 The evidence of Mr. Surender Singh (PW-31), Fire Man, is crucial. PW-31 proved
Occurrence Book maintained between 06.05.1997 and 11.06.1997. He identified Ex.PW-
31/A-1, the entry showing departure of Mr. H.S. Panwar for the purpose of inspection. He
stated that the last line was in his writing and that he wrote at the instance of the SDO, who
had called him at his house in June 1997. The words, ―Saath mein SDO‖ was added in June.
That entry showed departure at 10.20 am on 12.05.1997. He also proved entry (Ex.PW-31/B)
which was added later at the instance of SDO, Mr. Surender Dutt.
12.6 The prosecution sought to prove that on 22.12.1996, the date when Mr. H.S. Panwar
had inspected and given approval for issuance of No Objection Certificate, he was on leave.
This was sought to be done by placing on record an extract of his Leave Register (Ex. PW-
88/J). The said Leave Register was seized during the course of investigation through Ex.PW-
88/G. Dy. Chief Fire Officer (PW-88), who deposed in support of it submitted that the Leave
Register was maintained in the normal course of official duties and related to personnel from
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 492
the rank of Station Officer to Deputy Chief Fire Officer. He identified Ex.PW-88/J and his
signature on it. He also deposed that according to the record, Mr. H.S. Panwar was on leave
on 22.12.1996 which was also sanctioned by the Chief Fire Officer. In the cross-examination
on behalf of Mr. H.S. Panwar what was sought to be put to him was that an officer of Fire
Department is on duty for 24 hours and is available in case of need. The witnesses also
deposed in cross-examination that all equipments are not checked during inspection of
buildings.
12.7 This Court has recorded earlier that the inspection reports were issued mechanically;
Ex. 33/D explicitly granted ‗no objection' even mentioning that there was no objection from
the fire safety and means of escape point of view, entirely inconsistent with the mandate of
the gangway rules under Delhi Cinematograph Rules, 1953 and 1981. The last inspection
report dated 12.05.1997 does not show any application of mind to the cinema hall's
compliance with gangway rules, exit rules or other norms concerning fire safety. None of the
inspection reports on the record assessed the impact of transformers and the possibility of two
transformers in the balcony area and possibility of fire hazard in the event of an accident. The
inspection reports (Ex.33/D and 31/DB dated 24.12.1996 and 12.05.1997) crucially are
entirely silent about the concerns expressed in the previous letter on 18.11.1996 (Ex.33/C).
Having recorded that fire sprinklers were unavailable in the balcony area and that the fire
extinguishers in the cinema hall were filled-up, the least that could have been done by Mr.
H.S. Panwar and the others inspecting the cinema was to indicate whether all these concerns
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 493
had been fully addressed to their satisfaction in accordance with the rules. The mandate of
Section 12 of Cinematograph Act, 1952 and the further obligation of the Chief Fire Officer
under Section 6 of the 1986 Act read with Rule 5 is to be satisfied that the building housing
the cinema is completely safe from any hazard connected with fire.
12.8 In the course of argument, Mr. H.S. Panwar had contended that the working of the
Public Address Systems, exit gates and other lights in the balcony were not under his control
as that was the domain of the cinema management. This Court had found that the certificate
of ‗no objection' letters issued on 24.12.1996 and 12.05.1997 as well as the inspection reports
made no record of satisfaction that such electrical appliance had been tested and found in
working order.
12.9 The acts of Mr. H.S. Panwar, who had been inspecting the cinema hall right from
1994, show a completely negligent and rash attitude towards his duties. Without delving into
too deep whether he inspected the hall on 22.12.1996 and assuming contention to be so and in
view of his explanation in response to queries under Section 313 of Cr.PC, nevertheless what
cannot be overlooked is that the ‗No Objection Certificate' completely glossed over the fire
hazard, so glaringly evident due to the second DVB transformer in the balcony area as well as
the exit and the gangways in the balcony which were in clear violation of the norms. The fact
that accused 1 & 2 were licensees or there were others acting as Managers of the cinema hall
did not in any manner undermine Mr. H.S. Panwar's basic duty to record satisfaction on the
basis of the prescribed norms of fire safety. Building Bye law K.8.4 mandated that a
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 494
sprinkler had to be provided, in the area which housed transformers. In the report Ex. PW-
32/D mentioned about a sprinkler which was deficient. That sprinkler was in the ground
floor. There was no sprinkler seized after the event, although 22 fire extinguishers were
seized.
12.10 PW-85 mentioned that he was not trained to operate any fire safety equipment. H.S.
Panwar, in none of his reports, mentioned any details - a prescribed from was filled. The
report Ex. PW-64/D shows that a few extinguishers, sent for testing, were not in working
order.
12.11 The appellant, Mr. H.S. Panwar, as a responsible officer could reasonably be expected
to foresee that any laxity in the enforcement of fire safety norms and mechanical issuance of
‗No Objection Certificate' would result in the licensing authority proceeding ahead and
issuing permits under the Cinematograph Act. The role of the fire department under Delhi
Cinematograph Rules, 1953 as well as the 1986 Act and Rules was, therefore, crucial. The
importance of compliance with these norms was fully within the awareness of Mr. H.S.
Panwar who, on 18.11.1996, refused to issue ‗No Objection Certificate' listing out some
deficiencies. That in fact, held up the issuance of permit. He, more than the other statutory
authorities had to be absolutely satisfied that no fire safety norms were complied and that all
risks foreseeable under rules and otherwise reasonably foreseeable from a reasonable man's
perspective were not present. Yet, he completely omitted to adhere to all norms and in a
routine manner issued ‗No Objection Certificate'. Had he not done so and had diligently
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 495
listed deficiencies, including the fire hazard from the transformers and the fire hazard from
the exit point of view as well as tested the appliances in the cinema hall, the ‗no objection'
could not have been granted. This action has significance and to an important degree
contributed to the tragedy whereby 59 patrons lost their lives and 100 others sustained serious
and grave injuries due to smoke exposure. In these circumstances, the Court is of opinion that
the materials on record justify his conviction for the offences punishable under Sections
304A as well as 337/338 read with section 36 IPC.
on their issuing No Objection Certificates for 1995-96 and 1996-97 respectively. It was also
found that they handed over the certificates directly to Mr. K.L. Malhotra of the Uphaar
Cinema. It was held that the No Objection Certificates were issued mechanically, to benefit
the Uphaar Cinema and were not preceded by any inspection.
13.2 The cinema licenses had to be preceded by inspection of various authorities. DCR,
1953 mandated by Rule 12 states inspection of the cinema hall premises to access structural
and fire safety as a condition for grant of license. Rule 14 of DCR, 1981 prescribed for
inspections of the cinema premises by the electrical inspector, Executive Engineer and the
Chief Fire Officer.
13.3 The expression ‗Executive Engineer' was defined in DCR, 1953, to mean, by Rule 2
(viii) as follows:
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 496
―........in relation to licensing of any place for cinema exhibitions
means the officer holding charge of the Delhi State division of the Central
Public Works Department or such other officer as may be appointed by the
Chief Commissioner to perform the duty of the Executive Engineer under these
rules;‖
13.4 Rule 2 (ix) of the DCR, 1981 was cast in identical or parimetiria terms - it is thus
clear that in terms of the legal obligation to conduct the inspection, the concerned Executive
Engineer of the Central Public Works Department had to inspect the premises. The evidence
of PW-2 on records, in the form of deposition clearly shows that only the Executive
Engineers and the Zonal Engineers (of MCD) were competent to issue ‗No Objection
Certificate'. It is also a matter of record that the appellants, Mr. S.S. Sharma and Mr. N.D.
Tiwari used to deal with trade licenses. He had deposed that inspection was done only when a
new license was issued and that till the second license was issued annually, there was no
inspection. PW-65 deposed that the DCP (Licensing) used to routinely issue two month
license or permits on account of the said order of the High Court without receipt of technical
reports. It has further come on the record that the protocol for coordinating various
authorities's work was sought to be worked out through a statutory notification dated
03.05.1997; PW-39, the Executive Engineer deposed on this aspect. PW -22 deposed without
challenge that the trade department (where the accused Tiwari and Sharma were working)
used to look after licensing of cinema premises for storage of films.
13.5 In this case, the two No Objection Certificates pertain to the periods 01.04.1995 -
31.05.1995 and September 1996 - 31.03.1996. Apart from commenting that the accused Mr.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 497
S.S. Sharma and Mr. N.D. Tiwari acted casually or carelessly without ensuring any
inspection prior to issuance of No Objection Certificate, the prosecution had not substantiated
what were their duties. On the other hand, both provisions of DCR, 1953 (Rule 12) and DCR,
1981 (Rule 14) point to a duty, if at all, on the part of the Executive Engineer, as a technical
expert to assess the structural soundness of the cinema hall premises, certify it and ensure that
it complies with all norms. The curious practice of the designated official, i.e. the Executive
Engineer/Zonal Engineer, who in this case was PW-39 - ―marking‖ the letter for no objection
to officers not authorized to inspect the premises and not empowered to issue the certificates,
was not even examined, much less explained. The charge-sheet had mentioned about a
notification dated 03.05.1994 changing the procedure and the MCD Building Department,
having to inspect the premises annually instead of the PWD. The trial court also found it to
be so. However, no such notification was produced during the trial; on the other hand, PW-
39 spoke to having seen it when his statement was recorded by the CBI. Rule 14, DCR 1981
talks of inspection by Executive Engineer, defined as such official from CPWD. If the
position were indeed different, it is not clear how these accused could have been charged; the
duty was clearly that of the Executive Engineer.
13.6 The prosecution, in order to succeed in its charge of accused Mr. S.S. Sharma and Mr.
N.D. Tiwari having acted with criminal negligence and caused death and serious injury,
should have first established the duty of care either through some enacted law like DCR,
1953 or DCR, 1981 or a general duty discernable in their normal course of official functions.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 498
In addition, the prosecution should have established breach of such duty would have resulted
in a foreseeable damage and death to or in grievous injury to several persons. Unlike in the
case of the Fire Department, the Licensing Department or the Electrical Inspectorate, all of
whom are named authorities empowered to inspect the premises, there is no role assigned to
Administrative Officers of the MCD. The rationale for obtaining ‗no objections' from these
officers has been left unexplained. The prosecution has failed to establish the necessity for
such No Objection Certificate and how without such document, by the Administrative
Officers of MCD, the licensing authority, DCP (Licensing) would not have issued the
temporary permit. Ex. 22/A, the letter by the licensing department is in fact addressed to the
Building department, MCD.
13.7 The materials on record point to the fact that in Mr. S.S. Sharma's case, the No
Objection Certificate at best led to a temporary license for two months, which expired in
1995. In Mr. N.C. Tiwari's case, the license expired in March 1997. The prosecution has not
shown as to whether the subsisting license as on 13.06.1997 was based on a No Objection
Certificate issued by either of these accused. The prosecution has also not been able to
establish whether any competent MCD officer of the level of Executive Engineer inspected
the premises at any point of time. PW-65, ACP deposed about the licensing procedure and
stated that DCP licensing ―depended‖ on technical reports were given by the concerned
department of MCD or NDMC. Crucially, he said that the department had been issuing
temporary license because of stay order of the High Court, and ―non receipt‖ of technical
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 499
reports. This establishes that the obligation to issue the no objection was of the technical
expert in the MCD - a fact clearly known to the licensing department and that the licensing
department issued the permits, routinely without expert reports. It has been established by
the evidence adduced that in 1996, the licensing department had sought for reports from
various agencies, including the MCD. A three member team had inspected the premises on
30.04.1996 and submitted its report (Ex. PW-17/D). According to PW-17, the members of
this team were engineers; the report was marked to the Executive Engineer, PW-39, by
Ex.PW-17/E. This shows that the duty of inspecting premises, according to practice, was of
the Engineering staff; they had to furnish the technical report.
13.8 The materials on record nowhere disclose how, even if it were assumed that Mr. S.S.
Sharma and Mr. N.D. Tiwari breached their duties of care, the breach was of such magnitude
as would have inevitably led to death or grievous injury to several persons and that such
consequence was reasonably foreseeable by them when they issued No Objection
Certificates. No doubt, the issuance of No Objection Certificates and handing them over to
the beneficiary directly was a careless, even callous act. It was also used to be placed on the
record as a prelude to the issuance of the permits. But in the absence of clearly discernable
duty of care and the magnitude of foreseeable damage by these accused, this Court cannot
affirm the findings of the Trial Court and their conviction.
13.9 The appeals of Mr. S.S. Sharma and Mr. N.D. Tiwari are, therefore, entitled to
succeed.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 500
XIV CRIMINAL APPEAL NOS. 21, 33 AND 56 OF 2008: B.M.SATIJA, BIR SINGH
AND A.K. GERA
14.1 Earlier in this judgment, the Court had after appreciating the conspectus of materials
on the record upheld the findings of the Trial Court that the cause of the fire was faulty
repair of the transformer, and violation of the prescribed norms and regulations whereby
blue phase cable was improperly crimped to its socket. The finding that this improper
crimping ultimately led to its detachment to the bus bar, its de-coiling effect and its falling
upon the transformer fin, leading to a slit, as a result of intense sparking/arching was
upheld. The resultant lighting up of transformer fire and its spread into the parking area,
further aggravates into a dense toxic smoke which spread up through a chimney effect and
resulted in chocking of several patrons in the balcony, death of 59 persons and grievous
injury to 100 others has been upheld. The Trial Court convicted appellants B.M. Sateeja, Bir
Singh and A.K. Gera under Section 304 IPC read with Section 36 IPC and sentence them to
undergo imprisonment for 7 years with a fine of Rs.5000/- each and a default sentence of 6
months each.
14.2 The evidence on record establishes that: -
(1) In the morning of 13.6.1997 around 7:00 AM, a fire was reported in the
Uphaar DVB transformer. Information was received by PW-41; PW-47 Munna Lal was
deputed. The entry PW-41/A in the no current complaint register corroborated this; PW-42
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 501
C.J. Singh also deposed about this. PW-46 deposed having switched off the HT Panel and
reported the matter to its office.
(2) PW-40, Assistant Inspector at the R.K. Puram Sub-Station received
information and chocked out program with the appellant B.M. Sateeja.
(3) PW-44 Bhagwandin, a daily wager carried the tool box. He deposed about the
presence of B.M. Satija, Bir Singh and A.K. Gera. He also corroborated that the replacement
of the sockets and cable crimping was done with the aid of dye and hammer. The entire
operation was over in 45 minutes.
(4) PW-24 and PW-64 in their respective reports PW-24/A and PW-64/B clearly
stated about improper crimping and the defect in the manner of repairs conducted on the ‗B'
phase cable while joining the socket. PW/64 and PW/35 deposed that intense sparking of the
kind which happened could lead to slit of the transformer. PW-35 further deposed that such
rupture due to melting as a result of arching can take place within few seconds.
(5) The inspection of the transformer which was conducted on 22.1.1997 showed
that protection relays which were so crucial to precisely guard against the contingencies of
the type which occurred on 13.6.1997 were missing - they are mentioned in PW-40/DA-1
(6) The evidence of senior officials such as PW-48, PW-67 and PW-73 of the
DVB showed that crimping was the proper method of joining the cable. The evidence also
established that crimping machines were available at the sub-station.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 502
14.3 S.K. Behl, PW-48, the DVB Additional Chief Engineer deposed that Assistant
Electrical Fitters/Senior Fitters actually carried out the maintenance and the immediate
officer for getting such work done are Junior Engineer/Inspectors who are responsible in 100
% check of the sub-station. His evidence also points to accused B.M. Satija being the
Inspector of the concerned zone 1601, where the repairs were to be carried out upon the DVB
transformer. This is also spoken to by PW-43 V.K. Gupta who was the Inspector posted at
the Green Park Complaint Centre. He stated that in case of any problem with the 1000 KVA
transformer, it was to be dealt with by the R.K. Puram sub-station department.
14.4 It is clear from the conclusions and preceding discussion that Uphaar Cinema
transformer for maintenances purposes fell in Zone 1601; it was to be inspected on periodic
basis by the concerned Electrical Inspector which in this case was B.M. Satija. After
receiving the complaint, the DVB office deputed staff for emergency purposes, who switched
off the transformer. Later a discussion was held in the office of PW-40 and the planning for
attending complaints of various zones including that of Uphaar Cinema was made. The
evidence also established that B.M. Satija, Bir Singh and A.K. Gera went together; it also
shows that A.K. Gera did not belong to the Zone 1601 but was posted to zone 1603. It has
also been held that since January, 1997 there were no protection relays on the transformer.
PW-64/D also mentioned 5 other deficieinces in the transformer. Apart from the evidence of
experts PW-24, PW-35, PW-64 and PW-26 A.K. Agarwal also concurred with the view about
the manner of start of fire due to improper crimping and the resulting detachment of the cable
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 503
from the bus-bar, melting of the socket, the cable settling down on the transformer fin leading
to a slit on it and the transformer oil which gushed out catching fire. PW-25 in his cross
examination categorically rejected the alternative theory sought to be suggested that the fire
emanated from the parking area and not from the transformer area.
14.5 In view of these established facts, the Court has to now consider as to whether the
improper crimping and the resultant detachment of the cable and socket leading to the fire
and ultimately the smoke was such an inevitable consequence as to have been within the
knowledge of the appellants B.M. Satija, Bir Singh and A.K. Gera. No doubt when the
repairs were carried out those entrusted with the responsibility of doing so were reasonably
expected to be aware that any let up or fault on their part would be extremely dangerous.
Two transformers were located side by side; they were also within the parking area of the
ground floor of the building. However, one cannot be unmindful of the fact that the
transformer did function for about 4 hours seemingly without any problem. The problem
occurred almost by 4.55 PM when the power was restored after shut down. The conduct of
those carrying out these repairs no doubt shows callousness, rashness, and negligence. Yet it
does not show knowledge which would pre-suppose a higher degree of awareness in the
conscious state of mind. In order to succeed the prosecution has to establish beyond
reasonable doubt that the accused knew that in a normal course of events, the consequences
of their actions would be death of the patrons or grievous injury likely to cause death.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 504
14.6 In Shamsher Khan's case (2001 Crl. Law Journal 119), the accused were alleged to
have manufactured and stored bombs. An explosion occurred causing death of 3 persons and
injury to others. Even while affirming that the prosecution had established about the
involvement of the appellant in the manufacturing of bombs in his house, the Court
nevertheless set aside the conviction under Section 304 & 308 IPC. The Court held that to
prove commission of offences punishable under section 304 part-ii, the prosecution should
beyond reasonable doubt attribute knowledge to the accused that death of any person was a
likely consequence of his action.
14.7 Section 304-II covers cases which fall within the 3rd part of Section 299 which defines
culpable homicide not amounting to murder. In this context it has been held that knowledge
as used in the later part of Section 299 (defines the offence and section 304 part-ii) as a term
that imports certainty and not merely probability. As held in Faquira v. State (AIR 1955
All.321), knowledge as contrasted with intention, properly signifies a state of conscious
awareness of certain facts in which the mind itself remains supine or inactive. Knowledge
may be also contrasted with intention which signifies and even more positive awareness
coupled with the desire that the consequence should ensue. Russel on Crime (12th Edition)
states that term ‗intention' used in criminal law denotes the mental attitude of the man who
has resolved to brining about certain results if he can possibly do so.
14.8 It may be useful to analyze certain decisions to discern as to what precisely would be
―knowledge‖ in the context of a given set of circumstances. Thus in S.D. Sons v. State of
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 505
Gujarat (AIR 1991 SC 917), in Madhusudan Satpathi v. State of Orissa (AIR (1994) SC
474) the medical evidence showed that single injury proved fatal and other injuries were
simple although the weapons used were not deadly, the Court inferred that the accused only
had knowledge that their acts were likely to cause death and did not intend to do so, thus
convicting them under section 304 part-ii.
14.9 Similar findings were recorded in cases where single blows on the head were
administrated upon the victim by the accused in the judgment reported as Chamru Budhwa
v. State of Madhya Pradesh (AIR (1954) SC 652). In Willie (William) Slaney v. The State Of Madhya Pradesh (AIR (1956) SC 116) a solitary blow with the hockey stick was given on
the head of the victim by the accused, in the course of a sudden quarrel and heated
arguments. The accused was convicted under section 304 part-ii.
14.10 All the authorities consistently emphasize that the prosecution must prove beyond
reasonable doubt that the accused had the requisite mental awareness and consciousness
about the inevitability of consequences of his actions. In this case what has been proved is
that the repairs were conducted improperly and contrary to law. While there can be no doubt
that an extremely high degree of care is necessary for carrying out such repairs, it cannot
inevitably follow that the accused had knowledge that their departure from such degree of
care, and their improper repairing of the transformer would have inevitably led to the
consequences of death. In these circumstances, it is held that the conviction of the accused
for the offences under Section 304 cannot be sustained.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 506
14.11 The above finding does not, however, end the matter. Like in the earlier part of this
judgment dealing with the Manmohan Uniyal's appeal, the Court should examine whether the
facts proved establish a minor offence, though these accused may not have been charged for
it, and whether they were made aware about such facts, during the trial.
14.12 So far as role of the accused B.M. Satija and Bir Singh are concerned, PW-40 P.C.
Bhardwaj deposed having informed B.M. Satija about the morning complaint. PW-44
deposed that all 3, i.e., Gera, Satija and Bir Singh were instrumental in repairing of the DVB
transformer at Uphaar in the morning of 13.6.1997. Expert evidence in the form of PW-
35/A; Ex.PW36/A all established that the cause of fire was improper crimping of the cable
end with the socket which ultimately detached at the crucial time, resulted in intense
sparking, settling down of the cable on the transformer which resulted in a slit; transformer
oil gushed out, caught fire and spread to the parking area resulting in the improperly parked
vehicles catching fire.
14.13 Objections were taken to Ex.PW-40/A, compliance report said to have been signed by
all the three. The photocopy of that compliance report is spoken to by PW-40, yet the Court
cannot ignore the fact that Satija's signatures on this could not be established by the
prosecution. This document is, therefore, of no use to establish the presence of one or the
other employee.
14.14 The depositions of other witnesses assume importance. PW-40 clearly mentioned that
he had discussed the complaint with Satija and chalked out the programme. PW/44 clearly
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 507
deposed having accompanied Satija, Bir Singh and Gera to the relevant site at Uphar and
witnessing the repairs with the aid of dye and hammer. At one place, he mentioned that Bir
Singh carried out the repair under the supervision of both the officers, in another place of his
deposition, he mentioned that Bir Singh's work was supervised by Satija.
14.15 The evidence of PW-73 and PW 48 establish the role of various officials at the
Inspector/J.E. level. PW-40 also spoke about such responsibility and stated that he had to
inspect the transformer at least once a year, whereas the Inspector had to do it each month.
The entry in the general diary register Ex.40/C for the complaint reveals that the three
accused had carried out the repairs to the DVB transformer in the Uphar Cinema. The other
evidence relied upon by the Trial Court to conclude the involvement of all the officials is
PW-108/AA, a separate compliance report said to have been written by Gera. P.L. Bhardwaj,
PW-40 also spoke that whenever there was a break down, duties were not assigned according
to Zone.
14.16 As stated earlier Ex.PW-40/A, cannot be relied upon for more reasons than one, it is,
firstly a photocopy, the signatures appearing on it could not be established by the hand
writing expert PW-92. His report PW-92/B stated as much. So far as the other evidence is
concerned, what emerges is that B.M. Satija was the Inspector Incharge of the maintenance of
the Uphar DVB transformer. According to PW-40, he had a duty to inspect it every month.
PW-40 also spoke about chalking out the programme for attending the Uphar Cinema
complaint with B.M. Satija. The evidence of PW-48 and 73 further establish that zone-wise
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 508
distribution of the work was the norm followed by the DVB at the relevant time. Ex.PW-
67/DA, a list, listing the officials who worked in the R.K. Puram sub-station between 1989
and September, 1997 does not contain Gera's name as belonging to that sub-station. There is
also evidence on record that Gera was assigned Zone 1603.
14.17 PW-44 mentions that repairs were carried out through crimping by Bir Singh.
Although he does mention Gera's name initially, later he stated that Bir Singh was supervised
only by B.M. Satija. It is also a matter of record that the authorities in DVB had
recommended reinstatement of Gera through PW-48/A. Although some arguments was
sought to be made on behalf of Satija that comments of Bhardwaj was sought for at the
relevant time when he was suspended official, no illegality can be deduced from that score.
The evidence has also established that according to the relevant ISI standards, cables were to
be crimped or joined together with the aid of crimping machine. Expert evidence as to the
cause of fire has unanimously pointed to the improper crimping with the aid of the crimping
machine as the cause for the fire which occurred after 4.55 PM in the transformer room.
14.18 This Court has while discussing the law of negligence and causations dwelt upon
eventualities where causation may contain more than one significant factor. In such
circumstances, unless the Court is convinced that one among the many factors, which may
form part of a single indivisible transaction, broke the chain of causation, the problem would
be viewed from a common sense perspective without segmenting the incident and viewing
each factor independently. Therefore, the fact that deaths occurred somewhere else and not
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 509
in the parking lot, cannot take away the scrutiny of the accused' role by the Court. The
accused B.M. Satija and Bir Singh were proved to be responsible for the proper maintenance
and repairs of the DVB transformer in the Uphar Cinema building. Satija as the Inspector was
Incharge of that transformer and was also under to inspect it each month. PW-44 is
unambiguous about the role of Satija and Bir Singh. PW-48 and 73 also corroborate this as
far as the role of Satija is concerned in the improper crimping. Being experienced employees
and officials, with reasonable skill and competence, the duty of care cast upon them was to
ensure that repairs were of high standard having regard to the nature of the equipment.
Although nothing has been disclosed on the record about the awareness of these accused
regarding the 1989 fire outbreak, yet in the ordinary course, the said two accused could not
have over looked certain important facts such as: -
1. Two transformers existing side by side.
2. Absence of essential safety mechanisms to control the fire in the transformer
room.
3. Location of the transformer being in a parking lot where in a normal course of
affairs several vehicles would be expected to be parked.
4. Any fire incident in the transformer or the transformer room in such circumstances
would in all probability develop or magnify into greater proportions causing grave
danger to the life and public health.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 510
5. At any given point of time during the day, the hundreds of people would be
visiting inside the building maximizing the potential for fire to cause damage
resulting in high degree of possibility of loss of human life or danger to public
health.
6. Protection relays were missing in the transformer, enhancing the danger of a fire
since the possibility of tripping immediately upon a fault stood eliminated.
If one applies the test of reasonable skills and experience, mandated by the law of
negligence, to be possessed by professionals (the term extending to DVB Inspectors, as well
since these set of accused had vast experience of attending to transformer complaints), i.e.,
that in a situation involving the use of special skill or competence, what is to be seen to
determine negligence is not the common reasonable man's skill but the standard an ordinary
skilled man exercising or professing to have that special skill (Ref. Jacob Mathew (supra). On
an application of that test, the only conclusion which this Court can draw is that in such cases
the accused can successfully absolve himself by showing that he had acted in accordance
with the general and approved practice. Here the said accused were unable to point to such
factors. On the other hand their conduct showed a complete and careless disregard to the
dangers that were imminent as a consequence of their negligent acts. As experienced men
with reasonable standards of expertise, they could have foreseen that the most probable
consequence of their acts and omissions would have been a fire within the transformer room
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 511
that had the potential of destroying human life and imperlling public health. They could
have as prudent man prevented it by exercising due care and not switching on the
transformer but reporting that the cable ends sockets could be replaced only after crimping
with the aid of a crimping machine.
14.19 So far as the arguments about immunity to the accused on account of Section 56 of
the Electricity Act is concerned, it may be noticed that that provision enacts that no suit,
prosecution or other proceedings can be maintained against any public officer or any servant
of a local authority for anything done or on good faith purporting to be done under the Act.
14.20 In this case, the sanction for prosecution of the DVB employees has been placed on
record. Although Parliamentary intention was to confer immunity from prosecution and civil
action against public officers acting under the Act, that provision in the opinion of the Court
cannot have blanket application. The basis for such immunity is undoubtedly the good faith
action of an employee. So long as the employee discloses that the acts complained of were
performed by him in due course of
employment and in good faith, he cannot be prosecuted. Section 52 negatively defines good
faith as follows: -
―Nothing is said to be done or believed in "good faith" which is done or
believed without due care and attention."
The facts found disclose that the acts of Satija and Bir Singh cannot be termed as done or
believed to be done with due care or attention. All evidence points to the contrary. The mere
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 512
fact that they did the act in furtherance of their duties is insufficient, therefore, for them to
claim immunity under Section 56.
14.21 In view of the above, this Court is of opinion that though the evidence on record does
not establish that Satija and Bir Singh were guilty of the offence under section 304 part-ii
IPC, it establishes beyond reasonable doubt that they were guilty of criminal negligence and
are punishable under Section 304-A read with 337, 338 & 36 IPC.
14.22 As far as the appeal of A.K. Gera is concerned, this Court is of the opinion that
prosecution was unable to establish its case. The two circumstances put against him were the
evidence of PW-44 Bhagwandeen, an entry in the general diary register made by him and
evidence of PW-40 that there is no assignment of duties in break down situations. On the
other hand, the evidence of higher officials such as PW-48 and PW-73 is clear that Gera
never worked in the R.K. Puram sub-station; his name did not figure in the maintenance of
the Uphar Cinema DVB transformer. The evidence also points to a discussion between PW-
40, who was overall Incharge of the maintenance of the transformer, and accused Satija who
chalked out the programme for attending complaints. It also establishes that there was another
complaint in Zone-1603 which had to be attended to. The evidence further points the A.K.
Gera being assigned Zone-1603. In the reply to queries put under Section 313, Gera
mentioned that Zone-1603 contained 120 transformers and that only in emergencies could
anyone be assigned any duty but otherwise zone-wise allocations were followed for attending
the routine complaints. Speaking about the entry made by the Gera in the general diary
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 513
register, PW-40 admitted that such entry could be made by anyone. DW-3 R.C. Upadhyaya
spoke about the general diary register and the material at site register. This was Ex.100/D.
These clearly pointed to Gera not being assigned the duties or responsibility for maintenance
of Uphar Cinema DVB transformer. Undoubtedly Bhagwandin PW-44 mentions at one place
that Gera was present when the transformer was repaired and he along with Satija supervised
Bir Singh but in the subsequent part of his deposition in the general examination he mentions
that B.M. Satija supervised Bir Singh and makes no reference to the role of A.K. Gera.
Importantly Gera who was under suspension after the incident for some time was reinstated
after a full departmental review as to his role.
14.23 On an overall conspectus of the above facts, this Court is of opinion that though
Gera's presence at site stands established, in the absence of fuller evidence about the role
played by him, there can be no presumption that he played any part in the defective repairs,
carried out without the aid of the crimping machine on the Uphar DVB transformer. Mere
presence when that cannot lead to presumption of involvement of an actor who is not
expected to play any role and is insufficient, in the opinion of the Court, to saddle criminal
liability of the kind envisioned under Section 304-A. To establish that Gera had a duty of
care to ensure that notwithstanding the defective crimping carried out by the employees
competent to do so and that he had an overriding responsibility of objecting to the work done
by them, without proving whether he was there during the entire operation and if so how the
extent of his involvement, the conviction for causing death due to criminal negligence cannot
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 514
be arrived at. Although, there are circumstances which point to Gera's presence, they may
even amount to suspicion of the role played by him, yet such evidence proved are
insufficient to prove the case against him beyond reasonable doubt. In the circumstances,
neither can be he convicted under section 304 part-ii, nor under Section 304-A read with
337/338 and 36 IPC.
14.24 His conviction has to, therefore, be set aside.
XV CRIMINAL REVISION NO. 17 OF 2008: ASSOCIATION OF VICTIMS OF THE UPAHAAR
TRAGEDY
15.1 This revision, under Section 397 of the Code of Criminal Procedure, seeks
intervention of the court, to alter the conviction of Respondent Nos. 2-6, i.e Sushil Ansal,
Gopal Ansal, H.S. Panwar, S.S. Sharma and N.D. Tiwari. The revision was heard together
with appeals of the respondents, against the conviction recorded by the District and Sessions
Judge. The first part of this judgment has dealt with their appeal. By this part, the revision is
proposed to be dealt with and disposed of.
15.2 The revisionists, who are victims or relatives of victims of the Upahaar fire incident,
which claimed the lives of 59 and grievously injured 100 others, contend that the trial court
erred gravely in returning a conviction under Section 304-A IPC, read with Section 337/338
read with Section 36, IPC against the respondent accused. They urge that the evidence on
record establishes that the respondent accused were guilty of section 304, part ii ipc, since
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 515
they had knowledge that their acts and omissions would inevitably lead to the deaths and
grievous injury of several people.
15.3 Shri. K.T.S. Tulsi, learned Senior Counsel for the revisionists urged that although the
trial court had framed charges against the respondents under Section 304-A IPC, read with
Section 337/338 read with Section 36, IPC, yet the court, upon noticing that the evidence on
record pointed to commission of offences of a more serious magnitude, should have exercised
its powers and framed fresh charges, and, after proceeding to hear the accused, convicted
them under section 304, part ii, ipc, on the strength of the available evidence. Reliance was
placed on Section 216 of the Criminal Procedure Code. The said provision reads as follows:
―216 COURT MAY ALTER CHARGE.
(1) Any Court may alter or add to any charge at any time before judgment is
pronounced.
(2) Every such alteration or addition shall be read and explained to the
accused.
(3) If the alteration or addition to a charge is such that proceeding
immediately with the trial is not likely, in the opinion of the Court, to prejudice
the accused in his defence or the prosecutor in the conduct of the case, the
Court may, in its discretion, after such alteration or addition has been made,
proceed with the trial as if the altered or added charge had been the original
charge.
(4) If the alteration or addition is such that proceeding immediately with the
trial is likely, in the opinion of the Court, to prejudice the accused or the
prosecutor as aforesaid, the Court may either direct a new trial or adjourn the
trial for such period as may be necessary.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 516
(5) If the offence stated in the altered or added charge is one for the
prosecution of which previous sanction is necessary, the case shall not be
proceeded with until such sanction is obtained, unless sanction has been
already obtained for a prosecution on the same facts as those on which the
altered or added charge is founded.‖
15.4 It was argued that the evidence on record overwhelmingly established that the first
two accused were in charge of the day to day affairs of the company, which ostensibly owned
the cinema hall. Though they cleverly manipulated the records, showing that they had
resigned from the company, as directors, and also manipulated the shareholding pattern, yet
the fact remained that not a single of the 5000 shares of the company was owned by any
outsider. The cinema license continued in the name of the first accused, Sushil Ansal. Both he
and Gopal Ansal were engaged in the crucial decisions regarding running of the cinema hall.
They also had unlimited power to bind the company financially as well as encumber its
assets, to its detriment, even as on the day of the incidents. The materials produced by the
prosecution also conclusively established that these two accused had on many occasions
withdrawn large sums of money from the company's accounts. Crucial decisions, like
location and installation of the second, DVB transformer, the parking contract, letting out of
the building at once converting it into a commercial complex, and also hindering movement
in the top floor, besides causing obstructions in the lower floors, and most importantly, the
placement of additional seats on the one hand, and compromising all important norms
relating to fire safety, contrary to DCR 1981, were taken at the behest of the said Accused.
They were also aware that an identical accident occurred in 1989; the morning fire on 13th
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 517
June, 1997, should also have served as a warning. Yet, they proceeded to allow screening in
the cinema hall, which led to the catastrophe. They also did not ensure that fire safety
measures were taken, and no management personnel was present in the balcony to assist
patrons, attempting to flee the scene, and escape the after effects of the smoke, which was
choking them. These clearly were pointers to their knowledge about the most likely or
probable consequence of their actions, i.e deaths and grievous hurt to several patrons, thus
making them liable for the offence under section 304 part ii, ipc. Counsel relied on several
documents to bring home the point.
15.5 It was urged that the role of the Respondent Nos. 4 to 6 shows their complete
disregard to the prescribed norms, which mandated that no objections could be issued by
them, after proper inspection of the cinema premises. H.S. Panwar, it was urged, did not even
visit the cinema premises, in December 1996 and was on leave on the relevant date. Besides,
his inspection reports, recommending approval for license, were mechanical, and issued at
the behest of the cinema management, which wanted the renewals without any delay. The
accused did not test the apparatus, whenever he visited the premises; he knew that that
arrangement and re-arrangement of seats in the balcony inevitably, coupled with completely
inadequate fire safety measures, would have resulted in deaths of several patrons and injury
to others. Similar arguments were made in regard to the role of S.S. Sharma and N.D. Tiwari,
who had without even ensuring any inspection of the building or premises, recommended
issue of no objection certificate to the cinema management.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 518
15.6 Learned counsel relied on the judgment reported as Willie (William) Slaney v. State of
M.P.,(1955) 2 SCR 1140, where it was held that:
―Courts have to administer justice and justice includes the punishment of
guilt just as much as the protection of innocence. Neither can be done if the
shadow is mistaken for the substance and the goal is lost in a labyrinth of
unsubstantial technicalities. Broad vision is required, a nice balancing of the
rights of the State and the protection of society in general against protection
from harassment to the individual and the risks of unjust conviction. Every
reasonable presumption must be made in favour of an accused person; he
must be given the benefit of every reasonable doubt. The same broad
principles of justice and fair play must be brought to bear when determining a
matter of prejudice as in adjudging guilt. But when all is said and done, what
we are concerned to see is whether the accused had a fair trial, whether he
knew what he was being tried for, whether the main facts sought to be
established against him were explained to him fairly and clearly and whether
he was given a full and fair chance to defend himself. If all these elements are
there and no prejudice is shown, the conviction must stand whatever the
irregularities whether traceable to the charge or to a want of one.
44. In adjudging the question of prejudice the fact that the absence of a
charge, or a substantial mistake in it, is a serious lacuna will naturally
operate to the benefit of the accused and if there is any reasonable and
substantial doubt about whether he was, or was reasonably likely to have
been, misled in the circumstances of any particular case, he is as much
entitled to the benefit of it here as elsewhere; but if, on a careful consideration
of all the facts, prejudice, or a reasonable and substantial likelihood of it, is
not disclosed the conviction must stand; also it will always be material to
consider whether objection to the nature of the charge, or a total want of one,
was taken at an early stage.‖
15.6 It was argued that the trail court did not take any notice of the application moved by
the revisionists, and that this has led to the accused getting convicted for minor offences.
Learned counsel submitted that under these circumstances, this court should remedy the
situation, and if satisfied that the accused were guilty prima facie of graver offences, exercise
its revisional jurisdiction to cure the injustice, and see that perpetrators of serious offences do
not flee justice.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 519
15.7 The revision was opposed on behalf of the respondents, who urged that the petition
under Section 397 cannot be maintained, after the trial had concluded. It was argued that the
charges against each of the respondent accused had been framed over seven years ago. The
revisionists were also aggrieved by that. Some of the accused were aggrieved by the charges
framed by the trial court; these revisions Crl. R. No. 238 with Crl. R. 175 and Crl. M. 339,
Crl. R. 270 of 2001, were dismissed on September 11, 2001 (Sushil Ansal -vs- State 2002-
(108)-CRLJ -1369 -DEL). Counsel relied on Section 222 of the Code of Criminal Procedure,
which is in the following terms:
―222 WHEN OFFENCE PROVED INCLUDED IN OFFENCE CHARGED.
(1) When a person is charged with an offence consisting of several
particulars, a combination of some only of which constitutes a complete minor
offence, and such combination is proved, but the remaining particulars are not
proved, he may be convicted of the minor offence, though he was not charged
with it.
(2) When a person is charged with an offence and facts are proved which
reduce it to a minor offence, he may be convicted of the minor offence.
although he is not charged with it.
(3) When a person is charged with an offence, he may be convicted of an
attempt to commit such offence although the attempt is not separately charged.
(4) Nothing in this section shall be deemed to authorise a conviction of any
minor offence where the conditions requisite for the initiation of proceedings
in respect of that minor offence have not been satisfied.
Illustrations
(a) A is charged, under section 407 of the Indian Penal Code (45 of 1860),
with criminal breach of trust in respect of property entrusted to him as a
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 520
carrier. It appears, that he did commit criminal breach of trust under section
406 of that code in respect of the property, but that it was not entrusted to him
as a carrier. He may be convicted of criminal breach of trust under the said
section 406.
(b) A is charged under section 325 of the Indian Penal Code (45 of 1860), with
causing grievous hurt. He proves that he acted on grave and sudden
provocation. He may be convicted under section 335 of that code.‖
15.8 It was urged that having regard to the above provision, it cannot be contended that an
accused can be convicted for an offence graver in character than what he was charged with.
Learned counsel submitted that Slaney's case is an authority for the proposition that if an
accused is not charged with Section 34, though ingredients of that offence are made out, he
can yet be convicted.
15.9 It would be useful, before discussing the merits of the revision, to notice the extracts
from the order of this court, dismissing the revision against order on charges. The court held
that:
―In Crl. R. 238/2001 filed on behalf of petitioner-Sh. Sushil Ansal former
Managing Director of M/s. Green Park Theatres Associated Private Limited,
which had built and established Uphaar Cinema, the prayer is to discharge
him of the charges framed against him by the trial Court under Ss. 304-A, 337,
338 read with S. 36 of Indian Penal Code and S. 14 of Cinematograph Act,
1952. In Crl. R. 175/2001 also filed by Sh. N. S. Chopra, Manager of Uphaar
Cinema, the prayer is for discharge. He has been charged by the trial Court
under S. 304 read with S. 36, I.P.C. Crl. R. 270/2001 has been filed by
Association of Victims of Uphaar tragedy with a prayer to charge Sh. Sushil
Ansal and Sh. Gopal Ansal under S. 304, I.P.C. also in addition to the charges
already framed against them.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 521
I have heard Sh. Ram Jethmalani, Senior Advocate on behalf of petitioner-Sh.
Sushil Ansal, Sh. R. K. Naseem, Advocate for petitioner-Sh. N. S. Chopra and
Sh. K. T. S. Tulsi, Senior Advocate on behalf of the Association of Victims. Sh.
Harish Salve, Solicitor General of India has made submissions on behalf of
the State represented through Central Bureau of Investigation.
xxxx xxx xxxx
In the result, all the three revision petitions are held to be without any merit
and are dismissed. The intering orders dated 22-5-2001 stand vacated.
Nothing stated herein shall be taken as an expression of opinion on the merits
of the case pending before the trial Court as the observations made herein are
on prima facie basis and tentative only.‖
15.10 In a recent decision, Sukhram v. State Of Maharashtra,(2007) 7 SCC 502, the
Supreme Court had to consider what was a ―minor‖ offence in relation to something an
accused was charged with. The court held:
―We find that though charge for offence punishable under Section 302 IPC
had been framed against appellant A-1, no such charge was framed against
appellant A-2, even with the aid of Section 34 IPC. The only charge framed
against A-2 was for an offence punishable under Section 201 read with
Section 34 IPC. True that Section 222 CrPC clothes the court with the power
to convict a person of an offence which is minor in comparison to the one for
which he is charged and tried, but by no stretch of imagination, offences under
Sections 304-B and 498-A IPC, under which appellant A-2 was convicted by
the trial court, could be said to be minor offences in relation to that under
Section 201 IPC, for which he was charged. In fact, the three offences are
distinct and belong to different categories. The ingredients of the offences
under the said sections are vastly different. Therefore, Section 222 CrPC had
no application on facts in hand.‖
15.11 Similarly, earlier, in Shamnsaheb M. Multtani v. State Of Karnataka., (2001) 2 SCC
577 the Supreme Court held that:
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 522
―We often hear about ―failure of justice‖ and quite often the submission in
a criminal court is accentuated with the said expression. Perhaps it is too
pliable or facile an expression which could be fitted in any situation of a case.
The expression ―failure of justice‖ would appear, sometimes, as an
etymological chameleon (the simile is borrowed from Lord Diplock in Town
Investments Ltd. v. Deptt. of the Environment3). The criminal court,
particularly the superior court should make a close examination to ascertain
whether there was really a failure of justice or whether it is only a
camouflage.
24. One of the cardinal principles of natural justice is that no man should
be condemned without being heard, (audi alteram partem). But the law
reports are replete with instances of courts hesitating to approve the
contention that failure of justice had occasioned merely because a person was
not heard on a particular aspect. However, if the aspect is of such a nature
that non-explanation of it has contributed to penalising an individual, the
court should say that since he was not given the opportunity to explain that
aspect there was failure of justice on account of non-compliance with the
principle of natural justice.
xxxx xxxx xxxx
31. Now take the case of an accused who was called upon to defend only a
charge under Section 302 IPC. The burden of proof never shifts onto him. It
ever remains on the prosecution which has to prove the charge beyond all
reasonable doubt. The said traditional legal concept remains unchanged even
now. In such a case the accused can wait till the prosecution evidence is over
and then to show that the prosecution has failed to make out the said offence
against him. No compulsory presumption would go to the assistance of the
prosecution in such a situation. If that be so, when an accused has no notice of
the offence under Section 304-B IPC, as he was defending a charge under
Section 302 IPC alone, would it not lead to a grave miscarriage of justice
when he is alternatively convicted under Section 304-B IPC and sentenced to
the serious punishment prescribed thereunder, which mandates a minimum
sentence of imprisonment for seven years.
32. The serious consequence which may ensue to the accused in such a
situation can be limned through an illustration: If a bride was murdered
within seven years of her marriage and there was evidence to show that either
on the previous day or a couple of days earlier she was subjected to
harassment by her husband with demand for dowry, such husband would be
guilty of the offence on the language of Section 304-B IPC read with Section
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 523
113-B of the Evidence Act. But if the murder of his wife was actually
committed either by a dacoit or by a militant in a terrorist act the husband can
lead evidence to show that he had no hand in her death at all. If he succeeds in
discharging the burden of proof he is not liable to be convicted under Section
304-B IPC. But if the husband is charged only under Section 302 IPC he has
no burden to prove that his wife was murdered like that as he can have his
traditional defence that the prosecution has failed to prove the charge of
murder against him and claim an order of acquittal.
33. The above illustration would amplify the gravity of the consequence
befalling an accused if he was only asked to defend a charge under Section
302 IPC and was alternatively convicted under Section 304-B IPC without any
notice to him, because he is deprived of the opportunity to disprove the burden
cast on him by law.
34. In such a situation, if the trial court finds that the prosecution has
failed to make out the case under Section 302 IPC, but the offence under
Section 304-B IPC has been made out, the court has to call upon the
accused to enter on his defence in respect of the said offence. Without
affording such an opportunity to the accused, a conviction under Section 304-
B IPC would lead to real and serious miscarriage of justice. Even if no such
count was included in the charge, when the court affords him an opportunity
to discharge his burden by putting him to notice regarding the prima facie
view of the court that he is liable to be convicted under Section 304-B IPC,
unless he succeeds in disproving the presumption, it is possible for the court to
enter upon a conviction of the said offence in the event of his failure to
disprove the presumption.‖
15.12 The above discussion would reveal that the revisionists were aggrieved by the charges
framed against these respondents; according to them, they should have been charged for
graver offences. Their revisions were rejected. That order became final; the revisionists did
not carry the matter further to the Supreme Court. The accused went to trial, on these charges.
The trial court convicted, and sentenced them to prison terms. Their appeals were heard, and
have been disposed of in this common judgment. In such a situation, the court is of opinion
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 524
that unless convincing facts plainly and unequivocally establish that there was misjoinder of
charges, and the facts proved point to commission of a graver offence, interference should not
be ordered. The procedure, in cases of mis-joinder spelt out in Section 216, applies during the
stage of trial; here what the revisionist is seeking is a direction to remand the matter for fresh
charges under Section 304 Part II, which goes against the scheme of the Code. The
revisionists were unable to point out any instance, recorded in the authorities, where the
course being suggested by them was adopted.
15.13 Besides the above consideration, the court is of opinion that the structure and scheme
of the code, indicated by provisions like Section 222 is such that accused can be convicted
without charge for ―minor‖ offence, necessarily minor in relation to what they are charged
with. Such statutory provision also indicates Parliamentary thinking that if charges for an
offence are not proved, but the prosecution proves facts which establish another offence, the
accused can be convicted in the absence of a charge only if the latter offence, he is not
charged with, is ―minor‖. Here, the revisionists take the untenable position that the accused
respondents, though charged with the offences under sections 304-a, 337/338 and 36,
punishable up to a maximum of two years imprisonment, should be convicted of Section 304
Part II, which is punishable with imprisonment that can extend to seven years. Plainly, the
argument is unreasonable.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 525
15.14 The court, after a careful examination of the materials, and the submissions urged, is
of opinion that revisional interference of the kind sought for in this petition, is not warranted.
The Revision Petition is therefore, rejected.
XVI CONCLUSION AND SENTENCE
16.1 Before proceeding with the conclusions, the Court has to voice its disquiet in the
manner the case was prosecuted. The evidence gathered and placed before the Court showed
that there were glaring lapses in the licensing department, the MCD, the DVB and the
Electrical Inspectors office. Accused after accused argued that several senior level officials in
these departments were either kept out of the orbit of investigation, or were deliberately not
sent up as accused. These concerns were held to be justified by the trial court, which directed
the CBI to investigate into the role of such persons. Though more than a year has elapsed,
nothing seems to have happened. On the other, hand the CBI chose to array, as accused for
the charge under section 304 Part-II persons against whom there was no material to
substantiate knowledge. Thus, R.K. Sharma, N.C. Chopra, A.K. Gera, S.S. Sharma and N.D.
Tiwari were made to face such charges; the trial court even convicted them. The discussion
concerning their appeals has shown how those charges, and convictions under section 304
Part II IPC, were untenable. Many of them are to be acquitted completely. One such accused
appellant, A.K. Chaudhary, died in jail, before the judgment could be pronounced. The
horrific nature of the tragedy, understandable anguish of survivors and relatives, and their
determination to see that the law is enforced, cannot be lost sight of. Yet, that should not
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 526
obscure the Court's duty to ensure that accused are convicted on the basis of proof beyond
reasonable doubt, the only standard ordained by law, and equally applicable to all citizens.
16.2 So far as directions given by the trial court, are concerned, having regard to the above
observations, the CBI shall complete the task in a time bound manner, and report its
conclusions, in accordance with law, to the trial Court, on or before 15.03.2009.
16.3 Now, the issue of sentence. It is acknowledged that sentencing is a complex task,
beset with many inexactitudes. The Law Commission's 47th Report, commenting on what
would be an appropriate sentence, says that proper sentence is a composite of many factors,
including the nature of the offence, the circumstances (extenuating or aggravating) of the
offence, the prior criminal record, if any, of the offender, the age of the offender, the
professional and social record of the offender, the background of the offender with reference
to education, home life, sobriety and social adjustment, the emotional and mental condition of
the offender. It also includes, the prospect for the rehabilitation of the offender, the possibility
of a return of the offender to normal life in the community, the possibility of treatment or of
training of the offender, the possibility that the sentence may serve as a deterrent to crime by
this offender, or by others, and the present community need, if any, for such a deterrent in
respect to the particular type of offence involved.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 527
16.4 All the convicted appellants, have been convicted under Section 304-A read with
Sections 337/338 and 36 IPC; Accused Nos 1 & 2 have, in addition been convicted of the
offence under Section 14, Cinematograph Act. The court proposes to take up the case of each
set of appellants. Before that, it would be useful to notice the trend indicated by reported
judgments of the Supreme Court, in this regard. In Rustam Irani's case (supra), which
involved 11 deaths, the sentence for conviction under Section 304-A upheld was 18months;
In Bhalchandra, which again involved 11 deaths, the court awarded 6 months. Recently, in
Rathnashalvan v. State Of Karnataka,(2007) 3 SCC 474 which was a motor accident, case,
resulting in three deaths, the sentence upheld was 6 months under Section 337.
16.5 This court has to keep in mind the unique nature of this case, which not only involved
a large number of deaths and injuries, but exposed how safety norms were given a go-bye by
all the accused, such as the first two accused, as well as the employees of the statutory
authorities. The duty of care, as perceived by this Court, upon all those involved in the
management of establishments (be they private or public) involving several processes, such
as electricity supply, transport, malls, cinema houses, multiplexes, airports, railway stations,
bus terminals and commercial complexes housing several offices, is being aware not only of
dangers and potential risks which are immediately in their gaze, but also to factor in the
potential danger from equipment and actions which, though not under their control, are
integrally part of or associated with these premises. Rapid means of escape may be
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 528
necessitated due to several factors, only one of which is fire. Recent developments have
only highlighted that. This case has shown how complete disregard to this duty - more in the
nature of a trust, towards those who visit such premises, and are often unaware of the precise
exit points in cases of emergencies, has resulted in a disaster. The statutory authorities too
correspondingly showed utter disregard for their duties.
16.6 The role of the first two accused, as discussed in detail was that the series of decisions
taken by them led to breach of several mandatory norms, which blocked easy exit from the
balcony. This court has rejected their contention that they were not responsible. As leaders of
the enterprise, they were under a full time duty to ensure the viewers' safety at all times. The
mitigating factors, urged on their behalf are that they are both of advanced age with no
previous criminal record and that they are educated, respectable members of the society.
16.7 Having regard to all the factors, the court is of opinion that so far as Appellants in Cr.
Appeal No. 794/2007 (Sushil Ansal) and Cr. Appeal No. 846/2007 (Gopal Ansal) are
concerned, imposition of the maximum sentence is not justified. Ends of justice would be
served if the sentence is modified to rigorous imprisonment for a period of one year and fine
Rs.5000/- under section 304-A. They are sentenced to rigorous imprisonment for three
months under section 337 of IPC. They are further sentenced to rigorous imprisonment for a
period of one year under section 338 of the ipc and a fine of Rs. 1000/- each for the offence
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 529
under Section 14 of the Cinematograph Act, 1952. These sentences shall run concurrently,
and they will be entitled to set off the period of detention under section 428 of the crpc. The
default sentence is modified to simple imprisonment for two months in the case of section
304-A and section 338, and in the case Section 14 of the Cinematograph Act, 1952 it shall be
one-month simple imprisonment. Their conviction, recorded by the trial court, is accordingly
maintained. Cr. Appeal Nos 794/2007 and Cr. Appeal No. 846/2007 are therefore, partly
allowed to the extent of the above modification.
16.8 As regards Cr. A. 66/2008 concerning accused Manmohan Uniyal, the negligent and
rash behavior shown by him has been a held to be a significant and direct cause of the
accident. His presence at the balcony during the crucial time, could have prevented valuable
loss of life. He could have, as an employee aware about the topography in the building,
guided the patrons to safety, and facilitated their rapid escape. His acts maximized the
potential damage. In his case, the absence from his assigned duties, most certainly resulted in
greater loss of life and injuries to more patrons. This court has considered all factors, and
convicted him under Sections 304-A, 337 and 338 IPC, read with Section 36. Having regard
to all the conspectus of facts, this court sentences this appellant to undergo rigorous
imprisonment for a term of 2 years, for the offence under Section 304-A, along with fine of
Rs. 2000; rigorous imprisonment for six months, with fine of Rs. 500/- for the offence under
Section 337, IPC and rigorous imprisonment for one year, with fine of Rs. 1000/-, for the
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 530
offence under Section 338, IPC. In default of payment of fine for any of the sentences, he
shall undergo simple imprisonment for four months. The sentence shall run concurrently, and
the appellant shall also be entitled to set off the period of detention, under Section 428 Cr.
...
16.9 As regards Cr. A. 4/2008 concerning accused H.S. Panwar, the negligent and careless
inspection carried out by him has been a held to be a significant and direct cause of the
accident, which took away lives of innocent people, and grievously injured several others.
His vigil could have prevented the fire clearance certificate. If he had displayed the same zeal
that he did in November, 1996, when the inspection report did not yield a ―no objection‖
there would have been a greater scrutiny of the fire safety norms. Instead, he certified that fire
safety norms had been complied with, whereas in actuality they were not. No doubt, he has
served the Delhi Fire Service for a long time; according to the trial court judgment, he was 68
years when the impugned judgment was pronounced. He is also a recipient of
commendations. On a conspectus of all these circumstances, the court is of the opinion that
ends of justice would be served if the sentence is reduced to rigorous imprisonment for one
year and Rs. 5000/- under section 304-A. the default sentence in his case is also modified to
simple imprisonment for two months. The conviction by the trial court is therefore
maintained, and to the above extent. Cr. Appeal No. 4/2008 is partly allowed to this extent.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 531
16.10 The appellants in Crl Appeal Nos. 21/2008 (B.M. Satija) and 23/2008 (Bir
Singh) have been convicted of the lesser offence under Sections 304-A, read with Sections
337/338 and 36 IPC, for rash and negligent acts, endangering human life, and public safety,
and causing grievous hurt. Their rash acts caused the fire. As concluded earlier, being
professionally experienced and responsible, the standard of foresight attributable to them is
higher; they should have been reasonably aware of the risk factors existing that day in the
form of two transformers, one of which was unauthorized, both being in the parking area, the
lack of protection relays, etc. Yet, they went ahead, and carried out defective repairs without
the aid of standard equipments. Having regard to all the conspectus of facts, this court
sentences these appellants to undergo rigorous imprisonment for a term of 2 years, and a fine
of Rs. 5000/- each, for the offence under Section 304-A, rigorous imprisonment for six
months with fine of Rs. 500/- for the offence under Section 337, IPC and rigorous
imprisonment for one year, with fine of Rs. 1000/-, for the offence under Section 338, IPC. In
default of payment of fine for any of the sentences, they shall undergo simple imprisonment
for four months. The sentence shall run concurrently, and the appellants shall also be entitled
to set off the period of detention, under Section 428 Cr. PC.
16.11 For the reasons mentioned in the previous part of the judgment, the appeals of R. K.
Sharma, N.C. Chopra, S.S. Sharma, N.D. Tiwari and A.K. Gera, are allowed; they are
acquitted. They shall be forthwith released.
Crl. A. Nos.794,846,830/2007,
Crl.A. 4,9,21,33,45,46,56,66,/2008 & Crl. R.17/2008 Page 532
16.12 In view of the fact that the main appeals have been disposed, all applications
seeking interim relief have been rendered infructuous and the same are accordingly disposed
...