Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • sections 30 & 33 of the Arbitration and Conciliation Act, 1940,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • sections 30 & 33 of the Arbitration and Conciliation Act, 1940,
Smart Summary

Comprehensive Summary of the Opinion (Manmohan Sarin, J.)

Factual and Procedural Background

The appellant (Delhi Development Authority — "appellant-DDA") entered into a contract with the respondent for supply of machine-made door/window shutters. An offer dated 14 May 1984 was accepted and an agreement executed on 16 August 1984. Supplies were to be made within eight weeks from 24 May 1984, and the contractual period expired on 23 January 1985. The appellant made nine allocations between 29 May 1984 and 18 February 1986; confirmations by Executive Engineers were given against eight allocations between 16 June 1984 and 12 September 1986. Many confirmations (and some allocations) occurred after the contract expiry, making timely manufacture and supply difficult or impossible.

The respondent claimed enhanced rates for supplies made after 23 January 1985 (alleging escalation of timber price, seasoning costs, etc.); the appellant disputed these claims and withheld payments, prompting arbitration. Mr. M.S. Telang was appointed sole arbitrator. The Arbitrator awarded Rs. 7,86,245.08 plus future interest at 12% p.a. and costs Rs. 5,000/-. The appellant filed objections under sections 30 and 33 of the Arbitration and Conciliation Act, 1940 (I.A. No. 11358/1990), which the Single Judge dismissed by judgment dated 17 September 1992; the award was made rule of court except the Arbitrator's grant of future interest (set aside), with the Single Judge directing interest @ 12% p.a. on amounts for certain claims and conditional satisfaction if amounts were paid within two months.

The Division Bench admitted the appeal and ordered the appellant to deposit the decretal amount as a fixed deposit (F.D.R.) with the Registrar with interest calculated at 9% within eight weeks; execution stayed subject to deposit. The F.D.R. was furnished and renewed. The appeal was dismissed for default on 7 April 2005 when no one appeared for the appellant, and funds were ordered released to the respondent. The appellant successfully applied for restoration and condonation of delay; the appeal was restored on 20 February 2008 subject to payment of costs. Arguments were heard on 20 May 2008 and judgment reserved; the present opinion disposes of the appeal.

Legal Issues Presented

  1. Whether the arbitral award was vitiated for failure to give reasons—specifically, whether the Arbitrator failed to give reasons for amounts awarded for claims exceeding Rs. 50,000, thereby justifying setting aside the award.
  2. Whether the Arbitrator ignored material documents or failed to apply his mind (non-application of mind / misconduct) in arriving at the award.
  3. Whether the respondent was entitled to enhanced rates for supplies made after the contractual period, given contentions about extension of time sought under duress and alleged breaches/delays attributable to the respondent.
  4. Whether the Single Judge erred in dismissing the appellant's objections under sections 30 & 33 of the Arbitration and Conciliation Act, 1940, and in making the award rule of the court (subject to modification of future interest).

Arguments of the Parties

Appellant's Arguments

  • Under the arbitration agreement, the Arbitrator was required to give reasons for any claim/dispute over Rs. 50,000; the Arbitrator failed to give reasons and only stated conclusions without showing the basis for the quantum awarded.
  • The respondent failed to produce evidence of escalated costs or higher expenditures to justify enhanced rates.
  • Letters from the respondent (including 18 September 1985) indicated cooperation and a willingness to supply on contract rates while seeking provisional extension of time; therefore, the claim for enhanced rates was an afterthought.
  • The Arbitrator ignored material documents (letters dated 26.1.1985, 24.2.1986, 15.12.1986) showing factory accident and non-availability of timber — delays attributable to respondent — and thus did not apply his mind.
  • Relied on multiple precedents to argue that awards lacking reasons or showing non-consideration of material documents should be set aside.

Respondent's Arguments (as reflected in the opinion)

  • The respondent claimed entitlement to enhanced rates for supplies made after 23 January 1985 due to escalation in timber prices, seasoning costs and other increased expenses.
  • The respondent contended that provisional extension of time was applied for under duress (because payments were being withheld) and therefore they were not bound to supply at the original contract rate for delayed supplies.
  • The respondent produced calculation sheets and minutes of Arbitrator's proceedings which, as shown to the Single Judge, demonstrated the basis for the amounts awarded (rates adopted corresponded to rates at which the appellant itself had awarded tenders contemporaneously).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Gora Lal v. Union of India, (2003) 12 SCC 459 Authority relied on by appellant concerning requirement of reasons / scrutiny of arbitral awards. The court considered it among authorities relied upon by appellant but concluded the factual findings and the record showed adequate indication of the Arbitrator's thought process; Gora Lal did not advance appellant's position here.
College of Vocational Studies v. S.S. Jaitley, AIR 1987 Delhi 134 Addressed requirement of reasons by arbitrator and the extent of justification needed. The Single Judge and this court applied the principle that an arbitrator need indicate his thought process rather than provide detailed computations. The court held the award met that requirement.
Seth Mohanlal Hiralal v. State of M.P., (2003) 12 SCC 144 Authority on ignoring material documents / misconduct / non-application of mind. Cited by appellant but the court found those precedents inapplicable because the Arbitrator's factual findings were supported by records and the documents the appellant relied on did not negate those findings.
Union of India v. Banwari Lal & Sons (P) Ltd., (2004) 5 SCC 304 Relied on for proposition that ignoring material evidence vitiates award. The court held that the award's findings were based on record and contemporaneous confirmations; the cited precedent did not assist the appellant under the facts of this case.
M/s Bombay Ammonia Pvt. Ltd. v. Union of India, AIR 1987 Delhi 148 Authority invoked regarding non-application of mind and non-consideration of relevant writings. The court determined that the Arbitrator had considered relevant records and made categorical findings of fact; thus this precedent was not attracted.
Sathyanarayana Brothers (P) Ltd. v. T.N. Water Supply & Drainage Board, (2004) 5 SCC 314 Non-consideration of relevant documents can vitiate an award. Appellant relied on it, but court concluded the Arbitrator had considered documents and evidence sufficiently; therefore the precedent did not aid the appellant.
Delhi Development Authority, New Delhi v. Alkaram, New Delhi, AIR 1982 Delhi 365 Arbitrator required to indicate thought process; detailed computations not mandatory. The court cited and followed this principle, observing it is sufficient for an arbitrator to indicate the basis of decision rather than set out detailed mental computations.
Indian Oil Corporation Ltd. v. Indian Carbon Ltd., AIR 1988 SC 1340 Discussed nature and extent of reasons required in arbitration (short intelligible indication of grounds is sufficient to show arbitrator's mind). The court applied this principle to hold the award met the requirement of indicating the thought process; the absence of explicit computational steps was not fatal.

Court's Reasoning and Analysis

The court conducted a fact-focused analysis and reviewed (a) the arbitral award, (b) the objections, (c) the Single Judge's reasoning, and (d) the documentary record relied upon by the Arbitrator. The key analytical steps taken by the court were:

  1. Assessment of allocation and confirmation timeline: The Arbitrator (and Single Judge) had found the appellant failed to make timely allocations and that several confirmations by Executive Engineers arrived after the contractual expiry date (23 January 1985). The court accepted these findings as being supported by records (allocations/confirmations dates) and thus robust factual findings that undermined the appellant's contention that delay was attributable to the respondent.
  2. Evaluation of documentary evidence of respondent's factory accident: The court considered the letters relied upon by the appellant (which mentioned an accident and temporary closure). It held those communications might explain some manufacturing delay but did not negate the broader factual finding of breach/delay by appellant—those letters did not dilute or overturn the Arbitrator's clear findings based on the allocation/confirmation record.
  3. Examination of the issue of enhanced rates and duress: The Arbitrator found market costs rose after contract formation, and that the respondent sought extension under duress because appellant was withholding payments; therefore the respondent's entitlement to compensation for late supplies was justified. The court treated this as a factual finding supported by evidence (including the respondent's letter of 18 September 1985 noting market rates had risen by 25%). The court held such factual findings are not easily assailable in challenge proceedings.
  4. Consideration of the alleged failure to give reasons: The court reviewed the award, minutes of Arbitrator's proceedings (dates cited), and calculation sheets (pages 44–50 of the award file). The Single Judge had re-performed an exercise to satisfy his judicial conscience by tracing the basis of the calculations and found they were based on contemporaneous rates at which the appellant had itself awarded other contracts. The present court agreed that the Arbitrator had indicated his thought process sufficiently: an arbitrator need not set out detailed computations, only intelligible indications of the grounds (consistent with precedents cited).
  5. Application of jurisprudence on the sufficiency of reasons: The court applied prior authorities holding that arbitration is meant to be quick and that short intelligible indications of grounds suffice. While the court acknowledged it would have been preferable for the Arbitrator to state explicitly that computations were based on rates at which the appellant had awarded contracts, the omission was not a fatal flaw.
  6. Conclusion on non-application of mind allegations: Given the record, the court found that the Arbitrator had, in fact, considered the relevant documents and evidence and had reduced or denied claims where allocations were timely. Thus, allegations of non-application of mind and ignoring material documents were not substantiated on the record.
  7. Practical considerations and delay: The court noted the arbitration award dated March 1990 and observed that nearly 18 years had elapsed, implying that the challenge on merits to long-standing factual findings was not deserving of indulgence.
  8. Modification by consent on interest rate: Although the appeal was dismissed, the court accepted respondent's counsel's consent to reduce post-award interest to 8.25% p.a., and modified the decree accordingly.

Holding and Implications

Holding: The appeal is dismissed. The court found no error or infirmity in the arbitral award or in the impugned Single Judge's order. The only modification made to relief previously ordered is that post-award interest is reduced to 8.25% p.a. from the date of the award (by consent of respondent's counsel).

Implications:

  • Direct effect on the parties: The arbitral award (previously made rule of the court) stands; the appellant must satisfy the award subject to the modified interest rate of 8.25% p.a. from the date of the award. The appellant's objections under sections 30 & 33 were rejected, and the appellant's appeal was dismissed as lacking merit.
  • Scope of precedent / broader impact: The court applied established principles that an arbitrator need only indicate his thought process and that detailed computations are not mandatory. The opinion did not announce a new legal principle; it applied existing authorities to the facts and concluded that the award's reasoning met the accepted standard. In the court's view, the precedents relied upon by the appellant were not attracted on these facts.

This summary is strictly confined to the information contained in the provided opinion and does not add or infer facts beyond the text of the judgment.

    Delhi Development Authority v. Harbans Singh & Sons .

    Manmohan Sarin, J.:— Appellant-DDA has preferred this appeal impugning the judgment dated 17th September, 1992 passed by the learned Single Judge in Suit No. 2076-A/1990. The learned Single Judge dismissed the objections filed by the appellant-DDA vide I.A No. 11358/1990, against the arbitral award dated 28th March, 1990. With the dismissal of IA 11358/1990 i.e the objections under sections 30 & 33 of the arbitration and conciliation act, 1940, the arbitral award dated 28th March, 1990, was made rule of the court except that the award granting future interest by the Arbitrator was set aside. The learned Single Judge while making the award rule of the court directed payment of interest @ 12% p.a on the awarded amount in respect of claim Nos. 1 to 6 from the date of award till payment. It was further ordered if the awarded amount of Rs. 7,86,245.08 together with interest @ 9% p.a and costs of Rs. 5000/- as awarded by the Arbitrator were paid within two months from 17th September, 1992, the decree would stand satisfied.

    2. Appeal was admitted to hearing on 4th January, 1993. The Division Bench in CM 2/1993, vide orders dated 15th February, 1993, directed the appellant-DDA to deposit the decretal amount in the form of fixed deposit for a period of three years in the name of Registrar, with interest component to be calculated @ 9% on the award within eight weeks. The execution of the decree was stayed subject to said deposit. Appellant accordingly furnished F.D.R in compliance with the directions given. F.D was further directed to be renewed for a further term. On 7th April, 2005, none was present on behalf of the appellant to press the appeal and the same was dismissed in default and the amount lying in the Registry was directed to be released to the respondent. In the event, appellant moved CM 14868/2007 for restoration of appeal together with an application for condonation of delay being CM 14869/2007.

    3. For the reasons as set out in detail in our order dated 20th February, 2008, appellant's applications for condonation of delay and restoration of appeal were allowed and the appeal was restored to its original number subject to payment of costs of Rs. 10000/-.

    4. Arguments were heard in appeal on 20th May, 2008 and judgment reserved. We now proceed to decide the appeal. The relevant facts for appreciation of the appellant's contention in appeal may be noted in brief:—

    The offer of the respondent for supply of machine made door/window, shutters estimated at Rs. 50 lacs was accepted vide letter dated 14th May, 1984 of the Chief Engineer, DDA. An agreement was entered into between the parties on 16th August, 1984. In terms of the agreement, shutters were to be supplied to the appellant within eight weeks from 24th May, 1984 to 23rd January, 1985 at the agreed rates stipulated in the agreement. The Chief Engineer of the appellant was to make allocation to its different Divisions. The Executive Engineers of the concerned Divisions were to confirm the particulars, size and number of shutters required by them for their respective housing schemes under the Division. Appellant made nine allocations between the period from 29th May, 1984 to 18th February, 1986. The second allocation made on 20th June, 1984 was cancelled on 11th October, 1984. The concerned Executive Engineers of the Division gave confirmation against eight allocations between 16th June, 1984 to 12th September, 1986. It was on receiving of confirmation that supplies had to be made by the respondent. The contract period was to expire on 23rd January, 1985. The supply on confirmations received on 26th December, 1984 or thereafter could not be made before the expiry of the contract on 23rd January, 1985.

    5. It has come on record that appellant withheld certain payments in the absence of extension of time and the respondent, therefore, applied for grant of provisional extension of time under duress. Respondent claimed to be entitled to enhanced rate for supplies made after the contractual period i.e 23rd January, 1985, claiming that they were not bound to supply at the contract rate. The claims of the respondent were disputed by the appellant, resulting in arbitration clause being invoked. Mr. M.S Telang was appointed as the sole arbitrator to adjudicate upon the disputes/claims raised by the respondent. Respondent raised six claims all on account of escalation of timber price, seasoning costs and also claiming future interest and cost of arbitration proceedings. The Arbitrator after perusal of the pleadings and the evidence produced before him and hearing the parties, awarded Rs. 7,86,245.08 together with future interest @ 12% and costs of Rs. 5000/-. As noted earlier, objections filed were dismissed by the learned Single Judge vide impugned judgment and the said judgment is assailed in this appeal.

    6. The main contention of Mr. Bhupesh Narula, learned counsel appearing for the appellant is that as per the arbitration agreement, the arbitrator was required to give his reasons in respect of the award for any claim/dispute over Rs. 50,000/-. The Arbitrator has singularly failed to give his reasons for the amounts awarded. Counsel submits that the Arbitrator has simply given his conclusions without reasons. There is no reason justifying the quantum of award or indication in the award as to how the amount awarded had been arrived at. Learned counsel further contends that respondent has failed to lead any evidence of the escalated costs or higher amounts being expended by them in the acquisition of the material and in execution of the contract. Learned counsel for the appellant referred to the letter dated 18th September, 1985, written by the respondent to the appellant wherein while noting that due to placement of orders and confirmation of sizes after the expiry of contract period, delay had occurred. The respondent was still cooperating with the Department in execution of balance orders when the market rates had gone up by 25%. Respondent also sought six months' time as 55% of the work was ordered six to eight months after the expiry of contract. Respondent also protested against payment being stopped because of extension of time not having been applied for. Respondent sought issue of provisional time extension in the interest of work so that they could resume supply. Learned counsel for the appellant urges that use of expression by the respondent that they were cooperating with the respondent, indicated that they were willing to make the supply on the contracted rates and were only seeking extension of time. The claim for enhanced rate was thus an afterthought. Counsel further submitted that the Arbitrator had erred in ignoring letters of the respondent dated 26.1.1985, 24.2.1986 and 15.12.1986 which showed that due to an accident having occurred in the factory of the respondent and the non availability of timber etc., work remained closed Appellant urged that these were delays attributable to the respondent which were ignored.

    7. On the first submission that the basis of amounts awarded not having been disclosed the award suffered from vice of non giving of reasons and simply conclusions being given, the appellant places reliance on Gora Lal v. Union Of India. (2003) 12 SCC 459, College of Vocational Studies v. S.S Jaitley AIR 1987 Delhi 134. Regarding ignoring of material documents and resultant misconduct, counsel relied on Seth Mohanlal Hiralal v. State Of M.P., (2003) 12 SCC 144, Union Of India v. Banwari Lal & Sons (P) Ltd., (2004) 5 SCC 304, M/S. Bombay Ammonia Pvt. Ltd.… v. Union Of India…., AIR 1987 Delhi 148 to urge that award suffered from non application of mind. Reliance was also placed on Sathyanarayana Brothers (P) Ltd. v. T.N Water Supply & Drainage Board, (2004) 5 SCC 314 to urge that non consideration of relevant writings and documents deprived a just and fair decision and vitiated the award.

    8. We have heard learned counsel for the parties, carefully perused the arbitral award, the objections thereto, the impugned judgment and the grounds of appeal and the submissions made before us. The learned Single Judge in his judgment and the Arbitrator in the award have clearly set out the facts which bring out that there was failure on the part of the appellant to make allocation for the orders to be executed in time and also delayed confirmation by the concerned Executive Engineers of the Divisions, who were to confirm their requirement of particular sizes of doors/window shutters in respect of different Divisions. The Arbitrator has found that confirmation in respect of housing scheme of 288 LIG houses was well within reasonable time. However, confirmation in relation to 160 SFS houses was sent on 26th December, 1984 which hardly gave one month time to manufacture and supply thereof. The Arbitrator has found that effectively only four allocations out of nine were made before 23rd January, 1985 and confirmation in respect of one and a half of them was made before the said date. All other allocations and the confirmations were made in the extended period of contract. In view of these clear and categorical findings of facts in the award which are based and supported by records, it is idle for the appellant to contend that delay had occasioned on account of respondent, based on two or three letters written wherein they had intimated the factum of an accident in their factory and temporary closure flowing therefrom. The said intimation may have explained the delay that was taking place in manufacture and supply of the particular consignment in question. The said letters do not dilute or negate the findings of breach or delay having been occasioned in the execution of contract on account of appellant. Moreover, the Arbitrator is the master of facts and law. He has given clear findings of breach by appellant which cannot be assailed in these proceedings. The judgments cited by the appellant regarding non consideration of material documents would not be attracted and do not advance the appellant's case in these circumstances.

    9. This takes us to the second submission regarding the claim of the respondent for payment at enhanced rates being not admissible under the agreement and in view of the respondent having themselves applied for extension of time which was granted without levy of compensation or damages. The Arbitrator had found on examination of evidence that the costs of machine made shutters were rising after the agreement had been entered into. He also found that claimant/respondent applied for extension of time not under free consent but only under duress and the threats of withholding of eligible and due payments by the appellant. Letter dated 18th September, 1985 on which reliance was placed by the appellant and where the respondent mentioned the factum of cooperating with the Department in executing the balance orders, respondent had significantly pointed out that market rates had gone up by 25%. Respondent had also protested and described the appellant's action unjustified in directing the Executive Engineer to stop payment because extension of time had not been applied for. It was, in these circumstances, that provisional extension of time was sought for to resume supplies. The findings of the learned Arbitrator is in consonance with the basis as unfolded and as noted by us it is a finding of fact, which is not assailable. Similar is the position with regard to finding reached by the Arbitrator that appellant committed breach of the agreement as they failed to make allocations and confirmation in sizes before the stipulated date and the respondent was thus entitled to receive suitable compensation.

    10. Let us now consider the last contention of the appellant with regard to award being vitiated by non giving of reasons and only the conclusions having been given. The learned Single Judge has duly discussed and noted the decision as in College of Vocational Studies v. S.S Jaitley (supra). The learned Single Judge has held that the Arbitrator has given ample reasons for the award of higher rates to the respondent for the supplies made after the expiry of the stipulated date of supply i.e 23rd January, 1985. The learned Single observed that the Arbitrator had not explicitly stated as to how he worked out the figure awarded by him against each claim. In other words, he had not given the computation or quantification of the amount awarded. The learned Single Judge with a view to satisfy his judicial conscience that Arbitrator had applied his mind in making the award and findings and conclusions were not arbitrary even went through the exercise to find out as to how the amount against each of the claims on account of price rise of timber, rise in seasoning cost etc had been arrived at by the Arbitrator. It was demonstrated before the learned Single Judge that the amounts have been worked out on the basis of rates at which the appellant had awarded tender on or about the dates of supply made by the respondent. The Arbitrator's minutes of proceedings dated 8th November, 1989, 9th January, 1990 and 16th January, 1990 and the calculation sheets on pages 44 to 50 of the award file were perused by the learned Single Judge to satisfy himself as to the basis of the award. This exercise had been duly gone into. The learned Single Judge has also noted that counsel for the appellant was confronted with this position who did not dispute the explanation given by the counsel for the respondent but only insisted that this basis of arriving at the amount should have been mentioned in the award itself. Perusal of the award as also the judgment of the learned Single Judge and the proceedings sheet referred to him, have also been seen by us. We have no reasons to reach a different conclusion than the one reached by the learned Single Judge.

    11. We may observe that the Arbitrator is required only to indicate his thought process. As held out in Delhi Development Authority, New Delhi v. Alkaram, New Delhi AIR 1982 Delhi 365 and College of College Of Vocational Studies… v. S.S Jaitely…. (supra), an Arbitrator is not required to give the details of his computation and give his mental meanderings. It is sufficient if his thought process is indicated and the basis for awarding the amount is disclosed. Reference may also be made to the judgment of the Supreme Court in Indian Oil Corporation Ltd. v. Indian Carbon Ltd.., AIR 1988 SC 1340 where the court has considered the requirement of reasons being given for the award and the nature and extent of such reasons. The court observed that “Arbitration process should be quick and that quickness of the decision can always be ensured by insisting that short intelligible indications of the grounds should be available to find out the mind of the arbitrator for his action.” The award in the present case meets the said requirements. It would perhaps help had the learned Arbitrator explicitly stated that the computations were based on the rates at which the appellant itself had awarded contracts to others at the relevant period. It would have obviated the exercise which the learned Single Judge went through to satisfy his judicial conscience with regard to the basis of computation for the amount awarded. However, the absence did not introduce any fatality in the award.

    12. This is not a case where the findings of the Arbitrator is not based on evidence. The purpose of arbitration is to provide a speedy and economical remedy for commercial disputes. The Arbitrator is not required to give detailed judgment or detailed reasons. Courts are not required to go into the reasonableness of the reasons or sufficiency of the reasons. The court, is not required to reappraise the evidence and sit as a court of appeal. In this case, it would be seen that award is dated 19th March, 1990 and a period of nearly 18 years has elapsed since then, such objections and pleas do not deserve to be countenanced.

    13. We may observe in addition that the Arbitrator has carefully considered each item of claims and wherever required had not granted or reduce the claim where the allocation was made before the stipulated date i.e 23rd January, 1985. It is only in cases where allocation or confirmation of sizes was given by appellant belatedly which made the execution impossible, before the stipulated date that compensation has been awarded taking into account the rise in price of timber, rise in seasoning cost, rise in fabrication cost and rise in truck freight. Moreover adopting the rates at which the appellant itself had awarded the work in competitive bidding to other parties during the contemporaneous period was a rational method adopted for assessing the enhancement in rates.

    We, therefore, find no error or infirmity in the award or in the impugned order. Needless to mention that none of the judgments referred to in view of the discussion aforesaid and the facts as noted would apply and advance the appellant's case.

    Appeal has no merit and is liable to be dismissed. However, on the question of award of interest, considering the prevalent rate of interest and the rate as admissible for F.D's, counsel for the respondent on behalf of the respondent has consented that post award interest may be reduced to 8.25% p.a We, accordingly, dismiss the appeal subject to the modification in the decree that the interest shall be @ 8.25% p.a from the date of award.