Smart Summary

Structured Summary of the Opinion (ARUN KUMAR, J.)

Factual and Procedural Background

The plaintiff (respondent in the appeal) filed a summary suit under Order 37 CPC for recovery of Rs. 1,37,22,137/- (principal Rs. 1,05,55,490/- plus interest) arising from a sale contract dated 7 June 1995 for 14,250 metric tons (MT) of Di-Ammonia Phosphate (DAP) at US$240 per metric ton. The cargo had been imported from Jordan and was at Jawaharlal Nehru Port Trust (JNPT), Bombay, having been unloaded and held in silos.

The seller contended that delivery and transfer of property occurred upon the buyer's acceptance and subsequent steps taken by the buyer and its clearing agent. The buyer (defendant/appellant) partly paid but disputed liability for the full contracted quantity, claiming it had received only 13,941.500 MT and raising, in the leave-to-defend application, a plea of short delivery and an arbitration clause in the contract.

The learned single Judge (judgment dated 7 February 2000, reported at 2000 AIHC 2985) dismissed the defendant's application for leave to defend under O.37 and decreed the suit as prayed. The defendant appealed against that dismissal. On appeal, counsel for the defendant did not press the arbitration-clause point, and the court treated it as given up.

Legal Issues Presented

  1. When did delivery take place and when did property in the goods pass from seller to buyer under the contract?
  2. Whether, in light of the contractual "Quantity Determination" clause and the absence of an MMTC official's certification, the buyer could limit payment to 13,941.500 MT rather than the contracted 14,250 MT.
  3. Whether the defendant was entitled to leave to defend the suit under O.37 CPC on the basis of the short-delivery defence (and, originally, an arbitration plea which was decided against the defendant and not pursued on appeal).

Arguments of the Parties

Appellant's (Defendant's) Arguments

  • The contract's clause headed "Quantity Determination" required that quantity be certified "AS PER ACTUAL QUANTITY RECEIVED AT THE PORT DULY CERTIFIED BY INDEPENDENT SURVEYOR/MMTC'S REPRESENTATIVE AT THE PORT/BASED ON ACTUAL DESPATCH FROM THE PORT. QUANTITY SHOULD BE CERTIFIED BY MMTC'S OFFICIAL ALSO." Absence of certification by MMTC officials meant the contracted quantity was not finally determined.
  • On actual delivery the defendant received only 13,941.500 MT, and therefore it is liable to pay only for that actual quantity.
  • The defendant also raised (in its leave-to-defend application) an arbitration-clause defence in the contract (not pressed on appeal).

Respondent's (Plaintiff's) Arguments

  • The contract was for 14,250 MT and the plaintiff complied with the payment/ delivery conditions — including submission of invoice, weight and quality certificates issued by the independent surveyor (SGS) — thereby entitling the plaintiff to payment on COD terms.
  • The defendant accepted delivery and the quantity at the relevant time, including by correspondence: seller's letters to customs and clearing agent of 7 June 1995 confirming sale of 14,250 MT; clearing agent's letter of 7 June 1995 confirming it was holding 14,250 MT; defendant's own letters of 8 and 9 June 1995 confirming purchase of 14,250 MT and intent to clear.
  • Any shortage could have occurred during packing into bags by the clearing agent (acting on the buyer's instructions); the buyer's later reliance on bagged-despatch quantities was an afterthought to avoid payment.
  • The plaintiff produced documentary proof (bill of lading copies, weight certificate, SGS quantity and quality certificates, certificate of origin) which were not disputed and satisfied the contract's requirements for quantity determination.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court framed the "crucial question" as the timing of delivery and the passing of property. It proceeded by applying the contract terms and focussing on contemporaneous correspondence and documentary evidence placed before the court.

Principal elements of the court's analysis (as stated in the opinion):

  1. Contract terms: The court examined clauses in the agreement, notably:
    • Clause 6 (quality / approximate quantity: "SPOT CARGO CF 14250 MT APPROX.");
    • Clause 7 (delivery: "AT BOMBAY JNPT");
    • Clause 8 (payment: "ON 'COD' BASIS" and list of documents to be presented including commercial invoice, weight certificate and surveyor's certificates (SGS)); and
    • The "Quantity Determination" clause which referred to certification by independent surveyor/MMTC representative and despatch-based determination.
  2. Documentary and correspondence evidence: The court placed decisive weight on several contemporaneous documents:
    • Letters of 7 June 1995 from the plaintiff to the Assistant Collector of Customs and to the clearing agent (Vilas Transport), and the clearing agent's letter of 7 June 1995 confirming it was clearing 14,250 MT and holding the cargo in JNPT silos (and that 3,300 MT had been bagged and was ready for despatch).
    • An acceptance/confirmation letter from the defendant dated 8 June 1995 evidencing acceptance of the 14,250 MT offer.
    • The defendant's letter dated 9 June 1995 to the Assistant Collector of Customs confirming purchase of 14,250 MT and that the consignment would be cleared by the defendant.
    • A fax on 9 June 1995 from the defendant to the clearing agent giving despatch instructions for specified bagged quantities and requesting coordination with MMTC's regional office; and internal MMTC communications describing Vilas Transport as "our handling agent" and acknowledging despatches effected as per MMTC's 9 June instructions.
    • Submission on 20 June 1995 by the plaintiff of original documents including bills of lading, a weight certificate, quantity and quality certificates from SGS, and certificate of origin; the surveyor's report and clearing-agent confirmation were on record and undisputed.
  3. Legal principle: The court cited Section 33 of the Sale of Goods Act (reproduced in the opinion) which provides that delivery may be effected by anything agreed to be treated as delivery or which has the effect of putting the goods into the buyer's possession or that of a person authorized to hold them on his behalf. The court applied s.33 to conclude that, by confirming purchase and issuing despatch instructions and by the clearing agent holding and dealing with the goods, the buyer had the goods in its possession (through its agent) and had accepted delivery.
  4. On the quantity issue, the court found that the contractually required documentary proof of quantity (independent surveyor's certificate/weight certificate) had been produced and that the defendant's own correspondence (especially the 9 June 1995 confirmation to customs) established acceptance of 14,250 MT. The court treated the later contention (first raised in the defendant's 14 July 1995 letter) that final payment would be made only after despatch-based certification by MMTC officials as an afterthought and a tactic to avoid payment.
  5. Conclusion on leave to defend: Given the documentary record and the contractual position, the court held that no prima facie case had been made out to grant leave to defend under O.37 CPC based on the short-delivery defence; the learned single Judge's rejection of leave to defend was upheld.
  6. Interest and decretal relief: The court reviewed the time elapsed and the nature of the commercial transaction, and declined to interfere with the single Judge's award of interest (18% p.a. on the principal from the date of suit until realisation). The court noted the plaintiff had been deprived of the money for several years.
  7. Preliminary objection about certified copy: The court disposed of the respondent's preliminary objection that the appellant had not filed a certified copy of the judgment under appeal, accepting the appellant's affidavit and registry receipt showing application for the certified copy (applied on 17 February 2000 with likely delivery date shown as 7 June 2001). The objection was held not tenable.

Holding and Implications

Core Ruling: Appeal dismissed.

Direct effects and consequences as stated in the opinion:

  • The court affirmed the finding that delivery (and transfer of property) was completed at the latest on 9 June 1995 and that the plaintiff had divested possession and property in the goods in favour of the defendant (through its agent).
  • The defendant was held liable to pay for the full contracted quantity of 14,250 MT.
  • The decree for Rs. 1,37,22,137/- (which incorporated principal Rs. 1,05,55,490/- and interest claimed up to institution) was affirmed, with interest awarded at 18% p.a. on the principal from the date of institution of the suit until realisation (the court declined to interfere with that rate).
  • The appeal was dismissed with costs.

Broader precedent: The opinion does not announce or analyse any new legal principle beyond applying contract terms, contemporaneous documentary evidence and Section 33 of the Sale of Goods Act to determine delivery and passing of property. The judgment addresses the specific dispute between the parties; no broader precedent was discussed in the opinion.

Appeal dismissed.

    Minerals And Metals Trading Corporation Ltd. v. Dimple Overseas Ltd. .

    ARUN KUMAR, J.:— This appeal is directed against a judgment of the learned single Judge of this Court dated 7th February, 2000 (reported in 2000 AIHC 2985) on an application of the defendant for leave to defend a suit filed under the provision of O.37 of the Code of Civil Procedure. By the impugned judgment the learned single Judge dismissed the application of the defendant/appellant seeking leave to defend the suit. As a result of refusal to grant leave to defend the suit to the defendant the suit was decreed as prayed. Briefly the facts are that the plaintiff, respondent in this appeal, filed a suit for recovery of Rs. 1,37,22,137/- along with interest and costs of the suit under the summary procedure prescribed in O.37 of the Code of Civil Procedure. The case of the plaintiff is that on 7th June, 1995 it entered into a contract with the defendant for sale of 14,250 M.T of Di-Ammonia Phosphate (for short, DAP) at a rate of US $ 240 per metric ton. The goods had been imported by the plaintiff from Jordan and had already reached the Bombay Port. In fact the cargo had already been unloaded from the ship and was lying at the Jawaharlal Nehru Port Trust, Bombay. It is the case of the plaintiff that in pursuance of the contract entered into between the parties on 7th June, 1995, the goods were delivered to the defendant. In other words the property in goods passed to the defendant. M/s. Vilas Transport Company who were the clearing agent of the plaintiff and had cleared the cargo on its arrival at the JNPT, Bombay in silos belonging to the Port Trust. In view of the contract of sale on 7th June, 1995 the said clearing agent became the clearing agent of the defendant. The cargo was in the shape of open mass of granules and had to be put in containers or bags for purposes of removal from the port. It is to disputed that the clearing agent started putting the DAP granules into bags as per instructions of the defendant before despatching the same to various destinations in India as per instructions of the defendant with effect from 9th June, 1995. This fact is even otherwise established from the undisputed documents on record. The defendant took its own time in removing the cargo from the port and paid demurrage for it. The plaintiff i.e the vendor started claiming the price of the goods as per the terms of the contract. On this the defendant raised the dispute that it will pay the price based on quantity of goods as per their despatch from the port in bags. The defendant made part payment but a balance of more than rupees one crore remained to be paid. The plaintiff refuted the stand of the defendant regarding payment by stating that as per the terms of the contract the payment was on COD basis i.e cash on delivery basis. Delivery of the cargo took place on 7/8th June, 1995 because on 9th June, 1995 defendant started issuing instructions about the disposal of the cargo. The plaintiff was entitled to payment of price of the entire quantity of goods latest on 9th June, 1995. The payment could not be linked with despatch of the entire quantity of goods nor the determination of the total quantity could be based on the despatches. The defendant took its own time in arranging for the despatch of goods. The payment of price of the goods, therefore, could not be made dependent on this. Ultimately the plaintiff filed the present suit for recovery of Rs. 1,37,22,137/- the break-up of which is that Rs. 1,05,55,490/- was the balance price while the rest was the element of interest.

    2. The crucial question for determination in this case is as to when the delivery took place and property in goods passed from the seller to the buyer. The learned single Judge held that the delivery of the goods took place at the most on 9th June, 1995 and in view of the terms of the contract the plaintiff became entitled to the price of the entire goods on that date. In the application for leave to defend the suit the only defence raised by the defendant besides raising a plea of existence of arbitration clause in the contract is about short delivery. According to the defendant it did not receive full 14,250 M.T quantity. The quantity received by it was only 13941.500 M.T and it is liable to pay only for that much quantity. The point regarding arbitration clause was decided against the defendant. However, during the course of hearing of the present appeal the learned counsel for the defendant/appellant did not address any arguments on this point and, therefore, it is deemed to have been given up. Thus the only point for consideration in this appeal is as to when the delivery of goods took place and when did the liability to pay the price of goods arise. If delivery of 14,250 MT took place on or up to 9th June, 1995, the defendant would be liable to pay for this much quantity. There is no dispute about the price.

    3. Fortunately, the answer of the above questions is not difficult as it is to be found from the contract between the parties and the correspondence in relation thereto which has been placed on record. Neither party raised any dispute about the authenticity of the copies of the correspondence exchanged between the parties on this issue which have been placed on record. The case of the appellant is that against the agreed quantity of 14,250 MT it received delivery of only 13,941.500 MT and the defendant was, therefore, liable to pay to the plaintiff price of only the said quantity. There is no dispute about the price. The only dispute is about the quantity of goods supplied. In order to make good his submission the learned counsel for the appellant relied on a clause in the contract under the heading “Quantity Determination.” It is written against the said clause “AS PER ACTUAL QUANTITY RECEIVED AT THE PORTDULY CERTIFIED BY INDEPENDENT SURVEYOR/MMTC'S REPRESENTATIVE AT THE PORT/BASED ON ACTUAL DESPATCH FROM THE PORT. QUANTITY SHOULD BE CERTIFIED BY MMTC'S OFFICIAL ALSO.” On the basis of the above specification it is argued that certification from the MMTC official was essential for quantity determination. As there is no certification from the MMTC's official, it cannot be said that a quantity of 14,250 MT was finally determined. Further it was argued that the plaintiff had only offered the quantity of 14,250 MT. The offer did not mean that the quantity had been officially determined. On actual delivery it was found that the quantity was less and the defendant was, therefore, liable to pay only for the quantity supplied to it.

    4. On the other hand the learned counsel for the respondent argued that the contract was for 14,250 MT. For this quantity sufficient proof had been offered to the defendant as per the terms of the contract. The defendant did not raise any dispute about quantity at the relevant time. It took delivery of the goods as offered by the plaintiff. The present dispute about quantity being short was an afterthought. It is explained that shortage, if at all, could have occurred while packing the goods in bags by the clearing agent as per instructions of the defendant. In such a bulky cargo some amount of shortage could occur due to loss in packing. The cargo is received in the shape of granules and is packed in bags running into thousands. The defendant must have proceeded on the basis of the quantity of material as per the bags while the contract was of the quantity of material as per the total cargo. In support of his submissions the learned counsel for the respondent/plaintiff drew our attention first to the agreement itself the relevant clauses whereof are as under :

    6. QUALITY : SPOT CARGO CF 14250 MT APPROX.

    7. DELIVERY : AT BOMBAY JNPT

    8. PAYMENT : ON ‘COD’ BASIS SELLER TO PRESENT FOLLOWING DOCUMENTS FOR PAYMENT :—

    — COMMERCIAL INVOICE

    — WEIGHT CERTIFICATE ISSUED BY INDEPENDENT

    — SURVEYOR WHICH IS SGS

    — CERTIFICATE OF QUALITY ISSUED BY

    — INDEPENDENT SURVEYOR WHICH IS SGS.

    5. It was submitted on behalf of the respondent that the respondent complied with all the conditions contained in the contract. Clause 8 is regarding payment. Invoice of the goods was submitted. Weight certificate issued by independent surveyor which is SGS was submitted. A certificate of quality issued by independent surveyor that is SGS was also submitted. The term of payment as per the contract was COD i.e, ‘cash on delivery’ basis. Therefore, there could be no hurdle in the way of respondent being paid the price of the goods. About the reliance placed on behalf of the appellant on Cl.9 which relates to quantity determination it is submitted that proof of actual quantity received at the port as certified by the independent surveyor had been submitted. About the requirement of a certificate from MMTC official our attention was invited to appellant's own letters dated 9th June, 1995 to the Asstt. Collector of Customs showing that they accepted the quantity as 14,250 MT and that was sufficient compliance of the said requirement. The correspondence which followed in our view really clinches the issue. Of 7th June, 1995 itself there are three letters on record. First is a letter by the respondent (Dimple Overseas) to the Assistant Collector of Customs, JNPT, Bombay confirming having sold 14,250 MT of DAP, ex JNPT to MMTC, i.e, the appellant. It was further intimated to the customs that the consignment would be cleared by MMTC. Second letter of 7th June, 1995 is by respondent/Dimple Overeseas to M/s. Vilas Transport Company, the clearing agent. This also contains a confirmation from the side of the plaintiff regarding sale of 14,250 MT of DAP, ex JNPT to MMTC. The clearing agent who was so far the clearing agent of the plaintiff was requested to deliver the entire consignment directly to the buyer i.e MMTC. This means delivery instructions were issued on 7th June. 1995 itself. The third letter of 7th June, 1995 is by Vilas Transport Company i.e the clearing agent to the MMTC i.e the defendant/appellant. The said letter needs to be reproduced :

    7-6-1995

    The General Manager,

    M/s. MMTC Ltd.

    Core 1, Scope Complex,

    7, Institutional Area, Lodi Road,

    NEW DELHI

    Dear Sir,

    We hereby confirm that we are clearing 14,250 MT of Di Ammonium Phosphate (DAP) of Jordanian origin arrived per vessel, m.v Al. Shams imported by M/s. Dimple Overseas Limited, New Delhi,

    We further confirm that we are holding the above cargo spot purchase with us in JNPT cylos and will deliver as per the instructions to be received from you or from your Bombay office from time to time.

    We have also bagged 3,300 MT in 50 kg bags which is lying at the port ready for despatch. Please give us despatch instructions accordingly.

    Thanking you

    Yours faithfully,

    VILAS TRANSPORT CO.

    PARTNER

    6. On 8th June, 1995 appellant wrote to the respondent signifying acceptance of the offer to buy 14,250 MT of DAP in bulk. This shows that the entire quantity was lying in the shape of one consignment in bulk. The next letter is a letter dated 9th June, 1995 from appellant to the Assistant Collector of Customs. This letter has an important bearing and needs to be reproduced :

    9th June, 1995

    The Asstt. Collector of Customs,

    Customs House,

    Jawaharlal Nehru Port Trust.

    Nhava Sheva,

    BOMBAY

    Sub : Purchase of 14,250 MT of Di-Ammonium Phosphate

    Ex-JNPT Port.

    Dear Sir,

    We hereby confirm having purchased 14,250 MT of Di-Ammonium Phosphate from M/s. DIMPLE OVERSEAS LIMITED, 10/60, Industrial Area, Kirti Nagar, New Delhi-110015 Ex-JNPT Port.

    We further confirm that the said consignment will be cleared by us and the goods imported/purchased are for use as manure by farmers only.

    Thanking you,

    Yours faithfully,

    for MMTC Limited

    (S.K PATRA)

    GENERAL MANAGER (FERT)

    CC to M/s. Dimple Overseas Ltd., 10/60, Industrial Area. Kirti Nagar, New Delhi-110015.

    7. By this letter the defendant/appellant confirmed having purchased 14,250 MT of DAP from the plaintiff ex JNPT. The defendant also confirmed that the said consignment would be cleared by it. This means that on 9th June, 1995 the defendant/appellant confirmed the purchase of the cargo and also confirmed to the Customs that it will be clearing the goods. It signifies acceptance of delivery of goods by MMTC. The question of clearing the goods by the appellant would arise only when the property in goods has passed. The relevant provision contained in the Sale of Goods Act in this behalf is S.33 The said provision is reproduced as under:

    “33. Delivery — Delivery of goods sold may be made by doing anything which the party is agreed shall be treated as delivery or which has the effect of putting the goods in the possession of the buyer or of any person authorised to hold them on his behalf.”

    8. In this case the goods had come in the possession of the buyer and that is why the buyer confirmed that it would clear the goods. This fact is further established from a fax message sent on 9th June, 1995 by the defendant/appellant to Vilas Transport Company, Bombay i.e, the clearing agent. In the said fax message despatch instructions were given by the defendant to the clearing agent. The instructions are for transportation of specified quantities of the cargo packed in bags for this purpose. The clearing agent was further requested to contact the regional office of the MMTC at Bombay for further necessary instructions regarding despatch and payment of transportation charges. This fax message from MMTC to the clearing agent in our view completely clinches the issue in favour of the plaintiff. Unless the property in goods had passed to the defendant/MMTC there could be no occasion for MMTC to issue despatch instructions regarding goods to its clearing agent. M/s. Vilas Transport Company and Company were the clearing agents of the MMTC is established from MMTC's own inter-departmental fax message dated 19th June, 1995 where the said clearing agent has been described as “our handling agent.” In this connection letter dated 15th June, 1995 is also relevant and Important. This is a letter from Vilas Transport Company i.e clearing agent to MMTC where MMTC has referred to “existing contract agreement with you.” Further Vilas Transport Company informed MMTC in the said letter that “deliveries have been effected as per your despatch instructions dated 9th June, 1995 to the following places...............”

    9. The clearing agent had confirmed to the defendant about quantity of 14,250 MT held by them. The plaintiff had vide its letter dated 20th June, 1995 submitted following original documents to the defendant:

    1. B/L Nos. 1 to 5 all dated 25-4-1995.

    2. Weight certificate of Eurabia Shipping and Intl. Transport Co. certifying that 14,250 MT were loaded.

    3. Quantity certificate from SGS in respect of the consignment.

    4. Quality certificate from SGS in respect of the consignment.

    5. Certificate of origin issued by Singapore Indian Chamber of Commerce and Industry.

    10. The copy of the surveyor's report in respect of the quantity and clearing agent's confirmation that it was holding the aforesaid cargo of 14,250 MT are on record. These documents were not disputed.

    11. Thereafter there are several letters on record including some legal notices sent on behalf of the plaintiff requiring the defendant to pay the balance price which the defendant failed to pay and ultimately the plaintiff had to file the present suit.

    12. Besides the correspondence referred to above it is important to note that as per the agreement between the parties the delivery of the goods was ex JNPT, Bombay. This means that the delivery was to be effected at the Bombay Port as per the contract. The quantity of the goods naturally had to be determined at the time of delivery and not subsequently. For quantity determination reference was also invited to photo copies of the certificate of the independent surveyor M/s. J.B Boda Surveyors Private Limited, Bombay as proof of delivery of the contracted quantity. A copy of the certificate is on record. Thus the requirement as to quantity determination under Cl.9 of the agreement was also satisfied. The only point about which the appellant raised a question is about there being no certification of quantity by MMTC officials. To this answer is contained in MMTC's own letter dated 9th June, 1995 confirming purchase of 14,250 MT. To us it appears that the dispute about quantity is an afterthought to avoid payment. First time this dispute was raised by the appellant was in its letter dated 14th July, 1995 where it was stated that “MMTC would release final payment on the basis of actual quantity received at the port based on actual despatch from the port duly certified by the MMTC officials. .....” This letter was immediately replied by the plaintiff on 17th July, 1995. In the reply plaintiff placed reliance on Cl.8 of the contract regarding payment which is ‘cash on delivery’ basis. The plaintiff categorically stated that there was no agreement that final payment would be made only after the despatches are completed and on the basis of report of MMTC officials. Despatches would depend on the sweet-will of the appellant besides other factors. Payment could not be linked to this. This plea taken by the appellant, in our view, was totally false and was intended to avoid payment. The MMTC letter dated 9th June, 1995 addressed to the Assistant Collector of Customs wherein MMTC confirms having purchased 14,250 MT of DAP leaves no scope for the MMTC to dispute the quantity as at the time of delivery ex JNPT, Bombay and, therefore, in our view the MMTC i.e the appellant is liable to pay the price of 14,250 MT. No other dispute was raised. In view of this clear position emerging from admitted documents on record, no case was made out for grant of leave to defend the suit. In our view the learned single Judge rightly rejected the application of the appellant for leave to defend the suit.

    13. Accordingly we endorse the finding of the learned single Judge “that the plaintiff had divested itself of the possession and property in goods in favour of the defendant and the property in the goods vested in the defendant through their agent at the most on 9th June, 1995. The sale and transfer of the property in the goods from plaintiff to the defendant thus was complete on 9th June, 1995. This delivery was accepted by the defendant without any reservation and defendant had dealt with the goods as owner after taking such delivery on 9th June, 1995. The defendant is liable to make payment of the price of the goods weighing 14,250 MT.”

    14. According to the plaintiff the principal outstanding amount was Rs. 1,05,55,490/-. On this amount the plaintiff claimed interest @ Rs. 24% p.a The suit was filed on 16th September, 1996. Interest was included in the amount claimed in the suit up to the date of institution of the suit and, therefore, a sum of Rs. 1,37,22,137/- was claimed as the suit amount besides pendente lite future interests and costs. The learned single Judge passed a decree in the sum of Rs. 1,37,22,137/-along with interest @ 18% p.a on the principal amount of Rs. 1,05,55,490/- from the date of institution of the suit till realisation. The learned counsel for the appellant argued that the rate of interest awarded by the Court was too high. The transaction in suit was a commercial transaction. As per the decree and judgment in the suit the delivery of the goods took place latest on 9th June, 1995. The condition regarding payment was ‘cash on delivery’. Therefore, the plaintiff became entitled to the price of the goods on the said date. The plaintiff has been deprived of the amount for such a long time. The suit which was filed on 16th September, 1996 was decreed on 7th February, 2000. Thereafter the execution of the decree could not take place in view of the present appeal. The plaintiff/respondent has thus been deprived of the money due to it for nearly six years as of now. We would not like to interfere with the decision of the learned single Judge regarding award of interest as well as about the rate of interest.

    15. We find that the appeal has no merit and the same is dismissed with costs.

    16. Before parting with this judgment we would like to note that the learned counsel for respondent had raised a preliminary objection regarding maintainability of the appeal on the ground that the appellant had failed to file certified copy of the judgment under appeal. The appellant has filed an affidavit stating that the certified copy of the judgment dated 7th February, 2000 was applied for on 17th February, 2000 but the same is not yet ready and, therefore, it has not been made available to the appellant so far. The appellant has annexed with the affidavit photo copy of the receipt issued by the registry of this Court for the application for certified copy. The receipt shows that the next date on which the delivery of the certified copy is likely to be given is 7th June, 2001. Accordingly the preliminary objection is not tenable and is disposed of as such.

    Appeal dismissed.