Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

This appeal challenges an order of Shri N.C. Gupta, Sub Judge 1st Class, Delhi, which accepted objections filed by M/s. Tribhuwan Das Lalji Patel to an umpire's award made by Shri Ram Labhaya and, consequently, refused to make that award a rule of the Court.

The underlying facts (as stated in the opinion) are: a contract was entered into between the Union of India and M/s. Tribhuwan Das Lalji Patel (Bhavnagar) for the supply of Indian teak sleepers of specified sizes and rates. Deliveries were to be made monthly from June 1952 and the full quantity delivered by 31 December 1952. The contract incorporated the Supply Department's general conditions (form W.S.B. 133), which included an arbitration clause providing for two arbitrators (one appointed by each party) and an umpire in case of disagreement.

Disputes arose regarding the alleged non-supply of the contracted goods and the Government's claim for damages. The arbitrators disagreed, and the matter was referred to the umpire, Shri Ram Labhaya, who made an award on 21 November 1960 upholding the Government's claim for damages to the extent of Rs. 18,320. On filing the award in Court, the contractor objected, contending the award contained an error apparent on the face of it. The trial Court accepted those objections, set aside the award, and dismissed the Union of India's application to make the award a rule of Court. The Union of India appealed from that decision.

Legal Issues Presented

  1. Whether Clause 11(3) of the contract (part of the Supply Department's general conditions) entitles the Government to recover damages from the contractor irrespective of whether the Government actually suffered any loss.
  2. Whether Illustration (a) to Section 73 of the Indian Contract Act (as interpreted in some decisions) requires or permits compensation to be awarded to a buyer without proof of actual loss, i.e., whether compensation can be awarded even when no loss was sustained and no repurchase was proved.
  3. Whether the umpire's award contained an error apparent on the face of it sufficient to justify the trial Court in setting the award aside and refusing to make it a rule of Court.

Arguments of the Parties

Appellant's Arguments (Union of India)

  • Counsel for the appellant, Mr. Brijbans Kishore, argued that Clause 11(3) of the contract must be read to mean that the Government was entitled to damages irrespective of whether it suffered any loss because of the contractor's failure to supply.
  • He relied on Illustration (a) to Section 73 of the Contract Act to support the proposition that compensation may be measured by the difference in prices even if the buyer did not actually procure substitute goods or suffer a loss.
  • He relied on the decision in Vishwanath v. Amarlal (AIR 1957 Madh Bha 190) and other authorities to support his interpretation that a buyer may be entitled to compensation without proving repurchase or actual loss.

Respondent's Arguments (M/s. Tribhuwan Das Lalji Patel)

  • The respondent's counsel contended that when it was admitted that the Government suffered no loss or damage, the umpire could not properly award damages because damages can only be awarded when there is actual loss.
  • The respondent challenged the award on the ground that it contained an error apparent on the face of it and thus should be set aside — a ground the trial Court accepted.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Vishwanath v. Amarlal, AIR 1957 Madh Bha 190 Interpreted Illustration (a) to Section 73 of the Contract Act as entitling a buyer to compensation measured by the difference in prices without proof of repurchase or actual loss. The court considered this decision but expressly disagreed with its expansive interpretation of Illustration (a), concluding that it cannot be read to allow compensation where no loss was suffered.
Errol Mackay v. Kameshwar Singh, AIR 1932 PC 196 (Privy Council) Held that where an available market existed at the date of breach, damages are to be based on the difference between the market price and the contract price; a resale contract becomes immaterial in that context. The court treated the Privy Council's observations as addressing the measure or quantum of damages when a market exists, not as authority for awarding compensation irrespective of any loss; the opinion rejected an expansive reading that would relieve a claimant from proving any loss.
Ismail Sait and Sons v. Wilson & Co., AIR 1919 Mad 1053 Was treated (by some earlier decisions) as supporting compensation without proof of loss in certain contexts. The court regarded the reasoning in that decision as suffering from the same fallacy as the Madhya Bharat decision and did not accept it as authority for awarding compensation where there was no loss.
Dhulipudi Namayya v. Union of India, AIR 1958 Andh Pra 533 Affirmed that courts award damages for breach of contract only by way of compensation for loss suffered and not as punishment. The opinion cited this case as supporting the principle that damages must correspond to actual loss and that courts do not award punitive sums in breaches of contract.
Sita-ram Bindraban v. Chiranjilal Brijlal, AIR 1958 Bom 291 Reiterated the compensatory nature of damages for breach of contract. Used as authority consistent with the proposition that damages are compensatory and tied to actual loss.
Jado Prasad v. Jamuna Prasad, AIR 1946 Pat 263 Held that under Section 73 compensation is not to be given for remote or indirect loss and that a cause of action under the section arises only when damage is actually suffered. The court expressed respectful agreement with this decision and relied on its principle that actual damage is a prerequisite for compensation under Section 73.

Court's Reasoning and Analysis

The court's reasoning proceeded from a careful textual analysis of Clause 11(3) of the contract and from a harmonising interpretation of statutory provisions and authorities (as cited in the opinion). The court's analysis can be summarized step-by-step as follows:

  1. Interpretation of Clause 11(3): The court set out the clause (which provides the Government three options when the contractor fails to deliver: (a) recover liquidated damages of 2% per month; (b) purchase elsewhere at the risk and expense of the contractor and recover any resulting loss; or (c) cancel the contract). The clause also states that where action is taken under (b) or (c) the contractor shall be liable for any loss which the purchaser may sustain, but the contractor shall not be entitled to any gain on repurchases.
  2. Conclusion from Clause 11(3): From the language of the clause the court concluded that the Government can recover only loss actually sustained and cannot claim damages if no loss is sustained. The court rejected the appellant's argument that the use of the words "shall" and "may" in different parts of the proviso indicates an unconditional liability to pay damages irrespective of loss. The court held the contractor's liability to reimburse exists only if there is any loss.
  3. On Illustration (a) to Section 73: The appellant relied on Illustration (a) and decisions construing it (including Vishwanath v. Amarlal) to argue that compensation can be awarded in the sum equivalent to the price shortfall whether or not the buyer actually obtained substitute goods. The court rejected this expansive reading, holding that Illustration (a) must be construed in light of Section 73 itself and its qualified language. The court emphasised that Section 73 excludes compensation for remote or indirect loss and that the statute presupposes actual damage.
  4. On the Privy Council authority (Errol Mackay): The court noted that the Privy Council's remarks about market price were directed to the quantification of damages when a market existed on the date of breach (where the law presumes the buyer can minimize damages by procuring substitutes). The court rejected the argument that the Privy Council laid down a principle permitting compensation without proof of loss; rather the Privy Council's observations related to how damages should be estimated where market substitutes exist.
  5. Reliance on other authorities and statutory recognition: The court cited Section 62 of the Sale of Goods Act to recognise that parties may contractually create special measures of damages, but emphasised that generally courts award damages only as compensation for actual loss (not as punishment). It referred approvingly to several High Court decisions (Dhulipudi Namayya; Sita-ram Bindraban; Jado Prasad) that align with the view that Section 73 requires proof of actual damage and excludes remote or indirect losses.
  6. Final analytical step: Because the contract clause and the relevant principles in Section 73 (as interpreted) require a showing of loss, and because the appellant conceded Section 74 was not attracted, the court concluded that the umpire's award could not stand where it purported to award damages in the absence of proven loss. On that basis, the court upheld the trial court's decision (albeit for reasons different from those originally given by the trial court) and dismissed the appeal.

Holding and Implications

Holding: The court's final decision was to dismiss the appeal and to uphold the trial court's order setting aside the umpire's award and refusing to make the award a rule of the Court. The opinion concludes: "In this view of the matter, though for a different reason, I uphold the decision of the trial court and dismiss this appeal with costs."

Implications:

  • The direct effect is that the trial court's order setting aside the award and not making it a rule of Court remains in force; the Union of India's appeal was dismissed with costs.
  • The court's reasoning emphasises that, under Clause 11(3) of the contract and under the general principle in Section 73 of the Contract Act, damages for breach of contract are compensatory and require actual loss. The opinion rejects an interpretation of Illustration (a) to Section 73 (and certain earlier case-law readings) that would permit recovery without proof of loss.
  • The court observed that parties are free, by agreement, to stipulate alternative measures of damages (and Section 62 of the Sale of Goods Act acknowledges such freedom), but where the contractual language and statutory scheme presuppose actual loss, courts will not award compensation in the absence of loss.
  • No broader, novel precedent expanding the compensatory scope of Section 73 was created: the judgment reaffirms the compensatory principle and rejects the view that a buyer may recover in all cases without establishing loss.

Note: This summary is confined strictly to the facts, arguments, authorities, reasoning and disposition as they appear in the provided opinion. No information has been added that was not present in the text supplied.

    Union Of India v. M/S. Tribhuwan Das Lalji Patel .

    1. This appeal is directed against the order of Shri N.C Gupta; Sub Judge 1st Class, Delhi whereby the objections filed by M/s. Tribhuwan Das Lalji Patel to an award made by Shri Ram Labhaya were accepted and the award was not made a rule of the Court.

    2. The facts leading up to the award were that a contract for the supply of Indian Teak Sleepers of specified sizes at a specified rate was entered into between the Union of India and M/s. Tribhuwan Das Lalji Patel of Bhavnagar. The contracted goods had to be supplied to the Union of India on monthly basis from June, 1952 onwards and the total quantity was to be supplied by 31st December, 1952. The contract entered Into by the Union of India was subject to its Supply Department's general conditions of contract contained in a printed booklet known as form W.S.B 133, These general conditions, inter alia, contained an arbitration clause under which in case of a dispute between the parties and differences arising between them the same were to be referred to the arbitration of two arbitrators, one to be appointed by each of the contracting parties and in case of disagreement to an umpire for his adjudication. Disputes did arise between the parties as to the claim of damages of Union of India arising out of the alleged non-supply of the contracted goods by the other party. The arbitrators did not agree among themselves and so the matter was referred to Shri Ram Labhaya, Umpire, who made his award on 21st November, 1960, By this award the Government's claim for damages was upheld to the extent of Rs. 18,320/-. On the award being filed in Court the Contractor filed objections against it and contended that the award is liable to be set aside as it suffered from an error apparent on the face of it. The trial Court agreeing with the contention set aside the award and dismissed the application of Union of India for making the award a rule of the Court. Aggrieved, the Union of India has preferred this appeal.

    3. Mr. Brijbans Kishore, the learned counsel for the appellant, has urged that on a reading of CL 11(3) of the conditions of contract it would be dear that irrespective of whether the Government suffered any loss or not on account of the contractor's failure to supply the contracted goods, the Government was entitled to damages. He further contended that the award was justified in terms of illustration (a) under Section 73 of the Contract Act, The learned counsel for respondent, on the other hand, contended that when admittedly the Government suffered no Joss or damage, the umpire could not award damages as damages can only be awarded provided there is a loss.

    4. Clause 11(3) of the conditions of contract reads as under:—

    “Failure and Termination. Should the contractor fail to deliver the stores or any consignment thereof within the period prescribed for such delivery the Secretary, Department of Supply shall be entitled at his option either:—

    (a) to recover from the contractor as “liquidated damage, and not by way of penalty, a sum of 2% of the price of any stores which the contractor has failed to deliver as aforesaid; for each month or part of a month during which the delivery of such stores may be in arrears.

    (b) to purchase elsewhere, without notice to the contractor on the account and at the risk of the contractor, the stores not delivered or others of a similar description (where others exactly complying with the particulars are not in the opinion of the Secretary, Department of Supply which shall be final, readily procurable) without cancelling the contract In respect of the consignment not yet due for delivery, or

    (c) to cancel the contract.

    In the event of action being taken under (b) or (c) above the contractor shall be liable for any loss which the purchaser may sustain on that account but the contractor shall not be entitled to any gain on repurchases made against default”

    5. Under this clause it is apparent that if the Contractor fails to deliver the stores or part of the stores, the Government becomes entitled at its option either Co recover as liquidated damages a sum of 2 per cent, of the price of the stores not supplied or if they are supplied late; or to purchase the stores not supplied or short supplied from anywhere else at the risk and expense of the contractor and claim any excess price paid by the Government; or to cancel the contract. In case there is risk purchase or cancellation of contract the contractor is liable for any loss which the purchaser or the Government may sustain. But the contractor will not be entitled to payment of any gain made by the Government on repurchase. Thus, it is apparent that the Government can recover only loss sustained by it and cannot claim damages from the contractor if no loss is sustained. Mr. Brijbans Kishore urged that in the proviso to Cl. 11(3) read above the word “shall” has been used to fix the liability of the contractor but the word “may” has been used with regard to any loss that may be sustained by the Government and this would tend to mean that irrespective of the loss there is a liability on the contractor to pay damages. I cannot agree to this interpretation of the clause as a very reading of the proviso would show that the contractor's liability to reimburse the Government exists only if there is any loss.

    6. Mr. Brijbans Kishore strongly relied on illustration (a) given under Section 73 of the Contract Act and urged that this Illustration amplifies the legislative intent contained in Section 73 as opposed to Section 74 of the Contract Act and irrespective of any loss compensation has to be paid by the person who breaks the contract in the sum equivalent to the price which falls short of the price at which the other party might have obtained the goods whether the same were obtained or not. In support of his contention he first relied on a decision of the Madhya Bharat High Court in Vishwanath v. Amarlal, AIR 1957 Madh Bha 190. It was held by Dixit, J, that:

    “In a suit for damages for breach of a contract for sale of goods it is not necessary for the plaintiff to prove that he purchased the goods from other sources at a price exceeding the contract price and sustained a loss. The fact that the buyer sustained no actual loss from the seller's failure to deliver the goods is no ground for awarding nominal damages to the buyer. The buyer is entitled as indicated by Illustration (a) to Section 73, Contract Act, to receive from the seller by way of compensation the sum by which the contract price falls short of the price for which the buyer might have obtained goods of like quantity at the time when they ought to have been delivered.”

    7. The learned Judge came to the above conclusion primarily on the basis of the decision of the Privy Council in Errol Mackay v. Kameshwar Singh, AIR 1932 PC 196. To my mind the decision of the judicial committee cannot be construed in the manner it has been construed by Dixit, J. or now sought to be construed by Mr. Brijbans Kishore. In the case before the Privy Council the facts were as under:—

    A contract was entered into on 9-11-1912 for the sale of 200 mds. of new crop Java indigo seed at Rs. 22/- per maund excluding bags, f.o.r, Purnea, railway station, delivery to be made in April, 1920 between the parties. The plaintiff had given Rs. 1,000/- as earnest money. The defendant failed to make the deliveries as stipulated. The question that arose for determination was what estimated damages and with reference to which date the defendants were liable to pay the plaintiff. After determining the date of breach their Lordships of the Privy Council observed as under:—

    “……………On the basis of the date of 30th April, 1920, it is now necessary to consider how the damages are to be estimated. If there was an available market for the goods at the date of breach the damages must be based on the difference between that market price and the contract price: a contract of resale becomes immaterial, because if there was a market, the law presumes that the buyer can minimize his damages by procuring substituted goods in the market, so that he is thus in the same position, apart from the difference in price as if the seller had not made default. Hence the difference of price, if the market price exceeds the contract price, is the sole damage in general re-coverable……………”

    8. From the above quoted observations it is sought to be argued that the question of market price was immaterial and no repurchase is required to be proved. In my view, the observations of the Privy Council were made only in the context of fixing the quantum of damages and does not lay down the proposition that irrespective of whether there was any loss or not damages must still be paid. In fact, a reading of Section 73 of the Contract Act makes this obvious. Illustration (a) to Section 73, Contract Act, has to be construed in the light of the statutory provision so as to harmonise with the principles laid down in the section and not to enlarge the scope of the section by imputing to the statute something what is not stated therein. It is specifically provided in the second clause of Section 73 that that compensation is not to be given for any remote or indirect loss or damage. If even indirect loss or damage is excluded it cannot be conceived how compensation can be awarded when there has been no loss or damage. The decision in Ismail Sait and Sons v. Wilson and Co., AIR 1919 Mad 1053, also, in my opinion, suffers from the same fallacy. I am in respectful disagreement with the rule laid down in the Madhya Bharat and the Madras decisions.

    9. To my mind the principle is well settled that the measure of damages, normally, in case of breach of contract for sale of goods, is a difference between the contract price and the market price on the date of the breach. It is, however, open to the parties to the contract to create for themselves any special rights and obligations that they may please, such as providing therein measure of damages in case of breach of contract and specifically exclude the conditions which law generally attaches to contract of sale of goods.

    10. In fact Section 62 of the Sale of Goods Act is a statutory recognition of this right in the parties. As was observed by Bench of the Andhra Pradesh High Court in Dhulipudi Namayya v. Union of India, AIR 1958 Andh Pra 533:

    “It is well settled that courts will give damages for breach of contract only by way of compensation or loss suffered and not by way of punishment.”

    11. The same rule was laid down by a Bench of the Bombay High Court in Sita-ram Bindraban v. Chiranjilal Brijlal, AIR 1958 Bom 291, and by a Bench of the Patna High Court in Jado Prasad v. Jamuna Prasad, AIR 1946 Pat 263. In the last noted case it was observed that

    “under the terms of Section 73 the compensation is not to be given for any remote or indirect loss or damage sustained by reason of the breach of contract. The section does not give any cause of action unless and until the damage is actually suffered.”

    12. I am in respectful agreement with the observations contained in the decision of Jado Prasad's case, AIR 1946 Pat 263. If the contrary view was to be taken the provision of section 73 will become nugatory and a party would be penalised though the other party has suffered no loss. Mr. Brijbans Kishore frankly conceded that Section 74 was not attracted in this case and so I need not comment upon that aspect of the case relied upon by the lower Court.

    13. In this view of the matter, though for a different reason, I uphold the decision of the trial court and dismiss this appeal with costs.

    14. Appeal dismissed.