Structured Summary of the Opinion — O.P. Nos. 95 & 96 of 2003

Factual and Procedural Background

Two Original Petitions (O.P. No. 95 of 2003 and O.P. No. 96 of 2003) were filed under Section 34 of the Arbitration and Conciliation Act, 1996 seeking to set aside awards dated 21.09.2001 issued by the second respondent (the Arbitrator). Both petitions arise out of disputes under two separate railway construction agreements: Agreement No. 152.CN/95 dated 16.10.1995 (O.P. No. 95 of 2003) relating to superstructure construction across the Manimutharu river; and Agreement No. 206.CN/95 dated 01.12.1995 (O.P. No. 96 of 2003) relating to construction across the Vellar river. The parties and disputes in both petitions are the same and therefore were disposed of by a common order.

Procedurally, earlier O.Ps (O.P. Nos. 271 and 252 of 1998) led to the appointment of the second respondent as Arbitrator by an order dated 25.02.1999. Separate awards were made on 21.09.2001 and clarification orders were issued by the Arbitrator on 05.11.2001. The petitioner challenged those awards and clarification orders under Section 34.

The factual matrix before the Arbitrator (and summarized in this opinion) included: tendering and award of contracts (work order and agreement dates noted); disputes over timing and approval of designs and drawings; alleged delays in handing over the site; alleged short supply and delayed supply of steel cribs needed for girder launching; severe floods in December 1996 causing damage and loss of materials; subsequent non-payment or withholding of payments by the petitioner; off-loading/termination of part of the work and award to another contractor (M/s K.S. & Co.); and claims and counterclaims relating to compensation, counter-claims for damages and costs, and release of bank guarantees/security deposits.

Legal Issues Presented

  1. Whether the arbitral awards dated 21.09.2001 (and the Arbitrator's orders of 05.11.2001) are liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.
  2. Whether the Arbitrator's factual findings and legal conclusions (including findings on breach, termination, entitlement to compensation for flood losses, entitlement to release of bank guarantees, and counter-claims) are vitiated by errors that fall within the limited grounds for interference under Section 34 (for example, fraud, bias, violation of natural justice, or patent illegality).
  3. More specifically (as framed by the Arbitrator and treated in the proceedings): issues such as whether the respondent (petitioner in the Section 34 petition) committed breach of contract; whether termination was legal and valid; entitlement to compensation for flood losses and other heads of loss; entitlement to release of bank guarantees/security deposits; liability for counter-claims; and appropriate interest and costs.

Arguments of the Parties

Petitioner's Arguments (seeking to set aside the award)

  • The Arbitrator did not evaluate the evidence properly.
  • The award is contrary to the express provisions of the contract and therefore liable to be set aside.
  • Implicit in the petitioner's case were allegations supporting termination/off-loading under contract clauses (the petitioner argued that the contractor had not taken serious steps to execute work, delays in casting girders, machinery failures, and thus termination/off-loading was within the Railway's rights under para 29.2 and related clauses).

First Respondent's Arguments (defending the award)

  • No ground as contemplated under Section 34 was made out to set aside the award.
  • The court should not re-evaluate evidence or substitute its own view for that of the Arbitrator.
  • Relied on the Supreme Court decision McDermott International Inc. v. Burn Standard Co. Ltd. & others (2006) 11 SCC 181 and an unreported judgment of this Court (Union of India owning Southern Railway v. TECCO) to support minimal interference with arbitral awards and the limited supervisory role of courts.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
McDermott International Inc. v. Burn Standard Co. Ltd. and others, (2006) 11 SCC 181 Describes the limited supervisory role of courts under the 1996 Act: interference is to be minimal; courts may intervene in cases of fraud, bias, violation of natural justice, or patent illegality that goes to the root. The Court relied on this precedent to emphasise that Section 34 allows only limited interference and that it cannot re-evaluate evidence or substitute its view for that of the Arbitrator in absence of the narrow grounds for interference.
Union of India owning Southern Railway v. TECCO Trichy Engineers & Contractors (unreported), O.P. No. 547 of 2006 (15.12.2006) Observations on treatment of extraordinary floods as an act of God and deference to arbitral findings where arbitrators had inspected the site and unanimously accepted the flood as an act of God. The Court cited its own earlier unreported judgment to support deference to the Arbitrator's factual finding that the flood was an act of God and to reinforce that such factual conclusions, especially after site inspection, are not open to interference under Section 34.
M/s. Hind Construction v. State of Maharashtra, AIR 1979 SC 720 Authority applied by the Arbitrator (and cited by this Court) in determining whether "time is the essence" and in whether certain contractual clauses (like invoking Clause 17(4)) could be applied to deny claims or invoke termination. The Arbitrator relied on this Apex Court decision to hold that time was not the essence of the contract for this project and that Clause 17(4) could not be invoked as contended by the petitioner; this view was accepted as reasonable by this Court.
M/s. Brijpal Singh v. State of Gujarat, AIR 1984 SC 703 Authority for the law relating to compensation for off-loading of work and related claims for loss of profit. The Arbitrator relied on this case in awarding compensation for loss due to off-loading/work being handed over to another contractor (Issue No. 6); this reliance was accepted by the Court.
Renusagar Power Co. Ltd. v. General Electric Co. Principle that arbitral awards can be set aside if contrary to (a) fundamental policy of Indian law; (b) the interests of India; or (c) justice or morality (narrow meaning of "public policy"). The Court reproduced these principles (via McDermott) to explain the limited scope of judicial review under Section 34 and to show that interference requires a fundamental/public-policy type of illegality.
Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (ONGC) Expanded the scope of public policy to include patent arbitrariness as an additional ground for interference with an arbitral award. The Court cited the ONGC line to explain that patent illegality must be such as to go to the root of the matter; the decision is used to frame the threshold for interference under Section 34.
Central Inland Water Transport Corpn. Ltd. v. Brojo Nath Ganguly Considered the applicability of "public policy" with reference to Article 14 of the Constitution and Section 23 of the Indian Contract Act, particularly in cases of patently arbitrary contractual terms. Referenced by the Court (through discussion in other precedents) to explain the narrower tests for public policy and to caution against setting aside awards unless the arbitral decision contravenes these fundamental norms.

Court's Reasoning and Analysis

The Court proceeded by careful review of the pleadings, evidence, the Arbitrator's framed issues (16 issues enumerated by the Arbitrator) and the Arbitrator's findings on those issues. The Court emphasized the limited scope of interference under Section 34 of the 1996 Act and applied that standard throughout its analysis.

Key steps in the Court's reasoning:

  1. Deference to Arbitral Findings on Factual Questions: The Court repeatedly held that many disputed matters (e.g., whether there was delay in furnishing/approving drawings, delay in handing over the site, adequacy/timeliness of supply of steel cribs, the extent and consequences of the December 1996 floods) were pure questions of fact. The Arbitrator had elaborately evaluated evidence (and in some cases conducted site inspection), and the Court found no basis to re-evaluate that evidence under Section 34.
  2. Issue-by-Issue Evaluation: The Court summarized and accepted the Arbitrator's findings issue-wise where appropriate:
    • Issue No.1 (breach): Arbitrator found petitioner committed multiple breaches (delays, inadequate supply of cribs, non-payment, illegal termination favoring another agency); Court upheld these findings as based on evidence and interpretation of contract clauses and not open to interference under Section 34.
    • Issue No.2 (legality of termination): Arbitrator found termination illegal, relying in part on Clause 17(2) of GCC and on Hind Construction; Court accepted this reasoning and the conclusion that Clause 17(4) had not been properly invoked to justify termination.
    • Issue No.3 (compensation for flood losses): Arbitrator found claimant entitled to compensation limited to loss of material; Court treated this as a factual finding and declined to interfere.
    • Issue No.6 (loss due to off-loading of work and profit): Arbitrator found in favour of claimant, relying on Brijpal Singh; Court accepted the reasoning and rejected the challenge.
    • Issues Nos. 4, 5, 7: Held against the first respondent by the Arbitrator and not challenged by the first respondent, hence not gone into further by the Court.
    • Issue No.8 (release of bank guarantee and security deposit): Arbitrator held claimant entitled to release; Court accepted that Clause 17(4) could not be invoked and relied on Hind Construction for applicability to facts.
    • Issues Nos. 9 & 15 (counter-claims on risk and cost): Arbitrator found petitioner not entitled to counter-claim; Court upheld this as dependent on Issues 1 & 2 findings.
    • Issue No.10 (interest): Arbitrator awarded interest at 18% p.a. after reference to Clause 16(2) of GCC and five Supreme Court decisions; Court found the rate not arbitrary or illegal.
    • Issue No.11 (costs): Arbitrator directed parties to bear their own costs and dismissed counter-claims (Issues 12–14); Court upheld the same.
  3. Application of Precedents and Legal Principles: The Court relied on McDermott to frame the threshold for interference under Section 34—keeping the supervisory role minimal and intervening only for fraud, bias, violation of natural justice, or patent illegality going to the root. The Court also relied on the other cited authorities (Hind Construction, Brijpal Singh, Renusagar, ONGC and related decisions) to test whether the Arbitrator's conclusions offended public policy or fundamental principles. The Court concluded they did not.
  4. Conclusion on Scope of Review: The Court found the award to be a reasoned award, based on proper evaluation of evidence and correct application of law. Many grounds urged by the petitioner were treated as attempts to reframe a Section 34 petition as an appeal; the Court declined such re-evaluation.

Holding and Implications

Holding:

O.P. No. 95 of 2003 is DISMISSED and the arbitral award dated 21.09.2001 (and the Arbitrator's orders of 05.11.2001) is upheld.

O.P. No. 96 of 2003 is also DISMISSED and the corresponding award is upheld.

Consequential directions and immediate implications:

  • The awards are sustained in their entirety to the extent set out by the Arbitrator and accepted by the Court (including findings of breach by the petitioner, illegality of termination, entitlement to certain compensations, release of bank guarantee/security deposit, and award of interest at 18% p.a.).
  • The Court awarded no costs: "No costs" was the order for both petitions (each party to bear its own costs as per the Arbitrator and no costs were awarded by this Court).
  • No broader or novel legal principle was laid down by this judgment; the Court applied and reaffirmed existing standards for judicial interference under Section 34 and relied on established Supreme Court authorities and its prior unreported decision for similar factual issues (act of God/floods and deference to arbitral findings after site inspection).

Note: This summary is confined to the content of the provided opinion and does not add or infer facts beyond that text.

    The Chief Engineer (Construction Ii), (Guage Conversion), Southern Railway, Egmore, Chennai-600 008 Petitioner v. Nilakantan & Sons Pvt. Ltd., Engineers & Builders, 47, Luz Avenue, Mylapore, Chennai-600 004. 2. Hon'Ble Mr. Justice K.M Natarajan, Sole Arbitrator, No. 136, Lattice Bridge Road, Kamaraj Nagar, Thiruvanmiyur, Chennai-600 041 S

    1. Both the Original Petitions are filed to set aside the award dated 21.09.2001 passed by the second respondent pertaining to the disputes in relation to the agreement Nos. 152.CN/95 dated 1.12.1995 and 206.CN/95 dated 1.12.1995 respectively.

    2. As the parties and the dispute involved in both the Original petitions are one and the same, a common order is being passed to dispose of both the Petitions.

    3. O.P No. 95 of 2003 has been filed by the petitioner to set aside the Award dated 21.09.2001 and the further orders of the second respondent/Arbitrator dated 5.11.2001 The contract involved in O.P No. 95 of 2003 is the work of guage conversion from Madras Beach - Tiruchirapalli - Villupuram - Tiruchirapalli section - construction of a bridge with 10 × 18 metres PSC Girders, opposite to the existing MG Bridge No. 129, across the river Manimuthar and construction of bridge with 2 × 18 meter PSC Girders opposite to the existing MG Bridge No. 128, across Mari odai between VRI and VRT stations under agreement No. 152.CN/95 dated 16.10.1995

    4. The contract involved in O.P No. 96 of 2003 is the work of guage conversion from Madras Beach - Tiruchirapalli - Villupuram - Tiruchirapalli section - construction of a Bridge with 21 × 18 metres PSC Girder, opposite to the existing Bridge No. 181, across the Vellar river under agreement No. 206.CN/95 dated 01.12.1995

    5. Certain disputes arose in respect of both the agreements and the first respondent filed O.P No. 271 of 1998 in respect of the agreement dated 16.10.1993 and O.P No. 252 of 1998 with regard to the agreement dated 1.12.1995 By an order dated 25.02.1999, this Court appointed the second respondent as an Arbitrator to go into both the disputes. In both the matters separate awards were made by the second respondent/Arbitrator on 21.9.2001 The petitioner herein filed applications for clarification of both the awards and separate orders were passed by the second respondent/Arbitrator in those applications on 5.11.2001 Aggrieved by the award and the orders passed in the Clarification Applications, the above Petitions have been filed under Section 34 of the Arbitration and Conciliation Act, 1996.

    6. Heard the learned counsel for the petitioner and the learned counsel for the first respondent. I have also gone through the documents and judgments referred to by them in support of their submissions.

    7. The learned counsel for the petitioner contends that the second respondent/Arbitrator has not evaluated the evidence properly and the award passed by him is contrary to the express provisions contained in the contract and therefore, the same is liable to be set aside.

    8. Per contra, the learned counsel for the first respondent submits that no ground as contemplated under Section 34 of the Act were made out and it is not for this Court to re-evaluate the evidence to come to a different conclusion. In support of his submission, he relied on the judgment of the Hon'ble Supreme Court McDermott International Inc. v. Burn Standard Co. Ltd. and others, (2006) 11 SCC 181, and an unreported judgment of this Court made in Union of India owning Southern Railway, rep. by its Chief Engineer/Construction, Chennai-8 v. TECCO Trichy Engineers & Contractors and 3 others, O.P No. 547 of 2006 dated 15.12.2006

    9. I have considered the rival submissions carefully with regard to facts and citations.

    10. For the sake of convenience, I am referring to the award assailed under O.P No. 95 of 2003 and it is admitted by both the parties that the decision to be taken in O.P No. 95 of 2003 will cover the award challenged under O.P No. 96 of 2003 also.

    11. The dispute involved in O.P No. 95 of 2003 is relating to the agreement No. 152.CN/95 dated 16.10.1995 for the construction of superstructure across the Manimutharu river. In response to the invitation of tenders for the above work, the first respondent submitted their offer on 6.7.1995 and after negotiation, the petitioner herein accepted the tender and issued the work order on 14.8.1995 The agreement was signed on 16.10.1995 The cost of the work is valued at Rs. 69 lakhs and the period of work is nine months, i.e, by 13.5.1996 The first respondent submitted designs and drawings on 11.9.1995 and the designs were finally approved on 23.02.1996 The foundation and substructure contract works were awarded to another agency and the contract for earth filling of the embankment of approaches was given to yet another agency. According to the first respondent, by the failure of the petitioner herein in handing over the site in the required manner, the petitioner committed breach of contract. The short supply of cribs seriously handicapped the launching programme of the girders on the bed level. The first respondent was forced to adopt different pattern of casting and launching by the officials of the petitioner, which resulted extra cost and time. In the year 1996, there was heavy rain and flooding of all the rivers causing severe disruption of casting and launching of the work on the river-bed in spite of the first respondent incurring heavy expenditure on account of protective works. Because of the rains, the first respondent's office, stores, labour shed, etc. were totally submerged and the materials were washed away. It took nearly a month for the floods to recede and the first respondent thereafter assessed the extent of damages and made a claim for Rs. 19,06,067.50. Initially, the officers of the petitioner were very sympathetic and assured the first respondent, the payment of compensation for the floods and also for non-recovery of losses of materials. The first respondent was directed to get on with the work and it was decided to form a committee to assess the damages and to recommend compensation. The petitioner granted acceleration advance of 5% of the contract value. The petitioner invoking Clause 17(2) of GCC extended the time and in a meeting held on 15.9.1997, expressed sympathy and advised the first respondent to seek through Arbitration a larger compensation. But this was not adhered to and the first respondent was forced to approach this Court for appointment of Arbitrator. There was no payment for the first respondent's bills for nearly eight months after the floods. Thereafter, differences arose between the parties and the petitioner stopped completely the payment. However, on a representation made by the first respondent to the petitioner, the first respondent was allowed to carry on with the offloaded portion of the work and accordingly the first respondent went ahead with the work. However, the department stopped the work again stating that this work would be handed over to a competitor for completion. According to the first respondent, all the works were stopped to favour M/s. K.S & Co. Thereafter, the petitioner called for re-tendering as per tender notice dated 10.02.1998 for the portion of work and the tender of M/s. K.S & Co. was accepted. Despite all these provocations, it was claimed by the first respondent that they went ahead and completed whatever work was allotted to them. In the above factual background, the respondent filed a Claim Petition before the second respondent/Arbitrator.

    12. The Claim Petition was resisted by the petitioner herein by filing a counter. According to the petitioner, the designs and drawings were submitted by the Contractor only on 11.11.1995 and not on 11.9.1995 as alleged by the first respondent. The first respondent had been receiving the payment from October, 1995 towards the mobilisation advance and submission of approved drawings. The contractor could not launch the girder due to the failure of their machineries. The first respondent completed the concrete work only on 11.5.1996 Since the first respondent has not taken any step to complete the work, the stressing and launching the girders 1 to 5 were not launched prior to flood and hence the Railway is not responsible for the first respondent's failure. Though, the first respondent had to cast all the girders by 30.6.1997, they cast only 3 girders within the period. The first respondent was lethargic in carrying out the instruction of the Railway officers. The petitioner contended that as the first respondent had not taken any serious step in the execution of the work, as per para 29.2 of the agreement, the Railway has got every right to terminate or offload the contract. Therefore, the agreement was terminated on 27.01.1998 and it is upto the Railways to award the work to any other Contractor. The petitioner denied the liability to various claims made by the first respondent and instead made counter claims on the grounds of damage of girders, the cost of steel cribs, wooden sleepers, etc. due from the first respondent and also towards risk and cost.

    13. To the counter statement filed by the petitioner before the Arbitrator, the first respondent filed a rejoinder sticking to their earlier stand.

    14. On the pleadings of the parties, the second respondent Arbitrator framed the following issues:

    1. Whether the respondent has committed breach of contract as alleged ?

    2. Whether the termination of the agreement, is legal and valid ?

    3. Whether the claimant/petitioner is entitled to compensation for loss suffered due to flood in December 1996 ?

    4. Whether the claimant/petitioner is entitled to compensation for loss due to infrutous over-heads and profits due to breaches committed by the respondents ?

    5. Whether the claimant/petitioner is entitled to compensation or loss due to reduced productivity from idle of labour, machinery, equipments' etc. ?

    6. Whether the claimant/petitioner is entitled to compensation for the loss incurred due to off-loading of work and profit ?

    7. Whether the claimant/petitioner is entitled to claim increased cost in carrying out the works due to breaches of contract and delay by the respondent ?

    8. Whether the claimant/petitioner is entitled to release of the Bank guarantee given towards mobilisation and acceleration advance and security deposit ?

    9. Whether the claimant/petitioner is liable for the extra cost incurred in carrying out certain portions of the contract work through other agency ?

    10.Whether the claimant/petitioner is entitled to any interest, if so, at what rate ?

    11. Whether the claimant/petitioner is entitled to the cost of this Arbitration proceedings ?

    12. Whether the respondent is entitled to counter-claim for the loss due to damages of girders ?

    13. Whether the respondent is entitled to counter claim towards the cost of steel cribs due from the contractor/petitioner ?

    14. Whether the respondent is entitled to counter-claim for cost of wooden sleepers from the claimant/petitioner ?

    15. Whether the respondent is entitled to counter-claim underthe heads of Risk and cost ?

    16. To what relief, parties are entitled to ?

    15. Issue No. 1 relates to the breach of contract by the petitioner as alleged by the first respondent. This issue was further sub-divided into the following breaches:

    a. Delay in providing the approved drawings;

    b. Delaying in handing over the site;

    c. Not provided adequate steel cribs in time;

    d. Make claimant to adopt enormous methods of launching;

    e. Delay in withholding the payments

    f. Non-payment of compensation for the flood damages; and

    g. Illegal termination of contract and favouring another agency by awarding the balance of work at the cost of the claimant.

    16. While considering the above said breaches, the second respondent/Arbitrator found that the first respondent clearly established that there is a delay of more than seven months from the date of submission of preliminary drawings and designs and six months from the date of submission of detailed design and drawings by approving them by the petitioner. The second respondent/Arbitrator also found that there is enourmous delay in handing over the site to the first respondent. It was also found by the Arbitrator that the number of steel cribs required for launching one girder is 300 and number of steel cribs provided by the petitioner are not adequate and also not in time. Hence, the second respondent/Arbitrator accepted the contentions of the first respondent that the supply of materials were not adequate and besides there was a delay in supplying the same. The Arbitrator has also rejected the contentions of the first respondent that they were forced to adopt numerous launching methods requiring different types of arrangements, infrastructure, tools, etc. by relying on Clauses 20 & 21 of GCC. It is the finding of the Arbitrator that there are no regular payments for the work done after the floods and withholding of the payments by the petitioner for the work done by the first respondent. No amount is paid towards flood damages despite many demands by the first respondent. The second respondent/Arbitrator further found that the contract was illegally terminated and the award of the contract by M/s. K.S & Co. is irregular. Thus, the second respondent/Arbitrator found that it is the petitioner who has committed the breaches of the contract and answered the issue No. 1 in favour of the first respondent. To arrive at the above said findings, the second respondent/Arbitrator has elaborately evaluated the evidence adduced before him and this Court sitting under Section 34 of the Act 1996, cannot re-evaluate the same to find out the correctness of those findings. The above said conclusion was arrived at by the second respondent/Arbitrator purely on the basis of the evidence adduced and also by interpreting the relevant clauses contained in the agreement and I hardly find any grounds to interfere with the same.

    17. For Issue No. 2, after adverting to the fact that the petitioner had always granted extension of time without disputing the reasons given by the first respondent and after going through Clause 17(2) of GCC, the second respondent/Arbitrator found that the termination of the contract is illegal. The Second respondent/Arbitrator has pointed out the fact that even though the time is the essence of the contract under Clause 17(4) of the agreement, the clause was never invoked while terminating the contract. The second respondent has also referred to the judgment of the Apex Court M/s. Hind Construction v. State of Maharashtra, AIR 1979 SC 720, and held that time is not the essence of the contract between the parties with regard to this project is concerned. He also referred to the various documents and the oral evidence of R.W.1, who is the Deputy Chief Engineer and R.W.3, the Section Engineer, while arriving at conclusion with regard to issue No. 4.

    18. The second respondent/Arbitrator has given sufficient reasons and has also applied the correct decisions of the Hon'ble Supreme Court to answer issue No. 2 in favour of the first respondent. Thus, it is a reasoned one which is not open to any interference by this Court under Section 34 of the Act 1996.

    19. Issue No. 3 is whether the first respondent is entitled to compensation for the loss suffered due to floods. This is a pure question of fact. The second respondent/Arbitrator after elaborately dealt with the evidence in this regard held that the first respondent is entitled for compensation for the losses suffered due to flood in December 1996. The Arbitrator has also referred to Exh.C9 which is a letter dated 18.01.1997, which was marked by the first respondent containing the list of loss of items in the floods in December 1996 and found that this letter was not at all disputed by the petitioner. However, the second respondent/ Arbitrator restricted the compensation for the loss of material only and rejected the other claims in this regard. This issue being a pure question of fact, this Court can hardly interfere with the above said findings of the second respondent/Arbitrator.

    20. Issue Nos. 4 & 5 were held against the first respondent and therefore they need not be gone into in the absence of any challenge to them by the first respondent.

    21. Issue No. 6 is relating to the entitlement of confirmation to the first respondent for the loss incurred due to off-loading of work and profit. This issue was decided in favour of the first respondent in view of Arbitrator's finding in Issue Nos. 1, 2, 9 and 15. The Arbitrator has also adhered to the law in this regard by relying on the judgment of the Hon'ble Supreme Court M/s. Brijpal Singh v. State of Gujarat, AIR 1984 SC 703.

    22. I am in agreement with the reasons given by the Arbitrator for deciding the issue in favour of the first respondent and therefore the challenge to the same is hereby rejected.

    23. Issue No. 7 is held against the first respondent and therefore the same need not be gone into in the absence of challenge by the first respondent.

    24. For Issue No. 8, after going through Exh.C69 (Bills submitted for Br. No. 129 dated 24.07.1998) and after referring the Clause 17(4) of GCC, the second respondent/Arbitrator held that Clause, 17(4), GCC could not be invoked as contended by the petitioner. The second respondent/Arbitrator has also referred to the Hon'ble Supreme Court judgment M/S. Hind Construction v. State of Maharashtra, AIR 1979 SC 720, in this context and found that the ratio laid down in the above decision is applicable to the facts of the case on hand and therefore held that the first respondent is entitled to release of Bank Guarantee and security deposit.

    25. This is also a reasonable finding based on fact and law which is hardly open to challenge under Section 34 of the Act 1996.

    26. Issue Nos. 9 and 15 were taken together by the second respondent/Arbitrator who found that in view of the findings under Issue Nos. 1 & 2, the petitioner is not entitled to counter-claim under heads of risks and cost and further Clause 61(1)(vii) of GCC is not applicable.

    27. The findings to the above two issues are based on the findings under Issues Nos. 1 & 2 and therefore the same are to be upheld.

    28. Issue No. 10 deals with payment of interest and the Arbitrator after going through Clause 16(2) of GCC and after referring to five decisions of Hon'ble Supreme Court awarded interest @ 18% per annum which in my view cannot said to be arbitrary or illegal.

    29. In issue No. 11, the Arbitrator directed both the parties to bear their own cost and dismissed the counter-claims made by the petitioner in Issue Nos. 12, 13 & 14. After evaluating the entire evidence, which includes the heavy flooding which is an Act of God, the second respondent/Arbitrator dismissed the counter-claims under Issues 12 to 14 and as these issues are also decided based on the peculiar facts of the case, the findings could not be interfered with by this Court under Section 34 of the Act 1996.

    30. Thus, the award under challenge is a reasoned one and the same has been passed on the basis of proper evaluation of the evidence adduced before the Arbitral Tribunal. I am aware of the limited scope of Section 34 and if the parameters as contemplated under Section 34 are applied to the award under challenge, the same could not be interfered with by this Court. Though a number of grounds have been raised on behalf of the petitioner, they are all attempts made on behalf of the petitioner to assail the award as if Section 34 Petition is an Appeal.

    31. In McDermott International Inc. v. Burn Standard Co. Ltd. and others, (2006) 11 SCC 181, the Hon'ble Supreme Court held that the 1996 Act makes provision for the supervisory role of Courts and this supervisory role is to be kept at a minimum level and the interference envisaged only in cases of fraud, or bias, violation of natural justice, etc. The Hon'ble Supreme Court further held that interference on the ground of patent illegality is permissible only if the illegality goes to the root of the matter and also the public policy violation should be so unfair and unreasonable so as to shock the conscience of the Courts. The relevant paras reads as under:

    “52. The 1996 Act makes provision for the supervisory role of Courts, for the review of the Arbitral Award only to ensure fairness. Intervention of the Court is envisaged in few circumstances only, like, in case of fraud or bias by the Arbitrators, violation of natural justice, etc. The Court cannot correct errors of the Arbitrators. It can only quash the award leaving the parties free to begin the Arbitration again if it is desired. So, the scheme of the provision aims at keeping the supervisory role of the Court at minimum level and this can be justified as parties to the agreement make a conscious decision to exclude the Court's jurisdiction by opting for Arbitration as they prefer the expediency and finality offered by it.

    58. In Renusagar Power Co. Ltd. v. General Electric Co., this Court laid down that the arbitral award can be set aside if it is contrary to (a) fundamental policy of Indian law; (b) the interests of India; or (c) justice or morality. A narrower meaning to the expression “public policy” was given therein by confining judicial review of the arbitral award only on the aforementioned three grounds. An apparent shift can, however, be noticed from the decision of this Court in Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (for short “ONGC”). This Court therein referred to an earlier decision of this Court in Central Inland Water Transport Corpn. Ltd. v. Brojo Nath Ganguly, wherein the applicability of the expression “public policy” on the touchstone of Section 23 of the Indian Contract Act and Article 14 of the Constitution of India came to be considered. This Court therein was dealing with unequal bargaining power of the workmen and the employer and came to the conclusion that any term of the agreement which is patently arbitrary and/or otherwise arrived at because of the unequal bargaining power would not only be ultra vires Article 14 of the Constitution of India but also hit by Section 23 of the Indian Contract Act. In ONGC this Court, apart from the three grounds stated in Renusagar, added another ground thereto for exercise of the Court's jurisdiction in setting aside the award if it is patently arbitrary.

    59. Such patent illegality, however, must go to the root of the matter. The public policy violation, indisputably, should be so unfair and unreasonable as to shock the conscience of the Court. Where the arbitrator, however, has gone contrary to or beyond the expressed law of the contract or granted relief in the matter not in dispute would come within the purview of Section 34 of the Act. However, we would consider the applicability of the aforementioned principles while noticing the merits of the matter.”

    32. In the unreported judgment dated 15.12.2006 Union of India owning Southern Railway, rep. by its Chief Engineer/Construction, Chennai-8 v. TECCO Trichy Engineers & Contractors and 3 others, in O.P No. 547 of 2006, I had an occasion to deal with and decide an award passed by an Arbitral Tribunal against the Southern Railway. Based on the facts and circumstances of that case, I observed as under:

    “11. Insofar as the 1st claim is concerned, after holding that the extraordinary floods happened on 15.12.1996 is an act of God, respondents 2 and 3 in their majority award awarded a sum of Rs. 20.8 lakhs. The 4th respondent in her minority award after accepting that the floods that happened on 15.12.1996 was an unusually heavy discharge of more than 1 lakh cusecs from Ponniar river awarded a sum of Rs. 18.36 lakhs for the 1st claim. Thus all the Arbitrators have unanimously upheld that the flood happened on 15.12.1996 is unprecedented, extraordinary and should be taken as an act of God. The Arbitrators have also taken a site inspection on 28.8.2000 In such circumstances, the learned counsel for the petitioner cannot contend that the award is contrary to various clauses contained in the GCC, Special Conditions of Contract and technical specifications. As rightly submitted by the learned Senior Counsel for the 1st respondent when an act of God has been unanimously accepted by all the members of the Arbitral Tribunal the same cannot be assailed on the ground that some of the clauses are violated. Further, this Court under Section 34 of the Act, 1996 cannot come to a different conclusion when all the Arbitrators who had the advantage of taking a site inspection, held that unprecedented flood that happened on 15.12.96 should be taken as an act of God.”

    33. In the present case, the second respondent/Arbitrator had an opportunity to inspect the site on 06.02.2000 to have a first hand information.

    34. In the light of the above facts and the law declared by the Hon'ble Supreme Court, I find no merits in O.P No. 95 of 2003 and the same is dismissed upholding the award. No costs.

    35. In view of the order passed in O.P No. 95 of 2003, O.P No. 96 of 2003 is also dismissed upholding the award. No costs.