  • Section 87 of the Tamil Nadu Co-operative Societies Act, 1983,(hereinafter called as Act)
  • Section 33(3) of the Tamil Nadu H.R & C.E Act,
  • Section 87 of the present Act of 1983
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Section 87 of the Tamil Nadu Co-operative Societies Act, 1983,(hereinafter called as Act)
  • Section 33(3) of the Tamil Nadu H.R & C.E Act,
  • Section 87 of the present Act of 1983
Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

The first respondent initiated proceedings under Section 87 of the Tamil Nadu Co-operative Societies Act, 1983 alleging that the petitioner, while serving as Senior Inspector/Special Officer of Anna Co-operative House Building Society, Thanjavur, misappropriated Rs. 35,840 in respect of laying a road and constructing a culvert without prior permission of the Registrar (Housing) and falsified records. The petitioner denied the charges, stating the works were undertaken only after a General Body resolution and payments were made in three instalments upon inspection of progress.

The first respondent concluded the explanation was unsatisfactory, found a loss of Rs. 35,840 and ordered recovery with interest at 15% per annum. The petitioner appealed to the Co-operative Tribunal (Principal District Judge, Thanjavur) in C.M.A No. 18/1995, which confirmed the first respondent's order and dismissed the appeal. The petitioner filed this civil revision petition challenging that confirmation.

Relevant documentary and procedural points appearing in the opinion: a report of the Co-operative Sub-Registrar (Housing), Kumbakonam dated 29.11.1990 indicated the road and culvert were actually constructed and that four complainants were purchasers (not regularised members) whose complaint might be biased; a criminal case against the petitioner was dropped; charges were framed on 7.2.1992 and the impugned order was passed on 2.7.1993.

Legal Issues Presented

  1. Whether the enquiry and proceedings under Section 87 of the Tamil Nadu Co-operative Societies Act, 1983 were time-barred because they were not completed within the period mandated by the second proviso to Section 87, and no permissible extension by the next higher authority was shown.
  2. Whether the respondents established that the petitioner caused any loss to the society, thereby justifying a surcharge order.

Arguments of the Parties

Petitioner's Arguments

  • The enquiry framed under Section 87 on 7.2.1992 was not concluded within the time stipulated by the second proviso to Section 87; there is no record of any extension being granted by the next higher authority that would lawfully extend the statutory period.
  • The Co-operative Sub-Registrar's report dated 29.11.1990 (finding the road and culvert were actually laid and that the complainants were purchasers, not regularised members) was not properly considered by the first respondent, and if it had been, no action should have been taken.
  • The respondents have not established that any loss was caused to the society; at best there may have been procedural irregularity (lack of prior permission), but not misappropriation leading to loss. The petitioner asserted that works were carried out pursuant to a General Body resolution and payments were made in instalments after inspecting progress.
  • The criminal proceedings were dropped for lack of case, which the petitioner relied on to support absence of culpability causing loss.

Respondents' Arguments

  • The respondents contended that the first respondent had properly considered the Sub-Registrar's report dated 29.11.1990 and only thereafter initiated proceedings under Na.Ka.752/92.Sa.Pa dated 7.2.1992.
  • Respondents were not able to offer an explanation for the delay in completing the enquiry within the statutory period under the second proviso to Section 87 and did not dispute that charges were framed on 7.2.1992 and concluded on 2.7.1993.
  • Respondents did not, according to the opinion, establish that the petitioner had caused any loss to the society.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Ekambaram v. Co-operative Tribunal-cum-District Judge, Madurai, 2000 (2) C.T.C 659 Where surcharge/surcharge-like proceedings are not completed within the stipulated six months and there is no material to show that an extension was obtained from the higher authority, the proceedings are invalid; the second proviso's timing requirement is mandatory. The court followed the observations in Ekambaram to hold that the action in the present case—completed well after the statutory period and without any shown extension—was time-barred and non est in law.
N. Ranganathan v. The Principal District Judge, V.R.P District (W.P. Nos. 4724 & 17955 of 1997), dated 15.12.98 (unreported) Obtaining permission under the relevant provision in the previous Act (Section 173 then; reference made to current provision) is mandatory; action under the provision must be completed within the proviso period and, if it exceeds six months, there must be an extension from the higher authority. The court applied the unreported N. Ranganathan observations to reinforce that the second proviso to Section 87 is mandatory and that absent an extension, the action is non est. The opinion states this observation is squarely applicable to the present case.
R. Sethumadhavan v. The Deputy Commissioner, H.R & C.E Administration Department, Coimbatore, 1987 TLNJ 244 The order of surcharge can be passed only if loss is established; if a delinquent shows justifiable circumstances, there is no liability to surcharge. The court relied on this principle to hold that where respondents did not make out any loss and the petitioner offered explanations (e.g., General Body resolution, staged payments), surcharge was not justified. The case was invoked by the petitioner and accepted as persuasive on the loss requirement.

Court's Reasoning and Analysis

The court proceeded in two principal analytical strands corresponding to the petitioner's primary contentions: (A) compliance with the mandatory time-limits in the second proviso to Section 87, and (B) whether any loss to the society was made out to justify a surcharge.

A. Analysis on Time-Limit (Second Proviso to Section 87)

  • The charges were framed on 7.2.1992 (commencement of action) and the enquiry was concluded with the impugned order on 2.7.1993.
  • The second proviso to Section 87 requires completion of action within six months from commencement, subject to possible extensions by the next higher authority, but such extensions collectively may not exceed an additional six months (i.e., maximum aggregate one year).
  • The court found nothing on record to show any extension by the next higher authority. The respondents did not offer an explanation for exceeding the statutory period.
  • Applying the mandatory wording of the proviso and following precedent (Ekambaram and the unreported N. Ranganathan), the court held that because the inquiry was concluded beyond the permissible statutory period (indeed beyond one year in the present facts), the proceedings were time-barred and therefore legally impermissible (non est in law).
  • The court emphasized that in the present case the delay was worse than in Ekambaram because the action concluded well beyond one year, strengthening the conclusion that the order was barred by time.

B. Analysis on Loss and Surcharge

  • The Tribunal had observed (paragraph 14 of its order) that the works had been completed without obtaining orders from higher authorities and held the petitioner liable for surcharge of amounts spent, but did not expressly find that the petitioner had caused any loss to the society.
  • The court considered the distinction between misappropriation (which typically results in loss) and mis-application or procedural irregularity (which may not cause loss). It noted that where there is no misappropriation and no resulting loss, surcharge proceedings are not justified.
  • Relying on the principle in R. Sethumadhavan, the court observed that surcharge requires a demonstrated loss; where the delinquent has reasonable explanations (here, acts pursuant to General Body resolution, staged payments monitored by inspection), liability to surcharge does not follow.
  • The court concluded that respondents had not made out any loss. At best the petitioner had failed to secure certain permissions or follow procedure, which could warrant disciplinary action but not a surcharge order in the absence of loss.

On both strands the court found in favour of the petitioner: procedurally the enquiry and order were time-barred under the mandatory proviso to Section 87, and substantively the respondents had not established loss necessary to sustain a surcharge.

Holding and Implications

Holding: The civil revision petition is allowed. The court set aside the surcharge/order passed on 2.7.1993 relating to the charges framed under Section 87 of the Tamil Nadu Co-operative Societies Act, 1983.

Core Ruling: The civil revision petition is allowed and the surcharge order (2.7.1993) is set aside as time-barred and unjustified for lack of proved loss.

Implications

  • Direct effect: The recovery order for Rs. 35,840 (plus interest) made against the petitioner was quashed; the tribunal's confirmation was set aside. The petitioner is relieved of the surcharge ordered in the impugned proceedings.
  • Procedure vs. Discipline: The court made clear that procedural lapses (e.g., failure to obtain prior permission) may expose an official to disciplinary proceedings, but absent demonstrated loss, surcharge is not an appropriate remedy.
  • Precedential effect: The opinion applied existing precedents and mandatory provisos of the statute; it does not purport to create a new legal principle beyond applying those authorities. The court relied on earlier case law to reach its decision; the opinion itself does not state that it establishes novel precedent.

Note: This summary is strictly confined to the facts, arguments, cited authorities, reasoning and result as contained in the provided opinion. It does not add or infer information beyond the opinion's text.

    Gabriel Petitioner v. The Deputy Registrar (Housing), Cuddalore And Another S

    1. This civil revision petition is directed against the decree and judgment of the Principal District Judge, Thanjavur passed in C.M.A No. 18/95 dated 20.11.1997 confirming the order of the Deputy Registrar, Housing, Cuddalore, passed in Rc. No. 752/92.Sa.Pa dated 2.7.1993

    2. The first respondent initiated action against the revision petitioner under Section 87 of the Tamil Nadu Co-operative Societies Act, 1983,(hereinafter called as ‘Act’) wherein the charges were framed against him stating, while he was working as a Senior Inspector/Special Officer in Anna Co-operative House Building Society at Thanjavur, had misappropriated amount to a sum of Rs. 35,840 for laying road and for constructing culvert and no prior permission was obtained from the Registrar (Housing) and also falsified the records to that extent and thereby he had caused loss of Rs. 35,840 to the society. The petitioner was called upon to give his reply and he in his reply had stated that only after passing of the resolution in the General Body of the Society, the works were undertaken and the amounts were also disbursed on three instalments by inspecting the progress of the work and thereby, he denied the charges leveled against him. But however, the first respondent found that the explanation offered by the petitioner was not satisfactory, came to the conclusion that the petitioner had caused loss to the extent of Rs. 35,840 and passed an order for the recovery of the amount together with interest at 15% per annum. The said order was challenged by the petitioner before the Co-operative Tribunal i.e, The Principal District Judge at Thanjavur in C.M.A No. 18/1995 and the Tribunal accepted the finding of the first respondent and confirmed the said order and dismissed the appeal. Aggrieved by the same, this revision has been filed.

    Heard, learned counsel for the petitioner and the respondent.

    3. Learned counsel for the petitioner has submitted that the order passed against the petitioner is vitiated on two grounds i.e, (1) the order passed by the first respondent on 2.7.93 is not legal on the ground that the enquiry initiated against the petitioner under Section 87 of the Act dated 7.2.1992 was not concluded within the time as stipulated in second proviso under Section 87, and (2) the respondents have not made out that the petitioner had caused loss to the society.

    4. As far as the first submission is concerned, learned counsel for the petitioner would submit that the report filed by the Co-operative Sub- Registrar (Housing) Kumbakonam dated 29.11.1990 was not at all properly considered by the first respondent which resulted in passing an order against the petitioner and the same is vitiated.

    5. Had the first respondent taken into consideration, the report dated 29.11.90 wherein it was found that road has actually been laid and the culvert was also constructed and the persons who are four in number reported, were not at all members of the society and they are only purchases of the plots, which were allotted to the members and their purchases were not yet regularised and therefore, the complaint given by them is biased. It is also pointed out that if the said report dated 29.11.90 was properly scrutinised by the first respondent, no action could have been taken. Incidentally, learned counsel for the petitioner has also submitted that the criminal action initiated against the petitioner was also dropped as no case has been made out.

    6. Learned counsel for the petitioner also submitted that the charges were framed under Section 87 of the Act under reference No. 72/92.Sa.Pa. dated 7.2.1992 and the second proviso to Section 87 states “Provided further that the action commenced under this sub-section shall be completed within a period of six months from the date of such commencement or such further period or periods as the next higher authority may permit but such extended period or periods shall not exceed six months in the aggregate” Pointing out this, it is submitted that admittedly the charges were framed on 7.2.1992 and it should have been completed within a period of six months. But the said period could be extended, not exceeding six months, that too by an order of the next higher authority concerned.

    7. Learned counsel would contend that there is nothing on record to show that the statutory period of six months was further extended by any next higher authority for the period, not exceeding six months. In any event total period stipulated under the second proviso to Section 87 could not extend beyond one year (i.e, six months + six months) whereas it is seen that the enquiry was completed only on 2.7.93 and it is beyond the stipulated period and therefore, the order passed by the first respondent on 2.7.93 is beyond the time and the same is liable to be set aside.

    8. Learned counsel for the respondents are not in a position to contradict the submission made by the learned counsel for the petitioner as far as the dropping of the criminal case against the petitioner is concerned, but however, it is submitted that the first respondent had properly considered the report of the Co-operative Sub-Registrar (Housing) Kumbakonam dated 29.11.90 and only after going through the said report, proceedings were initiated by the first respondent under Na.Ka.752/92.Sa.Pa. dated 7.2.1992

    9. Learned counsel for the respondent also was not in a position to dispute that the charges were framed under Section 87 of the Act under Na.Ka.753/92 Sa.Pa dated 7.2.92 and it was concluded only on 2.7.93 The respondents are not able to offer any explanation for the time fixed under the second proviso to Section 87 of the Act, and also the delay in completing the enquiry. I have to necessarily accept the submission made on behalf of the petitioner that the order so passed on 2.7.93 for the charges framed under Section 87 of the Act, is beyond the stipulated period and therefore the same is time barred one. Learned counsel for the petitioner also relied upon the Judgment reported in Ekambaram v. Co-operative Tribunal-cum-District Judge, Madurai, 2000 (2) C.T.C 659 wherein also surcharge proceedings were initiated and the same was not completed within six months from the date of commencement of action and there was no materials to show that the second respondent in that case sought for extension of time by the higher authority after the expiry of six months time and in the said circumstances, the Court followed the observations made in the unreported Judgment of this Court in N. Ranganathan v. The Principal District Judge, V.R.P District made in W.P No. 4724 and 17955 of 1997 dated 15.12.98 wherein it was held that …”obtaining of permission under Section 173 of the old Act and now Section 876 is mandatory”. It was further held “that the action has to be completed within a period as stipulated under the proviso of Section 87. Under the circumstances it is to be held that the second proviso to Section 87 of the present Act of 1983 is mandatory in nature and the proviso also stated that the action “shall be” completed within a period of six months and if exceeds beyond the period of six months, there must be an extension from the higher authority. As the second respondent has not obtained the extension from the higher authority, the action initiated has to be held as non-est in the eye of law”. The said observation is squarely applicable to our case. In fact in our case, it is still worse, as the action was completed only on 2.7.93 which is beyond one year and therefore the order passed by the first respondent barred by time and liable to be set aside.

    10. As far as the second submission is concerned, the learned counsel for the petitioner relied upon para 14 of the order passed by the Tribunal, wherein it is stated that though the works undertaken have been completed, no orders have been obtained from the higher authorities and therefore, the petitioner is liable for the surcharge for the amounts spent. It is pointed out that even the Tribunal has not given the finding that the petitioner has caused any loss to the Society. Usually, surcharge proceedings are taken only when any loss is made to the department.

    11. Learned counsel for the petitioner also relied upon the case of R. Sethumadhavan v. The Deputy Commissioner, H.R & C.E Administration Department, Coimbatore, 1987 TLNJ 244. This case arose out of Section 33(3) of the Tamil Nadu H.R & C.E Act, but the principles laid down in the said case can be usefully referred to in this case also. It was held in the said case “The order of surcharge could be passed only if loss is made out, but if the delinquent is able to show that there were justifiable circumstances, as found in this case, then there could be no liability to surcharge him”.

    12. In our case also the respondents had not made out that the petitioner had caused any loss to the society. The petitioner has also given reasons for carrying out the work and the same cannot be rejected on the ground that they are not convincing but on the other hand, the explanation offered by the petitioner appears to be that he had acted only pursuant to the resolution passed in the General body and if there is any further latches in observing certain procedure, it would not amount to mis-appropriation of the amount. When there is no misappropriation of amount, then it would only amounts to mis-application and when the mis-application not having caused any loss to the society, a surcharge proceeding is not justifiable. If any irregularity committed by the petitioner in failing to secure permission from the authorities concerned, it would not result in being surcharged but may result in any disciplinary action being taken as against him.

    13. Therefore, it is left open to the authorities, if they consider that it is necessary, to take disciplinary action against the petitioner for failure on his part in not having followed certain procedures, but the order of surcharge is not legal and the same is liable to be set aside, accordingly, it is set aside.

    14. In the result, the civil revision petition is allowed. No costs.