  • provisions of the Maharashtra Recognition of trade unions and Prevention of Unfair Labour Practices Act, 1971, hereinafter referred to as the MRTU and PULP Act
  • CONTRACT LABOUR REGULATION AND ABOLITION ACT 1970
  • S. 10(1)(d) of the Industrial Disputes Act
  • provisions of the Contract Labour Act.
  • S. 10(1) of the Contract Labour Act
  • S. 10 of the Contract Labour Act
  • INDUSTRIAL DISPUTES ACT 1947
  • S. 10(1) of the Contract Act
  • S. 10(1) of the I.D Act.
  • S. 2(k) of the I.D Act.
  • S. 10 of the I.D Act
  • COMPANIES ACT 1956
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • provisions of the Maharashtra Recognition of trade unions and Prevention of Unfair Labour Practices Act, 1971, hereinafter referred to as the MRTU and PULP Act
  • CONTRACT LABOUR REGULATION AND ABOLITION ACT 1970
  • S. 10(1)(d) of the Industrial Disputes Act
  • provisions of the Contract Labour Act.
  • S. 10(1) of the Contract Labour Act
  • S. 10 of the Contract Labour Act
  • INDUSTRIAL DISPUTES ACT 1947
  • S. 10(1) of the Contract Act
  • S. 10(1) of the I.D Act.
  • S. 2(k) of the I.D Act.
  • S. 10 of the I.D Act
  • COMPANIES ACT 1956
Smart Summary

Factual and Procedural Background

The petitioners, two registered trade unions representing workers and contract workers in the establishments of respondent No. 4-company, challenged the engagement of workmen on contract basis by respondent No. 4 through various contractors (respondent Nos. 8 to 16). The petitioners contended that these contracts were sham and bogus, aimed at minimizing direct employment and that contract workers should be treated as permanent employees due to the perennial nature of the work and long duration of their service. The petitioners had earlier filed complaints under the Maharashtra Recognition of Trade Unions and Prevention of Unfair Labour Practices Act, 1971 (MRTU and PULP Act), alleging sham contracts and seeking recognition of contract workers as permanent employees. The company had denied termination of contracts or workers. The disputes were pending before various authorities, including the State Advisory Board under the Contract Labour (Regulation and Abolition) Act, 1970, and the Labour Commissioner. The petitioners also raised an industrial dispute seeking declaration of contract workers as permanent employees.

Legal Issues Presented

  1. Whether the Industrial Court and Labour Court constituted under the MRTU and PULP Act have jurisdiction to entertain disputes on behalf of contract workers.
  2. Whether contract workers engaged through contractors can be declared permanent employees of the principal employer where contracts are alleged to be sham.
  3. The authority and procedure for abolition of contract labour under Section 10 of the Contract Labour (Regulation and Abolition) Act, 1970.
  4. The appropriate forum for adjudication of industrial disputes involving contract workers under the Industrial Disputes Act, 1947.
  5. The rights and remedies available to contract workers and principal employers upon abolition of contract labour.

Arguments of the Parties

Petitioners' Arguments

  • The contract labour system employed by respondent No. 4 is a sham designed to keep direct employment minimal.
  • Contract workers have been engaged for over a decade performing perennial and ancillary work, warranting their treatment as permanent employees.
  • Disputes concerning contract workers should be adjudicated by the Labour Court/Tribunal constituted under the Industrial Disputes Act, 1947, as held by the Supreme Court.
  • Petitioners applied to the State Advisory Board under Section 10 of the Contract Labour Act for abolition of contract labour, and also raised industrial disputes before the Commissioner of Labour.

Respondents' Arguments

  • Preliminary objection to maintainability of the petition under Article 226 against a private company.
  • Petitioners have already raised industrial disputes before competent authorities under the Industrial Disputes Act, which are pending.
  • Demands for abolition of contract labour will be dealt with by the State Government under the Contract Labour Act.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Cipla Ltd. v. Maharashtra General Kamgar Union [2001 (2) L.L.N 19] Industrial Court and Labour Court under MRTU and PULP Act lack jurisdiction over contract workers’ disputes; such disputes fall under Labour Court/Tribunal under Industrial Disputes Act. Confirmed that disputes for contract workers must be adjudicated under Industrial Disputes Act framework, not MRTU and PULP Act.
Vividh Kamgar Sabha v. Kalyani Steels Ltd. [2001 (1) L.L.N 782] Reaffirmed Cipla Ltd. ruling on jurisdiction of Labour Courts for contract labour disputes. Supported the direction for disputes to be adjudicated under Industrial Disputes Act.
Gujarat Electricity Board Thermal Power Station v. Hind Mazdoor Sabha [1995 (2) L.L.N 59] Authority to abolish contract labour rests exclusively with the Appropriate Government under Section 10(1) of the Contract Labour Act; jurisdictional limits of Industrial Adjudicators on sham contracts and industrial disputes. Detailed the procedure and jurisdiction regarding abolition of contract labour and adjudication of disputes concerning sham contracts.
Air India Statutory Corporation v. United Labour Union [1997 (1) L.L.N 75] Effect of notification under Section 10(1) of the Contract Labour Act entitling contract employees to absorption in principal employer’s service. Supported the process and consequences of abolition of contract labour and absorption of contract workers.
VST Industries, Ltd. v. VST Industries Workers' Union [2001 (1) L.L.N 786] Maintainability of petitions under Article 226 against private companies concerning labour disputes. Supported respondents’ objection to maintainability of the petition under Article 226.

Court's Reasoning and Analysis

The court examined the jurisdictional boundaries between various forums under different statutes. It relied on Supreme Court precedents to conclude that disputes involving contract workers must be adjudicated by Labour Courts or Industrial Tribunals constituted under the Industrial Disputes Act, 1947, rather than under the MRTU and PULP Act. The court emphasized that the authority to abolish contract labour lies exclusively with the Appropriate Government under Section 10(1) of the Contract Labour Act, and no court, including Industrial Adjudicators, has jurisdiction to abolish contract labour. However, where contracts are found to be sham, the Industrial Adjudicator can adjudicate disputes raised by contract workers claiming to be employees of the principal employer. The court acknowledged that the petitioners had already initiated proceedings under the Industrial Disputes Act and had applied to the State Advisory Board for abolition of contract labour. Given the absence of any possibility of amicable settlement, the court directed the State Government to refer the disputes to the Industrial Tribunal/Labour Court within eight weeks and to constitute the Advisory Board to consider the application for abolition of contract labour, with timelines for reporting and decision-making. The court also provided interim protection to contract workers against termination pending adjudication.

Holding and Implications

DISPOSED OF

The court directed the State Government to refer the industrial disputes raised by the petitioners to the Industrial Tribunal/Labour Court under Section 10(1)(d) of the Industrial Disputes Act within eight weeks. It also directed constitution of the Advisory Board to consider the petitioners' application for abolition of contract labour and to report within six months. Interim relief was granted to prevent termination of contract workers pending adjudication. The decision clarifies the appropriate forum and procedure for addressing disputes involving contract labour and reinforces the exclusive authority of the Appropriate Government to abolish contract labour under the Contract Labour Act. No new legal precedent was set; the ruling applied established Supreme Court principles to the facts of the case, ensuring procedural clarity and protection for the workers involved.

    Federation Of Hindustan Lever, Ltd., And Another v. Secretary, State Contract Labour Advisory Board, And Others

    1. Heard learned counsel for the parties.

    2. Rule made returnable forthwith.

    3. The petitioner No. 1 is a registered trade union and represents various unions operating in the establishments of respondent No. 4-company. The petitioner No. 2 is also a registered trade union and represents contract workers working in the training centre of respondent No. 4 situated at Worli. The respondent No. 1 is the Advisory Board set up under the Contract Labour (Regulation and Abolition) Act, 1970, hereinafter referred to as the Contract Labour Act. The respondent No. 2 is the Commissioner of Labour. The respondent No. 3 is State of Maharashtra which is the ‘Appropriate Government’ in respect of the establishments of the respondent No. 4. The respondent No. 4 is a company incorporated under the Companies Act, 1956, and the respondent Nos. 5, 6 and 7 are its establishments. The respondent Nos. 8 to 16 are the contractors through whom respondent No. 4 allegedly gets various jobs done in its establishments.

    4. The petitioners have contended that more and more workmen are being engaged by respondent on contract basis with a view to keep the employees under its employment at the bearest minimum and get several operations/processess/work through so-called contractors. It is contended that the so-called contracts are totally sham and bogus and contract workers should be treated as permanent and direct workers of the 4 respondent-company. It is contended that many of these employees have been working in the establishments of respondent No. 4 for more than 10 years. It is pointed out that direct employees of respondent No. 4 are paid monthly wages ranging from Rs. 10,000 to Rs. 12,000 whereas contract workers are paid a meagre salary of Rs. 2000 to Rs. 2500. The petitioners contend that various jobs which are performed through the so-called contract workers are of perennial nature which can be seen from the fact that most of the workers have been working with respondent No. 4 for more than a decade.

    5. At the outset we may mention that the petitioners have filed Complaint (ULP) No. 758 of 1996 and Complaint (ULP) No. 658 of 1998 under the provisions of the Maharashtra Recognition of trade unions and Prevention of Unfair Labour Practices Act, 1971, hereinafter referred to as the MRTU and PULP Act contending inter alia, that contracts entered into between respondent No. 4 and respondents Nos. 9 to 16 are sham and bogus contracts and the contractors are merely for name-lending. It is also the case of the petitioners in the said proceeding that work performed by the workmen of the so-called contractors is in fact work of incidental and/or ancillary to the main activity of respondent No. 4 and that the said work is perennial in nature. In Complaint No. 652 of 1998 a statement was made by respondent No. 4 that the contracts will not be terminated as also the services of concerned contract workers will not be discontinued. In Complaint No. 758 of 1996 application for interim relief was rejected on the ground that there was no apprehension of termination of the contract workers. We may hastern to add that workers covered by the above complaints have been continued in the establishments of the respondent No. 4 even today.

    6. Ms. Doshi, learned counsel for the petitioners, contended that the Supreme Court in the case of Cipla, Ltd. v. Maharashtra General Kamgar Union, [2001 (2) L.L.N 19], held that Industrial Court and Labour Court constituted under MRTU and PULP Act would not have jurisdiction to entertain disputes on behalf of contract workers and the right forum would be Labour Court/Tribunal constituted under Industrial Disputes Act, 1947, and that such disputes could only be adjudicated upon in a reference under S. 10 of the said Act. This view was reaffirmed by the Supreme Court in the case of Vividh Kamgar Sabha v. Kalyani Steels, Ltd., [2001 (1) L.L.N 782], Ms. Doshi also brought to our notice that respondent No. 4 has fifed an application before the Industrial Court for dismissing the complaints in view of the decisions of the Supreme Court in Cipla, Ltd. and Kalyani Steels (vide supra). She submitted that petitioners have therefore approached the State Government by way of their application addressed to the State Advisory Board under S. 10 of the Contract Labour Act for abolition of the contract labour in respect of jobs performed by contract workers engaged through respondent Nos. 9 to 16 and the said application is pending before the Advisory Board. She submitted that petitioners have also raised an industrial dispute on behalf of contract workers before the Commissioner of labour seeking a declaration to treat the workers mentioned in Exhibit A to the petition as permanent workers of respondent No. 4 company and for other consequential reliefs.

    7. Ms. Doshi drew our attention to the decision of the Supreme Court in Gujarat Electricity Board Thermal Power Station, Ukai, Gujarat v. Hind Mazdoor Sabha, [1995 (2) L.L.N 59], wherein the Supreme Court has held that the authority to abolish the contract labour is vested exclusively in the appropriate Government under S. 10(1) of the Contract Act. In the said case Supreme Court also considered the issue as to who can raise industrial dispute under S. 10 of the I.D Act for claiming absorption or a declaration that the workmen of the contractors are in fact workmen of the principal employer. In this regard the Supreme Court summarised the law in Para. 50, at pages 86 and 89 of the judgment which reads as follows:

    “Our conclusions and answers to the questions raised are, therefore, as follows:

    (i) In view of the provisions of S. 10 of the Act, it is only the appropriate Government which has the authority to abolish genuine labour contract in accordance with the provisions of the said section. No Court including the Industrial Adjudicator has jurisdiction to do so.

    (ii) If the contract is a sham or not genuine, the workmen of the so-called contractor can raise an industrial dispute for declaring that they were always the employees of the principal employer and for claiming the appropriate service conditions. When such dispute is raised, it is not a dispute for abolition of the labour contract and hence the provisions of S. 10 of the Act will not bar either the raising or the adjudication of the dispute. When such dispute is raised, the Industrial Adjudicator has to decide whether the contract is a sham or genuine. It is only if the adjudicator comes to the conclusion that the contract is a sham that he will have Jurisdiction to adjudicate the dispute. If however, he comes to the conclusion that the contract is genuine, he may refer the workmen to the appropriate Government for abolition of the contract labour under S. 10 of the Act and keep the dispute pending. However, he can do so if the dispute is espoused by the direct workmen of the principal employer. If the workmen of the principal employer have not espoused the dispute, the adjudicator, after coming to the conclusion that the contract is genuine, has to reject the reference, the dispute being not an industrial dispute within the meaning of S. 2(k) of the I.D Act. He will not be competent to give any relief to the workmen of the erstwhile contractor even if the labour contract is abolished by the appropriate Government under S. 10 of the Act.

    (iii) If the labour contract is genuine a composite industrial dispute can still be raised for abolition of the contract labour and their absorption. However, the dispute will have to be raised invariably by the direct employees of the principal employer. The Industrial Adjudicator after receipt of the reference of such dispute will have first to direct the workmen to approach the appropriate government for abolition of the contract labour under S. 10 of the Act and keep the reference pending. If pursuant to such reference, the contract labour is abolished by the appropriate Government the Industrial Adjudicator will have to give opportunity to the parties to place the necessary material before him to decide whether the workmen of the erstwhile contractor should be directed to be absorbed by the principal employer, how many of them and on what terms. If however, the contract labour is not abolished the Industrial Adjudicator has to reject the reference.

    (iv) Even after the contract labour system is abolished, the direct employees of the principal employer can raise an industrial dispute for absorption of the ex-contractors workmen and the adjudicator on the material placed before him can decide as to who and now many of the workmen should be absorbed and on what terms.”

    8. Our attention is also drawn to the decision of the Supreme Court in the case of Air India Statutory Corporation v. United Labour Union, [1997 (1) L.L.N 75], wherein the Supreme Court has considered the effect of notification issued under S. 10(1) of the Contract Act and held that upon such notification contract employees would be entitled to be absorbed in the service of the principal employer.

    9. Sri Rele and Sri Singh the learned counsel for the company and the contractors respectively raised preliminary objection to the maintainability of the present petition on the ground that the petition of this nature under Art. 226 would not be maintainable against a private company like the respondent No. 4. It is submitted that the petitioners have already raised industrial dispute before the Labour Commissioner and the authorities under the I.D Act are seized of the matter. It is also submitted that as far as demand for abolition of the contract labour is concerned, petitioners application will be dealt with appropriately by the State Government in accordance with the provisions of the Contract Labour Act. Reliance is placed on the decision of the Supreme Court in the case of VST Industries, Ltd. v. VST Industries Workers' Union, [2001 (1) L.L.N 786].

    10. In the case of Cipla Ltd. (vide supra), the Supreme Court has categorically held that the dispute raised on behalf of contract labours will have to be adjudicated by the Labour Court/Industrial Court constituted under S. 10(1) of the I.D Act. It 4s a common ground that the petitioners have already raised an industrial dispute and the proceedings are now pending before the Labour Commissioner, ordinarily we would have directed the petitioners to resort to the machinery provided under the I.D Act. However the learned counsel for the parties fairly, stated that there is no possibility of resolution of the dispute by amicable settlement. Therefore asking the parties to resort to conciliation proceedings would be an empty formality. Having regard to the facts of the case we feel that the ends of justice would be met if the State Government is directed to make reference to the Industrial Court/Labour Court under S. 10(1)(d) of the Industrial Disputes Act for adjudication of various demands raised by the petitioners vide demand letters, dated 18 April, 2001 and 19 April, 2001, (Exhibits E and F to the petition). Accordingly the State Government is directed to refer the said demands raised by the petitioners for adjudication of the disputes to the Industrial Tribunal/Labour Court within a period of 8 weeks.

    11. The State Government is further directed to constitute the Advisory Board and to refer the application made by petitioners vide letters, dated 1 October, 1997 and 7 March, 2001 (Exhibits G and H to the petition) for abolition of contract labour to the Advisory Board within a period of 2 months. The Advisory Board will hear petitioners as well as management of the company and the concerned contractors and make suitable report to the State Government within a period of six months from the date of reference. The State Government upon receipt of the report from the Advisory Board will pass appropriate orders under S. 10(1) of the Contract Labour Act either to direct discontinuance of the contract labour or continuance thereof.

    12. The petitioners will apply to the Labour Court/Industrial Tribunal for interim relief within a period of four weeks from the date of notice of reference. Till the application for interim relief is decided by the Labour Court/Industrial Tribunal and for a period of four weeks thereafter respondent Nos. 4 to 16 are directed not to terminate the services of the concerned contract workmen listed in Exhibit A. It will be open for the respondent No. 4 to change the contractor but the new contractor will engage the same workers subject to the order of the Labour Court/Industrial Tribunal. All contentions on merits are left open.

    13. Rule is made absolute in terms of the order mentioned above.

    14. Certified copy expedited.

    15. The parties and the authorities to act on the ordinary copy of this order duly authenticated by the Personal Secretary of this Court.