Acts
  • rule 4 of the said Rules,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • rule 4 of the said Rules,
Smart Summary

Factual and Procedural Background

The petitioners were employed as Head Surveyors/classers in the Land Survey Department in the pay-scale of Rs. 1,400-2,300 and were declared surplus. Surplus Head Surveyors were offered either a lower post in the Land Survey Department or redeployment to other government departments. The petitioners opted for redeployment to the Irrigation Department as Field Surveyors in posts carrying the pay-scale Rs. 1,200-2,040, which was lower than their original scale; however, their original pay-scale was protected under rule 4 of the Redeployment of Surplus Staff Rules (the said Rules).

Some surplus Head Surveyors absorbed in the Land Survey Department were initially denied pay protection and filed Writ Petition No. 231 of 1988, in which it was held that they were entitled to protection of pay under the said Rules. Other surplus Head Surveyors were deployed to the Forest Department (given the 1,400-2,300 scale) and to the P.W.D. (given the 1,200-2,040 scale). A Time-Bound Promotional Scale (TBPS) scheme effective 1 June 1989 granted employees who had stagnated for 12 years the next promotional scale.

The petitioners claimed they had completed more than 12 years of service as of 1 June 1989 and applied for the TBPS; their requests were denied. The Forest Department incumbents were granted TBPS by order dated 27 July 1990. The petitioners' representations were refused by communication dated 5 November 1990, citing Clarification No. 17 of Office Memorandum (O.M.) dated 22 December 1989. After further representations and a legal notice, the petitioners filed the present writ petition. Meanwhile, Head Surveyors absorbed in P.W.D were granted TBPS by order dated 7 March 1991.

Legal Issues Presented

  1. Whether the petitioners are entitled to the Time-Bound Promotional Scale (TBPS) having had their pay protected under rule 4 of the Redeployment of Surplus Staff Rules.
  2. Whether Clarification No. 17 of the O.M. dated 22 December 1989 legitimately excludes employees with protected pay from receiving TBPS, or whether that clarification renders the statutory pay protection illusory.
  3. Whether denial of TBPS to the petitioners, when similarly placed employees (e.g., those in P.W.D or Forest Department) were granted TBPS, amounts to discrimination violative of Article 14 of the Constitution of India.

Arguments of the Parties

Petitioners' Arguments

  • The pay protection granted under rule 4 of the Redeployment of Surplus Staff Rules is statutory (rules framed under Article 309) and has to be given effect; executive office memoranda cannot be read to make that statutory protection illusory.
  • Some surplus Head Surveyors deployed to P.W.D. in the lower pay-scale were nevertheless granted TBPS; there is no reason to deny TBPS to the petitioners who likewise have protected pay in a lower post, and denial is arbitrary, unreasonable and violative of Article 14.
  • Clarification No. 17 of the O.M. is directory/advisory and the Government should examine individual cases on merit rather than applying the clarification as an inflexible bar.

Respondents' Arguments

  • The employees who were deployed from the Land Survey Department to P.W.D. were Field Surveyors originally in the pay-scale Rs. 1,200-2,040 and were deployed to P.W.D. in a still lower pay-scale (Rs. 950-1,500); their pay was protected under rule 4, and thus their cases are not comparable to the petitioners who were Head Surveyors in the pay-scale Rs. 1,400-2,300 prior to being declared surplus.
  • Clarification No. 17 of the O.M. indicates that employees who are presently getting the benefit of a higher (protected) pay-scale while discharging duties of a lower post should not be granted an additional higher TBPS, and thus denial to the petitioners was permissible under that clarification.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court identified the central question as whether the Government was justified in denying TBPS to the petitioners, noting that denial was made with reference to Clarification No. 17 of O.M. dated 22 December 1989. The clarification states:

“17. Whether the T.B.P.S is to be granted to the employees, who having declared surplus are redeployed, against lower pay-scale and allowed to carry higher scale of the previous post as per to him.

Since such employees are presently getting the benefit of higher pay-scale while discharging the duties of lower post, granting of still higher scale is not advisable.”

The court observed that the TBPS scheme (effective 1 June 1989) was intended to grant stagnating employees the next promotional scale after 12 years in the same post. The petitioners, though deployed to lower posts, continued to receive their original pay-scale because of pay protection under rule 4 of the Redeployment Rules—statutory rules framed under Article 309.

The court reasoned that once statutory pay protection is given under rule 4, that protection must be treated as effective "for all purposes," including eligibility for TBPS. To hold otherwise—i.e., to deny TBPS on the ground that the employees were actually discharging duties of a lower post—would render the statutory protection illusory. The court further stated that Clarification No. 17 is, at best, directory in nature and that the Government ought to have examined such cases on their merits rather than uniformly applying the clarification to deny TBPS.

The court also relied on parity and analogical reasoning: Field Surveyors who were in the pay-scale Rs. 1,200-2,040 and who were deputed to P.W.D. (to posts Rs. 950-1,500) had been granted pay protection and subsequently given TBPS (next scale). On the same principle, Head Surveyors whose pay was protected at Rs. 1,400-2,300 and who had completed the requisite period should be entitled to the next TBPS.

Holding and Implications

The writ petition is allowed: the petitioners are entitled to the Time-Bound Promotional Scale of Rs. 1,600-2,660 with effect from 1 June 1989, with all consequential benefits.

Direct consequences ordered by the court:

  • The writ petition is allowed and the rule is made absolute in the terms set out above.
  • Costs are quantified at Rs. 2,000 in favor of the petitioners.
  • Arrears due under the order are to be paid within four months from the date of the judgment; 50% of the arrears shall be deposited in the petitioners' G.P.F. accounts and the remaining 50% shall be paid in cash.

The opinion does not purport to set a broad new precedent beyond the facts before the court; its effect is to grant the petitioners the TBPS and consequential monetary relief. No further sweeping declaratory ruling or statement of broader doctrine was made beyond the court's application of statutory pay protection and parity under Article 14 to the petitioners' facts.

    J.M Fernandes And Others v. State Of Goa And Another

    Batta, J.:— The petitioners were working as Head Surveyors/classers in the pay-scale of Rs. 1,400-2,300 in the Land Survey Department, where they were declared surplus. The petitioners along with other surplus Head Surveyors, were given option to either work in a lower post in the said Department, that is the Land Survey Department or to opt for deployment in some other Government Departments. The petitioners opted for deployment in Irrigation Department to the posts of Field Surveyor, which posts were in the pay-scale of Rs. 1,200-2.040. Thus the said posts were in lower scale than the scales in which the petitioners were working prior to being declared as surplus. However, in terms of rule 4 of the Redeployment of Surplus Staff Rules (hereinafter called as the said Rules), the pay-scales of the petitioners were protected. This protection of pay was denied to the surplus Head Surveyors who were absorbed in the lower posts in the Land Survey Department, as a result of which, the said Heaa Surveyors filed Writ Petition No. 231 of 1988 and in this writ petition, it was held that the Head Surveyors who were absorbed in the Land Survey Department, were also entitled to protection of pay in terms of the said Rules Some of the Head Surveyors who had been declared surplus m the Land Survey Department, were deployed in the Forest Department and some of them to the P.W.D The Head Surveyors who were absorbed in the Forest Department were given pay-scale of Rs. 1,400-2,300, but the Head Surveyors who were absorbed in the P.W.D were given pay-scale of Rs. 1,200-2,040 like the present petitioners.

    2. The Government of Goa had introduced a Time Bound Promotional Scale Scheme with effect from 1 June 1989 and those employees who were stagnating for 12 years in a post and had not secured promotion, were entitled to the Tune-Bound Promotional Scale of the next promotional post. The petitioners claim that they had completed more man 12 years of service as on 1 June 1989, and represented to the Government for Time-Bound Promotional Scale, but the request was turned down. However, the Head Surveyors who had been deployed in the Forest Department, were granted the Time-Bound Promotional Scale vide order, dated 27 July 1990. The petitioners again represented to the Government of Goa on 29 October 1990 for the arbitrary denial of Time-Bound Promotional Scale to them, but the representation of the petitioners was, once again, turned down vide communication, dated 5 November 1990, in view of the clarification No. 17 contained in the O.M, dated 22 December 1989. Thereafter, the petitioners also continued to represent their claim lor the Time-Bound Promotional Scale and ultimately, after giving legal notice, this writ petition was filed. In the meantime, the Head Surveyors who had been absorbed in the P.W.D were also granted the Time-Bound Promotional Scale vide order, dated 7 March 1991. The petitioners' claim that their case and those Head Surveyors who had been absorbed in the P.W.D is, in no way, different siice both the categories had been absorbed in lower pay-scale of Rs. 1,200-2,040, but the Head Surveyors who were absorbed in P.W.D have been given Time-Bound Promotional Scale with effect from 7 March 1991 which had been denied to the petitioners. The petitioners, therefore, claim that the action of the Government in denying me Time-Bound Promotional Scale is violative of Art. 14 of the Constitution of India being discriminatory, arbitrary and unconstitutional. The petitioners, thus, seek directions for grant of Time-Bound Promotional Scale with effect from 1 June 1989, along with other consequential benefits and for a declaration that Cl. 17 of O.M, dated 22 December 1989, is arbitrary, unconstitutional, ultra vires and that the respondents be refrained from denying the Time-Bound Promotional Scale to the petitioners on the basis of Cl. 17 of the O.M, dated 22 December 1989.

    3. Learned advocate Sri MS. Sonak placed before us the facts which we have already enumerated and urged that the pay protection which is granted to the petitioners is under rule 4 of the said Rules, which are framed under Art. 309 of the Constitution of India and have statutory force and the office memorandums are executive instructions which cannot be read or interpreted to render pay protection granted under the statutory rules as illusory, which has been done in the case under consideration. He also pointed out that it is only in the fortuitous circumstances “that some of the Head Surveyors who had been declared surplus from the Land Survey Department along with the petitioners had been deployed in the P.W.D, in the, lower pay-scale of Rs. 1,200-2,040 like me present petitioners, but the said Head Surveyors deployed in the P.W.D have been granted the benefit of Time-Bound Promotional Scale and as such, there is no reason or justification to deny the said scale to the petitioners and denial of the same is arbitrary, unreasonable and unconstitutional. He further pointed out that in fact Cl. 17 of the O.M, dated 22 December 1989, itself is directory and advisory in nature and that the Government has to examine the cases of the employees falling under Cl. 17 on its own merits.

    4. Learned Government Advocate Sri H.R Bharne submitted before us that the employees who were deployed from the Land Survey Department to P.W.D after being surplus, were not Head Surveyors, but they were Field Surveyors in the pay-scale of Rs. 1,200-2,040 and they were deployed to P.W.D in lower pay-scale of Rs 950-1,500, but in view of rule 4 of the said Rules, their pay-scale of Rs. 1,200-2,040 was protected, He, therefore, submits that the petitioners' case cannot be compared with that of the surplus employees who were deployed to P.W.D, because initially, those employees were in the pay-scale of Rs. 1,200-2,040, whereas, the petitioners, as Head Surveyors, were in the pay-scale of Rs. 1,400-2,300.

    5. The basic question which is required to be determined is whether the Government was justified in denying the Time-Bound Promotional Scale to the petitioners. The scale was denied in view of Clarification No. 17 of O.M, dated 22 December 1989 The said clarification, reads as under

    “17. Whether the T.B.P.S is to be granted to the employees, who having declared surplus are redeployed, against lower pay-scale and allowed to carry higher scale of the previous post as per to him.

    Since such employees are presently getting the benefit of higher pay-scale while discharging the duties of lower post, granting of still higher scale is not advisable.”

    The Time-Bound Promotional Scale for Group C and Group D employees was introduced with laudable object that those employees who were stagnating for a period of 12 years in the same post and had not got any promotion should be granted next promotional scale. This scale was termed as “Time-Bound Promotional Scale.” The scheme was brought into effect from 1 June 1989. The petitioners were working as Head Surveyors in the Land Survey Department in the pay-scale of Rs. 1,400-2,300 prior to their being declared surplus. They opted deployment outside the department and were absorbed against lower post in the Irrigation Department, which posts carried pay-scale of Rs. 1,200-2,040. However, in view of S. 4 of the said Rules, the pay-scale-which the petitioners had in the Land Survey Department, was protected and they continued in pay-scale of Rs. 1,400-2,300 even though they were deployed against lower posts carrying pay-scale of Rs. 1,200-2,040. This pay protection was given to the petitioners in terms of rule 4 of the said Rules which are statutory rules. Once this pay protection is given, this protection has to be treated for all purposes, including for the purpose of Time-Bound Promotional Scale. The effect of clarification issued under serial No. 17 of O.M, dated 22 December 1989, is that the pay protection which had been granted to the petitioners under rule 4 of the said Rules would become totally illusory in case it is held that they are not entitled to the Time-Bound Promotional Scale since they were actually deployed in a post carrying lower pay-scale. Once the pay is protected and a person has worked in the post where his pay is protected for a period of 12 years, he would, in our opinion, be entitled to next Time Bound Promotional Scale, taking into consideration his protected pay-scale, which means that the petitioners would be entitled to the Time-Bound Promotional Scale of Rs. 1,600-2,660. Even, otherwise, the clarification at serial No. 17 is directory in nature and the Government was expected to examine the case of the petitioners on merits, but their claim was rejected merely on the ground that it was not permissible in terms of clarification at serial No. 17 of the O.M, dated 22 December 1989

    6. Moreover, in case of Field Surveyors in pay-scale of Rs. 1,200-2,040 on being deputed to P.W.D to lower post carrying pay-scale of Rs. 950-1,500 were similarly granted pay protection of Rs. 1,200-2,040 and they have been given T.B.P Scale of Rs. 1,350-2,200 which is the next scale. On same analogy the petitioners would be entitled to next scale of Rs. 1,600-2,660 as T.B.P.S If the same is declined to them, it would amount to discrimination under Art. 14 of the Constitution.

    7. In these circumstances, we are of the opinion that the petitioners are entitled to the Time-Bound Promotional Scale of Rs. 1,600-2,660 with effect from 1 June 1989 with all other consequential benefits. The writ petition is, accordingly, allowed in the aforesaid terms, with costs. The costs are quantified at Rs. 2,000 The rule is made absolute in the aforesaid terms. The arrears due under this order shall be payable within four months from today. 50 per cent of the arrears shall be deposited in the G.P.F Account of the petitioners and the balance 50 per cent shall be paid to them in cash.

    Use AI to get other relevant cases.

    Comments

    J.M Fernandes And Others v. State Of Goa And Another
    (Nov 10, 1998)