1. Introduction

The Building and Other Construction Workers’ Welfare Cess Act, 1996 (“Cess Act”) is a fiscal adjunct to the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 (“BOCW Act”). Together, the statutes seek to ensure that India’s vast and vulnerable construction workforce receives basic welfare benefits through a dedicated cess on the cost of construction. Nearly three decades after their enactment, courts continue to calibrate the scope of the levy, test its constitutional legitimacy, and compel executive authorities to operationalise the promised welfare architecture. This article critically analyses the jurisprudence emanating from the Supreme Court and various High Courts, appraises unresolved doctrinal tensions, and proposes pathways for more coherent enforcement.

2. Legislative Framework

2.1 Statutory Objectives

The Statement of Objects and Reasons of the BOCW Bill acknowledged approximately 8.5 million workers engaged in inherently hazardous, casual, and migratory construction work lacking basic amenities.[1] The BOCW Act accordingly regulates service conditions (Sections 6–40) and mandates State Welfare Boards (Sections 18–22), while the Cess Act provides the financial backbone by authorising a levy “not exceeding two per cent but not less than one per cent of the cost of construction” (Section 3).

2.2 Scheme of Levy and Collection

  • Trigger: Incurrence of cost of construction by an employer (Section 3, Cess Act).
  • Rate: Notified at 1 % since 26 September 1996.[2]
  • Mode: Self-assessment, deduction at source by public authorities, or advance collection at approval stage (Rules 4–6, Cess Rules 1998).
  • Earmarking: Entire proceeds credited to the Building and Other Construction Workers’ Welfare Fund.

3. Constitutional Competence and the Nature of the Cess

3.1 Fee versus Tax

In Dewan Chand Builders & Contractors v. Union of India (2011) the Supreme Court upheld the cess as a fee and not a tax, locating legislative competence in Entry 97, List I.[3] Applying the classical quid-pro-quo doctrine articulated in Hingir-Rampur Coal Co. (1961) and refined in Kewal Krishan Puri (1980), the Court found a rational nexus between the impost and the direct welfare benefits accruing exclusively to construction workers.[4]

3.2 Repelling the Vagueness and Legislative Competence Challenge

The Delhi High Court, in the consolidated decision Builders’ Association of India v. Union of India (2007), rejected arguments that Parliament lacked competence because “building” is a matter in List II.[5] The Court emphasised that the subject is not buildings per se but labour welfare — squarely traceable to the Concurrent List and the residuary power endorsed by the Supreme Court in Builders’ Association (1989) while upholding the 46th Constitutional Amendment concerning works contracts.[6]

4. Interface with the Factories Act and Other Exclusionary Regimes

4.1 The Lanco Doctrine

A recurrent controversy is whether registration of an establishment under the Factories Act, 1948 immunises it from the BOCW and Cess regime. The Supreme Court in Lanco Anpara Power Ltd. v. State of Uttar Pradesh (2016) resolved the issue by purposively interpreting Section 2(1)(d) of the BOCW Act: the exclusion applies only once the manufacturing process actually commences.[7] Consequently, during the construction phase of even a future “factory”, workers remain entitled to BOCW benefits, and cess is leviable.

4.2 Subsequent High Court Application

The Himachal Pradesh High Court in a trilogy of 2024 appeals (MS Batot Hydro Power; MS Lanco Thermal Power; MS Sarabhai Enterprises) faithfully applied Lanco, dismissing challenges premised on factory registration and holding that costs incurred post-constitution of the Welfare Board are cessable without violating the temporal limits.[8]

5. Temporal Operation and Allegations of Retrospectivity

The Supreme Court confronted the retrospectivity argument in A. Prabhakara Reddy v. State of Madhya Pradesh (2016). Contractors contended that contracts executed before the State Board’s constitution could not be subjected to cess. The Court, however, maintained that the levy attaches to costs incurred after 1 April 2003, regardless of when the contract was signed, thereby negating the retrospectivity plea.[9]

6. Mechanisms of Compliance and Dispute Scenarios

6.1 Deduction at Source in Public Contracts

In Delhi Metro Rail Corporation v. Simplex Infrastructures (2011) the High Court validated the contractual practice of the employer deducting 1 % from running bills, observing that Rule 4(3) of the Cess Rules expressly enables government undertakings to act as collecting agents.[10]

6.2 Contractual Clauses, Arbitration and Criminal Law

Ancillary disputes sometimes spill into criminal or arbitral fora. The Allahabad High Court in Larsen & Toubro v. State of Uttar Pradesh (2004) quashed criminal proceedings where parties had contracted for arbitration, illustrating how ordinary dispute-resolution clauses remain unaffected by the cess regime.[11]

6.3 Tender Conditions and Commercial Viability

Although not directly on cess, the Delhi High Court’s reasoning in GMR Chhattisgarh Energy Ltd. v. Union of India (2019) underscores that post-tender fiscal impositions (there, a tariff cap) may warrant withdrawal or restitution to preserve bid viability.[12] By analogy, sudden cess demands absent statutory notice could invite similar equitable reliefs, although the statutory nature of the cess limits contractual allocation.

7. Judicial Oversight of Implementation Deficits

7.1 The National Campaign Committee (NCC) Litigation

Beginning 2006, public-interest petitions by the National Campaign Committee for Central Legislation on Construction Labour exposed systemic non-implementation. A suite of Supreme Court orders (2009, 2010, 2011, 2014, 2015, 2018) chronically recorded that States collected thousands of crores in cess while failing to register workers or disburse benefits.[13] The 2018 judgment (Madan B. Lokur J.) issued time-bound directives: constitution of Boards, staff appointments, regular meetings, transparent audits, and utilisation of funds, emphatically linking non-compliance to a violation of Articles 21, 39(e)–(f), 41, and 47.[14]

7.2 Contemporary High Court Supervision

Recent High Court interventions adopt a supervisory tone. The Andhra Pradesh High Court in Hindustan Petroleum Corporation v. State of A.P. (2023) converted impugned recovery notices into show-cause notices and directed authorities to reconsider liability in light of Lanco within four weeks, staying coercive action in the interim.[15]

8. Persisting Challenges and Critical Perspectives

8.1 Multiplicity of Authorities

Dual oversight by labour departments (for registration and welfare) and revenue-collecting agencies often leads to disjuncture. Harmonised digital portals, akin to the GST framework, may reduce leakage and track cess flow in real time.

8.2 Determination of Cost of Construction

Courts have not yet evolved uniform principles for cost apportionment where contracts include both supply and installation of heavy machinery (e.g., HVAC systems, pipelines). The Andhra Pradesh High Court’s ruling in Vijayavisakha Milk Products (2023) that mere installation absent civil work is non-cessable invites a targeted legislative clarification.[16]

8.3 Overlapping Social Security Codes

The impending Code on Social Security, 2020 subsumes the BOCW Act. However, the draft rules presently dilute specific construction-centric safeguards. Unless the dedicated cess mechanism is preserved, the hard-won jurisprudence risk becoming otiose.

9. Conclusion

The Cess Act, fortified by consistent judicial endorsement, remains a constitutionally sound instrument for redistributive justice in India’s construction sector. The Supreme Court’s purposive interpretation in Lanco and meticulous classification analysis in Dewan Chand have settled foundational questions of applicability and competence. Nonetheless, the NCC litigation reveals an implementation gap so wide that constitutional promises ring hollow for most workers. Future discourse must pivot from validation to vigilant execution—entailing transparent cess collection, real-time fund utilisation, and convergence with emerging social-security codes. Only then can the cess realise its raison d’être: transforming precarious labour into dignified livelihoods.

Footnotes

  1. Statement of Objects and Reasons, Building and Other Construction Workers Bill, 1995 (extracted in Builders’ Association of India v. UOI, (2007) 139 DLT 578).
  2. Notification S.O. 2899, Ministry of Labour, 26 September 1996 (cited in Delhi Metro v. Simplex, (2011) Delhi HC).
  3. Dewan Chand Builders & Contractors v. Union of India, (2011) 1 SCC 101, ¶¶ 34–43.
  4. Hingir-Rampur Coal Co. v. State of Orissa, AIR 1961 SC 459; Kewal Krishan Puri v. State of Punjab, (1980) Supp SCC 416.
  5. Builders’ Association of India v. Union of India, (2007) 139 DLT 578 (Delhi HC).
  6. Builders’ Association of India v. Union of India, (1989) 2 SCC 645.
  7. Lanco Anpara Power Ltd. v. State of Uttar Pradesh, (2016) 10 SCC 329, ¶¶ 30–38.
  8. MS Batot Hydro Power Ltd. v. State of HP, 2024 SCC OnLine HP —; MS Lanco Thermal Power Ltd. v. State of HP, 2024 SCC OnLine HP —; MS Sarabhai Enterprises v. State of HP, 2024 SCC OnLine HP —.
  9. A. Prabhakara Reddy v. State of Madhya Pradesh, (2016) 1 SCC 600.
  10. Delhi Metro Rail Corporation v. Simplex Infrastructures, 2011 SCC OnLine Del —.
  11. Larsen & Toubro Ltd. v. State of Uttar Pradesh, 2004 SCC OnLine All 1575.
  12. GMR Chhattisgarh Energy Ltd. v. Union of India, 2019 SCC OnLine Del —.
  13. National Campaign Committee for Central Legislation on Construction Labour v. Union of India, (2011) 4 SCC 655; (2015) 17 SCC 160; (2018) 5 SCC 607.
  14. NCC v. UOI, (2018) 5 SCC 607, ¶¶ 17–28.
  15. Hindustan Petroleum Corporation Ltd. v. State of Andhra Pradesh, 2023 SCC OnLine AP —.
  16. Sri Vijayavisakha Milk Products Co. Ltd. v. State of A.P., 2023 SCC OnLine AP —.