Establishing Principles for Transmission Tariff Revision Based on Additional Capital Expenditure: CERC's Decision in Power Grid Corporation Ltd. v. Madhya Pradesh Power Trading Company Ltd.

Establishing Principles for Transmission Tariff Revision Based on Additional Capital Expenditure: CERC's Decision in Power Grid Corporation Ltd. v. Madhya Pradesh Power Trading Company Ltd.

Introduction

The case of Power Grid Corporation of India Ltd. v. Madhya Pradesh Power Trading Company Ltd. adjudicated by the Central Electricity Regulatory Commission (CERC) on August 7, 2009, marks a significant precedent in the realm of transmission tariff regulation. This petition sought the revision of transmission tariffs to account for additional capital expenditures incurred during the financial years 2005-2006 for the Fixed and Thyristor Controlled Series Compensation (FTCSC) of the 400 kV D/C Raipur-Rourkela transmission line.

The primary parties involved are the Power Grid Corporation of India Ltd. (the petitioner) and the Madhya Pradesh Power Trading Company Ltd. (the respondent). The crux of the dispute revolves around the adherence to the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2004, specifically regarding the allocation and capitalization of additional expenditures beyond the initially approved capital costs.

Summary of the Judgment

The CERC, upon reviewing the petition filed by the Power Grid Corporation, revisited the transmission charges previously approved for the period from April 1, 2005, to March 31, 2009. The petitioner claimed additional capital expenditure amounting to Rs. 13.21 lakh incurred during 2005-2006 for the FTCSC project. The commission meticulously examined the nature of the expenditure, the adherence to regulatory frameworks, and the economic implications of allowing such costs to be capitalized.

After thorough assessment, the CERC approved the revised transmission charges within the approved cost estimates, incorporating the justified additional capitalization. However, the commission denied the reimbursement of the petition filing fee and other related expenditures. The final transmission charges were adjusted and allowed to be recovered from the beneficiaries in three monthly installments.

Analysis

Precedents Cited

The judgment references several key regulatory provisions from the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2004. Specifically:

  • Regulation 52(1): Governs the determination of the final tariff based on the actual expenditure incurred.
  • Regulation 56: Details the computation of depreciation, return on equity, interest on loan, and other financial metrics essential for tariff calculation.
  • Previous orders such as Petition No. 11/2005 and Petition No. 3/2007 which dealt with capital cost approvals and provisions for initial spares.

These regulatory frameworks were pivotal in ensuring that the commission's decision adhered to standardized procedures, thereby maintaining consistency and fairness in tariff determinations.

Legal Reasoning

The CERC's legal reasoning hinged on the adherence to the 2004 regulations, particularly in assessing whether the additional expenditures were justifiable under the prescribed norms. The petitioner demonstrated that the additional Rs. 13.21 lakh was related to retention/final payments within the original scope of work, thereby qualifying for capitalization under regulation 52(1).

The commission also scrutinized the provisional increases in capital costs and ensured that the initial spares were within the permissible limit of 1.5% of the original project cost. Despite the petitioner's efforts to extend this ceiling to 5% through Petition No. 3/2007, the CERC maintained the application of the existing regulation, applying it retrospectively and not accommodating prospective amendments for assets already in operation.

Furthermore, the commission evaluated the debt-equity ratio, return on equity, and interest on loan calculations to ensure financial propriety and economic viability of the revised tariffs.

Impact

This judgment reinforces the importance of strict compliance with regulatory frameworks when seeking tariff revisions. By upholding the 1.5% cap on initial spares and ensuring only justified additional capital expenditures are capitalized, the CERC sets a clear precedent for future cases involving tariff revisions. It underscores the necessity for transmission companies to meticulously document and substantiate any additional expenditures to warrant tariff adjustments.

Moreover, the decision impacts the financial structuring of transmission projects, influencing how depreciation, return on equity, and interest on loans are calculated and integrated into tariffs. This contributes to greater transparency and predictability in tariff formulations, benefiting both the regulatory authorities and the beneficiaries.

Complex Concepts Simplified

Capital Expenditure and Capitalization

Capital Expenditure (CapEx) refers to funds used by a company to acquire, upgrade, and maintain physical assets such as property, industrial buildings, or equipment. In this case, the additional CapEx of Rs. 13.21 lakh was incurred for the FTCSC system.

Capitalization is the process of adding these expenditures to the asset's capital cost, thereby spreading the cost over its useful life through depreciation.

Depreciation

Depreciation is the systematic allocation of the cost of an asset over its useful life. The CERC uses a straight-line method based on the asset's historical cost, ensuring that only up to 90% of the capital cost is depreciable, excluding land.

Return on Equity (RoE)

Return on Equity represents the profitability related to shareholders' equity. The CERC mandated a 14% RoE, calculated based on the equity base determined under regulation 54.

Interest on Loan

Interest on Loan refers to the cost incurred on borrowed funds used for the project. The CERC provided detailed guidelines on calculating this interest, ensuring it reflects normative loan conditions.

Advance Against Depreciation (AAD)

Advance Against Depreciation allows the transmission licensee to receive a loan repayment advancement based on the depreciation charged on assets, subject to certain conditions.

Conclusion

The CERC's decision in Power Grid Corporation Ltd. v. Madhya Pradesh Power Trading Company Ltd. serves as a cornerstone for future tariff revision petitions involving additional capital expenditures. By meticulously adhering to established regulations and ensuring that only justified costs are capitalized, the commission fosters a regulated and transparent environment for transmission companies and their beneficiaries.

Key takeaways include the reaffirmation of the 1.5% cap on initial spares, the necessity for detailed documentation of additional expenditures, and the structured approach to calculating financial metrics like depreciation and return on equity. This judgment not only clarifies regulatory expectations but also enhances the integrity and reliability of tariff determination processes in the power sector.

Case Details

Year: 2009
Court: Central Electricity Regulatory Commission

Judge(s)

Pramod Deo Member S. Jayaraman Member Member V.S Verma

Advocates

1. Shri U.K Tyagi, PGCIL2. Shri M.M Mondal, PGCIL3. Shri V.V Sharma, PGCIL4. Shri J. Majumdar, PGCIL5. Shri Dilip Singh, MPPTCL

Comments