1.1 Purpose
These regulations, as authorized by 18 VSA Chapter 26, provide for the establishment of procedures to be followed and the standards for certification of asbestos contractors who perform asbestos abatement in any facility.
Pursuant to 18 VSA Chapter 26, these regulations require that all persons who perform asbestos abatement of asbestos-containing materials in any facility must obtain certification prior to commencing such asbestos abatement. The organizations or individuals who perform asbestos abatement are defined as Asbestos Abatement Contractor Entities, Asbestos Supervisor Contractors and Asbestos Worker Contractors. The organizations or individuals who perform activities for the evaluation of asbestos are defined as Asbestos Analytical Contractor Entities, Asbestos Analyst Contractor, Asbestos Consulting Contractor Entities and Asbestos Consultant Contractors. The organizations or individuals who perform activities for the purpose of accreditation or obtaining certification are defined as Training Contractor Entities. These regulations also set forth procedures for work practices and the standards for certification of Asbestos Contractor Training Courses to be used to meet certification requirements.
Alternative abatement methods for the control of asbestos-containing materials should be reviewed with the building owner prior to any removal of asbestos. The Vermont Department of Health does not require removal of asbestos-containing materials if they are intact, in good condition and have not been subject to damage by the general public and/or will not be disturbed by maintenance activities. When asbestos-containing materials will be disturbed either by renovation or demolition, removal of the asbestos-containing materials is required prior to the renovation or demolition commencing.
1.1.1 Scope
No person shall perform asbestos abatement in any facility without obtaining certification and a permit from the Commissioner. The Commissioner shall require the payment of fees at the time of application. The Commissioner shall not process an application for which a fee has not been paid. The Department also requires a 10 working day notification prior to the commencement of a demolition of a facility or an asbestos abatement activity in a facility.
1.1.2 Right of Entry
The Commissioner is authorized, upon presenting appropriate credentials, to seek permission to enter any asbestos abatement activity worksite located on public or private property, under the authority granted the Commissioner by 18 VSA Section 107. If permission is refused, the Commissioner may seek, pursuant to the authority granted by 18 VSA Section 121, a search warrant authorizing the inspection of such premises.
1.1.3 Enforcement
The Commissioner may enforce these regulations as necessary to protect the public health by exercising the authority granted the Commissioner by 18 VSA Chapters 1, 3 and 11.
1.1.4 Administrative Procedure
Any revocation, suspension, annulment or withdrawal of any certification shall be in accordance with 3 V.S.A. Chapter 25, Section 814.
1.1.5 Severability
If any provision of any section of these regulations or the application thereof to any firm, individual or circumstance is found by a court of competent jurisdiction to be illegal, invalid, or void, the remainder of these regulations shall be deemed unaffected and shall continue in full force and effect.
1.1.6 Homeowner Exemptions
Homeowners intending to do abatement in their own private residences must adhere to the work procedures of Sections 2.4.2, 2.4.3, 2.4.4, 2.4.5, 2.4.6, 2.6 and 6. If a homeowner chooses to hire an outside contractor to conduct asbestos abatement activities, then the contractor must be Vermont certified and follow all requirements per these regulations. Homeowners may collect bulk asbestos samples in their private residences. Samples shall be collected according to Department specifications and sent to a Department Certified Analytical Contractor Entity for analysis. Homeowners are exempt from Section 8; permit fees, when conducting their own abatement and may be exempt from Section 9.
1.3 Procedures for Contractor Certification
1.3.1 Application for Certification
A) To apply for a certificate as an Asbestos Contractor Entity, (Abatement, Analytical, Consulting, Training), or an Asbestos Contractor (Inspector, Inspector/Management Planner, Project Designer, Project Monitor, Analyst, Supervisor or Worker), the party seeking such certification shall submit a signed, completed application with all necessary documentation and the fee, made payable to the Vermont Department of Health, in accordance with the fee schedule outlined in Section
8, and submit the application to the Department on forms provided by the Department.
i) All contractors must complete an initial or refresher training course, as required, which has been certified or approved by the Department and is in accordance with EPA Asbestos Model Accreditation Plan, 40 CFR Part 763, Subpart E. Appendix C.
ii) All contractors shall be required to pass an examination, in accordance with EPA Asbestos Model Accreditation Plan, 40 CFR Part 763, Subpart E, Appendix C. The examinations shall be administered by the certified training contractor entity or another authority approved by the department.
iii) All contractors shall maintain accreditation in each category, in accordance with EPA Asbestos Model Accreditation Plan, 40 CFR Part 763, Subpart E, Appendix C.
1.3.2 Action upon Receipt of Applications
Within 15 working days after receiving an application, the Department shall notify the applicant of any deficiency in the application. Within 15 working days after receiving a completed application, including all additional information requested by the Department, the Department shall certify or deny the application. The Department may, on a case by case basis, extend the length of time for application review. The Department will notify the applicant of such extensions.
A) The Department will immediately return any application or fee which is incomplete. The Department may, within 15 working days after the filing of the application, require further information in order to better determine whether the application should be certified or denied.
B) If the Department requests further information from an applicant, and does not receive that information within 15 working days, then the application shall be considered abandoned and certification shall be denied. The fee will not be returned.
1.3.3 Denial of Applications
The Commissioner may deny an application for certification to any applicant who fails to meet the standards or who does not follow the procedures established by these regulations, including, but not limited to:
A) Failure to comply fully with applicable requirements, procedures, and standards set forth in these regulations.
B) Negligence on the part of the applicant and/or his/her employees or agents.
C) Submission of false information on an application, supplying false statements or failure to disclose required information.
D) Failure to submit the required information, fee payment and/or documentation with the application.
E) Any past violations of state or federal law pertaining to asbestos-related activities.
1.3.4 Suspension or Revocation of Certification
The Commissioner may suspend, modify, or revoke any certification issued under these regulations under the authority granted to the Commissioner by 18 VSA Section 123.
1.3.5 Expiration of Certification
Certifications shall expire one (1) year from the effective date on which the certificate was issued, unless suspended or revoked by the Commissioner before that time.
1.3.6 Renewal of Certification
A) Any request for renewal of certification issued under these regulations shall contain all the information requested by these regulations. A contractor may request the review of past submissions and petition the Department to reuse past documentation if the Department finds the past documentation to be complete.
B) Evidence of participation in annual refresher courses, specific to each contractor category, shall be provided with the renewal application.
C) An existing certification shall not expire until final action on the application has been taken by the Department, provided;
i) the application has been filed in proper form for renewal and;
ii) the application has been received at least 30 days prior to the expiration date of the existing certification.
1.3.7 Reciprocity
A) Each applicant for certification who is licensed, certified or permitted according to EPA Asbestos Model Accreditation Plan, 40 CFR Part 763, Subpart E, Appendix C for the appropriate asbestos abatement activity, consulting service, or analytical service in another state may petition the Department on a form provided by the Department to grant certification without repetition of the training requirements; provided the contractor meets the certification requirements outlined in these regulations for that type of certification and has paid the fee per Section
8.