1. An insured or the claimant shall give notice to the insurer of any loss arising under contract of insurance at the earliest or within such extended time as may be allowed by the insurer. On receipt of such a communication, a general insurer shall respond immediately and give clear information to the insured on the procedures that he should follow. In cases where a surveyor has to be appointed for assessing a loss/claim, it shall do so immediately, in any case within 72 hours of the receipt of intimation from the insured. Insurer shall communicate the details of the appointment of surveyor, including the role, duties and responsibilities of the surveyor to the insured by letter, email or any other electronic form immediately after the appointment of the surveyor.
2. The insurer/surveyor shall within 7 days of the claim intimation, inform the insured/claimant of the essential documents and other requirements that the claimant should submit in support of the claim. Where documents are available in public domain or with a public authority, the surveyor/insurer shall obtain them.
3. The surveyor shall start the survey immediately unless there is a contingency that delays immediate survey, in any case within 48 hours of his appointment. Interim report of the physical details of the loss shall be recorded and uploaded/forwarded to the insurer within the shortest time but not later than 15 days from the date of first visit of the surveyor. A copy of the interim report shall be furnished by the insurer to the insured/claimant, if he so desires.
4. Where the insured is unable to furnish all the particulars required by the surveyor or where the surveyor does not receive the full cooperation of the insured, the insurer or the surveyor, as the case may be, shall inform in writing to the insured under information to the insurer about the consequent delay that may result in the assessment of the claim. It shall be the duty equally of the insurer and the surveyor to follow up with the insured for pending information/documents guiding the insured with regard to submissions to be made. The insurer and/or surveyor shall not call for any information/document that is not relevant for the claim.
5. (i) The surveyor shall, subject to sub-regulation 4 above, submit his final report to the insurer within 30 days of his appointment. A copy of the surveyor's report shall be furnished by the insurer to the insured/claimant, if he so desires. Notwithstanding anything mentioned herein, in case of claims made in respect of commercial and large risks the surveyor shall submit the final report to the insurer within 90 days of his appointment. However, such claims shall be settled by the insurer within 30 days of receipt of final survey report and/or the last relevant and necessary document as the case may be.
(ii) Where special circumstances exist in respect of a claim either due to its special/complicated nature, or due to difficulties associated with replacement/reinstatement, the surveyor shall, seek an extension from insurer for submission of his report. In such an event, the insurer shall give the status to the insured/claimant fortnightly wherever warranted. The insurer may make provisional/on account payment based on the admitted claim liability.
6. If an insurer, on the receipt of a survey report, finds that it is incomplete in any respect, he shall require the surveyor, under intimation to the insured/claimant; to furnish an additional report on certain specific issues as may be required by the insurer. Such a request may be made by the insurer within 15 days of the receipt of the final survey report.
Provided that the facility of calling for an additional report by the insurer shall not be resorted to more than once in the case of a claim.
7. The surveyor, on receipt of this communication, shall furnish an additional report within three weeks from the date of receipt of communication from the insurer.
8. On receipt of the final survey report or the additional survey report, as the case may be, and on receipt of all required information/documents that are relevant and necessary for the claim, an insurer shall, with in a period of 30 days offer a settlement of the claim to the insured/claimant. If the insurer, for any reasons to be recorded in writing and communicated to the insured/claimant, decides to reject a claim under the policy, it shall do so within a period of 30 days from the receipt of the final survey report and/or additional information/documents or the additional survey report, as the case may be.
9. In case, the amount admitted is less than the amount claimed, then the insurer shall inform the insured/claimant in writing about the basis of settlement in particular, where the claim is rejected, the insurer shall give the reasons for the same in writing drawing reference to the specific terms and conditions of the policy document.