No Duty Without the Dike: Fourth Circuit Re-Affirms Plain-Language Contract Enforcement in Infrastructure-License Agreements
1. Introduction
Jimmy Edwards v. CSX Transportation, Inc., No. 23-1909 (4th Cir. Aug. 12, 2025) marks the
second appellate chapter in mass-flood litigation arising out of Hurricanes Matthew (2016) and
Florence (2018) in Lumberton, North Carolina. Residents and small businesses situated in the
low-lying southern and western quarters of Lumberton allege that a “gap” in the City’s levee—
created by CSX’s rail right-of-way paralleling the Lumber River—funneled floodwaters into
their neighborhoods. When CSX initially refused municipal requests to close the gap with
temporary sandbag barriers, the resulting inundation produced substantial property damage and
spawned a hybrid tort-and-contract class action.
In Edwards I (983 F.3d 112 (4th Cir. 2020)) the Fourth Circuit held that (1) federal pre-emption
under the Interstate Commerce Commission Termination Act (“ICCTA”) barred the tort
claims, but (2) a narrow breach-of-contract claim based on a 1960s “Tri-Party Agreement” (“TPA”)
between the City, Robeson County Drainage District No. 1, and CSX’s predecessor could proceed
because plaintiffs plausibly qualified as third-party beneficiaries.
On remand, the district court granted summary judgment to CSX on three alternative grounds,
including a merits ruling that no breach occurred. The present decision affirms solely on the
merits ground: the TPA obligated CSX to allow closure only of “said dike”—the specific earthen
dike authorized by the contract—yet the City never built such a dike. Consequently, CSX’s refusal
to permit an ad-hoc sandbag dam did not violate any contractual duty.
The Court’s opinion, authored by Judge Pamela Harris and joined by Judges Wynn and
Quattlebaum, crystallizes a straightforward but important contract principle: where parties
condition performance on the construction of a specified structure, failure to construct that
structure nullifies the other side’s reciprocal duty. The decision therefore provides fresh
appellate guidance on “conditional infrastructure licenses” and strengthens fidelity to
unambiguous contract text.
2. Summary of the Judgment
- The Fourth Circuit affirmed summary judgment for CSX.
- The Court addressed only the contract merits, bypassing alternative holdings on ICCTA
pre-emption and third-party beneficiary status.
- Key holding: Paragraph 8 of the TPA obligated CSX to allow the City to close the levee gap
only by closing “said dike,” i.e., the expressly-described 6-foot earthen dike with
10-foot top width and 3:1 side slopes. Because no such dike was ever erected, CSX owed
no duty to authorize alternative closures such as sandbag dams, and thus could not be in
breach.
- The Court declined to adopt the district court’s “condition precedent/contract never
became effective” rationale but reached the same result via plain-meaning
interpretation: CSX’s contractual duty is limited in scope to the constructed dike.
- The opinion underscores that courts will not rewrite contracts or impose liabilities
the parties did not bargain for, citing longstanding North Carolina authority.
3. Analysis
A. Precedents Cited and Their Influence
The panel’s reasoning is anchored in a constellation of prior rulings:
- Edwards v. CSX Transp., Inc. (“Edwards I”), 983 F.3d 112 (4th Cir. 2020)
Provided procedural history and set the stage by salvaging the contract claim from
wholesale dismissal. Though Edwards I dealt mostly with pre-emption and third-party
beneficiary questions, it framed the contractual argument that now fails on the merits.
- Cox v. Funk, 255 S.E.2d 600 (N.C. Ct. App. 1979)
Quoted by the district court for the condition-precedent doctrine. While the panel did
not adopt the doctrine as decisive, it implicitly recognised Cox’s conceptual validity
in conditional performance analysis.
- Woods v. Nationwide Mut. Ins. Co., 246 S.E.2d 773 (N.C. 1978)
Reaffirmed the principle that courts enforce contracts “as written,” without
implying unseen obligations. This bedrock rule supplied the doctrinal spine of the
Fourth Circuit’s reasoning.
- Sanders v. Wilkerson, 204 S.E.2d 17 (N.C. 1974)
Defined a licence as authority “to do certain specified acts upon the lands of the
licensor.” The Court cited Sanders to emphasize that the TPA grants only narrow
authority—to build and, if necessary, close the dike, nothing more.
- Federal procedural standards
Standard summary-judgment cases—Celotex Corp. v. Catrett, 477 U.S. 317 (1986)
and Fourth Circuit precedent in Carter v. Fleming, 879 F.3d 132 (4th Cir. 2018) and
Corder v. Antero Res. Corp., 57 F.4th 384 (4th Cir. 2023)—frame the de novo review
and contract-interpretation methodology.
Collectively, these authorities reinforced the panel’s textualist approach and limited
its analytic lens to the words of the TPA rather than extra-contractual equities.
B. The Court’s Legal Reasoning
- Contract Text Controls
The TPA meticulously describes a specific 6-foot earthen dike, supplies schematics,
and repeatedly references “said dike.” Under North Carolina law, clear language
is dispositive. CSX’s obligations are therefore tethered exclusively to that defined
structure.
- Scope of the License
The TPA is, in essence, a conditional licence on railroad property. Licences confer
only the rights enumerated; any act outside the licence is an encroachment on the
licensor’s property rights. Closing the gap by sandbagging tracks was never within
the licence’s enumerated acts.
- Duty Trigger—Construction of the Dike
Although the panel did not expressly adopt the “condition precedent” label, it
functionally treated the dike’s construction as a prerequisite to CSX’s duty to allow
closure. Absent that prerequisite, the contractual trigger was never pulled.
- No Implied Substitute Performance
Plaintiffs urged a pragmatic reading—any barrier that performs the dike’s job should
qualify. The panel rejected this as impermissible re-writing, citing Woods. Contract
specificity signals a deliberate allocation of risk and responsibility; courts will not
retrofit new duties because circumstances (e.g., extreme weather) reveal practical
gaps.
- Alternative Grounds Unnecessary
Because interpretation resolved the dispute, the Court expressly declined to weigh in
on (a) ICCTA pre-emption of the contract claim and (b) plaintiffs’ third-party
beneficiary status post-discovery—preserving analytical narrowness and leaving those
questions untouched for future cases.
C. Likely Impact of the Decision
- Infrastructure-Licence Drafting: Public entities frequently need easements or
licences from railroads and other utilities for levees, pipelines, fiber, or drainage
works. Edwards II (appellate) underscores that specificity is double-edged; where a
municipality bargains narrowly, failure to implement the bargained-for construction
defangs future enforcement rights. Drafters will be incentivised to include fallback
or substitute-method clauses.
- Climate-Adaptation Litigation: As climate events intensify, local governments may
seek emergency access to private infrastructure. This decision signals that courts
will not confer emergency rights extraneous to contract language, potentially
pressuring policymakers to negotiate broader, more flexible agreements ex ante.
- Railroad Pre-emption Strategy: Although the Court sidestepped ICCTA issues, the
litigation trajectory (complete pre-emption of tort claims plus contractual defeat)
offers railroads a template for defending floodgate-closure demands: enforce textual
limits and raise federal pre-emption in parallel.
- Third-Party Beneficiary Doctrine: The panel’s avoidance of that ground leaves the
doctrinal question open, but the result dampens practical utility—would-be third-party
claimants must still locate actionable covenants within the four corners of the
contract.
- Judicial Economy: The Court’s choice to affirm on the narrowest
ground foreshadows a jurisprudential trend: where textual interpretation suffices,
federal appellate courts may resist addressing broader pre-emption or standing issues.
4. Complex Concepts Simplified
- Third-Party Beneficiary: Someone who is not a signatory to the contract but whom
the parties intended to benefit directly. Such an individual may sue to enforce the
contract if that intent is manifest. Here, plaintiffs claim the levee gap clause was
meant to protect them.
- Condition Precedent: A contractual event that must occur before a party’s duty
to perform arises. Think of it as a “gate” that unlocks obligations. The district
court treated construction of the earthen dike as the gate.
- License vs. Easement: A licence is mere permission to do specific acts on
another’s land and is typically revocable or limited; an easement is a property right
that runs with the land. The TPA granted only a licence, signalling limited rights.
- ICCTA Pre-emption: A federal statute giving the Surface Transportation Board
exclusive authority over rail operations, thereby pre-empting many state-law
regulations or tort suits that would “manage” or “govern” rail activity.
- Plain-Meaning Rule: When contract language is clear, courts will enforce it as
written without inferring further obligations or considering extrinsic evidence.
5. Conclusion
The Fourth Circuit’s decision in Jimmy Edwards v. CSX Transportation, Inc. delivers a concise
yet consequential affirmation of contract orthodoxy: a party cannot be forced to comply with
obligations it never assumed, and courts must refrain from adding terms that parties omitted. By
holding that CSX’s duty to allow gap closure was contingent upon construction of the very dike it
licensed—something the City never built—the Court protects the integrity of negotiated
allocations of risk and responsibility, even against compelling public-policy narratives arising
from natural disasters. For practitioners, the message resonates beyond railroad flood cases:
draft precisely, perform conditions, and do not rely on judicial rewrites when crisis strikes.