Government-Required Training-Video Correction Counts as Labor Under the Miller Act
Case: Southern Equipment & Services, LLC v. Windamir Development, Inc.
Court: United States Court of Appeals for the Eleventh Circuit
Decision date: November 2, 2026
Docket: No. 26-10601
Disposition: Summary judgment on the Miller Act claim vacated; case remanded.
Precedential status: The opinion is designated “NOT FOR PUBLICATION.” It applies existing precedent rather than establishing a new binding circuit rule; its reasoning may nevertheless provide persuasive guidance in similar disputes.
1. Introduction
This appeal concerns when a subcontractor’s final corrective work qualifies as “labor” that starts the Miller Act’s one-year filing period. The Eleventh Circuit held that reshooting a contractually required training video, after the government rejected the original recording, qualified as labor because the correction was required for government approval.
The United States Army Corps of Engineers awarded Windamir Development, Inc. a contract to construct a vehicle paint-preparation facility at Fort Stewart, Georgia. Berkshire Hathaway Specialty Insurance Company furnished the payment bond as Windamir’s surety. Windamir subcontracted with Southern Equipment & Services, LLC (“SES”) to construct an abrasive blast booth system, a military-use facility valued at approximately $1.4 million.
SES’s obligations included supplying equipment, materials, labor, and associated documentation, as well as producing a training video with audio. The equipment’s operating procedures permitted only trained operators to use it and required operators to have viewed the video.
After a dispute arose over the unpaid subcontract balance and additional amounts SES claimed, SES sued Windamir and Berkshire. The district court concluded that SES’s Miller Act claim was untimely. The appeal addressed only that ruling; SES did not challenge the disposition of its other claims. Although Windamir remained in the case caption, the opinion expressly states that it was not a party to the appeal.
2. Material Facts and Procedural History
| Date |
Event |
Legal significance |
| May 29, 2020 |
SES began work. |
Established the commencement of subcontract performance. |
| December 21, 2020 |
SES achieved substantial completion. |
Did not establish that all qualifying Miller Act labor had ended. |
| January 2021 |
SES conducted in-person equipment training, which Windamir recorded. |
The Corps rejected the recording because its audio was inaudible. |
| February 16, 2021 |
SES was performing punch-list work. |
Defendants identified this as the last date of qualifying labor. |
| March 9, 2021 |
Windamir’s quality-control manager conveyed the Corps’ rejection and instructed SES to reshoot the video. |
Connected the later work to the government’s requirement for an acceptable original deliverable. |
| March 15, 2021 |
SES reshot the training video and addressed two punch-list items. |
The reshoot was qualifying labor within one year before suit. |
| April 14, 2021 |
The Corps accepted the project as complete. |
Supported the distinction between preapproval corrective work and later repairs. |
| February 22, 2022 |
SES filed suit. |
The action was timely measured from the March 15 reshoot. |
SES also performed later tasks, including replacing a pressure gauge and submitting drawings and warranties. It expressed willingness to assist with a possible addition involving fire monitoring and suppression. The appellate court did not decide whether these activities qualified as labor because the training-video reshoot independently established timeliness.
The parties filed cross-motions for partial summary judgment. Defendants argued that anything SES did after February 16 was merely repair work and therefore could not extend the filing period. The district court agreed that SES had not established qualifying labor within the relevant year and entered summary judgment against it.
3. Summary of the Opinion
The Eleventh Circuit vacated the judgment on the Miller Act claim. Its central conclusion was that SES’s March 15, 2021 training-video reshoot constituted labor under 40 U.S.C. § 3133(b)(4).
The court distinguished ordinary repairs after completion from corrective work required because the government refuses to approve original performance. Existing precedent recognizes the latter as qualifying labor. Here:
- The subcontract required an audio-enabled training video.
- The Corps rejected the original recording for inadequate audio.
- SES reshot the video in response to that rejection.
- The correction occurred before the Corps accepted the project as complete.
The decisive issue was therefore not whether the video was sufficiently important to the physical operation of the blast booth. It was whether the work was necessary to obtain government approval. Because SES filed suit within one year of the reshoot, its claim was timely.
The court did not decide that SES was owed the amounts claimed, determine the adjusted subcontract price, or direct payment under the bond. Those merits questions remained for further proceedings.
4. Analysis of the Court’s Legal Reasoning
A. The statutory inquiry concerns the last qualifying performance
The Miller Act requires payment bonds for covered federal construction contracts and permits qualifying suppliers of labor or materials to sue for unpaid amounts. Under § 3133(b)(4), an action must be brought no later than one year after the claimant last performed labor or supplied material.
This inquiry does not necessarily turn on substantial completion, submission of a final invoice, or formal government acceptance. Those events may supply context, but the statutory focus remains the claimant’s actual qualifying work. Accordingly, SES’s December substantial-completion date did not foreclose reliance on work performed the following March.
B. Ordinary repairs differ from government-required completion work
The court acknowledged the general rule that repairs, final inspections, and final measurements for estimates or statements do not constitute labor for limitations purposes. Nor does a task qualify merely because the subcontract requires it.
However, a separate line of binding authority recognizes corrective work demanded by the government before it will approve the original work. The distinction is between correcting rejected original performance to obtain approval and repairing work after completion. Describing an activity as a “repair” does not, by itself, resolve which category applies.
The training-video reshoot fit the government-approval category. SES had not simply volunteered to improve a previously accepted deliverable. It returned because the Corps had rejected the recording required by the subcontract.
C. Operational importance was not the controlling test
The district court relied on other district court decisions addressing whether repairs were significant or crucial to the project’s functioning. Berkshire likewise challenged whether SES’s evidence sufficiently established the video’s operational importance.
The appellate court treated that dispute as beside the central point. Although training was important, the applicable precedent asked whether the government required the correction before approval. This approach avoided making timeliness depend on a subjective ranking of how indispensable a particular task was to the facility’s operation.
D. The affidavit supplied specific evidence, not merely conclusions
SES relied on an affidavit from its managing member, Jim Cerny. He identified the training-video requirement, described the instruction conveyed by Windamir’s quality-control manager, and explained that he reshot the video on March 15.
Berkshire characterized the affidavit as conclusory. The court disagreed as to the relevant portions: they identified contractual requirements and specific events grounded in Cerny’s experience. An affidavit does not lose evidentiary value merely because it supports the affiant’s own interests.
The court characterized the decisive facts as unrefuted. Its holding therefore went beyond finding an unresolved factual dispute: it concluded that the reshoot qualified as labor and that the claim was timely.
E. Liberal construction supported, but did not replace, the doctrinal analysis
The opinion emphasized the Miller Act’s protective purpose and the requirement to construe it liberally for those supplying labor and materials to federal projects. That principle reinforced the application of the government-approval exception.
But the court did not excuse noncompliance with the one-year deadline or announce equitable tolling. It determined which performance counted under the statutory deadline. The action was timely under the statute itself.
5. Precedents Cited and Their Influence
A. Summary-judgment standards
- Ave. CLO Fund, Ltd. v. Bank of Am., N.A., 723 F.3d 1287 (11th Cir. 2013)
-
This decision supplied de novo review and the requirement that summary judgment be entered only when no genuine dispute of material fact exists and the movant is entitled to judgment as a matter of law. It also required viewing the evidence favorably to the nonmoving party. The Eleventh Circuit therefore independently assessed the district court’s legal classification of SES’s work.
- W. Grp. Nurseries, Inc. v. Ergas, 167 F.3d 1354 (11th Cir. 1999)
-
This case defined a material fact as one capable of affecting the outcome under governing law and a genuine dispute as one on which a reasonable jury could favor the nonmovant. Here, the facts concerning government rejection and the date of the reshoot directly affected timeliness.
B. The Miller Act’s protective purpose
- United States ex rel. Sherman v. Carter, 353 U.S. 210 (1957)
-
The Supreme Court explained that the Act protects those supplying labor and materials for federal public construction in place of protections potentially available under state law on nonfederal projects. This supplied the statutory context for SES’s payment-bond remedy.
- Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102 (1944)
-
The court relied on this decision for liberal construction of the Miller Act and its purpose of protecting those whose labor and materials enter public projects. It supported a practical application of the statutory remedy without eliminating the distinction between qualifying completion work and ordinary repairs.
- United States ex rel. Am. Civ. Constr., LLC v. Hirani Eng'g & Land Surv'ing, PC, 58 F.4th 1250 (D.C. Cir. 2023)
-
This persuasive authority reinforced that the Supreme Court interprets the Act broadly because of its highly remedial nature. It supported the interpretive approach but did not supply the controlling government-approval rule.
C. Ordinary repairs and qualifying corrective labor
- Gen. Ins. Co. of Am. v. United States ex rel. Audley Moore & Son, 406 F.2d 442 (5th Cir. 1969) (“Moore & Son I”)
-
This decision supported the general exclusion of repairs, final inspections, and final measurements for estimating or accounting purposes. It established the baseline against which SES’s later activities had to be evaluated.
- Gen. Ins. Co. of Am. v. United States ex rel. Audley Moore & Son, 409 F.2d 1326 (5th Cir. 1969) (“Moore & Son II”)
-
The subsequent decision clarified that a contractual obligation alone does not make an activity qualifying labor. Crucially, it also distinguished correction of defects after completion from replacement work required because an inspector refused approval of the original work. That distinction reconciled the ordinary-repair rule with the result here.
- United States ex rel. Dillon Constr., Inc. v. Cont'l Ins. Co., 776 F.2d 962 (11th Cir. 1985)
-
This Eleventh Circuit authority stated that repairs to the original project are not considered when determining the last day of labor. The court applied that rule alongside, rather than in place of, the government-approval exception and concluded that SES established qualifying labor within the filing period.
- Trinity Universal Ins. Co. v. Girdner, 379 F.2d 317 (5th Cir. 1967)
-
This was the principal substantive authority. It recognized that correcting defects in originally completed work can count as labor when a government inspector demands the correction before approval. The Eleventh Circuit treated SES’s reshoot as analogous: the government rejected an original deliverable and required its correction.
- United States ex rel. Benefit of Light & Power Utilities Corp. v. Liles Const. Co., 440 F.2d 474 (5th Cir. 1971)
-
This decision supported the continued application of the Trinity exception for repairs required as a condition of government approval. It confirmed that the general repair exclusion did not end the analysis.
D. Fact-specific analysis and binding circuit authority
- Ex parte Sw. Sur. Ins. Co., 247 U.S. 19 (1918)
-
The court cited this decision for the proposition that whether an activity constitutes labor depends on the particular facts. It cautioned against deciding timeliness solely through labels such as “repair” or “punch-list work.”
- S. Steel Co. v. United Pac. Ins. Co., 935 F.2d 1201 (11th Cir. 1991)
-
This circuit authority likewise supported a fact-sensitive assessment. The video’s contractual role, the Corps’ rejection, and the subsequent reshoot mattered collectively.
- Bonner v. City of Prichard, 661 F.2d 1206 (11th Cir. 1981)
-
This decision establishes that former Fifth Circuit decisions issued on or before September 30, 1981, bind the Eleventh Circuit. It explains why the older Fifth Circuit cases governing repairs and government-required corrections were controlling authorities, not merely persuasive examples.
E. Affidavits at summary judgment
- Evers v. Gen. Motors Corp., 770 F.2d 984 (11th Cir. 1985)
-
This case bars reliance on conclusory allegations unsupported by specific facts to defeat a properly supported summary-judgment motion. Cerny’s relevant statements satisfied that standard because they identified concrete requirements, communications, and performance.
- United States ex rel. v. Mortg. Invs. Corp., 987 F.3d 1340 (11th Cir. 2021)
-
As titled in the supplied opinion, this authority recognized that even self-serving, uncorroborated statements can create a material factual issue. It countered the suggestion that SES’s supporting evidence could be disregarded because it came from its own managing member.
- United States v. Stein, 881 F.3d 853 (11th Cir. 2018) (en banc)
-
This decision explained that Rule 56 does not prohibit an otherwise admissible affidavit from being self-serving or independently impose a corroboration requirement. Together with Rule 56(c)(4), it supported considering Cerny’s fact-specific affidavit while preserving ordinary admissibility requirements.
6. Potential Impact and Limits
A. Corrective deliverables may matter as much as physical installation
The opinion demonstrates that qualifying labor is not necessarily confined to installing or replacing physical components. Creating an acceptable training video can qualify when the government requires it as part of completing the contracted work. The decision does not, however, classify every manual, warranty, drawing, or administrative submission as labor.
B. Substantial completion and punch-list labels are not dispositive
Contractors and sureties cannot safely assume that substantial completion marks the final statutory performance date. Conversely, subcontractors cannot assume that every later punch-list task preserves a claim. The substantive reason for the work and its relationship to approval remain critical.
The video’s absence from the formal punch list did not defeat SES’s position. The documented government rejection and resulting instruction provided the relevant connection to contract completion.
C. Documentation of government rejection becomes especially important
Future disputes may turn on records showing what the government rejected, why correction was required, when the contractor communicated that requirement, and when the subcontractor performed it. Specific affidavits may also be important when supported by personal knowledge and concrete facts.
SES did not submit a separate invoice for the March 15 work. That circumstance did not prevent the court from finding qualifying labor, although the opinion announced no general rule about unbilled activities.
D. The holding does not create an open-ended extension
The decision does not establish that any government-requested repair restarts the filing period, particularly after original work has already been completed and approved. Nor does a subcontractor’s willingness to perform possible future work establish actual labor.
The holding rests on a narrower combination: a required original deliverable, government rejection, corrective performance, and subsequent project acceptance. Other later tasks remained undecided.
E. The appellate victory concerns timeliness only
On remand, SES still must establish entitlement to recovery under the applicable contractual and statutory requirements. The opinion removed the limitations ground for summary judgment; it did not resolve liability, damages, or every potential defense.
7. Complex Concepts Simplified
- Miller Act payment bond
- A financial undertaking protecting qualifying suppliers of labor and materials on federal construction projects if they are not paid.
- Surety
- The company backing the payment bond. Berkshire’s potential obligation depends on the bond and governing law.
- “Last labor”
- The claimant’s final work that legally qualifies under the Act—not necessarily its final visit, email, inspection, or repair.
- Substantial completion
- A stage at which the work is largely finished. It does not necessarily mean that all work relevant to the Miller Act deadline has ended.
- Punch list
- A list of outstanding construction tasks. Placement on the list does not automatically determine whether an item counts as statutory labor.
- Summary judgment
- A decision without trial when no genuine dispute of material fact remains and the law entitles a party to judgment.
- De novo review
- Independent appellate review without deference to the district court’s legal conclusion.
- Vacatur and remand
- Setting aside the challenged ruling and returning the case to the district court for further proceedings.
8. Conclusion
The opinion’s central lesson is that correcting rejected original work to obtain government approval can constitute Miller Act labor, even after substantial completion. SES’s required training-video reshoot therefore made its lawsuit timely.
The decision applies established precedent rather than creating a general exception for all late repairs. Its significance lies in its fact-sensitive treatment of completion work, its recognition of a nonphysical training deliverable, and its insistence that specific affidavit evidence receive proper consideration at summary judgment.