Contains public sector information licensed under the Open Justice Licence v1.0.
Ferson Contractors Ltd. v. Levolux AT Ltd.
Factual and Procedural Background
On 26 June 2002, His Honour Judge Wilcox in the Technology and Construction Court enforced an adjudicator's decision by summary judgment concerning an ongoing construction contract. The contract complied with Section 108 of the Housing Grants Construction and Regeneration Act 1996 ("the Act"), which mandates that construction contracts provide for interim dispute resolution through adjudication. The dispute arose between a subcontractor and a contractor regarding interim payments and alleged wrongful suspension of work. The subcontractor sought enforcement of the adjudicator's decision after the contractor failed to pay the sum awarded. The contractor challenged enforcement, citing contractual termination provisions. The initial enforcement order is now under appeal.
Legal Issues Presented
- Whether, pending final resolution by arbitration or litigation, an adjudicator's decision should be enforced even if it conflicts with other contractual rights.
- Whether contractual termination provisions can override the binding nature of an adjudicator's decision under Section 108 of the Act.
- The proper interpretation and effect of specific contract clauses relating to adjudication, arbitration, termination, and payment obligations.
Arguments of the Parties
Appellant's Arguments
- The judge misinterpreted the adjudicator's decision; the adjudicator only determined the sum due as of a specific date and did not decide on the validity of the contract termination.
- The adjudicator's decision remains binding but does not exclude argument on termination before the court.
- There are exceptions to the binding effect of adjudicator decisions: lack of jurisdiction, overriding contractual terms, and decisions superseded by subsequent adjudications.
- Contractual termination clauses (Clauses 29.8 and 29.9) should prevail over the adjudicator's decision, potentially negating payment obligations.
- Relies on authority from a first instance judgment (Bovis Lend Lease v. Triangle Developments Ltd) supporting that clear contractual terms can override adjudicator decisions.
Respondent's Arguments
- The adjudicator's decision implicitly found the contract termination invalid, entitling the subcontractor to payment.
- Section 108 of the Act intends adjudicator decisions to be binding and enforceable pending final dispute resolution, preventing contractual provisions from undermining this purpose.
- Contract clauses 29.8 and 29.9 must be read as not applying to monies due under an adjudicator's decision to give effect to Parliament's intention.
- The contract contains a clause (38A.9) expressly requiring compliance with adjudicator decisions notwithstanding arbitration provisions.
- Enforcement by summary judgment is appropriate and consistent with the parties' agreement and statutory scheme.
Table of Precedents Cited
Precedent | Rule or Principle Cited For | Application by the Court |
---|---|---|
Macob Civil Engineering Ltd v. Morrison Construction Ltd [1999] BLR 93 | Explains Parliament's intention to provide a speedy, interim, binding adjudication process under s.108. | Used to clarify the statutory scheme and the binding, provisional nature of adjudicator decisions pending final resolution. |
Bouygues v. Dahl-Jensen 2000 BLR 522 | Adjudicator's decisions are enforceable interim awards even if erroneous, provided jurisdiction is not exceeded. | Illustrated that errors by adjudicators do not invalidate provisional awards if jurisdiction is proper. |
C B Scene Concept Design Ltd v. Isobars Ltd [2002] EWCA Civ 46 | Reinforces the swift, binding, but provisional nature of adjudication under s.108. | Supported the principle that adjudicator decisions must be complied with immediately, subject to later challenge. |
Nikko Hotels (UK) Ltd v. MEPC Plc 1991 2 EGLR 103 | Distinguishes between an adjudicator answering the right question wrongly (binding) and answering the wrong question (nullity). | Adopted to confirm the validity of the adjudicator's decision despite alleged errors. |
K & S Industrial Services (Birmingham) Ltd v. Sindall Ltd [2000, 2001] | Contractual termination or other events may override adjudicator decisions if lawful and supported by prospects of success. | Relied upon by appellant to argue contractual provisions can supersede adjudicator awards; court distinguished and limited its application. |
Bovis Lend Lease v. Triangle Developments Ltd [2002] | Identifies exceptions where contractual terms may override adjudicator decisions; emphasizes clear words are required. | Examined to assess the scope of exceptions to the binding nature of adjudicator decisions; court found limited applicability here. |
Parsons Plastics (Research and Development) Ltd v. Purac Ltd [2002] BLR 334 | Allows set-off and counter-claims against adjudicator decisions not determined by adjudication. | Distinguished as dealing with non-construction contract and set-offs, not termination; court found it inapplicable to override adjudicator's award here. |
Court's Reasoning and Analysis
The court began by affirming the statutory framework established by Section 108 of the Housing Grants Construction and Regeneration Act 1996, which mandates that adjudicator decisions in construction contracts are binding and enforceable on an interim basis pending final dispute resolution. The court reviewed authoritative case law confirming that Parliament intended adjudication to provide a swift and effective interim remedy, even if the adjudicator errs, so long as jurisdiction is not exceeded.
The adjudicator had found that the contractor's notice of withholding payment did not comply with statutory requirements and thus the subcontractor was entitled to payment. The contractor argued that contractual termination provisions negated this obligation. The court rejected this, interpreting the adjudicator's decision as implicitly concluding that the contract termination was invalid, which was a necessary implication given the finding on payment entitlement.
The appellant's argument that contractual termination clauses (Clauses 29.8 and 29.9) could override the adjudicator's decision was considered but ultimately rejected. The court emphasized that to give effect to the statutory purpose and the parties' agreement (notably Clause 38A.9), these clauses must be read as not applying to monies due under an adjudicator's decision. The court found that allowing contractual provisions to undermine the binding nature of adjudication would defeat Parliament's clear intention.
The court distinguished the appellant's cited authorities on the basis that they either involved different factual contexts, non-statutory adjudications, or did not engage with the overriding statutory scheme. The court upheld the initial judge's reasoning that the adjudicator's decision was within jurisdiction and binding, and that enforcement by summary judgment was appropriate and consistent with the contract and statute.
Holding and Implications
The court DISMISSED THE APPEAL.
The adjudicator's decision was held to be binding and enforceable notwithstanding the contractual termination provisions cited by the appellant. The contract clauses allowing for termination and withholding of payments do not apply to monies due under a valid adjudicator's award. This affirms the primacy of Section 108 adjudication decisions as interim binding determinations in construction disputes, reinforcing the statutory scheme designed to ensure prompt and effective resolution of payment disputes. No broader precedent was established beyond affirming the binding nature of adjudicator decisions within the statutory framework and contractual context presented.
Please subscribe to download the judgment.
Comments