Finality in Tariff Determination: Central Electricity Regulatory Commission's Decision in NTPC v. Madhya Pradesh SEB

Date: Jan 26, 2006

Finality in Tariff Determination: Central Electricity Regulatory Commission's Decision in National Thermal Power Corporation Ltd. v. Madhya Pradesh State Electricity Board Introduction The case of...

Establishing Transmission Charge Framework and Capitalization Norms: PGCIL v. Karnataka Power Transmission C.C.

Date: Jan 18, 2006

Establishing Transmission Charge Framework and Capitalization Norms: PGCIL v. Karnataka Power Transmission C.C. Introduction The case of Power Grid Corporation Of India Limited (PGCIL) v. Karnataka...

Comprehensive Commentary on CERC's Decision in PGCIL v. Bihar State Electricity Board

Date: Jan 15, 2006

Comprehensive Commentary on CERC's Decision in Power Grid Corporation Of India Limited v. Bihar State Electricity Board, Patna 1. Introduction The case of Power Grid Corporation Of India Limited...

CERC Upholds FERV Capitalization and 50:50 Debt-Equity Ratio in Transmission Tariff Approval

Date: Jan 6, 2006

CERC Upholds FERV Capitalization and 50:50 Debt-Equity Ratio in Transmission Tariff Approval Introduction The case of Power Grid Corporation Of India Limited v. Bihar State Electricity Board, Patna...

Comprehensive Commentary on Power Grid Corporation Of India Limited v. Karnataka Power Transmission Corporation Ltd., Bangalore

Date: Jan 5, 2006

Establishing Transmission Charge Framework: Power Grid Corporation of India Limited v. Karnataka Power Transmission Corporation Ltd. Introduction The case of Power Grid Corporation of India Limited...

CERC's Comprehensive Framework for Transmission Tariff Approval in Power Grid Corporation Of India Ltd. v. Karnataka Power Transmission Corporation Ltd.

Date: May 11, 2005

CERC's Comprehensive Framework for Transmission Tariff Approval in Power Grid Corporation Of India Ltd. v. Karnataka Power Transmission Corporation Ltd. 1. Introduction The case of Power Grid...

Comprehensive Commentary on National Thermal Power Corporation Ltd. v. Madhya Pradesh State Electricity Board, Jabalpur

Date: Apr 2, 2005

Establishing Comprehensive Tariff Regulations: Insights from National Thermal Power Corporation Ltd. v. Madhya Pradesh State Electricity Board, Jabalpur Introduction The case of National Thermal...

Limitation on Retrospective Tariff Revisions for Capital Expenditure: Analysis of National Thermal Power Corporation Ltd. v. Uttar Pradesh Power Corporation Ltd.

Date: Apr 1, 2005

Limitation on Retrospective Tariff Revisions for Capital Expenditure: Analysis of National Thermal Power Corporation Ltd. v. Uttar Pradesh Power Corporation Ltd. Introduction The case of National...

Apportionment of Abnormal Security Expenses in Electricity Tariffs: Power Grid Corp v. Bihar SEB

Date: Feb 23, 2005

Apportionment of Abnormal Security Expenses in Electricity Tariffs: Power Grid Corporation of India Ltd. v. Bihar State Electricity Board, Patna Introduction The case of Power Grid Corporation of...

Revision of Transmission Tariffs Based on Loan Repayment: Power Grid Corporation of India Ltd. v. Madhya Pradesh Electricity Board

Date: Jul 31, 2004

Revision of Transmission Tariffs Based on Loan Repayment: Power Grid Corporation of India Ltd. v. Madhya Pradesh Electricity Board Introduction The case of Power Grid Corporation of India Ltd. v....

Finality of Capital Cost in Tariff Determination – Uttar Pradesh Power Corporation Ltd. v. National Thermal Power Corporation Ltd.

Date: Jul 2, 2004

Finality of Capital Cost in Tariff Determination Introduction The case of Uttar Pradesh Power Corporation Ltd. v. National Thermal Power Corporation Ltd. adjudicated by the Central Electricity...

CERC's Landmark Ruling on Tariff Determination: Insights from National Thermal Power Corporation Ltd. v. Uttar Pradesh Power Corporation Ltd.

Date: Jul 2, 2004

CERC's Landmark Ruling on Tariff Determination: Insights from National Thermal Power Corporation Ltd. v. Uttar Pradesh Power Corporation Ltd. Introduction The case of National Thermal Power...

Capital Cost Allocation and Tariff Determination in NTPC v. UP Power Corporation

Date: Jun 19, 2004

Capital Cost Allocation and Tariff Determination in NTPC Ltd. v. Uttar Pradesh Power Corporation Ltd. Introduction The case of National Thermal Power Corporation Ltd. (NTPC) v. Uttar Pradesh Power...

CERC Upholds Approved Capital Cost and O&M Expense Framework in Power Grid v. Bihar State Electricity Board (2004)

Date: May 12, 2004

CERC Upholds Approved Capital Cost and O&M Expense Framework in Power Grid v. Bihar State Electricity Board (2004) Introduction The case of Power Grid Corporation Of India Ltd. v. Bihar State...

Exclusion of Incentive and Ex-Gratia Payments from O&M Employee Costs: A Landmark Decision by CERC

Date: Apr 14, 2004

Exclusion of Incentive and Ex-Gratia Payments from O&M Employee Costs: A Landmark Decision by CERC Introduction The case of Power Grid Corporation Of India Ltd. v. Karnataka Power Transmission...

CERC’s Framework for Transmission Tariff Approval: Power Grid Corporation v. Bihar State Electricity Board

Date: Feb 18, 2004

CERC’s Framework for Transmission Tariff Approval: Power Grid Corporation v. Bihar State Electricity Board Introduction The case of Power Grid Corporation of India Ltd. v. Bihar State Electricity...

CERC Reinforces Payment Compliance for Unscheduled Interchange Charges under ABT Scheme in WRLDC v. MPSEB

Date: Nov 7, 2003

CERC Reinforces Payment Compliance for Unscheduled Interchange Charges under ABT Scheme in WRLDC v. MPSEB Introduction The case of Western Regional Load Despatch Centre (WRLDC) v. Madhya Pradesh...

Comprehensive Commentary on Power Grid Corporation Of India Ltd. v. Bihar State Electricity Board

Date: Aug 5, 2003

Approval of Transmission Tariff for Farakka STPS: Power Grid Corporation Of India Ltd. v. Bihar State Electricity Board Introduction The case of Power Grid Corporation Of India Ltd. v. Bihar State...

CERC's Enhanced Compliance Reporting Framework under IEGC

Date: Feb 23, 2002

CERC's Enhanced Compliance Reporting Framework under the Indian Electricity Grid Code (IEGC) Introduction The case of Power Grid Corporation Of India Ltd., In Re adjudicated by the Central...

Reduction of Normative Availability in Hydroelectric Projects: NHPC v. Union of India

Date: Feb 20, 2002

Reduction of Normative Availability in Hydroelectric Projects: NHPC v. Union of India Introduction The case of National Hydroelectric Power Corporation Ltd. (NHPC) v. Union Of India was adjudicated...