COSA “Abandon Ditches” Conditions and Constructive Notice Can Negate the Intent Element for an Implied Easement by Existing Use
Dolan v. Guenther, 2026 MT 73 (Mont. Apr. 7, 2026) — Supreme Court of Montana (Baker, J.)
1. Introduction
This appeal arises from a subdivision drainage/irrigation ditch dispute in the five-lot Cobb Hill Minor Subdivision in Gallatin County.
Plaintiffs-appellants James J. Dolan, Jr. and Samantha L. Dolan (the “Dolans”) asserted that a small ditch running through multiple lots
constituted an easement benefiting their Lots 2 and 3 and that neighbors Tracy and Jesse Guenther (the “Guenthers”) interfered with that
ditch by installing culverts to satisfy subdivision sanitation requirements tied to their septic drain field.
The central legal issue was whether the Dolans could establish an implied easement by existing use for the ditch crossing the Guenthers’ Lot 4,
notwithstanding a recorded Certificate of Subdivision Approval (“COSA”) condition requiring that “small ‘feeder’ irrigation ditches across the lots”
be abandoned. A second issue concerned the Guenthers’ entitlement to attorney fees and costs—including on appeal—under Montana’s ditch-easement
interference fee-shifting statute, § 70-17-112(5), MCA.
Procedurally, the case also tested the limits of summary-judgment case management (Rule 56(f) continuances, stays of briefing, and the district court’s
invocation of waiver and law-of-the-case), though the Montana Supreme Court ultimately treated any procedural missteps as harmless given its merits
conclusions.
2. Summary of the Opinion
Holding (merits): The Dolans did not prove an implied easement by existing use by clear and convincing evidence. In particular, the record—dominated by the recorded COSA’s abandonment condition, the lack of any pre-severance approval or mitigation, and regulators’ continued insistence that the ditch be abandoned or mitigated—did not support the required inference that the parties to the severing deed intended the ditch use to continue.
Holding (fees): Because the Guenthers prevailed on the ditch-easement interference claim, they are entitled to reasonable attorney fees and costs under § 70-17-112(5), MCA, including fees and costs incurred on appeal; the case was remanded to determine the reasonable appellate amount.
The Court affirmed the District Court’s grant of partial summary judgment for the Guenthers and the denial of the Dolans’ cross-motion for partial summary judgment.
Although the Supreme Court did not “adopt all” of the District Court’s reasoning, it agreed that the Dolans failed to establish the implied easement and that fees follow the prevailing party.
3. Analysis
3.1 Precedents Cited (and How They Shaped the Decision)
-
Blazer v. Wall — Used for foundational easement principles and the effect of recording on notice (“constructive notice”).
The Court leaned on Blazer to reinforce that recorded subdivision instruments can bind later parties through constructive notice and to support its discussion
of how COSA/plat recording places purchasers on notice of restrictions relevant to alleged property rights.
-
Yellowstone River, LLC v. Meriwether Land Fund I, LLC — The opinion’s most important doctrinal anchor.
It supplies (i) the “extreme caution” approach to implied easements (because they derogate from the preference for written instruments),
and (ii) the rule that implied easements cannot arise where evidence is “contrary to the parties’ intention.”
The Court used Yellowstone to justify a strict, intent-centered inquiry and to reject implication where the recorded COSA and regulatory stance point the other way.
-
Waters v. Blagg (overruled on other grounds by Earl v. Pavex, Corp.) — Cited for the general framework that implied easements may arise upon severance from common ownership,
and for the multi-element test later reaffirmed in other cases. The Court treated Waters as part of the stable line of implied-easement authority.
-
JRN Holdings, LLC v. Dearborn Meadows Land Owners Ass'n — Provided the current three-part test for an implied easement by existing use:
unity of ownership; apparent/continuous/reasonably necessary use at severance; and intent that the use continue after division.
The Court used JRN Holdings both to structure the analysis and to emphasize the “reasonably necessary” requirement.
-
Hoyem Tr. v. Galt and Wolf v. Owens — Cited (via JRN Holdings) on implied easements arising from severance and the quasi-easement concept.
These cases support the principle that pre-severance use matters because it is evidence of intent at the moment the land is divided.
-
Apecella v. Overman — Supplied the clear and convincing evidence burden for establishing the implied easement.
This heightened burden mattered because the Court found the COSA and regulatory record to be strong counter-evidence to intent and necessity.
-
White v. Landerdahl, Tungsten Holdings, Inc. v. Kimberlin, and Graham v. Mack — Used to explain how intent is proved:
it is “gathered from the evidence” of the overall transaction and the surrounding circumstances, including uses reasonably contemplated at conveyance.
The Court relied on this line to reject the Dolans’ attempt to build intent from later events rather than from the circumstances at severance.
-
Koestel v. Buena Vista Pub. Serv. Corp. — An out-of-state citation supporting the core logic that implied easements are grounded in supposed intent,
and thus are not implied when evidence shows an absence of such intent. It reinforced the Court’s refusal to infer intent contrary to the COSA record.
-
Hauseman v. Koski — Cited for Montana’s recording-statute notice principle: recording imports notice to interested parties on title-affecting matters.
This helped the Court treat the COSA as part of the legal/transactional environment that shapes “reasonable contemplation.”
-
Williams v. Schwager — Key to the Dolans’ “COSA deviations aren’t illegal per se” argument.
The Court accepted the general proposition from Williams (deviation is possible with approval) but distinguished it: there, authorities approved the shared well and it was customary;
here, regulators repeatedly insisted the ditch violated the COSA absent mitigation, undercutting any claim that continuation was reasonably contemplated at severance.
-
Reiman v. Anderson — Used (via the Water Court background) to clarify that water rights and ditch rights are distinct.
This helped keep the case focused on easement doctrine rather than water-right abandonment.
-
Baugh v. H2S2, LLC — Provided the standard of review for summary judgment (de novo).
-
Hinderman v. Krivor, Flying T Ranch LLC v. Catlin Ranch, LP, and State v. Keefe — Standards of review for Rule 56(f), stay orders, and law-of-the-case.
-
Stephenson v. Lone Peak Preserve, LLC and In re A.N. — Abuse-of-discretion definition and harmless-error principle.
The Court applied harmless error to the district court’s stray references to waiver and law-of-the-case.
-
Rosenthal v. Cnty. of Madison and Miller v. Goetz — Used to reject the Dolans’ Rule 56(f) challenge:
the Dolans had ample time to pursue key depositions and failed to identify what discovery would change the outcome.
-
Ike v. Jefferson Nat. Life. Ins. Co., Hajenga v. Schwein, and Kilby Butte Colony, Inc. v. State Farm Mutual Auto. Ins. Co. —
Clarified that cross-motions must each be evaluated on their merits; they did not require simultaneous consideration.
-
Roe v. City of Missoula, ex rel. Missoula City Council and Mountain W. Farm Bureau Mut. Ins. Co. v. Brewer —
Provided correct waiver principles, which the Court noted the district court misstated, but deemed non-prejudicial because the district court proceeded to decide the merits.
-
State v. Marcial — Supported affirmance where the district court reaches the correct result even for imperfect reasons.
-
Espy v. Quinlan — Confirmed that fee-shifting under § 70-17-112(5), MCA includes attorney fees incurred on appeal.
The Court applied Espy to award appellate fees to the Guenthers and remand for calculation.
3.2 Legal Reasoning
The Court framed implied easements as disfavored, “extreme caution” doctrines because they impose property burdens without an express written grant.
It then applied the three-element test (from JRN Holdings, LLC v. Dearborn Meadows Land Owners Ass'n), with two elements doing the decisive work here:
intent at severance and reasonable necessity.
3.2.1 Intent Must Be Reasonably Contemplated at Severance—and the COSA Record Cut Against It
The Dolans’ theory depended on the proposition that a common owner (Ewing Trust) reestablished/continued ditch use and represented to successors that ditch conveyance
served the lots. The Supreme Court’s response was twofold:
-
Timing: An implied easement by existing use arises (if at all) at the moment common ownership is severed; intent must be evidenced by the circumstances
and reasonable expectations at that time, not “formulated” later. The Court cited intent authorities (White v. Landerdahl, Tungsten Holdings, Inc. v. Kimberlin,
Graham v. Mack) and treatise principles to stress this temporal boundary.
-
Transactional environment: The recorded COSA and plat formed part of the objective context that shapes what is “reasonably contemplated.”
Because the COSA was recorded with the plat (and deeds referenced the plat), subsequent owners had constructive notice that approval was conditioned on abandoning feeder ditches,
maintaining setbacks, and locating systems per approved plans. The Court used recording/notice principles (notably Blazer v. Wall and Hauseman v. Koski)
to treat the COSA as legally salient evidence of intent.
The Court’s core inferential move: even if a COSA can be amended, an implied easement requires proof that continuation was within “reasonable contemplation” at severance.
With a recorded abandonment condition, no pre-severance request for amendment/approval, and later regulator insistence that the ditch remained noncompliant absent mitigation,
the record “is evidence contrary to the parties’ intent” required for implication.
3.2.2 “Not Illegal Per Se” Was Not Enough (Distinguishing Williams v. Schwager)
The Dolans leaned on Williams v. Schwager to argue that deviation from subdivision approval conditions is not automatically unlawful, so intent to continue ditch use
should still be inferable. The Court accepted the abstract point—deviations may occur if approved—but held it did not establish that ditch continuation was reasonably expected at severance.
Unlike Williams, where the authority approved the deviation and the arrangement was customary, the DEQ and Health Department here repeatedly treated the ditch as a violation absent
culverts/mitigation.
3.2.3 Reasonable Necessity Was Not Shown
The Court also held the Dolans failed to prove the ditch was “reasonably necessary” for beneficial use and enjoyment of their lots at severance.
Invoking the “extreme caution” principle from Yellowstone River, LLC v. Meriwether Land Fund I, LLC, the Court emphasized that implied easements are not granted for mere convenience
“short of proven necessity.”
3.2.4 Procedural Issues: Harmless Error and No Prejudice
The Supreme Court rejected the Dolans’ procedural attacks largely for lack of demonstrated prejudice:
(i) denial of the Rule 56(f) request was upheld because the Dolans had ample time and did not identify outcome-changing discovery (Rosenthal v. Cnty. of Madison;
Miller v. Goetz); (ii) no rule required the district court to decide cross-motions simultaneously (Hajenga v. Schwein and related cases);
and (iii) the district court’s references to waiver and law-of-the-case were erroneous but harmless because it decided the merits anyway (In re A.N.;
State v. Marcial).
3.3 Impact
The decision’s practical effect is to make it significantly harder to establish implied easements by existing use in modern subdivisions where recorded regulatory approvals
(COSA/plat conditions under Title 76, chapter 4, MCA) speak directly to the continued existence of the alleged servitude.
Key forward-looking implications include:
-
Recorded COSA conditions become powerful “anti-intent” evidence: Where a COSA expressly requires abandonment of features that later are claimed as easements,
courts may treat that as strong evidence that continuation was not within the parties’ reasonable contemplation at severance—especially if no pre-severance approval was sought.
-
“Amendable later” does not equal “intended then”: The availability of later amendment under § 76-4-104(7)(j), MCA and Admin. R. M. 17.36.112(3) (2023)
cannot substitute for proof of intent and reasonable expectation at severance.
-
Necessity is re-centered: The Court reaffirmed that implied easements cannot be awarded on convenience alone, reinforcing a stricter necessity showing in subdivision contexts.
-
Fee-shifting leverage remains strong in ditch disputes: By reaffirming appellate fees under § 70-17-112(5), MCA (via Espy v. Quinlan),
the opinion underscores that ditch-easement litigation carries substantial fee exposure for the losing party—potentially affecting settlement dynamics.
4. Complex Concepts Simplified
-
Implied easement by existing use: An easement the law infers (without a written grant) when a common owner used one part of land to benefit another part,
and—when the land is split—circumstances show the parties intended that use to continue and it is reasonably necessary.
-
Quasi-easement / quasi-servient and quasi-dominant tenements: Before land is split, the “benefited” and “burdened” portions are not legally dominant/servient
because one owner cannot hold an easement over their own land; the pre-split use is a “quasi-easement” that may later support implication.
-
COSA (Certificate of Subdivision Approval): A regulatory approval under Montana subdivision sanitation laws (Title 76, ch. 4, MCA) that can impose conditions
(e.g., ditch abandonment, septic setbacks, and approved locations). Recorded COSAs can shape property expectations and obligations.
-
Constructive notice: The legal rule that recorded documents affecting real property (like plats and associated COSAs) are treated as known to purchasers,
even if they did not actually read them.
-
Rule 56(f) (now commonly referenced as Rule 56(d) in some jurisdictions): A mechanism allowing a party opposing summary judgment to request more time for discovery
when they cannot yet present facts essential to justify opposition.
-
Law-of-the-case doctrine: A discretionary principle that courts generally should not revisit issues already decided earlier in the same case;
here, it was mentioned but not determinative because the merits were addressed.
-
Rule 54(b) certification: A procedural tool allowing a court to enter final judgment on fewer than all claims/parties so an immediate appeal can proceed.
-
Fee shifting under § 70-17-112(5), MCA: A statute awarding the prevailing party attorney fees and costs in actions based on interference with a ditch easement,
including fees incurred on appeal.
5. Conclusion
Dolan v. Guenther reinforces a stringent approach to implied easements by existing use in regulated subdivisions: the claimant must prove—by clear and convincing evidence—
that continuation of the use was intended and reasonably contemplated at the moment of severance, and that the use was reasonably necessary.
Where a recorded COSA expressly conditions subdivision approval on abandoning the very feature claimed as an easement, and regulators persistently reject unmitigated continuation,
Montana courts are unlikely to infer the requisite intent.
The opinion also highlights the litigation stakes in ditch-easement disputes: § 70-17-112(5), MCA operates as a meaningful fee-shifting regime, and under Espy v. Quinlan,
it reaches appellate fees—here prompting a remand solely to calculate the Guenthers’ reasonable fees and costs on appeal.