Factual and Procedural Background

The petitioner, TRF Ltd., is a company that received one or more Letters of Intent and Purchase Orders from the respondent, Energo Engineering Projects Ltd., for the supply, erection and commissioning of bulk material handling equipment (including a Reversible Bucket Wheel Type Stacker-cum-Reclaimer, wagon tippler, side arm charger, apron feeder and related items). To secure performance under the Purchase Orders the petitioner had furnished Advance and Performance Bank Guarantees. The petitioner filed multiple petitions under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim reliefs (including injunctions restraining the respondent from encashing bank guarantees); these Section 9 petitions remain pending before the Court.

By letter dated 28 December 2015 the petitioner invoked arbitration under Clause 33 of the General Terms and Conditions of the Purchase Order ("GTCPO"). The respondent communicated the appointment of Justice A.P. Shah (Retd.) as sole arbitrator in terms of Clause 33.c (the clause providing that disputes "shall be referred to sole arbitration of the Managing Director of the Buyer or his nominee"). Justice A.P. Shah (Retd.) gave disclosures under the Sixth Schedule and fixed a preliminary meeting on 9 February 2016.

The petitioner filed the present petition under Sections 11(5) and 11(6) of the Act seeking (i) appointment of a retired Judge of the Supreme Court as arbitrator by this Court, and (ii) a declaration that the arbitrator already appointed by the respondent was ineligible and that such appointment was void ab initio. The respondent defended the appointment and maintained that the appointment was made in accordance with the contractual procedure. The Court heard the matter and pronounced judgment on 19 April 2016.

Legal Issues Presented

  1. Whether the Court should exercise its jurisdiction under Section 11(5) or 11(6) of the Arbitration and Conciliation Act, 1996 to appoint an arbitrator notwithstanding the parties' agreed procedure in Clause 33.c of the Purchase Order.
  2. Whether the appointment by the respondent of Justice A.P. Shah (Retd.) as sole arbitrator is void or the nominee is ineligible in view of the amendments to the Act (including Section 12(5), the Fifth and Seventh Schedules) and related ineligibility/disclosure provisions.
  3. Whether the Managing Director's inability (or ineligibility) to act as sole arbitrator, if any, also vitiates his contractual right to nominate a sole arbitrator under the Purchase Order.

Arguments of the Parties

Petitioner's Arguments

  • The petitioner contended that the Managing Director of the respondent had become "ineligible" to act as an arbitrator and, consequently, could not nominate any other person as arbitrator; the nomination right itself was said to be invalid in view of the amended Act.
  • The petitioner alleged that the arbitration clause under Clause 33.c of the GTCPO was rendered void by the recent amendments (including Section 12(5) and the Seventh Schedule) and that the appointment of the Arbitral Tribunal was contrary to Item Nos. 22 and 24 (and Item 29 was referenced) of the Fifth Schedule to the Act.
  • The petitioner sought that the Court appoint a retired Judge of the Supreme Court as arbitrator and declare the respondent's appointment void ab initio.

Respondent's Arguments

  • The respondent maintained that the parties had agreed an appointment procedure under Clause 33.c and that the respondent's appointment of Justice A.P. Shah (Retd.) complied with that contractual procedure.
  • The respondent denied that any ground existed making the nominee arbitrator ineligible and pointed out that Justice A.P. Shah (Retd.) had made the required disclosures under the Sixth Schedule indicating no circumstances giving rise to justifiable doubts as to his independence or impartiality.
  • The respondent further suggested that the petition was filed to defeat or delay the arbitration proceedings and that any objections regarding the constitution of the Arbitral Tribunal should be raised before the Arbitral Tribunal itself.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court's analysis proceeded as follows:

  • The Court first identified that Clause 33.c of the GTCPO constituted an agreed procedure for appointment of the arbitrator (the Managing Director of the buyer or his nominee). Because the parties had agreed a procedure as contemplated by Section 11(2) of the Act, the petitioner could not invoke Section 11(5) on the ground of failure to agree a procedure for appointment.
  • The Court rejected the petitioner's contention that the Managing Director's alleged ineligibility to act as an arbitrator also nullified his contractual right to nominate an arbitrator. The Court held that the right to nominate is independent of the right to act personally as arbitrator.
  • The Court interpreted the Fifth and Seventh Schedules as relating to the appointed arbitrator's circumstances that may give rise to justifiable doubts; those Schedules do not per se disqualify a party's contractual right to nominate. The Court observed that the Seventh Schedule lists detailed ineligibility criteria pertaining to the arbitrator himself and that had the amendment intended to take away a party's right to nominate, it would have been expressly stated.
  • The Court found the petitioner's challenge under Item 22 of the Fifth Schedule frivolous. The challenge under Item 24 had no consequence given that Justice Shah (Retd.) had been appointed in relation to similar disputes; the Court also explained Item 29 as relating to appointments by the same counsel or law firm and not applicable in the manner the petitioner suggested.
  • The Court noted that objections to the constitution of the Arbitral Tribunal, including under the Fifth or Seventh Schedules, ought to be raised before the Arbitral Tribunal itself and that Justice Shah (Retd.) had made the disclosures required under the Sixth Schedule indicating no circumstances likely to give rise to justifiable doubts about independence or impartiality.
  • Given the agreed appointment procedure, the disclosures made, and the absence of any contingency under Section 11(6) shown by the petitioner, the Court concluded there was no basis to interfere with the appointment made by the respondent. The Court further indicated that, even independent of the contractual stipulation, it would appoint Justice A.P. Shah (Retd.) as sole arbitrator.

Holding and Implications

DISMISSED

Holding: The petition under Sections 11(5) and 11(6) of the Arbitration and Conciliation Act, 1996 was dismissed. The Court upheld the appointment of Justice A.P. Shah (Retd.) as the sole arbitrator (and indicated it would itself appoint him even apart from the contractual provision).

Implications: The direct effect is that the appointment of Justice A.P. Shah (Retd.) as sole arbitrator stands and the arbitration proceedings are to continue before him. The petitioner's challenge to the nomination procedure and to the arbitrator's eligibility was not accepted by the Court. The opinion does not purport to lay down any new, broader legal precedent beyond resolving the parties' dispute and confirming that contractual nomination under Clause 33.c is effective and that objections of the type raised should be addressed as provided in the Act (including before the Arbitral Tribunal).

    TRF LTD.  v. ENERGO ENGINEERING PROJECTS LTD

    * IN THE HIGH COURT OF DELHI AT NEW DELHI

    % Judgment reserved on: 8th March, 2016 Judgment pronounced on: 19 April, 2016 + Arb. P. No.86/2016

    TRF LTD. ..... Petitioner Through Mr.Ciccu Mukhopadhaya, Sr. Adv. with Mr.Kaushik Poddar and

    Ms.Rashmi Gogoi, Advs.

    versus

    ENERGO ENGINEERING PROJECTS LTD ..... Respondent Through Mr.Rajiv Nayar, Sr. Adv. with Ms.Anannya Ghose, Ms.Reena

    Choudhary and Mr.Saurabh Seth,

    Advs.

    CORAM:

    HON'BLE MR.JUSTICE MANMOHAN SINGH

    MANMOHAN SINGH, J.

    1. The present petition has been filed by the petitioner under Section 11(5) read with Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the 'Act') seeking appointment of a retired Judge of the Supreme Court as an Arbitrator for adjudication of the disputes between the parties by declaring the Arbitrator already appointed by the respondent ineligible and further declaring such appointment void ab initio.

    2. The petitioner is a Company duly incorporated under the Companies Act, 1956.

    1

    3. The respondent is engaged in the business of procuring Bulk Material Handling Equipment for installation in Thermal Power Plants on behalf of its clients like National Thermal Power Corporation ('NTPC' in short) and/or Moser Baer, Lanco Projects Ltd. etc.

    4. The respondent issued a Purchase Order dated 22ndOctober, 2011 to the petitioner for the supply of Reversible Bucket Wheel Type Stacker-cum- Reclaimer, including for the complete design, manufacturing, supply, erection, commissioning and performance guarantee testing of various Articles including wagon tippler, side arm charger, apron feeder etc. To secure the performance under the Purchase Order, the petitioner had submitted an Advance Bank Guarantee and a Performance Bank Guarantee.

    5. The petitioner approached this Court by way of petition under Section 9 of the Act praying for an injunction against the respondent from exercising its contractual rights to encash the Advance Bank Guarantee and the Performance Bank Guarantee, both of which are admittedly unconditional. Thereafter, the petitioner filed set of petitions under Section 9 of the Act seeking an order for the respondent to furnish security for the purportedly outstanding amounts.

    6. The details of the said 1stset of petitions filed by the petitioners under Section 9 of the Act are given as under:-

    S. No. Case Title Case Number Section Details Amount/ claim Amount outstanding
    1. Trf Ltd. Petitioner v. Energo Engineering Projects Ltd.(I) Comm.No.18/ 2016 Petition under Section 9 of the Arbitration and Conciliation Act, 1996 Letter of Intent on th 19 September, 2011 which was followed by Purchase Order nd dated 22 October, 2011 by Over Rs.2 crores Rs.5,40,52,473/-

    2

    the respondent for supply of Reversible Bucket Wheel Type Stacker-cum- Reclaimer by the respondent.
    2. Trf Ltd. Petitioner v. Energo Engineering Projects Ltd.(I) Comm.No.19/ 2016 Petition under Section 9 of the Arbitration and Conciliation Act, 1996 The petitioner was issued Letter of Intent dated st 21 November, 2013, which was issued to the petitioner by sole respondent for supply of ‘Plough Feeder’ for the end use project of Moser Baer and/or LANCO Projects Ltd. The said LOI was subsequently culminated into Purchase Order th dated 9 December, 2013. Over Rs.2 crores Rs. 1, 71,92,000/-

    3. TRF Ltd. v. OMP(I) Petition under Respondent had Over Rs.11,13,95,500/- Energo Comm.No.20/ Section 9 of issued a Letter of Rs.2 Engineering 2016 the Arbitration Intent dated 1stcrores Projects Ltd and January, 2014 for

    Conciliation the work of

    Act, 1996 supply, erection

    and

    commissioning of

    'Wagon Tippler

    and Side Arm

    Charger' in

    favour of the

    petitioner. After a

    lapse of almost

    five months from

    the issuance of

    LOI, a Purchase

    Order with

    respect to supply

    of Wagon Tippler

    and Side Arm

    Charger dated 6th

    May, 2014 was

    issued by the sole

    respondent.

    3

    4. TRF Ltd. v. OMP(I) Petition under The Respondent Over Rs. Rs. 6,95,99,122/- Energo Comm.No.21/ Section 9 of had issued Letter 2 crores Engineering 2016 the Arbitration of Intent

    Projects Ltd and dated 16thApril,

    Conciliation 2014, for supply,

    Act, 1996 erection and

    commissioning of

    Wagon Tippler

    and Side Arm

    Charger. The

    same was

    followed

    by Purchase

    Order dated 10th

    May, 2014 for

    supply of Wagon

    Tippler and Side

    Arm Charger.

    7. The details of the 2ndset of the petitions are given as under:-

    S.No. Case Case Section Details Amount Prayer Name Number /Claim

    1. TRF Ltd. O.M.P(I) Petition under Respondent No.1 Over Rs. Restrain the vs. Energo (Comm) Section 9 of issued purchase 2 crore respondent from Engineerin 65/2015 the Arbitration order to the encashing the Bank

    g Projects and petitioner dated 6thGuarantee

    Ltd., Conciliation May, 2014 for Nos. Act, for supply of Wagon 1403831BGA00007

    interim orders. Tippler and Side for Rs.4,62,92,400/-

    Arm Charger. and

    The petitioner was 1403831BGP00026

    issued another for Rs.5,01,09,200/-

    work order for executed by the erection and petitioner in favour commissioning of of the respondent in Wagon Tippler and pursuance to the Side Arm Charger agreement entered dated 26thMay, between the parties.

    2014.

    2. TRF Ltd. O.M.P(I) Petition under Respondent No.1 Over Rs. Restrain the vs. Energo (Comm) Section 9 of issued purchase 2 crore respondent from Engineerin 66/2015 the Arbitration orders to the encashing the Bank

    g Projects and petitioner dated Guarantee

    Ltd., Conciliation 10thMay, 2014 for Nos.

    Act, for supply of Wagon 1403831BGP00028

    interim orders. Tippler and Side for Rs.1,21,76,700/-

    Arm Charger and and

    for erection and 1403831BGA00010

    commissioning of for Rs.1,12,26,700/-

    Wagon Tippler and executed by the

    4

    Side Arm Charger dated. petitioner in favour of the respondent in pursuance to the agreement entered between the parties.
    3. TRF Ltd. vs. Energo Engineerin g Projects Ltd., O.M.P(I) (Comm) 68/2015 Petition under Section 9 of the Arbitration and Conciliation Act, for interim orders. Respondent No.1 issued to the petitioner purchase nd order dated 22 October, 2011 for supply of Reversible Bucket Wheel Type Stacker- cum- Reclaimer. Over Rs. 2 crore Restrain the respondent from encashing the Bank Guarantee Nos. Nos. 00191GPER004511 for Rs.3,51,50,000/- and 00191GPER004411 for Rs.3,51,50,000/- executed by the petitioner in favour of the respondent in pursuance to the agreement entered between the parties.

    5

    8. The said petitions under Section 9 of the Act are presently pending consideration before this Court.

    9. The petitioner by letter dated 28thDecember, 2015 invoked the arbitration in terms of Clause 33 of the General Terms and Conditions of the Purchase Order ("GTCPO") for reference of disputes between the parties to arbitration.

    10. However, the petitioner objected to the procedure for appointment of Arbitrator provided under the Purchase Order, who communicated to the respondent its consent for appointment of an Arbitrator de hors the specific terms of the Purchase Order.

    11. The contention of the respondent is that the submission of the petitioner is contrary to the binding contractual terms between the parties. The respondent denied such suggestion and by letter dated 27thJanuary, 2016 informed the petitioner about the appointment of Justice A.P.Shah (Retd.) as the sole Arbitrator in terms of clause 33.c of the Purchase Order.

    12. Later on, admittedly, Justice A.P.Shah (Retd.) ("Arbitral Tribunal") by letter dated 29thJanuary, 2016 addressed to both the parties directed them to appear before the Arbitral Tribunal for a preliminary meeting to be held on 9thFebruary, 2016.

    13. It is alleged by the respondent that with the sole purpose of defeating the arbitration proceedings, the petitioner has sought to invoke the jurisdiction of this Court under Section 11(5) read with Section 11(6) of the Act by way of the present petition.

    6

    14. The present petition has been filed under both Sections 11(5) and 11(6) of the Act. The fundamental procedure for invocation of this Court's jurisdiction under Section 11(5) of the Act, i.e. failure on part of the parties to agree on a procedure for appointment of Arbitrator under Section 11(2) of the Act is not made out.

    15. Clause 32.b of the GTCPO states that if the parties fail to amicably resolve the disputes, then either party may require that the dispute be referred to arbitration.

    16. Clause 33.c of the GTCPO provides that any dispute between the parties in connection with the Purchase Order "shall be referred to sole arbitration of the Managing Director of the Buyer or his nominee".

    17. The said terms of the Purchase Order makes it clear that the petitioner and the respondent have agreed on a procedure for appointing an Arbitrator as contemplated by Section 11(2) of the Act. In these circumstances, the disputes between the parties have to be decided in accordance with such procedure and recourse to Section 11(5) of the Act cannot be taken by the petitioner.

    18. The petitioner has also contended that since the respondent's Managing Director has himself become "ineligible" to be appointed as an Arbitrator, he cannot also nominate any other person as an Arbitrator and any such appointment is contrary to the rule of law and that is the intent and purpose of the recent amendments to the Act. The petitioner has also alleged that the arbitration agreement under clause 33.c of the GTCPO is rendered void. The petitioner's arguments in this regard are without any merit, as the right of the Managing Director to nominate a sole Arbitrator under the

    7

    Purchase Order is independent of his right to himself act as the sole Arbitrator.

    19. The mere reason that the Managing Director of the respondent cannot act as a sole Arbitrator in the disputes between the parties does not take away his right to nominate an independent and neutral Arbitrator.

    20. Appointment of an independent and impartial Arbitral Tribunal does not append the recent changes brought about in the Act, including Section 12(5) and the Seventh Schedule to the Act or in any manner contrary to the rule of law. Although, I must mention here and appreciate the fairness of the learned Senior counsel for the petitioner who has made his submission that he is merely arguing the matter on legal issue otherwise he and his client have full faith and respect for the learned sole Arbitrator appointed. He submits that since it is an important legal issue therefore, he is making his submissions on legal issue only.

    21. The Fifth and the Seventh Schedule reveal that the grounds provided thereunder are in relation to the appointed Arbitrator himself and thus, the petitioner's argument that the nominee Arbitrator being ineligible to act as an Arbitrator is without any force and against the scheme of the Act. The Purchase Order does not stipulate that the Managing Director of the respondent will have a right to nominate a sole Arbitrator only so long as he is also qualified to act as such.

    22. The right of one party to a dispute to appoint a sole Arbitrator prior to the amended Act has been well-recognized and the amended Act does not take away such a right. Had the intent of the amended Act been to take away a party's right to nominate a sole Arbitrator as suggested by the

    8

    petitioner, the same would have found mentioned in the detailed list of ineligibility criteria enumerated under the Seventh Schedule to the Act. Therefore, the petitioner's submission that the arbitration clause under clause 33.c of the GTCPO has been rendered void, is without any merit. Thus, the petitioner has been able to make out a case for exercise of powers by this Court under Section 11(5) of the Act.

    23. The recourse to Section 11(6) of the Act can be had only if there are any of the contingencies provided under Section 11(6) (a), (b) or (c). The petitioner is not able to indicate as to how any of the contingencies contemplated by Section 11(6) of the Act arise in the present case.

    24. The petitioner has contended that the appointment of the Arbitral Tribunal is contrary to Item Nos.22 and 24 of the Fifth Schedule to the Act. The Fifth Schedule to the Act does not per se provide for grounds for disqualification of an Arbitrator. The said Schedule merely provides an indicative list of the grounds which give rise to justifiable doubts as to the independence or impartiality of arbitrators. Under Section 12(1) of the Act, a person who is approached in connection with his possible appointment as an Arbitrator is to be guided by the Fifth Schedule while determining whether the circumstances exist which give rise to justifiable doubts and if so, he shall disclose the same in the form specified in the Sixth Schedule.

    25. The petitioner's argument that the appointment of the Arbitral Tribunal is bad in view of Item 22 of the Fifth Schedule to the Act is entirely frivolous and without any basis whatsoever. Insofar as the petitioner's challenge in terms of Item 24 of the Fifth Schedule is concerned, the said argument has no consequence as Justice Shah (Retd.) has been appointed as

    9

    an Arbitrator in relation to similar disputes between the same parties under two Purchase Orders pertaining to the same project at Annupur. With regard to Item 29 of the Fifth Schedule to the Act, it stipulates that if the Arbitrator has within the past three years received more than three appointments by the same counsel or the same law firm, the Item would show that the same is in relation to the counsel or the law firm who makes the appointment and does not pertain to the counsel or the law firm of the opposite side to an arbitration proceeding.

    26. Even otherwise, I agree with the suggestion of learned counsel for the respondent that the objections, if any, against the constitution of the Arbitral Tribunal on any ground whatsoever including under the Fifth and the Seventh Schedule of the Act can only be raised before the Arbitral Tribunal

    27. Before consenting to act as the learned sole Arbitrator, Justice Shah (Retd.) by letter dated 27thJanuary, 2016 had given the requisite disclosures under the Sixth Schedule wherein he had indicated that as per him, there are no circumstances which are likely to give rise to justifiable doubts as to his independence and impartiality.

    28. The Arbitral Tribunal has already been constituted and has entered into reference who has already ensured the compliance of the provision under the amended Act about no conflict. Now, the petitioner cannot be allowed to change the Arbitral Tribunal.

    29. Even, besides the stipulation of the agreement/purchase order governing the parties, this Court inclines to appoint Hon'ble Mr.Justice A.P.Shah (Retd. Chief Justice) as sole Arbitrator to decide the dispute between the parties.

    10

    30. For the reasons stated above, there is no merit in the petition and the same is accordingly dismissed.

    (MANMOHAN SINGH)

    JUDGE

    APRIL 19, 2016