RAJIV SHAKDHER, J. (ORAL):
1. We had heard the matter at some length on the first date i.e.,
04.03.2022.
1.1 On that date i.e., 04.03.2022, we had recorded the relevant dates and events. The said order reads as follows: "2. This appeal is directed against the order dated 30.11.2021, passed by the learned District Judge (Commercial Court)-02,
Patiala House Court, New Delhi.
2.1. Via this order, the learned District Judge dismissed the
appellant's petition filed under Section 34 of the Arbitration and Conciliation Act, 1996[in short, "the Act"].
3. The crucial dates, which are required to be noticed in the instant case, are the following:
(i) The arbitral award was rendered on 23.10.2012. This award, according to the appellant, was received in or around
30.10.2012.
1
(ii) The appellant instituted a petition under Section 34 of the Act, in the first instance, on 28.01.2013. This petition, however, was instituted in the District Court, Jaipur, in the State of Rajasthan.
(iii) The concerned court returned the petition to the appellant on 02.06.2018, with [the] liberty to file the same with the court of competent jurisdiction.
(iv) The appellant, concededly, applied for a certified copy of the order dated 02.06.2018, on 27.07.2018. A certified copy of the said order was received by the appellant on 02.08.2018.
(v) The appellant instituted a fresh petition under Section 34 of the Act, as noticed above, before the District Court, Patiala House Court, New Delhi on 29.09.2018.
4. Mr Nityanand Singh, who appears on behalf of the appellant, says that he will persuade the court that the petition filed before the learned District Judge in New Delhi, was within time.
5. Since Mr Singh is addressing arguments through [the] video-conferencing mechanism, and the audio is unclear, list the matter at his request on10.03.2022."
1.2. Thus, the issue that we are required to consider is simply this, whether the dismissal of the petitioner's petition, preferred under Section 34 of the Arbitration & Conciliation Act, 1996 [in short "the 1996 Act"] was tenable in law?
2. However, before we proceed further, some important parameters need to be set forth, as enunciated in law, to decide the issue at hand :
(i) Once limitation commences, it does not get interrupted.
(ii) The Limitation Act, 1963 (in short "the 1963 Act") is applicable to arbitration proceedings by virtue of Section 43 of the 1996 Act.
(iii) The limitation period prescribed for filing a petition under Section 34 of the 1996 Act, is three [3] months.
(iiia) Since the 1996 Act does not define the expression "month", the same will have the same meaning, as defined in Section 2(35) of the
2
General Clauses Act, 1897. The said section provides that the expression
"month" means a month reckoned according to the British calendar. Where the period prescribed is a calendar month running from an arbitrary date, it expires with the day in the succeeding month immediately preceding the day, corresponding to the date upon which the period starts, save and except where the period starts at the end of the calendar month which contains more days than the succeeding month, the period expires at the end of the latter month. [See Halsbury's Laws of England Volume 37 (third edition) 1.]
(iiib) However, the Supreme Court in the judgment rendered in State of H.P. v. Himachal Techno Engineers, (2010) 12 SCC 210, made the following observations with regard to how the terminal date of the three months timeframe should be ascertained :
"18. Therefore when the period prescribed is three months (as contrasted from 90 days) from a specified date, the said period would expire in the third month on the date corresponding to the date upon which the period starts. As a result, depending upon the months, it may mean 90 days or 91 days or 92 days or 89 days."
(iiic) The period of limitation commences from the date of receipt of the award, or if a request under Section 33 of the 1996 Act is made, the date on which the request is disposed of. Section 5 of the 1963 Act is not applicable to proceedings instituted under 34 of the 1996 Act. [See
Union Of India v. Popular Construction Co. ., (2001) 8 SCC 470.]
(iv) Section 14 of the 1963 Act is applicable to Section 34 proceedings, 1 143 Calendar month running from arbitrary date. When the period prescribed is a calendar month running from any arbitrary date the period expires with the day in the succeeding month immediately preceding the day corresponding to the date upon which the period starts; save that, if the period starts at the end of a calendar month which contains more days than the next succeeding month, the period expires at the end of the latter month (k). Also see Daryodh Singh vs. Union of India AIR 1973 Del 58,
3
preferred under the 1996 Act, provided the petitioner meets the requisite criteria i.e., the proceedings are prosecuted with due diligence, the matter in issue is the same, and was being taken forward in good faith in a court which could not have entertained it on account of a defect in the jurisdiction, or any other cause of like nature. [See Consolidated Engg. Enterprises v. Irrigation Deptt., (2008) 7 SCC 1692.] paragraph 16
4
3. As would be evident from the dates and events recorded hereinabove, in the instant case, the award was rendered on 23.10.2012.
3.1 The petitioner, admittedly, received a copy of the award dated 23.10.2012, on 30.10.2012.
3.2. Therefore, the prescribed period of limitation available under the 1996 Act, which is three months, commenced from the said date i.e., 30.10.2012.
3.3. A litigant who prefers proceedings under Section 34 of the 1996 Act can seek an extension of time, under the proviso appended to sub-section 3 of Section 34 of the 1996 Act, by a further period of thirty [30] days, only if the litigant is able to demonstrate to the satisfaction of the Court that he was prevented by sufficient cause from instituting proceedings under Section 34, within the prescribed period of limitation i.e., three months.
3.4. In the instant case, the prescribed period of limitation [i.e., three months], commenced from 30.10.2012, and, therefore, even if the maximum leeway is given, the limitation would expire on 30.01.2013.
3.5. The petitioner, concededly, filed the Section 34 petition under the
1996 Act in the first instance, as noticed in the order dated 04.03.2022, only on 28.01.2013. This petition was instituted in the Court of District and Sessions Judge, Jaipur Metropolitan, in the State of Rajasthan [hereafter referred to as "Jaipur Court"].
3.6. The Jaipur Court, however, returned the petition on 02.06.2018, while granting liberty to the petitioner to approach the Court of competent jurisdiction.
3.7. The petitioner, thereafter, approached the District Judge (Commercial Court)-02, Patiala House Court at New Delhi [hereafter referred to as "Delhi Section 14 of the Limitation Act, 1963 would be applicable to an application submitted under Section 34 of the Act of 1996 for setting aside an arbitral award."
5
Court"] and instituted a petition under Section 34 of the 1996 Act, only on
29.09.2018.
4. Therefore, even if we were to exclude the time between, when the Section 34 petition was filed for the first time in the Jaipur Court i.e., 28.01.2013 and the date when the petition was returned by the said court i.e., 02.06.2018, it would not help the cause of the petitioner.
4.1. The limitation period in the petitioner's case expired, on 04.06.2018.
4.2. Furthermore, the petitioner, as recorded hereinabove, had applied for a certified copy of the order dated 02.06.2018, only on 27.07.2018. Apart from anything else, this shows the petitioner's lack of good faith and alacrity. [See Simplex Infrastructure Ltd. v. Union of India, (2019) 2 SCC
4553.]
5. Therefore, for the aforesaid reasons, we find no merit in the appeal.
6
6. The appeal is, accordingly, dismissed.
6.1. The impugned order dated 30.11.2021 is, consequently, sustained.
7. Consequently, the pending application shall stand closed.
RAJIV SHAKDHER, J
JASMEET SINGH, J
MARCH 24, 2022/dm