AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 2 (r) of the Consumer Protection Act, 1986
  • provisions of the Agreement. 6.6. Section 2 (r) of the Consumer Protection Act, 1986
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 2 (r) of the Consumer Protection Act, 1986
  • provisions of the Agreement. 6.6. Section 2 (r) of the Consumer Protection Act, 1986
Smart Summary

Factual and Procedural Background

The complainant/respondent booked a residential flat in the Parsvnath Privilege project developed by the appellant company on a plot in Greater Noida. On 07.08.2008, unit T2-803 was allotted to the complainant, who executed an agreement with the appellant for the flat at a basic sale price of ₹45,01,001/-. The agreement stipulated that construction would be completed within 36 months from the commencement of construction of the relevant block. Despite full payment of the basic sale price by the complainant, the construction was not completed and possession was not offered. Consequently, the complainants filed a consumer complaint before the State Commission seeking refund of the amount paid along with compensation.

The appellant admitted the allotment and payment but attributed the delay in construction to the global recession. The State Commission, by its order dated 10.01.2019, directed the appellant to refund ₹45,01,001/- with 12% interest, pay ₹2,00,000/- as compensation for mental agony, and ₹25,000/- as litigation costs. Aggrieved, the appellant filed this appeal before the National Consumer Disputes Redressal Commission.

Legal Issues Presented

  1. Whether the appellant is liable to refund the amount paid by the complainant along with interest due to delay in possession of the flat.
  2. Whether the compensation awarded by the State Commission for harassment and mental agony is justified.
  3. Whether the terms of the Flat-Buyer Agreement, particularly clauses relating to compensation and delay, are fair and enforceable.

Arguments of the Parties

Appellant's Arguments

  • The delay in completion of the construction occurred due to the global recession in the real estate sector.
  • The appellant relied on Clause 10(c) of the agreement, which provides for payment of compensation at a fixed rate per square foot per month of delay, arguing this limits their liability.
  • The appellant contended that the complainant was not entitled to the interest rate or compensation claimed beyond the terms of the agreement.

Respondent's Arguments

  • The complainant sought refund of the entire amount paid along with interest and compensation for mental agony due to the appellant's failure to complete the project within the stipulated time.
  • The complainant argued that the delay was not excused by any force majeure or statutory restrictions as per the agreement.
  • The complainant challenged the fairness of the contractual clauses relied upon by the appellant, labeling them as one-sided and unfair trade practices.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Ashwin Mittal Vs. Parsvnath Developers Limited Establishes precedent for refund with interest and compensation due to delayed possession in the same project. Applied to confirm entitlement of complainant to refund with interest and compensation.
Puneet Malhotra Vs. Parsvnath Developers Ltd. Rejects the appellant's defense of delay due to recession and limits on compensation under the agreement. Used to reject appellant’s claims and confirm complainant's right to refund and compensation.
Surinder Kumar Sarna Vs. Parsvnath Developers Limited Considers one-sidedness of contractual clauses and defines unfair trade practices under Consumer Protection Act. Relied upon to hold the contractual terms as unfair and unreasonable, supporting complainant's claim.
Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghavan Supreme Court ruling on unfairness of one-sided contractual clauses in real estate agreements. Referenced to emphasize that the appellant’s contractual terms were unfair and not enforceable against the complainant.

Court's Reasoning and Analysis

The Court analyzed the terms of the agreement, particularly Clause 10(a) which stipulated completion within 36 months, and Clause 10(c) which prescribed compensation for delay. It found that the delay was not excused by force majeure or statutory restrictions as claimed by the appellant. The Court rejected the appellant’s defense attributing delay to the global recession and held that the appellant was duty bound to complete construction irrespective of market conditions or defaults by other allottees.

The Court further distinguished the applicability of Clause 10(c), noting it applies only when the buyer accepts possession despite delay, not when the buyer opts for refund due to non-possession. The clause allowing the builder to charge high interest from the buyer was held to be an unfair trade practice under Section 2(r) of the Consumer Protection Act.

Relying on prior decisions including Ashwin Mittal, Puneet Malhotra, Surinder Kumar Sarna, and the Supreme Court's ruling in Pioneer Urban Land, the Court found the contractual terms to be one-sided, unfair, and unconscionable, justifying the complainant’s claim for refund with interest and compensation.

The complainant expressed willingness to accept refund of principal along with simple interest at 10% per annum, which the Court accepted and disposed of the appeal accordingly.

Holding and Implications

The appeal is disposed of with directions that the appellant shall refund the entire principal amount of ₹45,01,001/- to the complainant along with simple interest at 10% per annum from the date of each payment till the date of refund.

The appellant is also directed to pay ₹25,000/- as litigation costs to the complainant, with payment to be made within three months from the date of the order.

The decision reaffirms the principle that delay in possession without valid excuse entitles the allottee to refund with interest and that contractual clauses heavily favoring builders at the expense of buyers constitute unfair trade practices under the Consumer Protection Act. No new precedent was set beyond these established principles.

To access the original judgment, please Sign In or Subscribe.

    Parsvnath Developers Limited (S) v. Sangeeta Mehra And Another (S).

    NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

    NEW DELHI

    FIRST APPEAL NO. 604 OF 2019

    (Against the Order dated 10/01/2019 in Complaint No. 67/2015 of the State Commission Delhi)

    1. PARSVNATH DEVELOPERS LIMITED

    THROUGH ITS AUTHORIZED SIGNATORY, MR.

    MADAN DOGRA, PARSVNATH TOWER, NEAR

    SHAHDARA METRO STATION SHAHADARA

    DELHI 110032 ...........Appellant(s) Versus

    1. SANGEETA MEHRA & ANR. D/O. SH. R N KAKKAR, 13, PEAR TREE ROAD,

    SMETHWICK , WEST MIDLANDS B676RB

    UK

    2. MS. STUTTEE MEHRA

    D/O. SMT. SANGEETA MEHRA, 13, PEAR TREE ROAD,

    SMETHWICK, WEST MIDLANDS B676RB

    UK ...........Respondent(s)

    BEFORE:

    HON'BLE MR. JUSTICE V.K. JAIN,PRESIDING MEMBER For the Appellant : : Mr. Vineet Sinha, Advocate : Mr. Manmeet Singh Nagpal, Advocate. For the Respondent : Mr. Sudhir Kumar Mishra, Advocate, Mr. N.P. Yadav, Advocate.

    Dated : 28 Jan 2020

    ORDER

    JUSTICE V.K.JAIN (ORAL)

    The complainant/respondent booked a residential flat with the appellant company in a project namely Parsvnath Privilege which the appellant was to develop on a plot bearing No. 11 in sector Pi of Greater Noida. Vide letter dated 07.08.2008, unit T2-803 in the afore-said project was allotted to the complainant who then executed an agreement with the appellant company on 07.08.2008, incorporating their respective applications in respect of the said transaction. The basic sale price of the flat was agreed at ₹45,01,001/-. In terms of clause 10(a) of the agreement the construction was likely to be completed within 36 months of commencement of construction of the block in which the flat was located. The construction of the flat allotted to the complainant, however, was not completed and the possession was not offered to them despite them having paid the entire basic sale price of ₹45,01,001/- to the appellant. The complainants, therefore, approached the concerned State Commission by way of

    1

    a consumer complaint seeking refund of the amount which they had paid to the appellant along-with compensation etc.

    2. The complaint was resisted by the appellant company which admitted the allotment made to the complainant and also did not dispute the payment received from her. It was inter alia stated in the written version filed by the appellant that the delay in completion of the construction happened on account of global recession.

    3. The State Commission vide impugned order dated 10.01.2019 directed as under:-

    "a. refund the amount of Rs. 45,01,001/- alongwith interest @ 12% p.a. from the date of its deposit till the date of its realization.

    b. to pay compensation to the tune of Rs.2,00,000/- to the complainant for harassment inconvenience, frustration, sadness, anguish and mental agony caused to her.

    c. to pay litigation charges to the tune of Rs.25,000/-"

    4. Being aggrieved by the order passed by the State Commission the appellant is before this Commission.

    5. The matter involved in this appeal is no more res integra being covered by several decisions of this Commission in respect of the allotments made in this very project. A reference in this regard can be made to the decision of this Commission dated 07.11.2019 in CC No. 1393 of 2016 - Ashwin Mittal Vs. Parsvnath Developers Limited where the complainant had booked a residential apartment in this very project and the construction was not complete despite he having made substantial payment to the appellant. The decision of this Commission in Ashwin Mittal (supra) to the extent it is relevant reads as under:-

    "5. It is an admitted position before me that the complaint has been resisted by the OP on the grounds which this Commission has already rejected in 'CC No. 232 of 2014 - Puneet Malhotra Vs. Parsvnath Developers Ltd. and connected matters decided on 29.01.2015 and several other subsequent decisions.

    6. The decision of this Commission in Puneet Malhotra (supra) to the extent is relevant, reads as under:

    "4. The complaints have been resisted by the respondent company on the ground that the complainants are seeking refund with exorbitant interest. It is also claimed that since the basic value of the property is much less than Rupees one crore, this Commission lacks pecuniary jurisdiction to entertain the complaints. It is also pointed out in the reply

    2

    that as per the tripartite agreement executed between the complainants and opposite party and the Banks from which the loan was taken by the complainants, the bank has lien over the refund amount, in the event of cancellation and/or termination of the agreement. As regards the delay in construction, it is claimed that the said delay occurred due to recession in Real Estate Sector. It is also submitted in the reply that in view of the terms of the agreement between the parties, a complainant cannot claim more than the compensation stipulated in the Flat-Buyer Agreement.

    6. Vide Clause 10 (a) of the Flat-Buyers Agreement, the opposite party represented to the complainants that the construction of the flat was likely to be completed within thirty-six months from the date of commencement of the construction of the particular block in which the flat was located, on receipt of all requisite approvals but subject to force-majeure and restraints/restrictions from any Court/Authorities, non-availability of building material and any circumstances beyond the control of the Developers, subject to timely payment by the buyer. It is an admitted case that the opposite party failed to complete the construction within the aforesaid time. As far as the statutory approvals are concerned, the same were to be obtained by the opposite party and the complainants cannot be held responsible for any delay in grant of such approvals though, it is not the case of the opposite party that the construction could not be completed for want of aforesaid statutory approvals. The case of the opposite party is that the project could not be completed on account of the recession in the Real Estate market, including reduction in the number of bookings and default on the party of the some of the allottees in making timely payment. The terms of the agreement between the parties do not justify the delay in completion of the project on the aforesaid grounds and therefore, the opposite party was duty bound to complete the construction irrespective of the recession in the market, reduction in bookings and the alleged default on the part of some of the allottees in making timely payment. This is not the case of the opposite party; that the construction could not be completed due to any restriction from any Court/Authority or due to non-availability of building material. If some of the allottees had not made timely payment, it was for the opposite party to arrange the requisite finance either by taking loan or from its own resources or by liquidating Inventory at a lower price. Therefore, the delay in completion of the projects cannot be justified.

    7. Since the opposite party could not compete the projects in which the residential flats were booked by the complainants, either within the agreed time of thirty-six months or even within a reasonable time thereafter, and even today the projects are nowhere near completion, the complainants are entirely justified in seeking refund of the amount, which they had paid to the opposite party. In fact, during the course of hearing, the only contention on behalf of the opposite party was that the complainants are not entitled to interest at the rate claimed by them nor are they entitled to

    3

    the compensation claimed by them and they can be awarded only the refund of the amount paid by them, along with compensation in terms of Clause-10(c) of the Flat-Buyer Agreement.

    8. The Clause on which the reliance is placed by the opposite party, reads as under:

    "In case of delay in construction of the Flat beyond the period as stipulated subject to force majeure and other circumstances as aforesaid under Clause 10 (a), the Developer shall pay to the Buyer compensation @ Rs.53.82/- (Rupees Fifty three and paise eighty two only) per sq. meter or @ Rs.5/- (Rupees Five only) per sq. ft. of the super area of the Flat per month for the period of delay. Likewise, if the Buyer fails to settle the final account of the Flat within thirty days from the date of issue of the final call notice, the buyer shall be liable to pay to the Developer holding charges @ Rs.53.82/- (Rupees Fifty three and paise eighty two only) per sq. meter or @ Rs.5/- (Rupees Five only) per sq. ft. of the super area of the Flat per month on expiry of thirty days' notice. Further, in the event of his failure to take possession for any reason whatsoever, the Buyer shall be deemed to have taken possession of the Flat on expiry of thirty days of offer of possession for all intents and purpose under this Clause/Agreement including for liability to payment of maintenance and any other charges, levies in respect of the Flat".

    9. In our opinion, the aforesaid Clause applies only in a case where construction of the flat is delayed but despite delay, the buyer accepts possession of the said flat from the seller, and consequently, accounts have to be settled between the parties. At that stage, the buyer would pay the agreed holding charges to the seller, who will pay the agreed compensation on account of delaying the construction of the flat. The aforesaid Clause, in our opinion would not apply to a case where the buyer, on account of the delay on the part of the seller in constructing the flat, is no more interested in the flat subject matter of the agreement and wants to take refund of the amount, which he had paid to the seller. In any case, such a clause, where the seller, in case of default on the part of the buyer, seeks to recover interest from him at the rate of 24% per annum will amount to an unfair trade practice since it gives an unfair advantage to the seller over the buyer. We may note here that the enumeration of the unfair trade practices in Section 2(r) of the Act is inclusive, not exhaustive."

    7. Reliance is also placed upon the decision of this Commission in CC No.1503 of 2016 Surinder Kumar Sarna Vs. Parsvnath Developers Limited

    & connected matter decided on 11.04.2019 which to the extent it is relevant, reads as under:

    7. A clause similar to clause 10(c) of the Buyers Agreement providing for payment of compensation @ 5/- per sq.ft. of super area per month in the event of delay, came up for consideration of the Hon'ble Supreme

    4

    Court recently in Civil Appeal No. 12238 of 2018 - Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghavan decided on 2.4.2019 and following was the view taken by the Hon'ble Supreme Court:-

    6.3. The National Commission in the Impugned Order dated 23.10.2018 held that the Clauses relied upon by the Builder were wholly one-sided, unfair and unreasonable, and could not be relied upon.

    The Law Commission of India in its 199th Report, addressed the issue of 'Unfair (Procedural & Substantive) Terms in Contract'. The Law Commission inter-alia recommended that a legislation be enacted to counter such unfair terms in contracts. In the draft legislation provided in the Report, it was stated that :

    "A contract or a term thereof is substantively unfair if such contract or the term thereof is in itself harsh, oppressive or unconscionable to one of the parties."

    6.4. A perusal of the Apartment Buyer's Agreement dated 08.05.2012 reveals stark incongruities between the remedies available to both the parties.

    For instance, Clause 6.4 (ii) of the Agreement entitles the Appellant - Builder to charge Interest @18% p.a. on account of any delay in payment of installments from the Respondent - Flat Purchaser. Clause 6.4 (iii) of the Agreement entitles the Appellant - Builder to cancel the allotment and terminate the Agreement, if any installment remains in arrears for more than 30 days.

    On the other hand, as per Clause 11.5 of the Agreement, if the Appellant - Builder fails to deliver possession of the apartment within the stipulated period, the Respondent - Flat Purchaser has to wait for a period of 12 months after the end of the grace period, before serving a Termination Notice of 90 days on the Appellant - Builder, and even thereafter, the Appellant - Builder gets 90 days to refund only the actual installment paid by the Respondent - Flat Purchaser, after adjusting the taxes paid, interest and penalty on delayed payments. In case of any delay thereafter, the Appellant - Builder is liable to pay Interest @ 9% p.a. only.

    6.5. Another instance is Clause 23.4 of the Agreement which entitles the Appellant - Builder to serve a Termination Notice upon the Respondent - Flat Purchaser for breach of any contractual obligation. If the Respondent - Flat Purchaser fails to rectify the default within 30 days of the Termination Notice, then the Agreement automatically stands cancelled, and the Appellant -

    5

    Builder has the right to forfeit the entire amount of Earnest Money towards liquidated damages.

    On the other hand, as Clause 11.5 (v) of the Agreement, if the Respondent - Flat Purchaser fails to exercise his right of termination within the time limit provided in Clause 11.5, then he shall not be entitled to terminate the Agreement thereafter, and shall be bound by the provisions of the Agreement.

    6.6. Section 2 (r) of the Consumer Protection Act, 1986 defines 'unfair trade practices' in the following words :

    "'unfair trade practice' means a trade practice which, for the purpose of promoting the sale, use or supply of any goods or for the provision of any service, adopts any unfair method or unfair or deceptive practice …", and includes any of the practices enumerated therein. The provision is illustrative, and not exhaustive.

    6.7. A term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder.

    The contractual terms of the Agreement dated 08.05.2012 are ex- facie one-sided, unfair, and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2 (r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the Builder.

    7. In view of the above discussion, we have no hesitation in holding that the terms of the Apartment Buyer's Agreement dated 08.05.2012 were wholly one-sided and unfair to the Respondent - Flat Purchaser. The Appellant - Builder could not seek to bind the Respondent with such one-sided contractual terms."

    6. The Learned Counsel for the complainant states on instructions that for giving quietus to the matter the complainant is ready and willing to accept the refund of the principal amount paid to the appellant, along with compensation in the form of simple interest @ 10% p.a. from the date of each payment till the date of refund, in terms of the order of this Commission in Ashwin Mittal (supra). The appeal is, therefore, disposed of in terms of the following directions:-

    i) The opposite party shall refund the entire principal amount of ₹45,01,001/- to the complainant alongwith compensation in the form of simple interest @ 10% p.a. from the date of each payment till the date of refund.

    6

    (ii) The opposite party shall pay a sum of Rs.25,000/- as the cost of litigation to the complainant.

    (iii) The payment in terms of this order shall be made within three months from today.

    ......................J

    V.K. JAIN

    PRESIDING MEMBER

    7

    Use AI to get other relevant cases.

    Comments

    Parsvnath Developers Limited (S) v. Sangeeta Mehra And Another (S).
    (Jan 28, 2020)