AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 29, Arbitration Act, 1940
  • The Provisions of the Arbitration Act, 1940
  • Section 31(7) of the new Arbitration Act
  • The Arbitration and Conciliation Act, 1996
  • Section 37(1) of the new Act
  • The Arbitration Act, 1940
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • The old Arbitration Act, 1940
  • Section 34 of the Civil Procedure Code
  • Constitution Bench decisions in G.C Roy (1992) 1 SCC 508 and N.C Budharaj (2001) 2 SCC 721 rendered before and after the decision in Engineers-De-Space-Age (1996) 1 SCC 516
  • The Interest Act, 1839
  • The proviso to Section 41 and Section 3 of the Arbitration Act
  • The new Act (referring to the Arbitration and Conciliation Act of 1996)
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Section 29, Arbitration Act, 1940
  • The Provisions of the Arbitration Act, 1940
  • Section 31(7) of the new Arbitration Act
  • The Arbitration and Conciliation Act, 1996
  • Section 37(1) of the new Act
  • The Arbitration Act, 1940
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • The old Arbitration Act, 1940
  • Section 34 of the Civil Procedure Code
  • Constitution Bench decisions in G.C Roy (1992) 1 SCC 508 and N.C Budharaj (2001) 2 SCC 721 rendered before and after the decision in Engineers-De-Space-Age (1996) 1 SCC 516
  • The Interest Act, 1839
  • The proviso to Section 41 and Section 3 of the Arbitration Act
  • The new Act (referring to the Arbitration and Conciliation Act of 1996)
Smart Summary

Factual and Procedural Background

The respondent contractor was awarded a contract dated 16-5-1988 for providing signalling arrangements on specified sections of the Central Railway at an agreed cost of Rs 18,10,400. After completion of the work, disputes arose and Suit No. 2822 of 1993 was filed in the Bombay High Court seeking arbitration. An umpire finally made an award on 26-4-2005 allowing several claims (including Claims 11 and 13) and directing return of a bank guarantee.

The Union of India challenged the award, limited to the grant of interest on Claims 11 and 13, by filing Arbitration Petition No. 274 of 2005 before a Single Judge of the Bombay High Court. The petition was dismissed on 6-12-2005. The Union’s intra-court Appeal No. 219 of 2006 also failed by judgment dated 24-4-2006. The present civil appeal by special leave was thereafter filed before the Supreme Court.

Legal Issues Presented

  1. Whether, under the Arbitration Act, 1940, an arbitrator has jurisdiction to award interest pendente lite and/or pre-reference interest when the contract between the parties contains an express prohibition against payment of interest (Clause 1.15 of the General Conditions of Contract).

Arguments of the Parties

Appellant (Union of India)

  • Relied on Clause 1.15, which states that “No interest will be payable … on amounts payable to the contractor under the contract”, to contend that the arbitrator lacked power to grant any interest.
  • Submitted that contractual prohibition overrides any general discretion an arbitrator might otherwise possess.

Respondent (Contractor)

  • Contended that an arbitrator retains authority to award interest notwithstanding a contractual bar, relying on precedent such as Port of Calcutta v. Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani Construction Corpn. (P) Ltd. v. Union of India (2010) 1 SCC 549.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Irrigation Deptt., Govt. of Orissa v. G.C. Roy (1992) 1 SCC 508 (Const. Bench) An arbitrator may award interest pendente lite if the contract is silent and there is no prohibition. Relied upon to stress that a contractual prohibition removes the arbitrator’s power; otherwise the power exists.
Dhenkanal Minor Irrigation Division v. N.C. Budharaj (2001) 2 SCC 721 (Const. Bench) Arbitrator can award pre-reference interest absent any contractual bar. Cited to reaffirm that the key test is the presence or absence of an express prohibition.
Port of Calcutta v. Engineers-De-Space-Age (1996) 1 SCC 516 Held that arbitrator could award interest even where the contract barred the employer from paying it. Distinguished and declared not good law after later Constitution Bench and larger Bench rulings; reliance by respondent rejected.
Madnani Construction Corpn. (P) Ltd. v. Union of India (2010) 1 SCC 549 Followed Engineers-De-Space-Age to uphold award of interest despite prohibition. Considered inapplicable; court declined to follow for reasons similar to rejection of Engineers-De-Space-Age.
Sayeed Ahmed & Co. v. State of U.P. (2009) 12 SCC 26 Clarified that a contractual clause barring interest bars the arbitrator as well; overruled Engineers-De-Space-Age. Expressly followed to set aside the interest component of the award.
Union of India v. Saraswat Trading Agency (2009) 16 SCC 504 Where contract bars any interest or damages, arbitrator cannot grant the same. Cited as supportive authority for the Union’s position.
Sree Kamatchi Amman Constructions v. Railways (2010) 8 SCC 767 Re-affirmed that contractual prohibition on interest binds the arbitrator; analysed Madnani and Engineers-De-Space-Age. Endorsed; used to bolster the conclusion that interest could not be awarded.
Executive Engineer v. Abhaduta Jena (1988) 1 SCC 418 (“Jena case”) Earlier view denying power to award interest; later overruled in Budharaj. Referenced in historical survey; acknowledged as overruled.
Thawardas (AIR 1955 SC 468) Earlier case limiting arbitrator’s power on interest. Mentioned as having been distinguished and not followed in later jurisprudence.

Court's Reasoning and Analysis

The Court focused on Clause 1.15, noting its unequivocal bar on “amounts payable to the contractor under the contract”. Drawing on Constitution Bench authority in G.C. Roy and N.C. Budharaj, the Court held that an arbitrator’s power to award interest exists only when the agreement is silent; where there is an express prohibition, that discretion is extinguished.

The Court examined conflicting earlier decisions. It observed that Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani (2010) 1 SCC 549, both decided under the 1940 Act, had permitted interest despite contractual bars, but these rulings were effectively overruled or rendered inapplicable by later larger-bench pronouncements, particularly Sayeed Ahmed (2009) 12 SCC 26 and Sree Kamatchi Amman Constructions (2010) 8 SCC 767. Accordingly, reliance on Engineers-De-Space-Age or Madnani was rejected.

Because the contract here expressly excluded interest and the governing statute (Arbitration Act, 1940) contained no provision overriding such exclusion, the arbitrator’s award of interest on Claims 11 and 13, as affirmed by the High Court, was held to be without jurisdiction. Maintaining such an award would amount to rewriting the contract.

Holding and Implications

Appeal Allowed; award of interest set aside.

The Supreme Court annulled the arbitrator’s grant of interest and consequently set aside the orders of both the learned Single Judge and the Division Bench of the Bombay High Court insofar as they had upheld that interest. The decision underscores that, under the Arbitration Act, 1940, an explicit contractual prohibition on interest is absolute and binds both the arbitrator and the courts. No broader new legal principle was introduced, but the ruling reinforces the supremacy of contractual terms in arbitral matters concerning interest.

To access the original judgment, please Sign In or Subscribe.

    Union Of India v. Krafters Engineering And Leasing Private Limited .

    P. Sathasivam, J.— This appeal by the Union of India arises out of the final judgment and order dated 24-4-2006 passed by the High Court of Judicature of Bombay in Appeal No. 219 of 2006 in Arbitration Petition No. 274 of 2005 whereby the Division Bench of the High Court dismissed its appeal.

    Brief facts

    2. On 16-5-1988, the respondent was awarded with a contract for the work of provision of signalling arrangements at C Class stations on Igatpuri-Bhusawal section and 2 C Class stations on Bhusawal-Badnera section of Bhusawal Division of Central Railway at the cost of Rs 18,10,400. On completion of the contract, the respondent raised certain disputes/claims by filing Suit No. 2822 of 1993 before the High Court and demanded for adjudication through arbitration. The High Court directed the General Manager of the Central Railway to appoint an arbitrator and refer the disputes for adjudication. Since the arbitrator appointed could not deliberate the matter within the time-limit, the respondent invoked the jurisdiction of the umpire. The umpire, by order dated 26-4-2005, gave award for Claims 1, 3, 6, 8, 9, 10, 11, 12 and 13 and rejected Claims 2, 5, 7 and 14 and mentioned that a bank guarantee towards security deposit against Claim 4 is to be returned.

    3. Challenging the award given by the umpire for Claims 11 and 13, the appellant herein filed Arbitration Petition No. 274 of 2005 before the High Court. The learned Single Judge of the High Court vide order dated 6-12-2005 dismissed its petition. Aggrieved by the order passed by the learned Single Judge, the appellant herein filed an appeal being Arbitration Appeal No. 219 of 2006 before the Division Bench of the High Court. The Division Bench by impugned order dated 24-4-2006, dismissed the appeal. Challenging the said order, the Union of India preferred this appeal by way of special leave before this Court.

    4. Heard Mr A.S Chandhiok, learned Additional Solicitor General for the Union of India and Mr Ramesh Babu M.R, learned counsel for the respondent.

    5. Before the High Court as well as before us, the appellant projected their case only with regard to interest that was granted by the arbitrator and confirmed by the High Court. Therefore, the only point for consideration in this appeal is: whether an arbitrator has the jurisdiction to grant interest despite the agreement prohibiting the same?

    6. Though the appellant has challenged the award of the umpire in respect of Claims 11 and 13, they are mainly concerned about the grant of interest; hence there is no need to traverse all the factual details except the required one which we have adverted to.

    7. According to Mr A.S Chandhiok, learned ASG, in view of Clause 1.15 of the general conditions of the contract between the parties, the arbitrator does not have the power to award interest pendente lite. The said clause reads as under:

    “1.15 Interest on amounts.—No interest will be payable upon the earnest money or the security deposit or amounts payable to the contractor under the contract but government securities deposited in terms of Clause 1.14.4 will be repayable with interest accrued thereon.”

    According to the learned ASG, in view of the abovementioned clause, no interest is payable on the amount payable to the contractor under the contract.

    8. On the other hand, Mr Ramesh Babu M.R, learned counsel appearing for the respondent submitted that irrespective of the bar in the contract the arbitrator has the power to award interest for which he strongly relied on the decision of this Court in Port of Calcutta v. Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani Construction Corpn. (P) Ltd. v. Union of India (2010) 1 SCC 549.

    9. We have already extracted the relevant clause wherein the words “amounts payable to the contractor under the contract” are of paramount importance. If there is no prohibition in the arbitration agreement to exclude the jurisdiction of the arbitrator to entertain a claim for interest on the amount due under the contract, the arbitrator is free to consider and award interest in respect of the period. If there is a prohibition in the agreement to pay the interest, in that event, the arbitrator cannot grant the interest. Clause 1.15 prohibits payment of interest on the amount payable to the contractor under the contract.

    10. It is not in dispute that the provisions of the Arbitration Act, 1940 alone are applicable to the case on hand. Now, let us consider the various decisions of this Court dealing with similar prohibition in the agreement for grant of interest.

    11. In Irrigation Deptt., Govt. of Orissa v. G.C Roy (1992) 1 SCC 508, the Constitution Bench had considered Section 29 of the Arbitration Act, 1940 which deals with interest pendente lite. After analysing the scheme of the Act and various earlier decisions, the Constitution Bench considered the very same issue, namely, whether an arbitrator has the power to award interest pendente lite and, if so, on what principle. The relevant paragraphs are extracted hereunder:

    “43. The question still remains whether the arbitrator has the power to award interest pendente lite, and if so on what principle. We must reiterate that we are dealing with the situation where the agreement does not provide for grant of such interest nor does it prohibit such grant. In other words, we are dealing with a case where the agreement is silent as to award of interest. On a conspectus of aforementioned decisions, the following principles emerge:
    (i) A person deprived of the use of money to which he is legitimately entitled has a right to be compensated for the deprivation, call it by any name. It may be called interest, compensation or damages. This basic consideration is as valid for the period the dispute is pending before the arbitrator as it is for the period prior to the arbitrator entering upon the reference. This is the principle of Section 34 of the Civil Procedure Code and there is no reason or principle to hold otherwise in the case of arbitrator.
    (ii) An arbitrator is an alternative form (sic forum) for resolution of disputes arising between the parties. If so, he must have the power to decide all the disputes or differences arising between the parties. If the arbitrator has no power to award interest pendente lite, the party claiming it would have to approach the court for that purpose, even though he may have obtained satisfaction in respect of other claims from the arbitrator. This would lead to multiplicity of proceedings.
    (iii) An arbitrator is the creature of an agreement. It is open to the parties to confer upon him such powers and prescribe such procedure for him to follow, as they think fit, so long as they are not opposed to law. (The proviso to Section 41 and Section 3 of the Arbitration Act illustrate this point). All the same, the agreement must be in conformity with law. The arbitrator must also act and make his award in accordance with the general law of the land and the agreement.
    (iv) Over the years, the English and Indian courts have acted on the assumption that where the agreement does not prohibit and a party to the reference makes a claim for interest, the arbitrator must have the power to award interest pendente lite. Thawardas AIR 1955 SC 468 has not been followed in the later decisions of this Court. It has been explained and distinguished on the basis that in that case there was no claim for interest but only a claim for unliquidated damages. It has been said repeatedly that observations in the said judgment were not intended to lay down any such absolute or universal rule as they appear to, on first impression. Until Jena case (1988) 1 SCC 418 almost all the courts in the country had upheld the power of the arbitrator to award interest pendente lite. Continuity and certainty is a highly desirable feature of law.
    (v) Interest pendente lite is not a matter of substantive law, like interest for the period anterior to reference (pre-reference period). For doing complete justice between the parties, such power has always been inferred.
    44. Having regard to the above consideration, we think that the following is the correct principle which should be followed in this behalf:
    Where the agreement between the parties does not prohibit grant of interest and where a party claims interest and that dispute (along with the claim for principal amount or independently) is referred to the arbitrator, he shall have the power to award interest pendente lite. This is for the reason that in such a case it must be presumed that interest was an implied term of the agreement between the parties and therefore when the parties refer all their disputes—or refer the dispute as to interest as such—to the arbitrator, he shall have the power to award interest. This does not mean that in every case the arbitrator should necessarily award interest pendente lite. It is a matter within his discretion to be exercised in the light of all the facts and circumstances of the case, keeping the ends of justice in view.”
    (emphasis in original)

    12. In Dhenkanal Minor Irrigation Division v. N.C Budharaj (2001) 2 SCC 721, another Constitution Bench considered payment of interest for pre-reference period in respect of cases arising when the Interest Act, 1839 was in force. The following conclusion in para 26 is relevant which reads thus:

    “26. For all the reasons stated above, we answer the reference by holding that the arbitrator appointed with or without the intervention of the court, has jurisdiction to award interest, on the sums found due and payable, for the pre-reference period, in the absence of any specific stipulation or prohibition in the contract to claim or grant any such interest. The decision in Jena case (1988) 1 SCC 418 taking a contraview does not lay down the correct position and stands overruled, prospectively, which means that this decision shall not entitle any party nor shall it empower any court to reopen proceedings which have already become final, and apply only to any pending proceedings. No costs.”
    (emphasis supplied)

    13. In the earlier paragraphs, we have referred to the stand taken by the learned counsel for the respondent and reliance based on the decision Engineers-De-Space-Age (1996) 1 SCC 516. It is true that in that decision, this Court has held that the arbitrator has the jurisdiction to interpret the clauses of the contract and to decide whether interest pendente lite could be awarded by him. The short question that arose in that case was that the arbitrator had awarded interest pendente lite notwithstanding the prohibition contained in the contract against the payment of interest on delayed payments. Ultimately, the two-Judge Bench of this Court has concluded that irrespective of the terms of the contract, the arbitrator was well within his jurisdiction in awarding interest pendente lite.

    14. It is useful to point out that the ratio in Engineers-De-Space-Age (1996) 1 SCC 516 decision was considered by this Court in Sayeed Ahmed and Co. v. State of U.P (2009) 12 SCC 26 While considering the very same issue, particularly, the specific clause in the agreement prohibiting interest pendente lite, this Court considered the very same decision i.e Engineers-De-Space-Age (1996) 1 SCC 516. After adverting to the clause in the Engineers-De-Space-Age (1996) 1 SCC 516 and the Constitution Bench in G.C Roy case (1992) 1 SCC 508, this Court concluded as under: (Sayeed Ahmed and Co. case (2009) 12 SCC 26)

    “23. The observation in Engineers-De-Space-Age (1996) 1 SCC 516 that the term of the contract merely prohibits the department/employer from paying interest to the contractor for delayed payment but once the matter goes to the arbitrator, the discretion of the arbitrator is not in any manner stifled by the terms of the contract and the arbitrator will be entitled to consider and grant the interest pendente lite, cannot be used to support an outlandish argument that bar on the Government or department paying interest is not a bar on the arbitrator awarding interest. Whether the provision in the contract bars the employer from entertaining any claim for interest or bars the contractor from making any claim for interest, it amounts to a clear prohibition regarding interest. The provision need not contain another bar prohibiting the arbitrator from awarding interest. The observations made in the context of interest pendente lite cannot be used out of contract.
    24. The learned counsel for the appellant next contended on the basis of the above observations in Engineers-De-Space-Age (1996) 1 SCC 516, that even if Clause G1.09 is held to bar interest in the pre-reference period, it should be held not to apply to the pendente lite period, that is, from 14-3-1997 to 31-7-2001. He contended that the award of interest during the pendency of the reference was within the discretion of the arbitrator and therefore, the award of interest for that period could not have been interfered with by the High Court. In view of the Constitution Bench decisions in G.C Roy (1992) 1 SCC 508 and N.C Budharaj (2001) 2 SCC 721 rendered before and after the decision in Engineers-De-Space-Age (1996) 1 SCC 516, it is doubtful whether the observation in Engineers-De-Space-Age (1996) 1 SCC 516 in a case arising under the Arbitration Act, 1940 that the arbitrator could award interest pendente lite, ignoring the express bar in the contract, is good law. But that need not be considered further as this is a case under the new Act where there is a specific provision regarding award of interest by the arbitrator.”

    15. Considering the specific prohibition in the agreement as discussed and interpreted by the Constitution Bench, we are in respectful agreement with the view expressed in Sayeed Ahmed and Co. (2009) 12 SCC 26 and we cannot possibly agree with the observation in Engineers-De-Space-Age (1996) 1 SCC 516 in a case arising under the Arbitration Act, 1940 that the arbitrator could award interest pendente lite ignoring the express bar in the contract.

    16. In Union of India v. Saraswat Trading Agency (2009) 16 SCC 504, though it was a case under the Arbitration and Conciliation Act, 1996, this Court has considered elaborately the legal position in regard to interest after adverting to all the earlier decisions and basing reliance on Clause 31 of the agreement held:

    “33. In the case in hand Clause 31 of the agreement is materially different. It bars payment of any interest or damages to the contractor for any reason whatsoever. We are, therefore, clearly of the view that no pre-reference or pendente lite interest was payable to the respondent on the amount under Item 3 and the arbitrator's award allowing pre-reference and pendente lite interest on that amount was plainly in breach of the express terms of the agreement. The order of the High Court insofar as pre-reference and pendente lite interest on the amount under Item 3 is concerned, is therefore, unsustainable.”

    17. At the end of the argument, the learned counsel for the respondent heavily relied on the recent decision of this Court in Madnani Construction Corpn. (P) Ltd. (2010) 1 SCC 549 which arose under the Arbitration Act, 1940. There also, Clause 30 of SCC and Clause 52 of GCC prohibits payment of interest. Though the Bench relied on all the earlier decisions and considered the very same clause as to which we are now discussing, upheld the order awarding interest by the arbitrator dehors to specific bar in the agreement.

    18. It is relevant to point out that the decision of Madnani Construction Corpn. (P) Ltd. (2010) 1 SCC 549 was cited before another Bench of this Court in Sree Kamatchi Amman Constructions v. Railways (2010) 8 SCC 767, wherein the decision in Madnani Construction Corpn. (P) Ltd. (2010) 1 SCC 549 was very much discussed and considered. After adverting to all the earlier decisions including the Constitution Bench judgments, this Court has analysed the effect of Madnani Construction Corpn. (P) Ltd. (2010) 1 SCC 549 The following discussion and ultimate conclusion are relevant: (Sree Kamatchi Amman Constructions case (2010) 8 SCC 767)

    “17. In Madnani (2010) 1 SCC 549 the arbitrator had awarded interest pendente lite, that is, from the date of appointment of arbitrator to the date of award. The High Court had interfered with the same on the ground that there was a specific prohibition in the contract regarding awarding of interest. This Court following the decision in Engineers-De-Space-Age (1996) 1 SCC 516 reversed the said rejection and held as follows: (Madnani case (2010) 1 SCC 549)
    ‘39. In the instant case also the relevant clauses, which have been quoted above, namely, Clause 16(2) of GCC and Clause 30 of SCC do not contain any prohibition on the arbitrator to grant interest. Therefore, the High Court was not right in interfering with the arbitrator's award on the matter of interest on the basis of the aforesaid clauses. We therefore, on a strict construction of those clauses and relying on the ratio in Engineers (1996) 1 SCC 516 find that the said clauses do not impose any bar on the arbitrator in granting interest.’
    18. At the outset it should be noticed that Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani (2010) 1 SCC 549 arose under the old Arbitration Act, 1940 which did not contain a provision similar to Section 31(7) of the new Act. This Court, in Sayeed Ahmed (2009) 12 SCC 26 held that the decisions rendered under the old Act may not be of assistance to decide the validity of grant of interest under the new Act. The logic in Engineers-De-Space-Age (1996) 1 SCC 516 was that while the contract governed the interest from the date of cause of action to the date of reference, the arbitrator had the discretion to decide the rate of interest from the date of reference to the date of award and he was not bound by any prohibition regarding interest contained in the contract, insofar as pendente lite period is concerned. This Court in Sayeed Ahmed (2009) 12 SCC 26 held that the decision in Engineers-De-Space-Age (1996) 1 SCC 516 would not apply to cases arising under the new Act. We extract below, the relevant portion from Sayeed Ahmed (2009) 12 SCC 26:
    ‘23. The observation in Engineers-De-Space-Age (1996) 1 SCC 516 that the term of the contract merely prohibits the department/employer from paying interest to the contractor for delayed payment but once the matter goes to the arbitrator, the discretion of the arbitrator is not in any manner stifled by the terms of the contract and the arbitrator will be entitled to consider and grant the interest pendente lite, cannot be used to support an outlandish argument that bar on the Government or department paying interest is not a bar on the arbitrator awarding interest. Whether the provision in the contract bars the employer from entertaining any claim for interest or bars the contractor from making any claim for interest, it amounts to a clear prohibition regarding interest. The provision need not contain another bar prohibiting the arbitrator from awarding interest. The observations made in the context of interest pendente lite cannot be used out of contract.
    24. The learned counsel for the appellant next contended on the basis of the above observations in Engineers-De-Space-Age (1996) 1 SCC 516, that even if Clause G1.09 is held to bar interest in the pre-reference period, it should be held not to apply to the pendente lite period, that is, from 14-3-1997 to 31-7-2001. He contended that the award of interest during the pendency of the reference was within the discretion of the arbitrator and therefore, the award of interest for that period could not have been interfered with by the High Court. In view of the Constitution Bench decisions in G.C Roy (1992) 1 SCC 508 and N.C Budharaj (2001) 2 SCC 721 rendered before and after the decision in Engineers-De-Space-Age (1996) 1 SCC 516, it is doubtful whether the observation in Engineers-De-Space-Age (1996) 1 SCC 516 in a case arising under the Arbitration Act, 1940 that the arbitrator could award interest pendente lite, ignoring the express bar in the contract, is good law. But that need not be considered further as this is a case under the new Act where there is a specific provision regarding award of interest by the arbitrator.’
    The same reasoning applies to the decision in Madnani (2010) 1 SCC 549 also as that also relates to a case under the old Act and did not independently consider the issue but merely relied upon the decision in Engineers-De-Space-Age (1996) 1 SCC 516.
    19. Section 37(1) of the new Act by using the words ‘unless otherwise agreed by the parties’ categorically clarifies that the arbitrator is bound by the terms of the contract insofar as the award of interest from the date of cause of action to the date of award. Therefore, where the parties had agreed that no interest shall be payable, the Arbitral Tribunal cannot award interest between the date when the cause of action arose to the date of award.
    20. We are of the view that the decisions in Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani (2010) 1 SCC 549 are inapplicable for yet another reason. In Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani (2010) 1 SCC 549 the arbitrator had awarded interest for the pendente lite period. This Court upheld the award of such interest under the old Act on the ground that the arbitrator had the discretion to decide whether interest should be awarded or not during the pendente lite period and he was not bound by the contractual terms insofar as the interest for the pendente lite period. But in the instant case the Arbitral Tribunal has refused to award interest for the pendente lite period. Where the Arbitral Tribunal has exercised its discretion and refused award of interest for the period pendente lite, even if the principles in those two cases were applicable, the award of the arbitrator could not be interfered with. On this ground also the decisions in Engineers-De-Space-Age (1996) 1 SCC 516 and Madnani (2010) 1 SCC 549 are inapplicable.”
    (emphasis in original)

    19. Inasmuch as we have already expressed a similar view as mentioned above and conveyed our inability to apply the reasoning in Madnani Construction Corpn. (P) Ltd. (2010) 1 SCC 549, we fully endorse the view expressed in Sree Kamatchi Amman Constructions (2010) 8 SCC 767.

    20. In the light of the above discussion, the following conclusion emerges: reliance based on the ratio in Engineers-De-Space-Age (1996) 1 SCC 516 is unacceptable since the said view has been overruled in Sayeed Ahmed and Co. (2009) 12 SCC 26 and insofar as the ratio in Madnani Construction Corpn. (P) Ltd. (2010) 1 SCC 549 which is also unacceptable for the reasons mentioned in the earlier paras, we reject the stand taken by the counsel for the respondent. On the other hand, we fully accept the stand of the Union of India as rightly projected by Mr A.S Chandhiok, learned ASG. We reiterate that where the parties had agreed that no interest shall be payable, the arbitrator cannot award interest for the amounts payable to the contractor under the contract. Where the agreement between the parties does not prohibit grant of interest and where a party claims interest and the said dispute is referred to the arbitrator, he shall have the power to award interest pendente lite. As observed by the Constitution Bench in G.C Roy case (1992) 1 SCC 508, in such a case, it must be presumed that interest was an implied term of the agreement between the parties. However, this does not mean that in every case, the arbitrator should necessarily award interest pendente lite. In the subsequent decision of the Constitution Bench i.e N.C Budharaj case (2001) 2 SCC 721, it has been reiterated that in the absence of any specific stipulation or prohibition in the contract to claim or grant any such interest, the arbitrator is free to award interest.

    21. In the light of the above principle and in view of the specific prohibition of contract contained in Clause 1.15, the arbitrator ceases to have the power to grant interest. We also clarify that the Arbitration Act, 1940 does not contain any specific provision relating to the power of arbitrator to award interest. However, in the Arbitration and Conciliation Act, 1996, there is a specific provision with regard to award of interest by the arbitrator. The bar under Clause 1.15 is absolute and interest cannot be awarded without rewriting the contract.

    22. For the aforesaid reasons, we set aside the award of the arbitrator granting interest in respect of the amount payable to the contractor under the contract as well as the order of the learned Single Judge and the Division Bench of the High Court confirming the same.

    23. Consequently, the appeal is allowed to the extent pointed out above with no order as to costs.

    Use AI to get other relevant cases.

    Comments

    Union Of India v. Krafters Engineering And Leasing Private Limited .
    (Jul 12, 2011)