AMICUS AI
Citation Codes
Neutral Citations
2006 INSC 853
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Arbitration Act, 1996
  • the Act (Arbitration and Conciliation Act, 1996)
  • Section 11 of the Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 11 of the Arbitration and Conciliation Act, 1996
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2006 INSC 853
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Arbitration Act, 1996
  • the Act (Arbitration and Conciliation Act, 1996)
  • Section 11 of the Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 11 of the Arbitration and Conciliation Act, 1996
Smart Summary

Factual and Procedural Background

The appeals arise out of a batch of writ petitions decided by the High Court of Andhra Pradesh on 27-04-2001. The High Court, acting under Section 11 of the Arbitration and Conciliation Act, 1996 (“the Act”), appointed a former High Court Judge, Justice Y.V. Narayana, as sole arbitrator in Civil Misc. Petition No. 60 of 1998 and fixed his fee at ₹2 lakhs.

The underlying dispute concerns a contract dated 19-04-1993 between the Union of India (Railways) and M/s V.S. Engineering (P) Ltd. for supplying and stacking 1.8 lakh cu m of 50 mm machine-crushed stone ballast at Nallapadu Depot for ₹5,02,20,000. The work—scheduled from 26-04-1993 to 26-04-1996—fell substantially behind; only 88,214 cu m had been supplied by November 1997. The Railways recovered a penalty of ₹1.01 crore from the contractor’s running bills and refused a request for waiver and rescheduling, giving rise to disputes.

Invoking clauses 63 and 64 of the General Conditions of Contract (“GCC”), the contractor sought arbitration. On 05-05-1998 the General Manager, Railways, supplied four names of gazetted railway officers; the respondent chose Shri R.N. Raghavan, whereupon an Arbitral Tribunal was constituted on 20-08-1998. Alleging incomplete reference of claims, the contractor simultaneously filed Arbitration Application No. 60 of 1998 under Section 11 of the Act. A learned Single Judge appointed Justice Y.V. Narayana as sole arbitrator on 28-11-2000, withdrawing all matters from the tribunal already constituted.

The Union of India’s intra-court appeal was clubbed with other matters and disposed of by the Division Bench on 27-04-2001, which suggested approaching the Single Judge for modification. The Single Judge, however, refused to recall the order (21-02-2002), stating that the earlier tribunal had been “impliedly set aside.” Special Leave Petitions followed, culminating in the present appeals before the Supreme Court.

Legal Issues Presented

  1. Whether, in the presence of a valid arbitration clause (clauses 63 & 64, GCC) and an Arbitral Tribunal already constituted by the General Manager, Railways, the High Court could appoint a sole arbitrator under Section 11 of the Act.
  2. Whether the High Court’s appointment of a retired Judge in derogation of the contractual stipulation for two gazetted railway officers is sustainable.
  3. The extent to which prior Supreme Court precedents (particularly Union of India v. M.P. Gupta, 2004 10 SCC 504, and SBP & Co. v. Patel Engg. Ltd., 2005 8 SCC 618) govern the High Court’s power under Section 11.

Arguments of the Parties

Appellant (Union of India)

  • Clauses 63 and 64 of the GCC mandate that disputes be referred to a tribunal comprising two gazetted railway officers appointed by the General Manager; judicial interference is unwarranted once such a tribunal is in place.
  • Relied on Union of India v. M.P. Gupta (2004) 10 SCC 504, where the Supreme Court set aside a High Court-appointed sole arbitrator in analogous circumstances.
  • Cited Datar Switchgears Ltd. v. Tata Finance Ltd. (2000) 8 SCC 151 to contend that the Railway’s appointment was made before the contractor approached the court, preserving its contractual right.

Respondent (V.S. Engineering (P) Ltd.)

  • Invoked SBP & Co. v. Patel Engg. Ltd. (2005) 8 SCC 618, arguing that the High Court’s Section 11 power is judicial and that its exercise should not be disturbed.
  • Emphasised that arbitration proceedings before Justice Y.V. Narayana were almost complete and that setting aside his appointment would cause delay and prejudice.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union of India v. M.P. Gupta (2004) 10 SCC 504 Where the contract stipulates appointment of two gazetted railway officers, courts should not substitute a sole arbitrator. Treated as binding; used to set aside the High Court’s appointment of a retired Judge and to direct constitution of a tribunal as per GCC.
SBP & Co. v. Patel Engg. Ltd. (2005) 8 SCC 618 Clarified that the Chief Justice’s power under Section 11 is judicial, overruling Konkan Railway. Court held it did not aid the respondent because it did not dilute contractual stipulations already complied with.
Datar Switchgears Ltd. v. Tata Finance Ltd. (2000) 8 SCC 151 Party loses the right to appoint an arbitrator if it fails to do so within 30 days and the other side approaches the court. Referred to support the view that the Railways’ prompt appointment preserved its contractual right.
Konkan Railway Corpn. Ltd. v. Rani Construction (P) Ltd. (2002) 2 SCC 388 Earlier view of Section 11 as administrative (subsequently overruled). Cited only to note that it was overruled by SBP & Co.; not determinative of the present outcome.

Court's Reasoning and Analysis

The Supreme Court noted that the impugned Division Bench order of 27-04-2001 raised issues already answered by the seven-Judge decision in SBP & Co., rendering further examination unnecessary. Turning to the Single Judge’s appointment of Justice Y.V. Narayana, the Court applied the ratio of Union of India v. M.P. Gupta:

  • The contract expressly provides, through clauses 63 and 64, for disputes to be adjudicated by two gazetted railway officers appointed by the General Manager.
  • Such an appointment had, in fact, been made on 20-08-1998, before the respondent sought judicial intervention; therefore the High Court exceeded its jurisdiction in appointing a sole arbitrator.
  • While courts may step in if a public authority sleeps over a request for appointment, that contingency did not arise because the Railways had acted within the contractual and statutory timelines.

The Court cautioned public bodies that inordinate delay would legitimise court-appointed arbitrators, reaffirming that judicial discretion under Section 11 survives where contractual machinery is not promptly invoked.

Holding and Implications

Appeals Allowed; High Court orders set aside. Justice Y.V. Narayana’s appointment as sole arbitrator is quashed. The General Manager, Railways, is directed to constitute an Arbitral Tribunal in accordance with clauses 63 and 64 within 30 days, and the tribunal must conclude proceedings expeditiously.

Implications: The judgment reinforces party autonomy and contractual mechanisms for constituting arbitral tribunals, especially in government contracts. It signals that courts will respect such stipulations when authorities act within a reasonable time, but preserves judicial power to intervene where they do not. No new legal principle is created; the decision mainly applies existing precedent to the specific facts.

To access the original judgment, please Sign In or Subscribe.

    Union Of India And Another v. V.S Engineering (P) Ltd. .

    A.K Mathur, J.— These appeals are directed against the judgment and order passed by the High Court of Andhra Pradesh. By the impugned order dated 27-4-2001 a batch of writ petitions were disposed of including the one before us whereby the High Court appointed arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter to be referred to as “the Act”). In the present appeals, we are concerned with Writ Petition No. 2465 of 2001 [Union of India v. V.S Engg. (P) Ltd.]. So far as order dated 27-4-2001 passed by the Division Bench of the High Court is concerned, all the issues raised in that order have already been decided by this Court in SBP & Co. v. Patel Engg. Ltd. (2005) 8 SCC 618 by a seven-Judge Bench of this Court. Therefore, no purpose will be served by examining the validity of the order of the Division Bench of the High Court challenged in this present appeal as all issues are covered in the decision of SBP & Co. (2005) 8 SCC 618 Therefore this appeal is accordingly disposed of in the light of the aforesaid decision.

    2. Brief facts giving rise to another appeal are that M/s V.S Engineering Private Limited, Hyderabad was awarded the work of supply and stacking of 50 mm machine-crushed stone ballast at Nallapadu Depot and loading the same into B.T wagons by mechanical/manual means for a quantity of 1.8 lakhs cum at the value of Rs 5,02,20,000. Agreement No. GM/W/SC/93/2 providing payment of mobilisation advance and machinery and plant advance was executed by the contractor on 19-4-1993. The completion period was 39 months as per the acceptance letter dated 27-1-1993. As per the agreement the work was to be commenced from 26-4-1993 and completed by 26-4-1996 supplying the ballast at the rate of 60,000 cu. m. As the contractor could not commence the work as per the tender conditions and supplied only 88214 cu. m up to November 1997 penalty for an amount of Rs 1.01 crores was recovered from the running bills of the contractor. The appellant did not agree to the request of the contractor for waiver of penalty and rescheduling of supply. Therefore, a dispute arose between the parties and the contractor sought appointment of an arbitrator under clause 64 of the General Conditions of Contract. In pursuance of the contractor's demand the Arbitral Tribunal was appointed to adjudicate the contractor's claim. The Arbitral Tribunal initiated the proceedings and the contractor submitted his claim statement before the Arbitral Tribunal. Subsequently, the contractor filed Arbitration Application No. 60 of 1998 dated 16-10-1998 before the High Court of Andhra Pradesh at Hyderabad under Section 11 of the Act, seeking appointment of an arbitrator to resolve the dispute emanating from the agreement dated 19-4-1993. The appellant Union of India contested the arbitration application filed by the respondent by filing a counter and denying the allegations. It was pointed out that it was wrong to say that the payment was not done for the work done. It was alleged that the payment was made as per the terms of the contract and there was no delay on the part of the Railways. It was also contended that the request for referring the dispute for arbitration has to be done in accordance with clauses 63 and 64 of the General Conditions of Contract. As per clause 63, on receipt of the application the Railways had to notify the decisions on all matters including the matters which came up under the caption “excepted matters”. The respondent subsequently made a request for referring the matter to the Arbitral Tribunal. The General Manager of the Railways as per clause 64 of the General Conditions of Contract accepted the request of the respondent for referring the dispute to the Arbitral Tribunal and accordingly, a letter was sent on 5-5-1998 furnishing four names of railway officers out of which the respondent had to nominate up to two names which was the requirement in accordance with clause 64(3)(a)(ii) of the General Conditions of Contract. The respondent chose one name i.e Shri R.N Raghavan out of the four names given to him and the dispute was referred to the Arbitral Tribunal on 20-8-1998. Thereafter, some other railway official was appointed. Some claims were not referred to the Arbitral Tribunal. Meanwhile, the contractor filed petition in the High Court. The High Court on 28-11-2000 appointed Mr Justice Y.V Narayana as arbitrator to resolve the disputes and referred all 14 claims and also fixed the fee at Rs 2 lakhs. Aggrieved by the order dated 28-11-2000 passed in Civil Miscellaneous Petition No. 60 of 1998, the appellant filed a writ petition before the High Court challenging the order of the learned Single Judge appointing the arbitrator before the Division Bench. The Division Bench clubbed together large number of matters including various issues pertaining to the Arbitration Act, 1996 and decided by its order dated 27-4-2001. This order was also challenged by the Union of India by filing the present appeal. The Division Bench of the High Court by this order disposed of the Union of India's appeal pertaining to this subject-matter and directed that in view of the peculiar facts of this case that since the General Manager of the Railways has already constituted an Arbitral Tribunal, the appellant should approach the learned Single Judge for modification/recalling the aforesaid order dated 28-11-2000. Pursuant to that the appellant approached the learned Single Judge praying for modification of the order. The learned Single Judge dismissed the aforesaid application by order dated 21-2-2002. While dismissing the application, the learned Single Judge observed as follows:

    “As this Court is of the opinion that the Arbitral Tribunal constituted by the General Manager is impliedly set aside and the matters referred to are already withdrawn by referring the same to the sole arbitrator appointed by this Court, the question of functioning of the Arbitral Tribunal constituted by the General Manager, Railways, does not arise.”

    Hence, aggrieved against this order the present special leave petition was filed and leave was granted. Hence both the present appeals have come up before us for final disposal.

    3. The learned Additional Solicitor General appearing for the appellant Union of India has pointed out that as per clauses 63 and 64 of the General Conditions of Contract, this Court in no uncertain terms has held that the Arbitral Tribunal has to be constituted as per the General Conditions of Contract, the High Court should not interfere under Section 11 of the Act and the High Court should accept the Arbitral Tribunal appointed by the General Manager, Railways. In this connection, the learned ASG invited our attention to a decision of this Court directly bearing on the subject in Union of India v. M.P Gupta (2004) 10 SCC 504 wherein a similar question with regard to appointment of the Arbitral Tribunal for the Railways with reference to clause 64 of the General Conditions of Contract came up before this Court and this Court held that where two gazetted railway officers are appointed as the Arbitral Tribunal, the High Court should not appoint a retired Judge of the High Court as a sole arbitrator and the appointment of sole arbitrator was set aside. The conditions of clauses 63 and 64 of the General Conditions of Contract are almost analogous to the one we have in our hand. In that case also relying on clause 64 of the contract a three-Judge Bench presided over by the Chief Justice of India observed as follows:

    “4. In view of the express provision contained therein that two gazetted railway officers shall be appointed as arbitrators, Justice P.K Bahri could not be appointed by the High Court as the sole arbitrator. On this short ground alone, the judgment and order under challenge to the extent it appoints Justice P.K Bahri as sole arbitrator is set aside. Within 30 days from today, the appellants herein shall appoint two gazetted railway officers as arbitrators. The two newly appointed arbitrators shall enter into reference within a period of another one month and thereafter the arbitrators shall make their award within a period of three months.”

    4. Earlier also in Datar Switchgears Ltd. v. Tata Finance Ltd. (2000) 8 SCC 151 their Lordships have observed that the arbitrator should be appointed within thirty days on demand being made by the other party and the appointment could still be made but before the other party moves the court under Section 11 of the Act. It was observed that once the other party moves the court the right to make the appointment ceases to exist. In the present case as it appears that the General Manager, Railways has already appointed the arbitrator but despite this, the learned Single Judge has overruled the objection of the Union of India and appointed the learned Judge of the High Court as arbitrator.

    5. As against this learned counsel appearing for the respondent has invited our attention to a decision of this Court in SBP & Co. v. Patel Engg. Ltd. (2005) 8 SCC 618 in which a Bench of seven Judges by majority has overruled the earlier decision given in Konkan Rly. Corpn. Ltd. v. Rani Construction (P) Ltd. (2002) 2 SCC 388 So far as the case of SBP & Co. (2005) 8 SCC 618 is concerned it cannot come to the rescue of the respondent. Learned counsel for the respondent invited our attention to para 47 that this judgment will have prospective following. But it did not lay down that when as per agreement arbitrator is appointed then the court should or should not interfere in the matter, whereas this issue is covered by earlier judgment by this Court in Union of India v. M.P Gupta (2004) 10 SCC 504 by a three-Judge Bench which is binding on us. Therefore, the decision in SBP & Co. (2005) 8 SCC 618 cannot be of any help to the respondent. It has also been pointed out that the arbitration proceedings are almost complete. But this Court has stayed the pronouncement of the award. In the present case, in view of the decision in M.P Gupta (2004) 10 SCC 504 a three-Judge Bench has clearly stated that whenever the agreement specifically provided for appointment of two gazetted railway officers of equal status as arbitrators by the General Manager, Railways, then in that case the court should give this latitude to the General Manager to make appointment.

    6. However, before parting with this case we may also observe that Railways and public institutions are very slow in reacting to the request made by a contractor for appointment of the arbitrator. Therefore, in case appointment is not made in time on the request made by the contracting party, then in that case the power of the High Court to appoint arbitrator under Section 11 of the Act will not be denuded. We cannot allow administrative authorities to sleep over the matter and leave the citizens without any remedy. Authorities shall be vigilant and their failure shall certainly give rise to cause to the affected party. In case the General Manager, Railways does not appoint the Arbitral Tribunal after expiry of the notice of 30 days or before the party approaches the High Court, in that case, the High Court will be fully justified in appointing arbitrator under Section 11 of the Act. It is the discretion of the High Court that they can appoint any railway officer or they can appoint any High Court Judge according to the given situation.

    7. As a result of our above discussion, we allow these appeals and set aside the orders of the High Court. We direct the General Manager, Railways to appoint the Arbitral Tribunal within a period of 30 days from the date of receipt of a certified copy of this order. The Arbitral Tribunal so appointed shall enter into the matter and dispose of the arbitration proceedings as expeditiously as possible. Consequently, the appointment of Justice Y.V Narayana as arbitrator is set aside. There would be no order as to costs.

    Use AI to get other relevant cases.

    Comments

    Union Of India And Another v. V.S Engineering (P) Ltd. .
    (Nov 16, 2006)