2003 INSC 462
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Sections 16 and 30 of the Arbitration Act
  • Sections 15, 16, 30 and 32 of the Arbitration Act
  • Section 16 of the Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2003 INSC 462
Equivalent Citations
citation codes
Case Number
Disposition
Advocates
Judges
Acts
  • Sections 16 and 30 of the Arbitration Act
  • Sections 15, 16, 30 and 32 of the Arbitration Act
  • Section 16 of the Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
Smart Summary

Factual and Procedural Background

The appellant (Union of India) and the first respondent (contractor) entered into a contract on 16-3-1979 for construction of an auditorium complex at Willington, Nilgiris, initially valued at Rs 64,79,982.95. Owing to an expansion in the scope of work, the contract value was revised to Rs 85.10 lakhs and the completion date was successively extended to 31-12-1982. The appellant terminated the contract on 28-2-1983 after the extended completion date had lapsed.

Disputes were referred to a sole arbitrator, Brigadier M.M.L Sharma, who on 6-2-1986 awarded Rs 14,31,463 to the contractor (Respondent 1) and Rs 33,95,000 to the appellant on their respective claims.

The contractor challenged the Government’s award component in OP No. 29 of 1986, while each party sought a decree in its favour through OS Nos. 31 and 47 of 1986 in the District Court, Nilgiris. The District Judge set aside the Rs 33,95,000 award in favour of the Government, terming it inconsistent and a result of arbitrator misconduct.

The Union of India filed three appeals (AAO Nos. 364, 366, 367 of 1995) before the Madras High Court, which dismissed them on 6-1-1997. Special Leave Petitions against the contractor’s successful portion were earlier dismissed by the Supreme Court on 24-11-1997.

The present Supreme Court judgment considers the Union’s further appeals challenging the setting aside of its award portion.

Legal Issues Presented

  1. Whether the District Judge and the Madras High Court exceeded their limited statutory jurisdiction in setting aside that part of the arbitral award which favoured the appellant.
  2. Whether the award was legally vitiated by “misconduct” due to internal inconsistency—granting damages to both parties despite a finding that the appellant had caused the delay.
  3. Whether Clause 54 of the contract could be invoked against the contractor after the expiry of the extended completion date in the factual circumstances admitted by the parties.

Arguments of the Parties

Appellant’s Arguments

  • The award was non-speaking; therefore, courts could not probe the arbitrator’s reasoning or re-appraise evidence.
  • No material justified a finding of delay attributable to the Government beyond 31-12-1982, and hence Clause 54 was validly invoked.
  • The District Judge acted as an appellate court over the award, contrary to the limited scope for interference under the Arbitration Act.
  • Reliance placed on Sudarsan Trading Co. v. Government of Kerala (1989) 2 SCC 38 for the principle that courts cannot substitute their evaluation for that of the arbitrator.

Respondent’s Arguments

  • The appellant had admitted 1,654 days’ delay in approving designs; the arbitrator ignored this undisputed fact.
  • The award was internally contradictory—having found Governmental delay, the arbitrator still awarded the Government extra completion costs—constituting misconduct.
  • Courts may examine the totality of circumstances to test consistency, relying on Dandasi Sahu v. State of Orissa (1990) 1 SCC 214.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Sudarsan Trading Co. v. Govt. of Kerala, (1989) 2 SCC 38 Distinction between errors within jurisdiction and excess of jurisdiction; limits of judicial interference. Relied upon by both sides; Court distinguished its facts, noting that here the problem was jurisdictional inconsistency amounting to misconduct.
Dandasi Sahu v. State of Orissa, (1990) 1 SCC 214 Award liable to be set aside when non-application of mind amounts to legal misconduct. Used to support the finding that the arbitrator ignored admitted delays and therefore misconduct occurred.
K.P. Poulose v. State of Kerala, (1975) 2 SCC 236 Inconsistent conclusions on the face of the award constitute misconduct under Section 30. Cited by High Court; Supreme Court endorsed that the award’s inconsistency justified setting it aside in part.
Bharat Coking Coal Ltd. v. Annapurna Construction, (2003) 8 SCC 154 Arbitrator cannot act outside contract; jurisdictional errors invite court’s intervention. Quoted to emphasise that Clause 54 could be invoked only if the contractor was in default—an issue the arbitrator misapplied.
Associated Engineering v. Govt. of A.P., (1991) 4 SCC 93 Arbitrator cannot travel beyond contract terms. Referenced within the broader discussion on jurisdictional limits of arbitrators.
Union of India v. Jain Associates, (1994) 4 SCC 665 Failure to consider counter-claim and mechanical award amounts to misconduct. Analogous support for setting aside the Government’s award portion.
Hindustan Steelworks Construction Ltd. v. C. Rajasekhar Rao, (1987) 4 SCC 93 Court cannot probe the arbitrator’s mental process where no reasons are given. Distinguished: here inconsistency was apparent on the face of the award itself.
Municipal Corpn. of Delhi v. Jagan Nath Ashok Kumar, (1987) 4 SCC 497 Arbitrator is sole judge of evidence quantity and quality. Cited in the discussion but held inapplicable where award is self-contradictory.
Premier Tyres Ltd. v. Kerala SRTC, 1993 Supp (2) SCC 146 Unappealed decrees attain finality. Used to show that acceptance of contractor’s award portion barred Government from re-litigating breach findings.
Badri Narayan Singh v. Kamdeo Prasad Singh, AIR 1962 SC 338 Finality of findings not challenged in appeal. Cited conjointly with Premier Tyres to preclude challenge to established breach findings.
Sheodan Singh v. Daryao Kunwar, AIR 1966 SC 1332 Principle of res judicata between connected suits and appeals. Held that Government’s acceptance of contractor’s award portion operated as res judicata on breach issue.

Court's Reasoning and Analysis

The Supreme Court affirmed that the pivotal question was whether Clause 54 could be lawfully invoked against the contractor when the contract had already expired and the delay was attributable to the Government. Clause 54 authorised termination and seizure of materials only if the contractor failed to meet scheduled milestones due to its own default.

The Court noted:

  • The Government admitted 1,654 days’ delay in approving designs.
  • The arbitrator simultaneously (a) awarded damages to the contractor on the premise that the Government caused delay, and (b) awarded completion costs to the Government premised on contractor default. Such mutually exclusive findings rendered the award inherently inconsistent.
  • Under precedents like K.P. Poulose and Bharat Coking Coal, an arbitrator’s inconsistent or contract-ignoring conclusions amount to “legal misconduct” under Section 30 of the Arbitration Act.
  • The District Judge and High Court did not re-appraise evidence but identified patent contradictions on the face of the award—an inquiry permissible within their limited supervisory jurisdiction.
  • Because the Government had not succeeded in setting aside the contractor’s favourable portion (its SLPs were dismissed), findings of Governmental breach had attained finality and triggered the doctrine of res judicata (Sheodan Singh, Premier Tyres).
  • Remitting the matter to arbitration at this stage was futile, as the contractor’s award portion was final and unassailable.

Holding and Implications

APPEALS DISMISSED.

The Supreme Court upheld the Madras High Court’s decision to set aside the Rs 33,95,000 award in favour of the Union of India. The result is that only the contractor’s award portion (Rs 14,31,463) survives. The judgment reinforces that courts may intervene where an arbitral award is facially self-contradictory or ignores contract provisions, clarifying the boundary between “error within jurisdiction” and “misconduct.” No new precedent was fashioned, but existing principles on arbitrator misconduct and res judicata were emphatically applied.

To access the original judgment, please Sign In or Subscribe.

    Union Of India v. V. Pundarikakshudu And Sons And Another

    S.B Sinha, J.— The appellant and the first respondent herein entered into a contract for construction of an auditorium complex at Willington Nilgiris for a sum of Rs 64,79,982.95. The work commenced on 16-3-1979 and was to be completed on 15-3-1981. However, there had been an amendment to the said agreement owing to increase in the scope of work. An extra time of six months was also given to the contractor in terms of the said amendment. The time for completion of the contract was extended from 16-9-1981 to 30-6-1982 and 1-7-1982 to 31-12-1982. The contract amount was also increased, because of the aforementioned amendment therein owing to increase in the scope of work, to Rs 85.10 lakhs. Although the period of contract was over and the appellant did not grant any further extension, the same was purportedly terminated by the appellant herein on 28-2-1983 i.e after the due date for completion of work, namely, 31-12-1982. Disputes and differences having arisen, the arbitration agreement was invoked by Respondent 1 and the claims and counter-claims of the parties were referred to one Brigadier M.M.L Sharma who was appointed by the Engineer-in-Chief of the appellant. Before the arbitrator the first respondent submitted a claim for a total sum of Rs 23,59,534.72 comprising twenty-three claims whereas the claim of the appellant herein amounted to Rs 90,58,167.42 comprising eight claims.

    2. The sole arbitrator awarded a sum of Rs 14,31,463 in favour of the first respondent and a sum of Rs 33,95,000 in favour of the appellant herein. The award was filed in the District Court of Nilgiris.

    3. Original Petition No. 29 of 1986 was filed by Respondent 1 herein under Sections 15, 16, 30 and 32 of the Arbitration Act praying to vary, modify or set aside Claim 1 under ‘B’ claim of the Government in the award dated 6-2-1986 and confirm the award in Claim ‘q’ of the contractor made including the interest and decree in favour of the petitioner or in the alternative, to set aside the award dated 6-2-1986.

    4. Original Suit No. 31 of 1986 was filed by the first respondent for passing a judgment and decree in terms of the award passed in favour of the plaintiff in Claims Serial No. ‘A’ of the contractor by the second defendant and directing the first respondent (sic defendant) to pay the plaintiff Rs 14,31,463 whereas Original Suit No. 47 of 1986 was filed by the Union of India for a decree and judgment in terms of the award for a sum of Rs 33,95,000 with interest at 18% per annum with costs.

    5. The learned District Judge upheld the said objections of the first respondent holding: as the arbitrator made an award in favour of the first respondent presumably upon arriving at a finding that the appellant herein was responsible for causing delay in completion of the contract; the award made in favour of the appellant must be held to be inconsistent therewith.

    6. It was further held that the appellant herein “pushed in” some calculation sheets on the last date of hearing which was accepted by the arbitrator without assigning any reason and without prior intimation to the first respondent which amounted to misconduct on the part of the arbitrator. The Court further took into consideration the fact that the Union of India admittedly caused 1654 days' delay in accepting the designs and as the said admission was not taken into consideration by the arbitrator, that part of the award was vitiated.

    7. The District Judge further held that having regard to the fact that the arbitrator had awarded compensation to the first respondent on various items including Claim A towards additional amount claimed due to escalation in prices of materials and men at 25% of the work done at the contract rates, loss sustained due to underutilisation of cantering and shuttering materials, loss sustained due to underutilisation, compensation for loss sustained on overheads due to prolongation of work, the impugned award cannot be sustained.

    8. The learned District Judge furthermore laid emphasis on the claim towards extra expenditure incurred in dismantling of work done due to delays in decisions wherefor a sum of Rs 12,500 was awarded stating:

    “… Therefore it is clear that there was a delay on the part of the department in taking decisions. Because of the delay in taking decisions, the arbitrator has awarded the amount for delay solely on the part of the contractor. I failed to understand why the sole arbitrator should have awarded Rs 12,500 under Claim V(a) of the contractor.”

    9. Referring to clause 54 of the contract, the District Judge said:

    “… Therefore Condition 54 makes it abundantly clear that if there was any default on the part of the contractor the Union of India has got every right to impound the materials of the contractor, and at any time sell the materials and appropriate the proceeds towards any losses. Curiously enough under Claim VI the arbitrator has passed an award stating that the materials should be returned to the contractor. The approximate costs of the materials has been given as Rs 3,71,000 by the contractor. Once again, it has to be stated that if the sole arbitrator has come to the conclusion that the default was on the part of the contractor, he is not justified in directing the Union of India to hand over the materials. Since he has come to the conclusion that the Union of India is responsible for the breach of contract, the sole arbitrator has directed the Union of India to return the materials as the Union of India cannot take recourse under Condition 54 of the General Conditions of the Contract IAFW 2249. In the background of this we have now considered the amount awarded to the Union of India under Claims 1, 2 and 4; under Claim 1 Rs 33,64,000 has been awarded by the sole arbitrator towards extra expenditure involved to complete the incomplete item of work left by the defaulting contractor. Once again going back to contractor's claim under Claim 6(n) it is clear that the findings of (end of the original's 31st page) the arbitrator under Claim V of ‘A’ claim of the contractor and Claim 1 of ‘B’ of the Government of India is inconsistent. Since the arbitrator has already come to the conclusion that the breach of contract was due to the first respondent and has directed the Union of India to return the materials to the contractor, the sole arbitrator should not have awarded Rs 33,64,000 towards excess expenditure involved to complete the incomplete items of work left by the defaulting contractor. On the face of it, the arbitrator's award of Rs 33,64,000 under Claim 1 of ‘B’ claim of the Government is not sustainable.
    Since the award of Rs 33,95,000 by the sole arbitrator is inconsistent and is a misconduct, the order of the arbitrator in respect of Claim 1 of ‘B’ claim of the Union of India in the award dated 6-2-1986 has to be set aside.”

    10. Aggrieved thereby three appeals being AAO No. 364 of 1995, AAO No. 366 of 1995 and AAO No. 367 of 1995 were filed by the appellant against the order of the District Court dated 21-2-1994 in OP No. 29 of 1986, OS No. 31 of 1986 and OS No. 47 of 1986 respectively.

    11. By reason of the impugned judgment dated 6-1-1997 the said appeals were dismissed.

    12. It, however, appears that the appellants herein also filed SLPs (Civil) Nos. … 8317-18 of 1997 arising out of the judgment and order dated 6-1-1997 in Appeals Nos. 242 and 243 of 1995 of the High Court of Madras questioning the award made in favour of the first respondent herein. The same was dismissed by this Court by an order dated 24-11-1997.

    13. Mr N.N Goswami, the learned Senior Counsel appearing on behalf of the appellant would submit that the High Court as also the District Judge committed a manifest error in setting aside the award made by the arbitrator in favour of the appellant insofar as it failed to take into consideration that the award was a non-speaking one.

    14. The learned counsel would contend that the appellant could be blamed for making delay in the matter and completion of job till 1982 but no finding has been arrived at nor could be arrived at on the basis of materials on record that thereafter it was at fault. No material has been shown in the impugned judgments which support the views taken by the courts below that the appellant was responsible for the delay caused beyond 31-12-1982. Mr Goswami would urge that the District Judge had no jurisdiction to analyse the materials on record as if it has an appellate jurisdiction over the award of the arbitrator. The learned counsel would contend that the jurisdiction of the High Court in setting aside an award being limited, the impugned judgments cannot be sustained. In support of the said contention, strong reliance has been placed on Sudarsan Trading Co. v. Govt. of Kerala (1989) 2 SCC 38.

    15. Mr M.N Rao, the learned Senior Counsel appearing on behalf of the respondent, per contra, would submit that a finding of fact has been arrived at to the effect that the award of the arbitrator was inconsistent. The learned counsel would submit that while considering the validity or otherwise of an award the court is not precluded from considering the totality of the circumstances. It was pointed out that having regard to the fact that the appellant admitted the delay of 1654 days on its part, the same ought to have been taken into consideration by the arbitrator, which was relevant for resolution of the dispute between the parties. The claims raised by the appellant based on the purported breach of contract on the part of the first respondent herein must be held to be mala fide. The learned counsel has placed strong reliance in support of his contention on Dandasi Sahu v. State of Orissa (1990) 1 SCC 214.

    16. The short question which arises for consideration in these appeals is as to whether the District Judge and the High Court, Madras exceeded their jurisdiction in passing the impugned judgments.

    17. It is not in dispute that the claims and counter-claims of the parties centred around determination by the arbitrator as to whether the appellant or the first respondent had committed a breach of contract. The power of the appellant to terminate the contract and to put forth the claim for extra expenditure involved to complete the incomplete items of work left out by the first respondent revolved around the issue as to whether it was a defaulter or not. The appellant could terminate the contract and get the work completed through another agency entitling it to lay the said claim, but its justifiability therefor indisputably would depend upon the interpretation of clause 54 of the contract. The said clause empowers the appellant to cancel the contract, only if the contractor “fails to complete the works, work order and items of work, with individual dates for completion, and clear the site on or before the date of completion”. Thus, the “failure” must be on the part of the contractors and not by reason of acts of omissions and commissions of the appellant herein.

    18. The following was furthermore contained in the said clause:

    “The Government shall also be at liberty to use the materials, tackle, machinery and other stores on site of the contractor as it thinks proper in completing the work and the contractor will be allowed the necessary credit. The value of the materials and stores and the amount of credit to be allowed for tackle and machinery belonging to the contractor and used by the Government in completing the work shall be assessed by the GE and the amount so assessed shall be final and binding.
    In case the Government completes or decides to complete the works or any part thereof under the provision of this condition, the cost of such completion to be taken into account in determining the excess cost to be charged to the contractor under the condition shall consist of the cost or estimated cost (as certified by GE) of materials purchased or required to be purchased and/or the labour provided or required to be provided by the Government as also the cost of the contractor's materials used with an addition of such percentage to cover superintendence and establishment charges as may be decided by the CWE, whose decision shall be final and binding.”

    19. The said clause could, thus, be invoked only on default on the part of the contractor and not otherwise.

    20. Apart from the findings of the District Judge, as noticed hereinbefore, the High Court also came to the conclusion that the contract could not have been terminated after the date of completion of work holding:

    “… Misconduct as defined under Section 30 is not a moral lapse. If the arbitrator on the face of the award arrives at an inconsistent conclusion, it would also amount to misconduct as per the decision reported in K.P Poulose v. State of Kerala (1975) 2 SCC 236, AIR 1975 SC 1259. Therefore, the finding of the learned District Judge that there is an inconsistent conclusion by the arbitrator who has admitted the delay on the part of the Government in my opinion is well founded. It is more so, when the Government has not chosen to set aside that portion of the award which implies that there is delay on the part of the Government.”

    21. The High Court further opined:

    “Clause 54 of the agreement provides for utilisation of the materials, machinery, tackle etc. for completion of the incomplete work and sell the same at any time and appropriate the sale proceeds towards the loss which may arise from the cancellation of the contract. In the case on hand, the cancellation of the contract is after the expiry of the time contended for completion of the contract. The materials, machineries etc. were ordered to be returned to the contractor or pay the costs of the same to the contractor. The non-utilisation of the materials has not been taken into consideration by the arbitrator. It is contended that no payment was made for the machineries and the contractor was at liberty to take in back the machineries and therefore the non-utilisation of the materials cannot be said to be a conduct which would absolve the liability of the Government. But, this contention is not tenable since when the contractor has attempted to remove the materials on the work it has been prevented and a complaint has also been lodged with the police. Therefore, awarding certain sum towards loss sustained by the Government on account of the delay said to have been committed by the contractor, is inconsistent with the award granted in favour of the contractor to get back the materials or value thereof from the Government. When the order of the arbitrator is inconsistent, it amounts to a misconduct. Therefore, the learned District Judge has rightly set aside Claim 1 under ‘B’ claim of the Government and I am of the opinion that it is not a matter to be interfered with by this Court.”

    22. It is not the case of the appellant that the contractor was allowed to work after 31-12-1982 on grant of further extension for the completion of the work. The rights and obligations of the parties were, thus, required to be considered as on the said date and not thereafter. The fact that there had been delay of 1654 days on the part of the appellant in accepting the designs and there had been an amendment of the schedule of the work stands admitted.

    23. The question as to whether one party or the other was responsible for delay in causing completion of the contract job, thus, squarely fell for consideration before the arbitrator. The arbitrator could not have arrived at a finding that both committed breaches of the terms of contract which was ex facie unsustainable being wholly inconsistent. Clause 54 of the contract could be invoked only when the first respondent committed breach of the terms of the contract. An action in terms thereof could be taken recourse to in its entirety or not at all. If one part of the award is inconsistent with the other and furthermore if in determining the disputes between the parties the arbitrator failed to take into consideration the relevant facts or based his decision on irrelevant factors not germane therefor; the arbitrator must be held to have committed a legal misconduct.

    24. In Bharat Coking Coal Ltd. v. Annapurna Construction (CA Nos. 5647-48 of 1997, dt. 29-8-2003) (2003) 8 SCC 154 this Court noticed:

    “19. So far as these items are concerned, in our opinion, the learned sole arbitrator should have taken into consideration the relevant provisions contained in the agreement as also the correspondences passed between the parties. The question as to whether the work could not be completed within the period of four months or the extension sought for on one condition or the other was justifiable or not, are relevant facts which were required to be taken into consideration by the arbitrator.
    20. It is now well settled that the arbitrator cannot act arbitrarily, irrationally, capriciously or independent of the contract.
    21. In Associated Engg. v. Govt. of A.P (1991) 4 SCC 93 this Court clearly held that the arbitrators cannot travel beyond the parameters of the contract. In Sudarsan Trading Co. v. Govt of Kerala (1989) 2 SCC 38 this Court has observed that an award may be remitted or set aside on the ground that the arbitrator in making it had exceeded his jurisdiction and evidence of matters not appearing on the face of it, will be admitted in order to establish whether the jurisdiction had been exceeded or not, because the nature of the dispute is something which has been determined outside the award, whatever might be said about it in the award by the arbitrator. This Court further observed that an arbitrator acting beyond his jurisdiction is a different ground from the error apparent on the face of the award.
    22. There lies a clear distinction between an error within the jurisdiction and error in excess of jurisdiction. Thus, the role of the arbitrator is to arbitrate within the terms of the contract. He has no power apart from what the parties have given him under the contract. If he has travelled beyond the contract, he would be acting without jurisdiction, whereas if he has remained inside the parameters of the contract, his award cannot be questioned on the ground that it contains an error apparent on the face of the record.”

    25. It was held that if the arbitrator has committed a jurisdictional error, the court can intervene. This Court in Bharat Coking Coal Ltd. (2003) 8 SCC 154 noticed its earlier decision in K.P Poulose v. State of Kerala (1975) 2 SCC 236, AIR 1975 SC 1259 wherein it was observed that the case of legal misconduct would be complete if the arbitrator on the face of the award arrives at an inconsistent conclusion even on his own finding or arrives at a decision by ignoring the very material documents which throw abundant light on the controversy to help a just and fair decision.

    26. In Union of India v. Jain Associates (1994) 4 SCC 665 this Court upon following K.P Poulose (1975) 2 SCC 236, AIR 1975 SC 1259 and Dandasi Sahu (1990) 1 SCC 214 held:

    “8. The question, therefore, is whether the umpire had committed misconduct in making the award. It is seen that Claims 11 and 12 for damages and loss of profit are founded on the breach of contract and Section 73 encompasses both the claims as damages. The umpire, it is held by the High Court, awarded mechanically, different amounts on each claim. He also totally failed to consider the counter-claim on the specious plea that it is belated counter-statement. These facts would show, not only the state of mind of the umpire but also non-application of the mind, as is demonstrable from the above facts. It would also show that he did not act in a judicious manner objectively and dispassionately which would go to the root of the competence of the arbitrator to decide the disputes.”

    27. In Dandasi Sahu (1990) 1 SCC 214 this Court held that the award suffering from non-application of mind by the arbitrator is liable to be set aside. It was held:

    “In this connection we have to keep in mind that we are concerned with a situation where the arbitrator need not give any reason and that even if he commits a mistake either in law or in fact in determining the matter referred to him, where such mistake does not appear on the face of the award, the same could not be assailed. The arbitrator, in the case of a reference to him in pursuance of an arbitration agreement between the parties, being a person chosen by parties is constituted as the sole and the final judge of all the questions and the parties bind themselves as a rule to accept the award as final and conclusive. The award could be interfered with only in limited circumstances as provided under Sections 16 and 30 of the Arbitration Act. In this situation we have to test the award with circumspection. Even with all these limitations on the powers of court and probably because of these limitations, we have to hold that if the amount awarded was disproportionately high having regard to the original claim made and the totality of the circumstances it would certainly be a case where the arbitrator could be said to have not applied his mind amounting to legal misconduct.”

    28. In Sudarsan Trading Co. (1989) 2 SCC 38 this Court clearly held that the court can look to the agreement where the question arises as to whether an award may be remitted or set aside on the ground that the arbitrator in making it has exceeded its jurisdiction. Drawing distinction between the disputes as to the jurisdiction of the arbitrator and the dispute as to in what way that jurisdiction should be exercised, this Court opined:

    “29. The next question on this aspect which requires consideration is that only in a speaking award the court can look into the reasoning of the award. It is not open to the court to probe the mental process of the arbitrator and speculate, where no reasons are given by the arbitrator, as to what impelled the arbitrator to arrive at his conclusion. See the observations of this Court in Hindustan Steelworks Construction Ltd. v. C. Rajasekhar Rao (1987) 4 SCC 93. In the instant case the arbitrator has merely set out the claims and given the history of the claims and then awarded certain amount. He has not spoken his mind indicating why he has done what he has done; he has narrated only how he came to make the award. In absence of any reasons for making the award, it is not open to the court to interfere with the award. Furthermore, in any event, reasonableness of the reasons given by the arbitrator, cannot be challenged. Appraisement of evidence by the arbitrator is never a matter which the court questions and considers. If the parties have selected their own forum, the deciding forum must be conceded the power of appraisement of the evidence. The arbitrator is the sole judge of the quality as well as the quantity of evidence and it will not be for the court to take upon itself the task of being a judge on the evidence before the arbitrator. See the observations of this Court in Municipal Corpn. of Delhi v. Jagan Nath Ashok Kumar (1987) 4 SCC 497.”

    29. In that case the Court was concerned with the first issue and not the second one wherewith we are concerned herein. In the fact situation obtaining therein the Court distinguished a large number of authorities placed before it holding:

    “But, in the instant case the court had examined the different claims not to find out whether these claims were within the disputes referable to the arbitrator, but to find out whether in arriving at the decision, the arbitrator had acted correctly or incorrectly. This, in our opinion, the court had no jurisdiction to do, namely, substitution of its own evaluation of the conclusion of law or fact to come to the conclusion that the arbitrator had acted contrary to the bargain between the parties.”

    30. Such is not the position here.

    31. In this case the District Judge as also the High Court of Madras clearly held that the award cannot be sustained having regard to the inherent inconsistency contained therein. The arbitrator, as has been correctly held by the District Judge and the High Court, committed a legal misconduct in arriving at an inconsistent finding as regards breach of the contract on the part of one party or the other. Once the arbitrator had granted damages to the first respondent which could be granted only on a finding that the appellant had committed breach of the terms of contract and, thus, was responsible therefor, any finding contrary thereto and inconsistent therewith while awarding any sum in favour of the appellant would be wholly unsustainable being self-contradictory.

    32. The Union of India while accepting the award made in favour of the first respondent must be held to have accepted the finding that it committed a breach of contract and the said finding has attained finality and would operate as res judicata in view of the decision of this Court in Sheodan Singh v. Daryao Kunwar AIR 1966 SC 1332, (1966) 3 SCR 300.

    33. Furthermore, as noticed hereinbefore, the appeal preferred by the appellant against the award of the arbitrator made in favour of the first respondent herein has been dismissed.

    34. In Premier Tyres Ltd. v. Kerala SRTC 1993 Supp (2) SCC 146 this Court held:

    “4. … The question is what happens where no appeal is filed, as in this case from the decree in connected suit. Effect of non-filing of appeal against a judgment or decree is that it becomes final. This finality can be taken away only in accordance with law. Same consequences follow when a judgment or decree in a connected suit is not appealed from.
    5. Mention may be made of a Constitution Bench decision in Badri Narayan Singh v. Kamdeo Prasad Singh AIR 1962 SC 338, (1962) 3 SCR 759. In an election petition filed by the respondent a declaration was sought to declare the election of appellant as invalid and to declare the respondent as the elected candidate. The tribunal granted first relief only. Both appellant and respondent filed appeals in the High Court. The appellant's appeal was dismissed but that of respondent was allowed. The appellant challenged the order passed in favour of respondent in his appeal. It was dismissed and preliminary objection of the respondent was upheld. The Court observed:
    ‘We are therefore of opinion that so long as the order in the appellant's Appeal No. 7 confirming the order setting aside his election on the ground that he was a holder of an office of profit under the Bihar Government and therefore could not have been a properly nominated candidate stands, he cannot question the finding about his holding an office of profit, in the present appeal, which is founded on the contention that that finding is incorrect.’ ”

    35. As the appellant failed to get that part of the award which was made by the arbitrator in favour of the first respondent set aside, the basic conclusion of the High Court cannot be faulted. The Court upon setting aside the whole award could have remitted back the matter to the arbitrator in terms of Section 16 of the Act or could have appointed another arbitrator, but at this juncture no such order can be passed as the award in part has become final.

    36. For the reasons aforementioned, we are of the opinion that the impugned judgment does not suffer from any legal infirmity. These appeals are, therefore, dismissed. No costs.