Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • provisions of sec. 74 of the contract Act.
  • sec. 74, Contract Act of 1872,
  • sec. 74 of the Contract Act
  • sec. 74, Contract Act,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • provisions of sec. 74 of the contract Act.
  • sec. 74, Contract Act of 1872,
  • sec. 74 of the Contract Act
  • sec. 74, Contract Act,
Smart Summary

Legal Opinion Summary

Factual and Procedural Background

This is a second appeal brought by the defendants Rameshwarlal and Gopi Kishan in a suit for damages originally instituted by the plaintiff Balabux. On 16-3-1962 the parties entered into an agreement (Ex. 1) under which the defendants agreed to sell to the plaintiff plots Nos. 1 to 12 (3,158 sq. yds.) and a bungalow at Ajmer. The bungalow price was Rs. 13,000 and the plots at Rs. 11.75 per sq. yd. The plaintiff paid Rs. 5,000 as earnest money. The agreement was executed by the defendants on their own behalf and on behalf of their brother's widow Mst. Ajodhia Bai, who was at Indore. Completion was to occur within one month, with the remaining purchase money to be paid by the vendee.

The agreement provided reciprocal remedies on breach: if the vendors failed to complete the sale they would refund the earnest money and pay Rs. 5,000 as damages to the vendee; if the vendee failed, the Rs. 5,000 earnest money would be forfeited.

On 14-12-1962 the plaintiff sued for recovery of earnest money (Rs. 5,000) and the stipulated damages (Rs. 5,000), alleging that the defendants breached the contract by failing to secure the widow's signature, failing to execute the sale-deed within one month, and that prior agreements in favour of other persons were disclosed to the plaintiff. The defendants admitted executing Ex. 1 but defended mainly on (1) that time was not the essence and the plaintiff had backed out, and (2) that the additional Rs. 5,000 was governed by section 74 of the Contract Act.

The trial court held the defendants responsible for the breach and decreed Rs. 10,000 (earnest money plus the Rs. 5,000 damages). On appeal the defendants challenged only the award of the Rs. 5,000 damages; the District Judge affirmed the decree, relying on the case of Badhava Singh v. Charan Singh. The defendants then preferred the present second appeal.

Legal Issues Presented

  1. Whether the claim for Rs. 5,000 named in the agreement as payable on breach was recoverable as reasonable compensation under section 74 of the Indian Contract Act, or whether it was a penalty (and thus not recoverable simpliciter).
  2. If section 74 applies, whether the plaintiff had pleaded and proved either actual loss or that the Rs. 5,000 was a genuine pre-estimate of damages so as to entitle him to that sum without proving actual damage.
  3. What heads of loss, if any, the plaintiff was entitled to recover as consequences of the defendants' breach (including refund of earnest money, interest, and other claimed expenditures).

Arguments of the Parties

Defendant-Appellants' Arguments

  • The covenant entitling the plaintiff to Rs. 5,000 in addition to refund of earnest money is in the nature of a penalty; to recover that amount the plaintiff must establish actual loss and that Rs. 5,000 is reasonable compensation in the opinion of the court.
  • The plaintiff's plaint claimed damages only for loss of interest on Rs. 50,000 kept ready and loss of interest on Rs. 5,000; the plaintiff did not plead that he intended to construct a cinema on the suit property or that he demolished a bungalow because of the breach—those facts emerged for the first time in the plaintiff's affidavit/witness statement.
  • The demolition of the bungalow occurred after the suit was filed and therefore could not be a consequence of the defendants' breach; the expenditure on demolition cannot be treated as arising from the breach and so cannot form the basis of the Rs. 5,000 damages.

Plaintiff-Respondent's Arguments

  • Reliance on section 74 of the Contract Act: the agreement named Rs. 5,000 payable on breach and this sum represented a genuine pre-estimate of the damage likely to be suffered; hence the plaintiff was entitled to recover the Rs. 5,000 irrespective of proving actual loss.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Maulabux v. Union of India Interpretation of section 74: where actual monetary loss can be ascertained the claimant must prove it; where the court cannot assess compensation the sum named may be taken as a genuine pre-estimate provided it is not a penalty. The court applied this principle to hold that because the plaintiff's pleaded losses made assessment possible, he should have proved actual loss or shown the Rs. 5,000 was a genuine pre-estimate. The court found no evidence that Rs. 5,000 was a genuine pre-estimate and therefore declined to award the contractual sum merely because it was specified.
Bhai Panna Singh v. Bhai Arjun Singh Illustrates that under section 74 plaintiffs cannot recover the liquidated sum simpliciter; they must prove the damages actually suffered (example: loss on resale). Used to support the principle that named sums are not automatically payable; the court cited this case as authority that evidence of actual loss is required when the loss can be ascertained.
Fateh Chand v. Balkishan Forfeiture or stipulated sums must be assessed against evidence of loss; arbitrary percentages of the contract value cannot be awarded without proof of damage. The court relied on this authority to reject awarding a large contractual sum without proof of loss and to hold that only the earnest money and the benefits derived by the defaulting party should be considered if no special damages are shown.
Badhava Singh v. Charan Singh Shows circumstances where a named sum may be reasonable compensation: where re-sale fetched an excess equal to the damages specified in the agreement. The court distinguished this case from the present facts: in Badhava Singh the re-sale produced an excess which justified the specified sum, whereas no such fact existed here; thus Badhava Singh did not support the award of Rs. 5,000 on the present facts.

Court's Reasoning and Analysis

The court framed the sole controversy as whether the Rs. 5,000 named in the agreement as payable on breach was properly decreed under section 74 of the Contract Act. The court set out the text of section 74 and then applied the interpretive guidance from Maulabux v. Union of India: where loss in money terms can be ascertained the claimant must prove actual loss; where the court cannot assess compensation the named sum may be used if it is not in the nature of a penalty and is a genuine pre-estimate.

The court examined the plaintiff's pleadings and evidence. It found that the plaintiff's pleadings (para 8 of the plaint) alleged two heads of loss: (1) that he had kept nearly Rs. 50,000 ready to cover the sale price; and (2) loss of interest on the amount advanced (earnest money). The court observed that the plaintiff had not pleaded nor produced material showing that Rs. 5,000 was fixed as a genuine pre-estimate of damage, nor that any resale or increase in value had caused a loss to that amount. The court therefore concluded that the lower courts' finding that Rs. 5,000 was a genuine pre-estimate was unsupported by evidence.

Applying the precedents (Bhai Panna Singh and Fateh Chand), the court emphasized that contractual stipulations for fixed sums do not entitle a claimant to that sum without proof of loss when loss can be ascertained by ordinary rules. The court rejected the reliance on Badhava Singh because that case turned on facts (re-sale at a higher price producing an excess equal to the stipulated sum) not present here.

Given the pleadings and evidence, the court held that the plaintiff was entitled to recover the earnest money (Rs. 5,000) and interest thereon because the defendants had the use of that sum. Looking at market rates for 1962–1965, the court found 12% per annum reasonable and computed interest on Rs. 5,000 from 16-3-62 to 30-7-65 as Rs. 2,025. The plaintiff also claimed he had kept Rs. 40,000–50,000 ready; the court awarded one month's interest on Rs. 40,000 at 12% (Rs. 400) for the period up to receipt of telegrams on 14-4-62.

The court declined to award Rs. 4,000 allegedly spent in dismantling the plaintiff's bungalow because (a) the plaint did not plead this expenditure and (b) the court did not consider that expense to have been incurred in consequence of the defendants' breach.

On these bases the court recalculated the proper decretal amount and modified the decree accordingly. The court also set the rate of post-decree interest (6% per annum from the date of the trial court decree till realization) and ordered costs to the plaintiff in this court and the courts below. Finally, the court refused leave to appeal to the Division Bench.

Holding and Implications

HOLDING: The appeal is allowed in part. The court modified the decree so that the total decretal amount is reduced from Rs. 10,000 to Rs. 7,425. The components awarded by the court are:

  • Refund of earnest money: Rs. 5,000 (acknowledged entitlement).
  • Interest on Rs. 5,000 from 16-3-62 to 30-7-65 at 12% p.a.: Rs. 2,025.
  • One month's interest on Rs. 40,000 at 12% p.a.: Rs. 400.
  • Total decretal sum: Rs. 7,425.

The decretal amount shall carry interest at 6% per annum from the date of the trial court's decree until realization. Defendant-appellants are ordered to pay costs to the plaintiff in this court and in both courts below. Leave to appeal to the Division Bench is refused.

Implications: The court applied section 74 and established on these facts that where the claimant could have his loss ascertained by ordinary means he must plead and prove the loss; a contractual sum named as payable on breach will not be awarded merely because it is specified unless it is shown to be a genuine pre-estimate or the loss cannot be assessed. The court did not set aside the principle in section 74 but applied existing precedents to deny recovery of the contractual Rs. 5,000 as a lump sum in the absence of pleading and proof. No broader or novel precedent was created; the decision adjusts the relief granted to the plaintiff to the proven and properly pleaded losses and interest.

This summary is confined strictly to matters appearing in the provided opinion and does not add or infer facts beyond that text.

    Rameshwarlal v. Bala Bux Tamra

    Modi, J.:— This is a second appeal by the defendants Rameshwarlal and Gopi Kishan in a suit for damages.

    2. On 16-3-1962 the defendants had entered into an agreement with the plaintiff Balabux by which the former agreed to sell to the latter plots Nos. 1 to 12 measu-ring 3158 sq. yds. and a bungalow situated in Ajmer. The bungalow was agreed to be sold for Rs. 13,000/- and the plots at the rate of Rs. 11.75 per sq. yds. The plaintiff paid Rs. 5,000/- as earnest money. The agreement was executed by the defendants on their own behalf and on behalf of their brother's widow Mst. Ajodhia Bai, who was at Indore. The sale was to be completed within one month when the remaining purchase money was to be paid by the vendee. It was agreed between the parties that if the vendors failed to complete the sale they would be liable to refund the earnest money and further pay a sum of Rs. 5,000/- as damages for the breach of contract. It was also agreed that in case the vendee failed to complete the sale, he will be liable to forfeiture of the earnest money amounting to Rs. 5,000/-. On 14-12-62 the plaintiff instituted the present suit for recovery of earnest money amounting to Rs. 5,000/- and the stipulated damages amounting to Rs. 5,000/-, total Rs. 10,000/- on the ground that the defendants had broken the contract. It was alleged that the defendants failed to get the signature of their brother's widow on the agreement Ex. 1; that they failed to execute the sale-deed within the stipulated period of one month; and that during this period the plaintiff received notices from two persons in whose favour certain portions of the land sought to be sold to the plaintiff had been earlier agreed to be sold to others by the defendants. The defendants admitted having executed the agreement Ex. 1 dt. 16-3-62. They resisted the suit mainly on two grounds—(1) that time was not the essence of the contract and it was the plaintiff who backed out from the contract and (2) that the claim for damages amounting to Rs. 5,000/- over and above the refund of earnest money was not liable to be decreed in view of the provisions of sec. 74 of the Contract Act. The trial judge held that the defendants and not the plaintiff were responsible for the breach of contract. It has been further held that the plaintiff was entitled to recover the amount of earnest money as well as the sum of Rs. 5,000/- named in Ex. 1 as damages. The su:t was accordingly decreed for Rs. 10,000/-. On appeal, the defendant-appellants did not challenge the trial court's finding that the defendants were responsible for the breach of contract. The only point that was urged before the appellate court was that the plaintiff was not entitled to recover the amount of Rs. 5,000/- claimed as damages. The learned District Judge placing reliance on the principles laid down in the case of Badhava Singh v. Charan Singh(1) affirmed the decree passed by the trial court and dismissed the appeal. The reasons which persuaded the learned District Judge to dismiss the appeal are contained in paras 3 and 9 of the judgment. They run as follows—

    “8. Applying the above principles to the present case, it is to be noted that it has been stipulated in agreement Ex. 1 that either party in the event of breach would be liable to pay a sum of Rs. 5,000/- to the other by way of damages. In the case of breach by the vendors, they were held liable to refund the earnest money and were to pay a sum of Rs. 5,000/- as damages to the vendee and in case of breach on the part of the vendee the amount of Rs. 5,000/- as earnest money with the vendors was to be forfeited. The question to be considered is whether the amount of Rs. 5,000/- as damages for the breach by the vendors would be termed as “reasonable compensation.” The plaintiff's version is that he wanted to construct a cinema house on the piece of land covered by Ex. 1 and that he had to incur heavy loss because of the defendants' failure to have completed the contract as he was forced to dismantle his own bungalow for the construction of a cinema house called Ajanta Cinema. The bungalow, which was dismantled by the plaintiff for the construction of a cinema-house had also been purchased by the plaintiff from these very defendants some-time back for a sum of Rs. 32,000/-. Defendant Rameshwarlal does not deny the fact of the sale of the bungalow to the plaintiff. He has also admitted that the said bungalow has been got dismantled by the plaintiff and a cinema house has been constructed. The cost of dismantling alone was not less then Rs. 4,000/-. Besides, the plaintiff had to keep ready money either at his house or at the bank to the tune of Rs. 50,000/- to meet the cost of the land and the house covered by Ex. 1. To that extent, the plaintiff was deprived to utilise the money in his, business.

    9. The estimate of damages amounting to Rs. 5,000/- seems very much a reasonable compensation for the breach and cannot be characterised as a sum fixed in terrorem. If the plaintiff had committed the breach, he would have lost Rs. 5,000/- which he had advanced as earnest money. It was likewise provided that if the defendants committed the breach they would as well be liable to pay damages amounting to Rs. 5,000/-. The plaintiff had to demolish his own residential bungalow, which he had purchased from the very defendants at a cost of Rs. 32,000/- on account of the breach of agreement Ex. 1 the suggestion on behalf of the defendants that the plaintiff purchased that bungalow for construction of the cinema house does not seem to be true. Had it been so, there would have hardly been any necessity for the plaintiff to again enter into the deal contained in Ex. 1, by which the plaintiff purported to purchase the piece of land for the construction of a cinema house with necessary facilities of car parking, cycle stand etc. These facilities could not be provided on the site where the plaintiff has constructed the cinema after demolishing his bungalow. The plaintiff had also to keep block amount equivalent to the purchase money covered by Ex. 1 The trial court's finding that the amount of Rs. 5,000/- claimed by the plaintiff as damages is quite reasonable and is not in terrorem seems to be justified and does not call for any interference by this Court.”

    Having lost in the appellate court the defendants have preferred this second appeal.

    3. Learned Advocate for the defendant-appellants has not challenged the plaintiff's right to claim refund of Rs. 5,000/- paid to the defendants as earnest money. His sole contention in this appeal is that the courts below committed gross error in awarding a decree for Rs. 5,000/- as damages. It is contended that the covenant which gave to the plaintiff the right to claim Rs. 5,000/- as damages in addition to the refund of the earnest money is a stipulation in the nature of penalty and the plaintiff can get that amount or part thereof, if he establishes that in consequence of breach of contract he suffered loss and that in the opinion of the court the amount of Rs. 5,000/- is a reasonable compensation for that loss. Learned counsel next contends that the learned District Judge completely ignored the allegations contained in the plaint with regard to the quantum of loss suffered by the plaintiff. It is argued that in the plaint the plaintiff claimed damages on the ground that he suffered loss of interest on the amount of Rs. 50,00/-, which he had to keep with him ready cash to cover the sale price and loss of interest on Rs. 5,000/-, which he had paid to the defendants as earnest money. It is further argued that neither in the agreement Ex. 10 nor in the plaint it was mentioned that the plaintiff wanted to construct any cinema house on the suit property and on account of breach of contract he had to demolish his own bungalow for construction of a cinema house and thereby he suffered a loss of Rs. 5,000/- or more. It is urged that these facts were disclosed by the plaintiff for the first time when he appeared in the witness box as P.W 1. It is also urged that the demolition of the bungalow by the plaintiff took place after the filing of the suit and, therefore, it had nothing to do with the breach of contract. The alleged loss incurred by the demolition of the bungalow, in any case, cannot be deemed as arising in consequence of the breach of contract. It has been further argued that in these circumstances the plaintiff cannot claime damages on that account.

    4. In reply, the learned counsel for the plaintiff-respondent relied on sec. 74, Contract Act, and urged that in the present case a sum of Rs. 5000/- was named in the agreement Ex. 1 as payable on breach of contract to the party not guilty of the breach. It was a genuine pre estimate of damages which a party complaining of the breach was likely to suffer as a result of the breach. The plaintiff in the circumstances was rightly held entitled to recover that amount irrespective of the fact whether or not he succeeded in proving the actual damage or loss.

    5. The sole controversy for determination between the parties is as to whether the claim for damages to the tune of Rs. 5,000/- was rightly decreed by the courts below in the light of sec. 74 of the Contract Act which reads as under:

    “74. When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.”

    6. This section provides that where a sum in named in the agreement as payable on breach, the party complaining of the breach is entitled, “whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation” subject to the amount named therein being the maximum. The expression “the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby” came for interpretation before their Lordships of the Supreme Court in Maulabux v. Union of India(2), J.C Shah, Acting Chief Justice, as he then was, observed,—

    “It is true that in every case of breach of contract the person aggrieved by the breach is not required to prove actual loss or damage suffered by him before he can claim a decree and the Court is competent to award reasonable compensation in case of breach even if no actual damage is proved to have been suffered in consequence of the breach of contract. But the expression “whether or not actual damage or loss is proved to have beer caused thereby” is intended to cover different classes of contracts which come before the Courts. In case of breach of some contracts it may be impossible for the Court to assess compensation arising from breach, while in other cases compensation can be calculated in accordance with established rules. Where the Court is unable to assess the compensation, the sum named by the parties if is to be regarded as a genuine pre-estimate may by taken into consideration as the measure of reasonable compensation but not if the sum named is in the nature of a penalty. Where loss in terms of money can be determined, the party claiming compensation must prove the loss suffered by him.”

    Sec. 74, therefore, contemplates that where loss in terms of money on account of breach of contract can be ascertained in accordance with the established rules, the party claiming compensation must prove the actual loss. If it fails to prove the actual loss in such a case it cannot be held entitled to the sum named in the agreement simply because such a sum is mentioned therein. It is only in those cases where the Court is unable to assess the actual loss that the sum named in the agreement may be taken into consideration provided the sum named be regarded as a genuine pre estimate damage or otherwise be a reasonable compensation for the breach. If on the other hand the Court comes to the conclusion that the amount so fixed was in terrorem, excessive or extravagant, the plaintiff would be entitled to only such sum as may appear to the court as reasonable. Both the courts below have held that the amount of Rs. 5,000/- specified in the agreement was a genuine pre-estimate of damages and was not fixed in terrorem. In my opinion this finding is based on no evidence. In the present case the plaintiff neither pleaded nor proved that sum of Rs. 5,000/- fixed in the agreement was a genuine pre-estimate of damages. No material has been placed on record by the plaintiff which may go to show that a breach by a party was likely to cause loss to the other party to the extent of Rs. 5,000/-. On the contrary the plaintiff in para No. 8 of the plaintiff claimed damages on two grounds,— (1) “the plaintiff had always kept a sum of nearly Rs. 50,000/- to cover the sale price”, and (2) “he lost interest on the amount already advanced” to the defendants as earnest money. The agreement Ex. 1 also does not suggest that the amount of Rs. 5,000/- specified therein was a genuine pre-estimate of damages. It is true that by the agreement each party was fastened to pay an equal sum of Rs. 5,000/- in the event of breach, but simply on that account it cannot be inferred that the amount specified in the agreement was a genuine pre-estimate of damages or was otherwise a reasonable compensation for the breach. The plaintiff in the present case made no attempt to show that the value of the property to be sold had increased subsequent to the date of the agreement. Again there is no evidence that the defendant sold the property to some other person at a higher price so that inference of loss suffered by the plaintiff may be assessed on that footing. In the absence of any pleading or proof, direct or circumstantial, on the question that the sum specified in the agreement was fixed as a genuine pre-estimate of damages or is otherwise a reasonable compensation, the plaintiff cannot be held entitled to the sum named in the agreement. The present contract is also not that type of a contract where it may be impossible for the court to assess compensation arising from the breach. On the contrary the plaintiff himself in the plaint pointed out the loss suffered by him and that shows not only that it was possible for the court to assess compensation, but also that he suffered no other loss than that pleaded by him. I may now cite a few cases where in similar circumstances the plaintiff was held entitled to the actual loss suffered by him for the breach of contract and not the sum specified in the contract.

    7. In Bhai Panna Singh v. Bhai Arjun Singh(3) there was a contract for sale of a building for Rs. 1,05,000/- and it was one of the conditions in the agreement that “the party retracting from the contract shall pay Rs. 10,000/- as Pashemana (damages).” The vendors eventually sold the building to another purchaser at Rs. 1,04,000-, as the vendee had broken the contract. The case ultimately went to the Privy Council and it was observed by their Lordships,—

    “The effect of sec. 74, Contract Act of 1872, is to disentitle the plaintiffs to recover simpliciter the sum of Rs. 10,000/- whether penalty or liquidated damages. The plaintiffs must prove the damages they have suffered. The only evidence of loss is that of the loss on resale by Rs. 1,000/-”

    8. In the case of Fateh Chand v. Balkishan(4) the vendor by agreement dated 21-3-49 agreed to sell his rights in the land and the building standing thereon for Rs. 1,12,500/- and Rs. 1,000/- were recovered by him as earnest money. The vendor agreed to deliver the property to the vendee on further payment of Rs. 24,000/- out of sale price on 30th March, 1949. The agreement provided that for any reason if the vendee failed to get the sale registered by 1.6.49, the amount of Rs. 25,000/- (Rs. 1,000 paid as earnest money and Rs. 24,000/- paid out of the sale price on delivery of possession) shall stand forfeited and the agreement shall be deemed cancelled and the vendees shall have to deliver back vacant possession of the property to the vendee. Likewise the agreement provided that if the contract is not completed on account of delay on the part of the vendor, the latter shall be liable to pay a sum Rs. 25,000/- as damages apart from the sum of Rs. 25,000/- received by him from the vendee. On March 25, 1949, the plaintiff-vendor received Rs. 24,000/- and delivered the possession of the property to the vendee, but the sale of the property could not be completed on or before the stipulated date due to the default of the vendee. The vendor then filed a suit for recovery of possession of the property alleging that the sum of Rs. 55,000/- paid to him by the vendee stood forfeited under the agreement. The question arose whether the plaintiff-vendor in the circumstances was entitled to forfeit the amount of Rs. 25000/-. Their Lordship of the Supreme Court held,—

    “There is no evidence that any loss was suffered by the plaintiff in consequence of the default by the defendant, save as to the loss suffered by him by being kept out of possession of the property. There is no evidence that the property had depreciated in value since the date of the contract provided; nor was there evidence that any other special damage had resulted. The contract provided for forfeiture of Rs. 25,000.consisting of Rs. 1,000/- paid as earnest money and Rs. 24,000/- paid as part of the purchase price. The defendant has conceded that the plaintiff was entitled to forfeit the amount of Rs. 1,000/- which was paid as earnest money. We can not however agree with the High Court that 13 per cent of the price may be regarded as reasonable compensation in relation to the value of the contract as a whole, as that in our opinion is assessed on an arbitrary assumption. The plaintiff failed to prove the loss suffered by him in consequence of the breach of the contract committed by the defendant and we are unable to find any principle on which compensation equal to ten per cent of the agreed price could be awarded to the plaintiff. The plaintiff has been allowed Rs. 1,000/- which was the earnest money as part of the damages. Besides he had use of the remaining sum of Rs. 24,000/-, and we can rightly presume that he must have been deriving advantage from that amount throughout this period. In the absence therefore of any proof of damage arising from the breach of the contract, we are of the opinion that the amount of Rs. 1,000/- (earnest money) which has been forfeited, and the advantage that the plaintiff must have derived from the possession of the remaining sum of Rs. 24,000/- during all this period would be sufficient compensation to him.”

    9. I would now like to refer Badhava Singh v. Charan Singh's case (1) relied upon by the learned District Judge. In that case the sum specified in the agreement as damages was held to be reasonable compensation, because it was found that on re-sale the defendant got price of the property in excess of the amount agreed upon by the party to the tune of the amount of damages specified in the agreement. This case is, therefore, clearly distinguishable.

    10. In my opinion in the circumstances of the case the plaintiff is entitled to the loss suffered by him in consequence of the breach of contract. Doubtless the plaintiff is entitled to recover the earnest money amounting to Rs. 5,000/- as also the interest thereon, as the defendants must have derived benefit on that amount. Looking to the prevailing market rate of interest during the period 1962-1965, the interest 12% per annum appears to be reasonable. The amount of Rs. 5,000/- was paid to the defendants as earnest money on 16-3-62. The trial court decreed the suit on 30th July, 1965. The amount of interest @ 12% on the sum of Rs. 5,000/- from 16-3-62 to 30-7-65 comes to Rs. 2,025/-. The plaintiff has in his statement that he kept with him ready cash to the tune of Rs. 40,000/- to Rs. 50,000/- to meet the sale price of the property. It is further deposed that he was willing to purchase the suit property upto the time he received telegrams informing him of prior agreements to sale of certain portions of the suit property. The telegrams were received by the plaintiff on 14-4-62. He is, therefore, entitled to a month's interest on a sum of Rs. 40,000/-, which comes to Rs. 400/- @ 12% per annum. The plaintiff has further deposed in his statement that he had incurred an expenditure of Rs. 4,000/- in dismantling his bungalow. In my opinion he cannot get this amount or part thereof for the simple reason that no allegation to that effect was made in the plaint. That apart this expenditure cannot be regarded to have been incurred in consequence of the breach of contract.

    11. In the result I allow the appeal partly and modify the decree passed by the trial court and affirmed by the appellate court by reducing the decretal amount from Rs. 10,000/- to Rs. 7,425/-. The decretal amount shall carry interest @ 6% per annum from the date of the decree passed by the trial court till realisation. The defendant-appellants shall pay costs to the plaintiff on the decretal amount in this court as well as in both the courts below.

    12. Learned counsel for the appellants prays for leave to appeal to Division Bench. The prayer is refused.