AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Order 21 Rule 23 read with Section 151 of the Code of Civil Procedure, 1908 (hereinafter referred
  • SECTION 3 INTEREST ACT
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Advocates
Judges
Acts
  • Order 21 Rule 23 read with Section 151 of the Code of Civil Procedure, 1908 (hereinafter referred
  • SECTION 3 INTEREST ACT
Smart Summary

Summary of Opinion — R.C. Chopra, J.

Factual and Procedural Background

This application was filed by the Judgement Debtor under Order 21 Rule 23 read with Section 151 of the Code of Civil Procedure, 1908, seeking dismissal or deferral of an execution petition on the ground that the decretal amount had been paid in full. The dispute concerned a claimed shortfall of Rs. 54,798/- as interest on the decretal amount calculated up to 10 November 2003.

Relevant procedural and factual points from the opinion:

  • An Arbitrator had awarded Rs. 7,30,083/- in favour of the Decree Holder, which included interest @ 15% per annum from 18.12.1991 to 10.8.1993 on the claims upheld.
  • An additional interest of Rs. 10,25,117/- accrued from 11.8.1993 to 19.12.2002, taking the total to Rs. 17,55,200/-.
  • The Court dismissed objections to the Award and ordered future interest @ 12% per annum w.e.f. 20.12.2002.
  • The Judgement Debtor made payment on 22.5.2003. The Decree Holder calculated that Rs. 88,866/- became due on the total decree at 12% p.a.; the Judgement Debtor paid only Rs. 36,984/-, having calculated future interest on Rs. 7,30,083/- (the principal claims) on the basis that interest should not be payable on interest.
  • The Decree Holder insisted that a balance of Rs. 54,798/- remained payable as interest @ 12% p.a. for the period from 20.12.2002 to 21.5.2003 (and the Court's final direction addressed interest up to 10.11.2003, including interest on the balance from 24.5.2003 to 10.11.2003).

Legal Issues Presented

  1. Whether interest can be calculated on interest awarded by an Arbitrator or a Court (i.e., whether pre-suit and pendente lite interest crystallize into the decretal amount and attract future interest).
  2. Whether the Judgement Debtor's payment (which excluded interest-on-interest) satisfied the decretal obligation, or whether the Judgement Debtor remained liable to pay the claimed balance of Rs. 54,798/-.

Arguments of the Parties

Judgement Debtor's Arguments

  • No interest is payable on interest; therefore, the amount paid by the Judgement Debtor fully discharged the decree/Award.

Decree Holder's Arguments

  • Relied on a Supreme Court judgement (Oil and Natural Gas Commission v. M.C Clelland Engineers, S.A (1999) 4 SCC P-327) holding that interest granted by an Arbitrator as interest on damages becomes part of the principal amount and Section 3 of the Interest Act does not forbid payment of such interest.
  • Relied on a Punjab & Haryana High Court decision (Union of India v. Harbans Singh Tuli & Sons Builders (P) Ltd., AIR 2000 P&H 313) which followed the Apex Court's view that interest on interest may be treated as interest on damages/compensation for delayed payment and forms part of the principal adjudged sum.
  • Insisted that the balance Rs. 54,798/- represents unpaid future interest on the entire decretal amount and is therefore payable by the Judgement Debtor.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
“Oil and Natural Gas Commission v. M.C Clelland Engineers”, S.A” (1999) 4 SCC P-327 The power of the Arbitrator to grant interest on the amount of interest (termed interest on damages/compensation for delayed payment) becomes part of the principal amount; Section 3 of the Interest Act does not forbid payment of such interest. The Court relied on this principle to hold that interest awarded before the decree crystallizes into the decretal amount and that future interest is payable on that entire amount (claims plus pre-suit and pendente lite interest).
“Union of India v. Harbans Singh Tuli & Sons Builders (P) Ltd.” AIR 2000 P&H 313 Affirmed and applied the Apex Court's view that interest on interest may be termed as interest on damages/compensation for delayed payment and becomes part of the principal sum adjudged. The Court noted this High Court decision as supportive authority and applied the same reasoning in concluding that future interest must be calculated on the total decretal sum, including previously awarded interest.

Court's Reasoning and Analysis

The Court's analysis proceeded as follows:

  1. After an Award is passed by an Arbitrator and objections to the Award are dismissed and a decree is passed in terms of that Award, the presuit and pendente lite interest awarded by the Arbitrator or the Court crystallizes into the decretal amount.
  2. Consequently, future interest (post-decree interest) must be calculated on the entire decretal sum — that is, on the claims upheld by the Arbitrator/Court plus any presuit and pendente lite interest that was awarded and has crystallized into the decree.
  3. The Court relied on the cited precedents to support the proposition that interest awarded as compensation for delayed payment can become part of the principal amount and is not barred by Section 3 of the Interest Act from attracting further interest.
  4. The Court rejected the Judgement Debtor's contention that interest cannot be calculated on interest and that the payment made discharged the decree. The Court reasoned that allowing a Judgement Debtor to withhold amounts so as to avoid interest on interest would permit exploitation and cause wrongful loss to the Decree Holder; courts should not permit parties to take such undue advantage.
  5. Applying these principles to the facts, the Court found that the Judgement Debtor remained liable to pay Rs. 54,798/- as interest on the decretal amount for the relevant period and directed payment forthwith, failing which coercive processes could be initiated.

Holding and Implications

Holding: The Court held that the Judgement Debtor is liable to pay a sum of Rs. 54,798/- on account of interest on the decretal amount for the period from 20.12.2002 to 10.11.2003 (including interest on the balance amount of interest from 24.5.2003 to 10.11.2003), and ordered that this amount be paid to the Decree Holder forthwith; failing payment, coercive process may be issued. EA No. 563/2003 was dismissed.

Implications: The direct effect is that the Judgement Debtor must pay the specified balance interest and that execution proceedings may continue with coercive measures if payment is not made. The decision applies existing Supreme Court and High Court authority to hold that presuit and pendente lite interest form part of the decretal amount and attract future interest; the opinion does not purport to create a new legal principle beyond the precedents relied upon.

    Saraswati Construction Co. Decree Holder v. Delhi Development Authrority Judgement Debtor

    R.C Chopra, J.:— This application by the Judgement Debtor under Order 21 Rule 23 read with Section 151 of the Code of Civil Procedure, 1908 (hereinafter referred to as “the code” only) is with the prayer to dismiss or defer the execution petition in view of the payment of full decretal amount to the Decree Holder.

    2. The controversy raised before this Court is in regard to a sum of Rs. 54,798/- which the Decree Holder claims to be due on account of interest on the decretal amount calculated up to 10th November, 2003. According to the Decree Holder, the Arbitrator had awarded a sum of Rs. 7,30,083/- in favour of the Decree Holder which included interest @ 15% per annum from 18.12.1991 to 10.8.1993 on the claims upheld by the Arbitrator. A further interest of Rs. 10,25,117/- also became due to the Decree Holder from 11.8.1993 to 19.12.2002 making the total amount Rs. 17,55,200/-. The Court while dismissing the objections filed by the Judgement Debtor against the Award ordered future interest @ 12% per annum w.e.f 20.12.2002 Since the payment was made by the Judgement Debtor on 22.5.2003, a further amount of Rs. 88,866/- became due to the Decree Holder on the total amount of decree @ 12% per annum but the Judgement Debtor paid interest of Rs. 36,984/- only calculating future interest on Rs. 7,30,083/- on the plea that the interest was payable on the amount claims only and not on the interest. The Decree Holder, however, insists that a sum of Rs. 54,798/- should be paid by the Judgement Debtor, which is the balance amount of interest @ 12% per annum from 20.12.2002 to 21.5.2003

    3. The objection of the Judgement Debtor is that the interest as claimed by the Decree Holder is not payable as no interest can be calculated on interest and as such, the entire amount under the decree/Award stands paid.

    4. Learned counsel for the Decree Holder has relied upon a judgement of Apex Court in “Oil and Natural Gas Commission v. M.C Clelland Engineers, S.A” (1999) 4 SCC P-327 in which their Lordships considered the question of interest on interest and held that the power of the Arbitrator to grant interest on the amount of interest, which may be termed as interest on damages or compensation for delayed payment, would also become part of the principal amount and as such, Section 3 of the Interest Act does not come into play to forbid the payment of such interest. He has also relied upon a judgement pronounced by a learned Single Judge of the Punjab & Haryana High Court in “Union of India v. Harbans Singh Tuli & Sons Builders (P) Ltd.” AIR 2000 P&H 313 in which the aforesaid judgement of the Apex Court was relied upon to hold that the interest on the amount of interest may be termed as interest on damages/compensation for delayed payment and would become part of the principal sum adjudged.

    5. In view of the aforesaid judgements, this Court is of the considered view that after the passing of an Award or the dismissal of the objections by the Court and passing a decree in terms of the Award, not only the amount of a claim upheld by the Arbitrator or the Court but the presuit and pendente lite interest awarded in favour of the Decree Holder crystallizes into the decretal amount and the future interest becomes payable on the entire amount comprised of the claims as well as the presuit and pendente lite interest. Therefore, from the date of the passing of the decree, the future interest is not to be calculated merely on the amount of the claims upheld by the Arbitrator/Court but also on the amount of the interest awarded by the Arbitrator or the Court. In many cases, as in the present case, the amount of interest up to the date of the passing of the Award or passing of the decree is much higher than the principal amount and in case a view is taken that the future amount is not payable on the amount of interest, a Decree Holder may be put to substantial monetary loss by an unscrupulous Judgement Debtor by withholding the amount and ultimately paying future interest only on the amount of claims. Courts cannot permit any party to take undue advantage of law and exploit legal provisions to cause wrongful loss to the opposite party.

    6. Under the circumstances, this Court has no hesitation in holding that the Judgement Debtor is liable to pay a sum of Rs. 54,798/- on account of interest on the decretal amount from 20.12.2002 to 10.11.2003 which includes interest on the balance amount of interest from 24.5.2003 to 10.11.2003 Let this amount be paid to the Decree Holder forthwith failing which, coercive process may be issued.

    7. EA No. 563/2003 stands dismissed.

    Use AI to get other relevant cases.

    Comments

    Saraswati Construction Co. Decree Holder v. Delhi Development Authrority Judgement Debtor
    (Jul 8, 2004)