Factual and Procedural Background

M/s. Saraya Distillery entered into a contract dated August 14, 1972, to supply 3,87,666 litres of rum to the Union of India at Rs. 2.13 per litre, to be delivered in five instalments between September 21, 1972, and January 21, 1973. The contractor supplied only 45,000 litres out of the first instalment and failed to deliver the remaining quantity despite extensions of time, constituting a breach of contract. The Union of India claimed damages amounting to Rs. 3,35,888/-, including Rs. 4,005/- for repurchase loss and the balance as general damages. The dispute was referred to arbitration under the contract's arbitration clause. The sole arbitrator awarded damages of Rs. 72,690.66 in favor of the Union of India. The Union of India filed a petition under Sections 14 and 17 of the Arbitration Act to make the award a rule of the court. The contractor objected under Sections 30 and 33 of the Arbitration Act, challenging the award on grounds including election of remedies, failure to establish market price and date of breach, and alleged judicial misconduct by the arbitrator. The learned single Judge dismissed the objections and made the award a rule of the court. This appeal challenges that judgment.

Legal Issues Presented

  1. Whether the Union of India was entitled to claim general damages in addition to repurchase loss for breach of contract.
  2. Whether the Union of India was required to actually purchase the undelivered goods to claim damages.
  3. Whether the arbitrator erred in determining the date of breach and the market price for computing damages.
  4. Whether the arbitrator committed judicial misconduct by admitting documents after conclusion of arbitration proceedings.
  5. Whether Clause XIV (7) (D) of the contract limited damages only to repurchase loss.

Arguments of the Parties

Contractor's Arguments

  • The Union of India elected to claim only repurchase loss by repurchasing the cancelled quantity and thus could not claim general damages.
  • The Union of India was not entitled to damages without actually purchasing the undelivered stores.
  • The arbitrator failed to determine the correct date of breach and the market price at that date and place, rendering the award erroneous.
  • The arbitrator was guilty of judicial misconduct by admitting documents filed after arbitration proceedings concluded.
  • Clause XIV (7) (D) restricted the Union of India's claim to repurchase loss only.

Union of India's Arguments

  • Denied the contractor's allegations and contended that general damages were recoverable beyond repurchase loss.
  • Asserted that actual purchase of goods was not a prerequisite for claiming damages under Section 73 of the Contract Act.
  • Maintained that the arbitrator correctly assessed market price based on available evidence, including prices from nearest markets.
  • Argued that Clause XIV (7) (D) did not limit damages to repurchase loss but was without prejudice to the right to claim damages for breach.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Ismail Sait and Sons v. Wilson and Co., AIR 1919 Mad 1053 Damages under Section 73 of the Contract Act do not require the buyer to actually purchase goods to claim damages. Supported the principle that damages are recoverable based on market price difference without necessity of actual purchase.
Vishwanath v. Amarlal, AIR 1957 Madh 190 Similar principle as Ismail Sait regarding assessment of damages without actual purchase. Reinforced the view that actual purchase is not a prerequisite for claiming damages.
Murlidhar Chiranjilal v. Harishchandra Dwarkadas, AIR 1962 SC 366 Damages aim to place the injured party in the position as if the contract was performed, subject to mitigation of loss. Clarified that proof of market price at the time and place of breach suffices for damages; actual purchase is not mandatory.
British Westinghouse Electric and Manufacturing Co. Ltd. v. Underground Electric Rly. Co. of London, 1912 AC 673 Principle of mitigation of loss in contract damages. Referenced to emphasize the duty of the injured party to mitigate loss when claiming damages.
Union of India v. Tribhuwan Dass Lalji Patel, AIR 1971 Delhi 120 Government can recover only actual loss sustained and not general damages if no loss was proved. Overruled by the court as contrary to Supreme Court precedent in Murlidhar Chiranjilal.
All India Institute of Medical Sciences v. American Refrigeration Co. Ltd., AIR 1982 Delhi 275 Overruled Union of India v. Tribhuwan Dass on the issue of damages recoverable by the government. Used to reject the contractor's argument limiting damages to actual loss only.

Court's Reasoning and Analysis

The court analyzed the contractual breach and the measure of damages under Section 73 of the Contract Act. It emphasized that damages aim to compensate for loss naturally arising from breach, calculated as the difference between contract price and market price at the time and place of breach. The court rejected the contractor's contention that actual purchase of the goods was necessary before claiming damages, relying on precedents including Ismail Sait and Murlidhar Chiranjilal. The court noted that the arbitrator properly considered market prices, including those from the nearest place when local data was unavailable, and fixed the market price reasonably. The court also examined Clause XIV (7) (D) of the contract and concluded that the right of repurchase did not exclude the right to claim general damages. Finally, the court overruled the precedent in Union of India v. Tribhuwan Dass Lalji Patel, aligning with subsequent authoritative decisions. The allegations of judicial misconduct were not found substantiated. Hence, the court found no merit in the appeal.

Holding and Implications

The appeal is dismissed with costs.

The decision upholds the arbitrator's award and confirms that a party suffering breach of contract is entitled to damages assessed by the difference between contract and market price without the necessity of actual purchase. It clarifies that contractual provisions allowing repurchase do not limit the right to general damages. No new precedent was established beyond affirming existing principles and overruling the contrary decision in Union of India v. Tribhuwan Dass Lalji Patel.

    Saraya Distillery v. Union Of India

    G.C JAIN, J.:— This appeal is directed against the judgment of a learned single Judge of this court dated September 21, 1979. It was dismissed by us by means of a short order dated February 27, 1984. Now we proceed to give reasons for the said decision.

    2. M/s. Saraya Distillery, the contractor agreed to supply 3,87,666 litres of rum to the respondent-Union of India at Rs. 2.13 per litre vide agreement dated August 14, 1972. The stores were to be delivered in 5 instalments 90,000 litres rum by 21-9-1972, 90,000 litres rum by 21-10-1972, 90,000 litres rum by 21-11-1972, 80,000 litres rum by 21-12-1972, and 37,666 litres rum by 21-1-1973. The contractor supplied only 45,000 litres of rum out of the first lot. He failed to supply remaining stores in spite of extension of time on his request and thus committed a breach of the contract.

    3. The Union of India claimed a sum of Rs. 3,35,888/- as damages. Out of this amount a sum of Rs. 4005/- was claimed for loss suffered on account of repurchase of 16,020 litres of rum and the remaining amount as general damages. The contractor admittedly refuted this claim. In pursuant to an arbitration clause the dispute was referred to the decision of Dr. Bakhshish Singh, the sole arbitrator. He made an award on August 12, 1977 holding that the Union of India was entitled to recover only Rs. 72,690,66 from the contractor.

    4. Union of India thereafter made a petition (Suit No. 798-A of 1977) under Sections 14 and 17, Arbitration Act, for directing the arbitrator to file the award and the proceedings in the court and making the award a rule of the court. The award and proceedings were duly filed. On receipt of the notice of the filing of the award the contractor filed objections (IA 196 of 1978) under Ss. 30 and 33, Arbitration Act, for setting aside the award. It was averred that the Union of India had gone for the repurchase of the cancelled quantity and had thus elected to claim only repurchase loss which amounted to Rs. 4005/- and, therefore, the claim for general damages was not maintainable. Even otherwise the Union of India having not actually purchased the remaining stores was not entitled to any damages. The arbitrator had failed to determine the date of breach of the contract, the market rate prevalent on that date at the place of the breach, the award was, therefore, erroneous and unsustainable. It was also averred that the arbitrator was guilty of judicial misconduct in taking upon the record certain documents filed by the Union of India after the conclusion of the arbitration proceedings.

    5. Union of India denied the averments. The objections did not find favour with the learned single Judge who dismissed the same vide his impugned judgment and made the award a rule of the court.

    6. The normal rule for computing damages for non-supply of the goods would be the difference between the contract price and the market price of such goods at the time when the contract is broken. If there is no available market, at the place of delivery, the market price at the nearest place or the price prevailing in the controlling market may be taken into consideration,

    7. Learned counsel for the contractor contended that before a party could claim damages he must go to the market, purchase the goods not supplied or short supplied and suffer actual loss. Only then, argued the learned counsel, he would be entitled to damages. We do not agree.

    8. Section 73 Contract Act, prescribes the method of assessing compensation due to a plaintiff suing upon a breach of contract. It says:

    “When a contract has been broken, the party who suffers by such breach is entitled to receive from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things for such breach.”

    9. What the buyer is deprived of in the usual course of things by non-delivery is the value of the goods at the time and place of the delivery, less price payable by him under the contract. This loss of value is the only natural result of the breach, the only kind of damage that ensues in the usual course of things. The quantum of damages on account of the breach of such contract would be the difference between the contract price and the market price of the goods in question at the time when the contract is broken. The provisions contained in S. 73 do not envisage that the buyer must resort to actual purchase and suffer loss before claiming damages. It was so held in Ismail Sait and Sons v. Wilson and Co., AIR 1919 Mad 1053. Similar view was taken in Vishwanath v. Amarlal AIR 1957 Madh a 190.

    10. The Supreme Court in the case of Murlidhar Chiranjilal v. Harishchandra Dwarkadas AIR 1962 SC 366 observed at page 369:

    “The two principles on which damages in such cases are calculated are well settled. The first is that, as far as possible, he who has proved a breach of a bargain to supply what he contracted to get is to be placed, as far as money can do it, in as good a situation as if the contract had been performed; but this principle is qualified by a second, which imposes on a plaintiff the duty of taking all reasonable steps to mitigate the loss consequent on the breach, and debars him from claiming any part of the damage which is due to his neglect to take such steps: (British Westinghouse Electric and Manufacturing Co. Ltd. v. Underground Electric Rly. Co. of London (1912 AC 673 at p. 689). These two principles also follow from the law as laid down in S. 73 read with the Explanation thereof. If, therefore, the contract was to be performed at Kanpur it was the respondent's duty to buy the goods in Kanpur and rail them to Calcutta on the date of the breach and if it suffered any damage thereby because of the rise in price on the date of the breach as compared to the contract price, it would be entitled to be reimbursed for the loss. Even if the respondent did not actually buy them in the market at Kanpur on the date of breach it would be entitled to damages on proof of the rate for similar canvas prevalent in Kanpur on the date of breach, if that rate was above the contracted rate resulting in loss to it. But the respondent did not make any attempt to prove the rate for similar canvas prevalent in Kanpur on the date of breach Therefore, it would obviously be not entitled to any damages at all, for on this state of the evidence it could not be said that any damage naturally arose in the usual course of things.”

    Learned counsel for the Contractor relied on a judgment of a learned single Judge of this court in Union of India v. Tribhuwan Dass Lalji Patel, AIR 1971 Delhi 120. In this case it was observed that the Government can recover the loss only sustained by it and could not claim damages, if no loss was sustained. With respect we do not agree with this view. This is contrary to the observations made by the Supreme Court in Murlidhar Chiranjilal (supra). A Division Bench of this court in All India Institute of Medical Sciences v. American Refrigeration Co. Ltd. AIR 1982 Delhi 275 came to the conclusion that the case Union of India v. Tribhuwan Dass (supra) was wrongly decided. We hereby overrule the decision in Union of India v. Tribhuwan Dass.

    11. Learned counsel for the contractor then contended that under Cl. XIV (7) (D) of the conditions of contract Union of India was entitled to claim only the loss which it suffered on account of the repurchase of the stores not delivered and was not entitled to any general damages. We have examined Cl. XIV (7) (D). The right of repurchase under this clause is without prejudice to the right of the purchaser to recover damages for breach of the contract. Therefore, it cannot be said that damages were limited only to the amount of loss suffered on repurchase.

    12. Learned counsel for the contractor also urged that the breach took place on 31-3-1972 at Sardar Daggar Distt. Gorakhpur and there was no evidence before the arbitrator regarding the rate prevalent on that date at that place and, therefore, the learned arbitrator erred in awarding the damages. A perusal of the award shows that the evidence was produced before the arbitrator showing the rates prevalent on various dates between 6th October, 1972 and 28-1-1974. The learned arbitrator awarded the damages treating the lowest price as the market price. We find no illegality in the approach. Admittedly the breach took place on 31-3-1973. On 1-2-1972 the price as per award was Rs. 2.90 per litre. It related to Shri Krishan Goyndoya. This was a very good piece of evidence. In spite of this evidence the arbitrator fixed the market price at Rs. 2.34 per litre. The contractor can have no grievance.

    13. It was pointed out that Shri Krishan Goyndoya was not in Gorakhpur and thus there was no evidence to prove the price prevalent at Gorakhpur. The arbitrator in the absence of any evidence regarding the prevalent price at Gorakhpur could take into consideration the market price at the nearest place.

    14. We find no merit in the appeal and dismiss the same with costs.

    Appeal dismissed.