B. Legal Reasoning
1. The PSC’s power to reopen and modify a final order is broad under § 24-2-2(a)
The Court treated the reopening question as primarily statutory and regulatory interpretation (reviewed de novo).
Although W. Va. Code § 24-1-9(g) sets a process by which an ALJ recommended decision becomes final if not
excepted to or reviewed sua sponte, the Court held that finality under § 24-1-9 does not create an unchangeable
order. The controlling provision, W. Va. Code § 24-2-2(a), states that “every order entered by the commission”
continues in force until it expires or is “revoked or modified by the commission” (unless altered by a court).
The Court read this language as an express grant of continuing authority to revise prior PSC orders.
2. W. Va. Code R. § 150-1-19.5 does not limit reopening to only post-hearing developments
BWC argued that § 150-1-19.5 narrows reopening to “matters which have arisen since the hearing” and prevents the
PSC from revisiting settled determinations unless the petition itself seeks modification based on such new
matters. The Court rejected this as an impermissible rewriting of the rule. The regulation requires that if a
petitioner seeks to vacate/reverse/modify an order “by reason of” new matters or newly discovered facts, those
matters must be set forth; it does not state that the PSC may consider only those matters, nor does it impose
a categorical subject-matter limitation on what the PSC may revisit once reopened.
Invoking Brooke B. v. Ray and Snider v. Fox, the Court emphasized a plain-language, no-additions
approach: courts should not insert constraints not present in the text. On that basis, the Court upheld the
PSC’s authority to revisit exclusivity and to ultimately vacate the earlier recommended decision.
3. The “gray and overlapping” determination: Lumberport test and isolation test applied to an undeveloped site
The merits dispute centered on prong three of the “Lumberport test”—whether the Site is located in an overlapping
service territory. The PSC used the “isolation test”: assume each utility exists alone, and ask whether the rules
and case law would require it to provide service if requested. If both would be required to serve, the territory
is gray/overlapping.
The Court accepted the PSC’s fact-driven application. The PSC considered: (1) the Site’s annexation into Mount
Hope’s corporate limits; (2) the absence of any prior service because the Site is undeveloped; (3) existing
facilities of both utilities in the area; (4) the PSC’s assessment that a 2.5-mile extension was not “too far”
in context; and (5) the Legislature’s expressed policy favoring pre-tenant infrastructure extensions for
economic development under W. Va. Code § 24-2-1n and the PSC’s balancing obligations under W. Va. Code § 24-1-1.
Importantly, the Court did not treat annexation as a per se rule awarding Mount Hope exclusive or “superior”
rights over a private utility; rather, it treated annexation as a relevant circumstance informing whether Mount
Hope would be required to serve under the isolation test and whether overlap exists given both utilities’
ability to serve a new user at a development site.
4. Deference sealed the result
Once the Court found the PSC acted within its statutory jurisdiction and applied a legally recognizable framework,
the deferential review standard did the remaining work. The Court concluded there was no reversible error in the
PSC’s application of its overlap methodology to these facts and affirmed.