Battery Storage as a Non‐Generation Resource: Clarifying Exclusive Power Contract Obligations

Battery Storage as a Non‐Generation Resource: Clarifying Exclusive Power Contract Obligations

Introduction

The case of APPALACHIAN POWER COMPANY v. FEDERAL ENERGY REGULATORY COMMISSION, with BLUE RIDGE POWER AGENCY as an intervenor, centers on a dispute regarding the interpretation of wholesale power contracts. At the heart of the matter is the question whether the installation and utilization of battery storage technology (BST) by certain Blue Ridge members violates exclusive supply contracts with Appalachian Power Company (APCO). These contracts were originally negotiated to ensure that member utilities would purchase all of their required electricity exclusively from APCO. However, as new energy storage technologies emerge, the interpretation of contract language—especially regarding “generation”—has come under scrutiny.

The petition challenges the Federal Energy Regulatory Commission’s (FERC) decision that permits Blue Ridge members to install BST and use it to manage peak demand. Appalachian Power Company argues that the agreements do not authorize such installations, asserting that using battery storage undermines the structure of an exclusive supply arrangement. In response, FERC’s order, now under appeal, explains that BST does not equate to a generation resource, thus preserving the contractual obligations regarding exclusive supply. This commentary reviews the factual background, the court’s reasoning, and the potential implications of the decision on future contracts and energy regulation.

Summary of the Judgment

The United States Court of Appeals for the Fourth Circuit denied APCO's petition for review in an unpublished per curiam opinion. The court’s decision upholds FERC’s earlier order which determined that:

  • Battery storage technology, being solely a medium to store and later discharge electricity, does not qualify as “generation” under the existing contractual schemes.
  • Even though the contracts between APCO and the Blue Ridge members do not expressly address battery storage or its use to reduce peak demand, the Commission’s interpretation that BST does not conflict with the agreements is supported by the contractual language and industry practice.
  • The dissenting provisions in a separate contract with Virginia Tech, which explicitly restrict battery storage installation, do not modify the terms of the earlier contracts with the Blue Ridge members.
  • APCO’s arguments that the FERC order substituted policy judgment for legal interpretation and that it would lead to unjust and unreasonable rates were found unpersuasive.

Consequently, the court concluded that the FERC order was neither arbitrary nor capricious and that the agency had properly interpreted the contracts under Virginia law principles.

Analysis

A. Precedents Cited

The judgment draws upon several precedents that guide both contract interpretation and agency review of administrative decisions:

  • FERC’s precedent concerning battery storage: The Commission relied on its prior decision in the NCEMPA case (172 FERC ¶ 61,249), which emphasized that battery storage, by its nature, is not “inherently” a generation resource. This case was central to the Court’s decision as it supports the view that the contractual terms regarding “generation” do not need to expand to include energy storage methods that merely relay electricity.
  • Contractual interpretation principles: The court referenced well-established contractual canons, such as "expressio unius est exclusio alterius" in support of APCO’s position. However, it noted that such canons—especially in Virginia law—are nonbinding in this context and must be balanced with the overall purpose and language of the agreements. The court also used cases like Fed. Power Comm'n v. Sierra Pac. Power Co. (350 U.S. 348) and BARNHART v. PEABODY COAL CO. (537 U.S. 149) to underline the importance of reading contracts as a whole.
  • Review standards for agency decisions: Cases such as Sierra Club v. State Water Control Bd. and Friends of Buckingham v. State Air Pollution Control Bd. were cited to affirm that agency actions may only be quashed if they are “arbitrary and capricious.” This standard necessitates that the agency’s reasoning must be grounded in the contractual language and the evidence presented.

B. Legal Reasoning

The court’s legal reasoning can be broken down into several key focal points:

  • Interpretation of “Generation”: The Commission's opinion hinges on the definition of “generation” within the contracts. It emphasized that battery storage is a mechanism for storing energy rather than an independent source of energy production. Therefore, while BST alters the timing of electricity use, it does not breach the exclusive supply obligations.
  • Focus on Contractual Language: The court noted the contracts provided for the full requirements electric service without setting forth restrictions on the methods used to manage fluctuating demand. The language was interpreted in its entirety, not merely by relying on isolated terms.
  • Duty to Uphold Choice of Law Clauses: The judgment underscores the importance of respecting choice of law clauses in private contracts. The court found that even under Virginia law, which APCO cited as potentially favoring a different interpretation, there was insufficient evidence to conclude that BST should be disallowed.
  • Separation of Issues: The court carefully separated the question of BST’s compatibility with the contracts from other issues such as the potential impact on electricity rates. It held that the Commission was not obliged to address all related financial implications within the same proceeding.

C. Impact on Future Cases and Energy Regulation

The decision has notable implications for both contractual interpretation and energy regulation:

  • Clarification on Technology Classification: By establishing that battery storage does not constitute “generation,” future disputes involving emerging energy technologies can be addressed with greater clarity, particularly in contracts that have been drafted before the widespread adoption of such technologies.
  • Influence on Contract Drafting: Parties entering into exclusive supply agreements may now explicitly address the role of battery storage and other energy management technologies. This case serves as an impetus for clearer contractual language to avoid future ambiguity.
  • Regulatory Consistency: The decision reinforces the discretionary authority of FERC, affirming that the agency’s expertise in handling complex energy market issues should be respected when evaluating technical nuances in contracts.
  • Precedential Guidance: Although the per curiam opinion is unpublished and thus not binding precedent in the circuit, its thorough analysis offers guidance on interpreting similar disputes, particularly when balancing technological advancements with longstanding contractual obligations.

D. Simplification of Complex Concepts

Several complex legal concepts are central to this judgment:

  • Battery Storage Technology (BST) vs. Generation: The Commission and the court clarified that while generation involves the production of new electricity, battery storage simply holds and later releases electricity. This distinction is critical because the contracts prohibiting "newly constructed or purchased generation resources" do not automatically extend to storage devices.
  • Arbitrary and Capricious Standard: This legal benchmark is used to assess whether an agency’s decision is backed by a rational explanation considering all relevant factors. Essentially, it prevents agencies from making decisions that are inexplicable or disconnected from the statutory framework.
  • Choice of Law Clauses: Such clauses allow contracting parties to predetermine which jurisdiction’s law will govern any disputes. The court’s insistence on upholding these clauses ensures that the negotiated mutual understanding remains intact.

Conclusion

In conclusion, the decision in APPALACHIAN POWER COMPANY v. FEDERAL ENERGY REGULATORY COMMISSION represents an important development in contract interpretation in the energy sector. By differentiating between energy storage and generation, the Court, following FERC’s analytical framework, confirms that battery storage can be compatible with exclusive supply contracts.

The judgment highlights the necessity for regulatory bodies to carefully consider technological evolutions when interpreting longstanding contractual terms. For the energy industry and agencies overseeing it, this ruling provides clarity that may encourage more flexible approaches in contract drafting and disputes, ensuring that new technologies do not inadvertently disrupt existing market structures.

Ultimately, the case reinforces foundational legal principles—such as upholding the clear text of contracts, adhering to the chosen legal framework, and ensuring that agency decisions are rational and well-supported—thereby setting a measured precedent for future cases in similar contexts.

Case Details

Year: 2025
Court: United States Court of Appeals, Fourth Circuit

Judge(s)

PER CURIAM

Attorney(S)

William Keyser, III, STEPTOE LLP, Washington, D.C., for Petitioner. Carol J. Banta, FEDERAL ENERGY REGULATORY COMMISSION, Washington, D.C., for Respondent. Karen Bruni, Megan McDowell, STEPTOE & JOHNSON LLP, Washington, D.C.; Jessica A. Cano, Assistant General Counsel, AMERICAN ELECTRIC POWER SERVICE CORPORATION, Columbus, Ohio, for Petitioner. Matthew R. Christiansen, General Counsel, Robert H. Solomon, Solicitor, FEDERAL ENERGY REGULATORY COMMISSION, Washington, D.C., for Respondent.

Comments