Restoration of PPA Tariffs and Upholding of Force Majeure Clauses in Solar Power Projects: Solantra Pvt. Ltd. v. KERC

Restoration of PPA Tariffs and Upholding of Force Majeure Clauses in Solar Power Projects: Solantra Pvt. Ltd. v. Karnataka Electricity Regulatory Commission

Introduction

The case of Solantra Private Limited v. Karnataka Electricity Regulatory Commission (KERC) adjudicated by the Appellate Tribunal for Electricity marks a significant development in the regulatory oversight of solar power projects under the Karnataka Solar Policy 2014-2021. This comprehensive appeal primarily revolves around the rejection of time extension requests by KERC for commissioning solar power projects (SPPs) developed by land-owning farmers. The appellants, represented by Solantra Pvt. Ltd., challenged the reduction of tariffs and imposition of liquidated damages imposed by respondent electricity distribution companies (ESCOMs) based on delays attributed to various administrative hurdles beyond the control of the developers.

Summary of the Judgment

The Appellate Tribunal, presided over by Hon'ble Mr. Justice R.K. Gauba, scrutinized multiple appeals where KERC had reduced the tariff rates from Rs. 8.40 per KwH to Rs. 4.36 per KwH and imposed liquidated damages due to delayed commissioning of SPPs. The appellants argued that delays were caused by force majeure events, including bureaucratic delays in obtaining necessary approvals, which were explicitly covered under the Power Purchase Agreements (PPAs). The Tribunal found in favor of the appellants, setting aside KERC's impugned orders. It mandated the restoration of the original tariff rates, annulment of liquidated damages, and directed the ESCOMs to honor their PPA obligations without delay.

Analysis

Precedents Cited

The judgment extensively references prior Tribunal decisions that reinforced the protection of SPDs under the Farmers' Scheme. Notably:

  • Chennamangathihalli Solar Power Project LLP & Anr. v. BESCOM & Anr. (Judgment dated 14.09.2020)
  • Basaragi KM Solar Power Project LLP & Anr. v. Hubli Electricity Supply Company Limited & Anr. (Appeal No. 328 of 2018)
  • Vatsala Ballary Solar Projects Private Limited v. KERC & Anr. (Appeal No. 66 of 2020)

These precedents collectively established that delays arising from governmental instrumentalities fall within force majeure clauses, thereby protecting the interests of SPDs from unjust tariff reductions and penalties.

Legal Reasoning

The Tribunal's legal reasoning hinged on the contractual provisions within the PPAs, specifically clauses related to force majeure and extensions of time. The key points include:

  • Force Majeure Applicability: The delays in securing approvals from various governmental departments were classified as force majeure events, excusing the appellants from being penalized.
  • Obligation of ESCOMs: Given that ESCOMs themselves recognized the delays and had previously extended commissioning dates, it was deemed inequitable to retroactively impose penalties.
  • Judicial Consistency: Upholding previous Tribunal decisions ensured consistency in judicial interpretation, fostering a stable regulatory environment for renewable energy projects.

Impact

This judgment has profound implications for future solar power projects in Karnataka and potentially other jurisdictions. Key impacts include:

  • Regulatory Clarity: Clear delineation of force majeure events provides SPDs with legal assurance against administrative delays.
  • Encouragement for Renewable Investment: Restoration of tariff rates and removal of unjust penalties make solar investments more attractive to farmers and developers.
  • Government Accountability: The ruling implicitly holds government bodies accountable for efficient processing of approvals, incentivizing streamlined administrative procedures.

Complex Concepts Simplified

Force Majeure

A contractual clause that frees both parties from liability or obligation when an extraordinary event or circumstance beyond their control prevents one or both parties from fulfilling their contractual obligations.

Power Purchase Agreement (PPA)

A contract between a power producer and a buyer, outlining terms such as the price at which electricity is sold, duration of the agreement, and obligations of both parties.

Scheduled Commissioning Date (SCD)

The agreed-upon date by which a power project is expected to begin commercial operations.

Conclusion

The Appellate Tribunal's decision in Solantra Pvt. Ltd. v. KERC underscores the judiciary's role in safeguarding the interests of renewable energy developers against administrative inefficiencies. By enforcing the sanctity of contractual agreements and recognizing the impact of bureaucratic delays as force majeure, the judgment fosters a conducive environment for sustainable energy projects. This not only benefits land-owning farmers involved in solar power generation but also aligns with broader governmental objectives of expanding renewable energy capacity. The ruling sets a robust precedent, ensuring that similar disputes will be adjudicated with fairness and consistency in the future.

Case Details

Year: 2022
Court: Appellate Tribunal For Electricity

Judge(s)

R.K. GaubaOfficiating ChairpersonSandesh Kumar Sharma, Member (Technical)

Advocates

Mr. Basava Prabhu Patil, Sr. Adv., Ms. Prerna Priyadarshini, Ms. Priyashree Sharma Mr. Geet Ahuja ;Ms. Prerna Priyadarshini, Ms. Priyashree Sharma ;Mr. Nitin Saravanan, Ms. Arunima Singh, Ms. Ridhima Malhotra Ms. Priyadarshini, Ms. Latha S, Mr. Murugesh R-2, Ms. Vaishnavi Rao, Ms. Swati Mittal for R-3 & 5Mr. Sriranga Subanna, Sr. Adv., Ms. Sumana Naganand, Ms. Medha M. Puranik, Mr. Sanjay Reddy, Ms. Gayathri Sriram for R-1Mr. Shahbaaz Husain, Mr. Fahad Khan for R-1

Comments