Application of RERA Sections 12 and 18 Quasi-Retroactively: Rohit Chawla v. M/s Bombay Dyeing Judgment

Application of RERA Sections 12 and 18 Quasi-Retroactively: Rohit Chawla v. M/s Bombay Dyeing Judgment

Introduction

The case of Rohit Chawla v. M/s Bombay Dyeing & Mfg. Co. Ltd. adjudicated by the Real Estate Regulatory Authority (RERA) in 2020, marks a significant development in the interpretation and application of the Real Estate (Regulation and Development) Act, 2016 (RERA). This case revolves around the grievances of allottees against promoters concerning delays in possession, misrepresentations about project amenities, and unilateral changes in project specifications.

Summary of the Judgment

The allottees filed complaints under Sections 12 and 18 of RERA against the promoters alleging breach of assurances regarding possession timelines and promised amenities. The initial orders by MahaRERA dismissed these complaints, asserting that Section 12 of RERA couldn't be applied retrospectively to transactions predating the Act’s enforcement. However, upon appeal, the appellate Tribunal revisited the applicability of RERA provisions, referencing the landmark Neel Kamal Realtors judgment. The Tribunal concluded that Sections 12 and 18 of RERA could be applied quasi-retroactively to ongoing projects, thus entitling allottees to withdraw from their agreements and claim refunds with interest and compensation.

Analysis

Precedents Cited

The judgment heavily relies on the Neel Kamal Realtors case, wherein the Honorable Bombay High Court delved into the retroactive and quasi-retroactive application of RERA provisions. The Tribunal referenced several Supreme Court rulings, including:

These precedents established that substantive laws like RERA can be applied retrospectively or retroactively, especially when enacted for public interest, and do not necessarily infringe upon vested rights unless explicitly stated.

Legal Reasoning

The Tribunal's reasoning hinged on the nature of RERA as a substantive law aimed at protecting consumer interests in the real estate sector. It determined that RERA's provisions could be applied quasi-retroactively to ongoing projects, meaning that while the law wasn't fully retrospective, it did apply to transactions in progress at the time of its enactment. This interpretation aligns with the principles outlined in the Neel Kamal Realtors judgment, which posited that such laws serve a larger public interest and can modify existing contractual relationships to prevent exploitation.

Furthermore, the Tribunal emphasized that the promoters had breached their obligations by failing to deliver possession by the promised timeline and by making unilateral changes to project amenities without the consent of allottees. These breaches warranted the application of Sections 12 and 18, thereby entitling the allottees to seek remedies under RERA.

Impact

This judgment sets a pivotal precedent in the realm of real estate regulation in India. By acknowledging the quasi-retroactive application of RERA provisions, it empowers consumers to seek redressal for breaches that occurred before the Act's enforcement, provided the transactions were ongoing. This enhances the protective framework for allottees, ensuring that promoters cannot evade accountability for promises made during the pre-RERA era.

For future cases, developers must now exercise greater diligence in adhering to commitments and transparent communication with buyers. Additionally, this judgment may encourage more buyers to register complaints under RERA, knowing that their grievances can be addressed even if their transactions began before RERA became effective.

Complex Concepts Simplified

Quasi-Retroactive Application: This refers to the application of new legal provisions to transactions that were in progress at the time the law was enacted. Unlike full retroactivity, which affects completed transactions, quasi-retroactivity targets ongoing ones to ensure fairness and compliance with current laws.

Section 12 of RERA: Deals with misrepresentations by promoters regarding aspects like project specifications, amenities, and possession timelines. Breach of this section allows allottees to seek refunds and compensation.

Section 18 of RERA: Pertains to the delay in handing over possession beyond the stipulated timeline. It mandates promoters to return the deposited amount with interest and allows allottees to withdraw from the project if delays are significant.

Conclusion

The Rohit Chawla v. M/s Bombay Dyeing judgment underscores the judiciary's commitment to upholding consumer rights in the real estate sector. By affirming the quasi-retroactive application of RERA provisions, the Tribunal has fortified the legal safeguards available to allottees against promoter malpractices. This decision not only rectifies past injustices but also serves as a deterrent against future contractual breaches, fostering a more transparent and accountable real estate market.

Case Details

Year: 2020
Court: RERA

Advocates

Comments