Almacantar Centre Point Nominee No.1 Ltd & Anor v De Valk & Ors

Smart Summary

Factual and Procedural Background

The appeal concerned whether the Building Safety Act 2022 prevented the freehold owners of a residential development (“the Appellants”) from recovering service charges from 13 leaseholders (“the Respondents”) for proposed façade-repair works. The façade had deteriorated through water ingress and timber rot, and the proposed works involved removing substantial parts of the existing façade and installing a new steel-framed glazing system. [1][2][3][4][5][6]

The Appellants applied to the First-tier Tribunal for a determination under section 27A(3) of the Landlord and Tenant Act 1985. The Tribunal held that the works fell within the repairing covenants and would ordinarily be service-chargeable, but that only leaseholders without qualifying leases were liable. The Upper Tribunal dismissed the Appellants’ appeal, and the Appellants appealed to the Court of Appeal. [7][8][9][10]

Legal Issues Presented

  1. Whether paragraph 8 of Schedule 8 to the Building Safety Act 2022 applies only to “relevant defects”. [11][12][13][14]
  2. Whether the façade constituted “cladding” or a “cladding system” for the purposes of the Act. [15][16][17]
  3. Whether the proposed works involved the removal or replacement of part of a cladding system. [18][19][20]
  4. Whether the cladding system formed “the outer wall of an external wall system”. [21][22][23]
  5. Whether “unsafe” in paragraph 8(2)(b) was limited to danger arising from fire or combustible cladding. [24][25][26]

Arguments of the Parties

Appellants’ Arguments

  • Paragraph 8 should be confined to “relevant defects”, given the structure and purpose of Part 5 and Schedule 8. [27][28][29]
  • Applying paragraph 8 without that limitation would create anomalies concerning remediation orders, contribution orders, limitation periods and associated professional costs. [30][31]
  • “Unsafe” should mean combustible or dangerous because it contributes to the spread of fire. [26][32][33]
  • The façade was not “cladding” within the statutory meaning, the proposed works did not remove or replace a cladding system, and any cladding system did not form only the outer wall of a wider external wall system. [16][34][35][20][36]

Respondents’ Arguments

  • Paragraph 8 was not restricted to “relevant defects”, and the decisions of the First-tier Tribunal and Upper Tribunal should be upheld. [37][38]
  • Whether the façade constituted cladding was a factual matter for the specialist tribunal, whose conclusion was supported by the evidence. [39][40][41]

Table of Precedents Cited

PrecedentRule or Principle Cited ForApplication by the Court
Darwall v Dartmoor National Park Authority [2025] UKSC 20Statutory interpretation requires determining statutory meaning in context and having regard to purpose.The Court applied contextual and purposive interpretation to paragraph 8. [42]
R (O) v Secretary of State for the Home Department [2022] UKSC 3Statutory words must be understood in their statutory context; explanatory notes are secondary aids.The Court relied on the principle when assessing the Act and explanatory notes. [42][43]
Black-Clawson International Ltd v Papierwerke Waldhof-Aschaffenburg AG [1975] AC 591Courts seek the meaning of the words Parliament used.The principle was quoted as part of the statutory-interpretation framework. [44]
R v Secretary of State for the Environment, Transport and the Regions, Ex p Spath Holme Ltd [2001] 2 AC 349Meaning depends on the statutory and wider legislative context.The Court used the principle in construing paragraph 8. [44]
R (Maughan) v Oxfordshire Senior Coroner [2020] UKSC 46Guidance concerning the proper role and content of statutory schedules.The Court rejected the argument that paragraph 8 should be restricted because it addressed an important matter in a schedule. [45][46]
Inland Revenue Commissioners v Gittus [1920] 1 KB 563Clear words in a schedule must be given effect even if they extend beyond the general purpose indicated by the Act or schedule heading.The Court held that the introductory provisions did not limit the clear wording of paragraph 8. [47][46]
Attorney-General v Lamplough (1878) 3 Ex D 214A schedule is as much part of the statute as any other enacted provision.The Court treated Schedule 8 as operative statutory text. [48]
Adriatic Land 5 Ltd v Long Leaseholders at Hippersley Point [2025] EWCA Civ 856Post-enactment explanatory notes have no particular legal status and are not a reliable guide to legislative intention.The Court gave the post-enactment notes no decisive weight. [49]
Lehner v Lant Street Management Co Ltd [2024] UKUT 135 (LC)Guidance on questions relevant to leaseholder protections and cladding remediation.The Court held that the decision did not determine whether a “relevant defect” was required for paragraph 8 to apply. [50][51]
Inco Europe Ltd v First Choice Distribution [2000] 1 WLR 586Courts may correct obvious drafting errors only in plain cases and must be abundantly sure of the intended purpose, the drafting mistake and the required correction.The Court found no sufficient basis to alter paragraph 8. [52][53][54][55]
Jones v Wrotham Park Settled Estates [1980] AC 74Limits the judicial power to correct statutory drafting errors.The case was cited within the rule applied in Inco. [56]
Edwards v BairstowAn appellate court may interfere with a factual conclusion only within the limited scope permitted on an appeal on a point of law.The Court held that the First-tier Tribunal’s cladding finding was not legally challengeable. [40][57][58]
A Taxpayer v HMRC [2025] EWCA Civ 106Construction of statutory language is a question of law, while applying ordinary words to established facts may be a question of fact.The Court used this distinction in reviewing the tribunal’s conclusions on cladding and the external wall system. [59][60][61]
Cozens v Brutus [1973] AC 854Meaning of ordinary words and the distinction between statutory construction and factual application.The principles supported deference to the specialist tribunal’s factual assessment. [59][62][63][60]
Moyna v Secretary of State for Work and Pensions [2003] 1 WLR 1929Meaning depends on the statutory context, syntax and background.The principle informed the Court’s approach to “cladding system” and related expressions. [59][64][65][60]
Pepper v HartConditions governing reliance on parliamentary material in statutory interpretation.The Court noted that the conditions for consulting Hansard had not been argued to be satisfied. [61]

Court's Reasoning and Analysis

The Court held that paragraph 8 is not limited to “relevant defects”. Unlike paragraphs 2–7 and 9, paragraph 8 contains no reference to that expression. The requirement that the cladding be “unsafe” would also be unnecessary if paragraph 8 already required a “relevant defect”, because such a defect must itself cause a building safety risk. [38][66][67]

The Court rejected the alleged anomalies and considered that the statutory scheme deliberately used “bright lines”. The explanatory notes and regulations did not support restricting paragraph 8, and the statutory purpose was consistent with giving dangerous cladding distinct treatment. [68][49][69][70]

The Court further held that “unsafe” bears its ordinary meaning of involving danger and is not confined to fire risk. The Building Safety Act addresses more than fire, and the statutory definition of “building safety risk” was not adopted in paragraph 8. [71][72][73]

On the façade, the Court treated “cladding” and “cladding system” as ordinary expressions applied in a specialist factual context. The First-tier Tribunal had considered the undisputed construction evidence, expert evidence, drawings and site view, and was entitled to find that the façade comprised a cladding system. [74][40][75][76][77]

The proposed works involved removing glazing, windows, spandrel panels, insulation, fixings and part of the timber frame, followed by replacement with a new steel-framed glazing system. That satisfied the ordinary meaning of removal and replacement. [78][79][80][81]

The Court reserved the broader question whether a cladding system constituting the whole of an external wall system could qualify under paragraph 8. It held that this case was different because the First-tier Tribunal found that the cladding system did not include the dwarf walls and was therefore not identical to the external wall system. [82][83][84]

Holding and Implications

APPEAL DISMISSED. The Court upheld the conclusion that paragraph 8 of Schedule 8 applied to the proposed cladding remediation, notwithstanding that the defect pre-dated the statutory 30-year period, and that the qualifying leaseholders were protected from liability for the relevant service charges. [85][73][86][87][88]

The direct consequence was that the Appellants could not recover the relevant remediation costs through service charges from the Respondents with qualifying leases. The Court expressly left open the broader question concerning a cladding system that constitutes the whole of an external wall system. [82][84]

To access the original judgment, please Sign In or Subscribe.

Almacantar Centre Point Nominee No.1 Ltd & Anor v De Valk & Ors

Contains public sector information licensed under the Open Justice Licence v1.0.

Use AI to get other relevant cases.

Comments

Almacantar Centre Point Nominee No.1 Ltd & Anor v De Valk & Ors
(Nov 17, 2026)