Ashdrum Lodge Limited [Trading as Kiernan Homes] v. Barbouti

Smart Summary

High Court — Summary of Judgment (Anonymised)

Judge: Judge Stack

Record: Single proceeding involving Company A (the Contractor) as the Plaintiff, the Defendant, and the Third Parties (architect and architect's firm). The judgment was delivered after a multi-day trial addressing a counterclaim and a third-party action.

Factual and Procedural Background

This judgment concerns a building project at a country house property ("the House") and associated external works (an extensive walled garden called "the Orchard", a Warehouse and access roads). The contracting entity, Company A (Plaintiff), carried out works over several years starting in late 2013. The principal contractor (Company A) sought payment for outstanding interim and final claims. The Defendant defended that claim, counterclaimed for defects in the works, and later joined the Third Parties (the supervising architect and his practice) alleging negligence and breach of contract in supervising and certifying the works.

The sequence in short:

  • The Contractor began extensive refurbishment and related works after an initial quotation, with the scope expanding substantially on rolling instructions from the Defendant.
  • No formal, executed building contract was ever produced covering the full scope; the parties treated some standard-form provisions (RIAI Blue Form) as operating by course of dealing in respect of interim certificates, retentions, insurance and the defects liability period.
  • Interim certificates were issued by the architect over the project. Partial Practical Completion was certificated for the House (November 2016), with a 12‑month defects liability period indicated for that part.
  • Disputes about cost escalations culminated in the Defendant excluding the Contractor from the site on or about 1–2 August 2017 and later dismissing the architect in December 2017.
  • The Contractor sued for unpaid sums; the Defendant counterclaimed for defects. The Contractor's claim and the Defendant's counterclaim against the Contractor settled early in trial (Day 4). The Defendant continued the third-party action against the Third Parties for alleged negligent failure to identify or prevent defects (principally defective bedding mortar in newly constructed walls) and for other alleged failings.
  • The third-party trial proceeded; expert evidence was led on both sides regarding mortar, pointing, weathering, standards of inspection by architects, valuation of works and costs. The Court heard lengthy fact and expert evidence and made findings on liability, causation and apportionment, and on statutory issues arising under the Civil Liability Act 1961 (ss. 17, 34 and s. 35(1)(h)).

Legal Issues Presented

  1. Whether, on the facts, the Third Parties (the supervising architect and practice) were negligent in failing to identify defective bedding mortar in the newly constructed and reconstructed walls by means of periodic visual inspections prior to the Contractor's exclusion from the site on 1–2 August 2017.
  2. Whether the terms of the Standard RIAI Blue Form Contract and/or the Standard RIAI Architect's Contract were incorporated into the parties' dealings by course of dealing, and what obligations therefore governed certification, retention, insurance and the defects liability period.
  3. Whether the defects pleaded (including defective mixing of bedding mortar and defects in haunching/capping of historic walls and foundations of the Warehouse) were patent (i.e. objectively visible) prior to the Contractor's exclusion and thus should have been discovered on reasonable periodic inspections.
  4. Whether the Defendant's actions in excluding the Contractor and dismissing the architect, and failing to appoint or cooperate with a quantity surveyor, amount to contributory negligence or failure to mitigate under s.34 of the Civil Liability Act 1961, reducing or extinguishing any recoverable damages from the Third Parties.
  5. Whether the Settlement between the Defendant and the Contractor discharged or reduced the Defendant's claim against the Third Parties under s.17 of the Civil Liability Act 1961 (i.e. the effect of the release/accord and the appropriate apportionment of liability between concurrent wrongdoers).
  6. Whether the Defendant can recover the quantity surveyor's fees incurred in preparing expert/valuation material from the Third Parties on the basis that better scrutiny of interim valuations would have avoided that expense.

Arguments of the Parties

Defendant's Arguments

  • The architect (Third Parties) owed and breached duties: to administer the contract impartially, to supervise by reasonable periodic inspection, and to have identified defective workmanship (in particular defective bedding mortar) that led to extensive remedial costs.
  • The RIAI Blue Form (contract between employer and contractor) and the RIAI Architect's Contract (architect's retainer) governed the relevant aspects of the parties' relationship by course of dealing, including certificate/retention/defects arrangements, and the architect's duties flowed from those terms.
  • The defects in the bedding mortar were patent (visible) and should have been detected on periodic inspection prior to August 2017; had the architect identified that, remedial steps could have been taken earlier and far less expensive remediation would have sufficed.
  • The Defendant sought quantification of substantial remedial costs for the orchard walls and other works and sought contribution from the Third Parties to cover those losses (including an ancillary claim for quantity surveying fees).

Third Parties' Arguments

  • The architect's contractual and professional duty was the limited, standard duty of periodic visual inspections (as set out in the Standard RIAI Architect's Contract and established authorities) and did not extend to continuous supervision or guarantee of workmanship.
  • The defects in the bedding mortar arose from defective mixing (a contractor's workmanship issue) and were therefore primarily the Contractor's responsibility; the architect was not obliged to test or oversee every mixing operation.
  • The mortar defect became evident only with time and weathering; the Third Parties contend the claim is tainted by hindsight and that, on the available contemporaneous evidence, the defects were not patent prior to the Contractor being excluded from the site.
  • The Defendant's decision to exclude the Contractor and later to dismiss the architect prevented the architect from completing the contractual inspection and final measurement processes; by these actions the Defendant failed to mitigate loss and acted unreasonably, attracting reduction or extinguishment of any Third‑party liability under s.34 of the Civil Liability Act 1961.

Pleaded Claim by the Contractor (relevant procedural posture)

  • The Contractor claimed outstanding payments; that main claim settled with the Defendant early in the trial. The settlement involved the Defendant agreeing to assume responsibility for specified subcontractor payments and mutual releases; the Third Parties were not party to that settlement.

Table of Precedents Cited

The table lists case authorities expressly cited or relied upon in the opinion and the way the court used them in reasoning.

Precedent Rule or Principle Cited For Application by the Court
Sunderland v. McGreevy [1987] I.R. 372 Architect's duty of care is related to and determined by the scope and terms of engagement. Cited to explain that the architect's obligations depend on the retainer and that one must identify the architect's retainer to define his duty in negligence.
McGlinn v. Waltham Contractors Ltd. (No. 3) [2006]/[2007] (TCC) Authoritative statement of an architect's duty when conducting periodic inspections; frequency, tailoring inspections to works, and limits of the inspector's obligation. The court accepted McGlinn as the appropriate statement of the scope of an architect's duty for periodic inspections and applied its principles in assessing whether defects were ascertainable on visual inspection.
East Ham Corporation v. Sunley [1966] A.C. 406 Architect is not permanently on site; inspections are at intervals and may focus on pressing matters; failure to discover defect not automatically negligence. Used to support the real-world limits of an architect's periodic inspection obligations and to reject a contention that continuous oversight was required.
Florida Hotels Pty Ltd v. Mayo (cited in McGlinn) Where necessary the inspecting professional can direct that certain elements not be covered up until inspected; tailoring to stage and importance of works. Referenced as part of the McGlinn principles reinforcing that inspections should be targeted to relevant work stages; not a ground to find broader duties here.
Jameson v. Simon (1899) Architect must see principal parts of work before they are covered up; failure to do so can be negligent. Distinguished on facts: case concerned bottoming of a cement floor; Court held it did not demonstrate that the architect here was negligent when mortar mixing is typically concealed and mixed in small batches.
Sutcliffe v. Chippendale & Edmondson (1971) 18 B.L.R. 149 Proposition that prolonged and detailed inspection at interim stage is impractical and not to be expected. Applied to support that an architect is not expected to conduct continuous, detailed inspections of every batch or mixing operation.
Iarnród Éireann v. Dowling [1996] 3 I.R. 321 Apportionment of liability between concurrent wrongdoers is to be based on respective blameworthiness (not causation) when assessing contribution. Applied when considering apportionment between the Contractor and the Third Parties under s.17(2) of the Civil Liability Act 1961.
KBC Bank Ireland plc v. BCM Hanby Wallace [2013] 3 I.R. 759 Observation that a professional is in a weak position if he seeks to rely on the client subsequently discovering the professional's negligence; contextualised. Distinguished: the court found the circumstances here were different because the Defendant concealed intentions and took unilateral steps preventing further work/inspection; KBC did not alter the conclusion that the Defendant's actions prevented the architect discharging functions.
McCord v. Electricity Supply Board [1981] ILRM 153 Principle that a plaintiff's unreasonable conduct in failing to cooperate can justify reducing liability to nil where fault overwhelmingly lay with the plaintiff. Applied analogously: the Court found the Defendant's exclusion of Contractor and dismissal of architect so unreasonable that justice and equity required reduction of Third Parties' liability to nil in respect of most claims.
Carroll v. Clare County Council [1975] I.R. 221 Definition of 'fault' in s.34 as departure from standard of reasonable conduct; degrees of fault determine apportionment. Quoted in support of s.34 analysis—assessing whether the Defendant's conduct constituted contributory negligence or failure to mitigate.
Defender Ltd v. HSBC France [2020] IESC 37; [2021] 1 I.R. 516 Interpretation regarding what constitutes 'satisfaction' or agreed quantification under related provisions; points on limits of treating a release as a monetary satisfaction. Used by analogy in construing 'consideration' in s.17(2): court held the Settlement did not identify a precise monetary 'consideration' that extinguished the Defendant's claim against the Third Parties.

Court's Reasoning and Analysis

The court's analysis followed a structured path. The main strands of reasoning and findings are set out below, strictly reflecting the material the opinion contains.

1. Characterisation of contractual relations and scope of the architect's retainer

  • Although no fully signed building contract was produced, the court found the parties had, by course of dealing, operated some provisions of the Standard RIAI Blue Form Contract (particularly those concerning interim certificates, retention percentages, insurance and a defects liability period). The architect's retainer was governed by the Standard RIAI Architect's Contract (standard services) so far as the architect's duties were concerned.
  • The court emphasised that an architect's duties are defined by the retainer: the architect undertakes periodic visual inspections appropriate to the stage of works rather than continuous supervision or a guarantee of workmanship.

2. Nature of the defect and its legal significance

  • Laboratory analysis (the Sandberg Report) showed the bedding mortar in many new and reconstructed sections had defects caused by inadequate mixing — a defect of workmanship.
  • Because mixing is a matter of execution and workmanship, primary responsibility rests with the Contractor; the architect was not obliged (nor required by the NRA specification used on site) to test the mortar for mixing quality in the newly constructed walls.

3. Whether defects were patent (ascertainable by periodic visual inspection before exclusion)

  • The court carefully compared contemporaneous photographic and witness evidence with expert reports. It found the evidence did not establish, on balance, that the defective bedding mortar was patent throughout the Orchard prior to the Contractor's exclusion in August 2017.
  • Expert evidence favourable to the Defendant (asserting rapid patentness) was analysed and—where that evidence relied on the materials scientist's view that globules would have been visible "within days"—the court rejected that aspect as outside that expert's practical experience of on-site mixing and contrary to the testimony of architects and engineers who explained the laitance effect and how defects typically emerge with weathering.
  • The court accepted that limited, localised problems had been observed contemporaneously (one photograph taken and recorded by the architect was discussed), but concluded those were properly treated by the architect as localised issues rather than evidence of a pervasive mixing problem across kilometres of walls.

4. The impact of the Defendant's conduct (lockout and refusal to co‑operate)

  • Key factual finding: the Defendant unilaterally excluded the Contractor from the site and later dismissed the architect; she had also refused to appoint or cooperate with a quantity surveyor when that was proposed—steps which prevented the normal post-construction contractual procedures (final measurement, final account, and final certificate) from occurring.
  • The court found that the Defendant concealed her intention to terminate and therefore did not seek or accept advice (even from her solicitors) before lockout; the architect did attempt to follow contractual/admin procedures, and his recommendations (including appointment of a quantity surveyor) were rejected.
  • Given these steps, the court concluded the Defendant obstructed the architect from discharging duties that would otherwise have addressed or further investigated defects once they became apparent.

5. Statutory apportionment / settlement consequences (Civil Liability Act 1961)

  • The court analysed s.17(2) (effect of release/accord with one concurrent wrongdoer) and s.35(1)(h) (identifying plaintiff with settled wrongdoer). It concluded the Settlement between the Defendant and the Contractor did not identify a precise monetary “consideration” capable of being applied under the first limb of s.17(2), so the first option could not be meaningfully applied.
  • Applying the third limb of s.17(2) (reduction by the extent the settling wrongdoer would have been liable), and the Iarnród Éireann principle that apportionment should reflect relative blameworthiness, the court concluded the Contractor bore overwhelmingly greater blame for the defective bedding mortar. Hypothetically, the court stated a 90%/10% apportionment (90% Contractor / 10% architect) would be appropriate if liability had been found against the architect on the bedding-mortar issue.

6. Contributory negligence and failure to mitigate (s.34)

  • The court held that the Defendant's unilateral exclusion of the Contractor and dismissal of the architect were unreasonable, prevented proper contractual processes, and in equity and justice required reduction or extinguishment of the architect's liability in most respects. The court relied on s.34 principles and analogous authorities (e.g., McCord) to reduce Third Parties' liability to nil for most of the alleged defects.
  • As to post-exclusion failure to protect the works (exposure leading to further degradation), the court did not find that conduct amounted to contributory negligence sufficient to allow recovery by the Defendant for the bedding-mortar issue; however, the longer exposure complicated the factual assessment of when defects became patent.

7. Claims for quantity surveying fees and other consequential claims

  • The Defendant sought to recover the quantity surveyor's fees (asserted as necessary because the architect allegedly should have been more rigorous earlier). The court concluded that the Defendant would, in any event, have had to appoint a quantity surveyor at final account stage and thus incurred those fees irrespective of any alleged prior architect breach; moreover, much of the quantity surveyor's work was for litigation/expert purposes and not purely final-account negotiation. The claim for such fees was therefore dismissed.

Holding and Implications

Core Ruling:

Partial Liability for Specific Defects; Most Claims Dismissed

The court's operative conclusions are as follows (anonymised):

  • The Third Parties conceded liability in respect of (a) defective foundations to the Warehouse and (b) inadequate haunching/capping of parts of the historic walls. The court accepted those concessions and ordered that the Defendant is entitled to judgment for compensation in respect of those conceded items.
  • As to the pervasive bedding-mortar defect in the newly constructed and reconstructed walls, the court concluded the Defendant had not discharged the burden of proof that those defects were patent and thus discoverable by reasonable periodic inspection prior to the Contractor's exclusion. On that issue the Third Parties were not held liable.
  • Even if the Third Parties had been held partially liable for the bedding-mortar defect, the court indicated (for purposes of apportionment) that the greater blameworthiness would rest with the Contractor (a suggested 90%/10% split), but that any residual Third‑party liability would be reduced to nil in equity because the Defendant prevented the architect from undertaking the inspections and steps that would have followed had she not summarily excluded the Contractor and dismissed the architect.
  • Claim for the quantity surveyor's fees (sought by the Defendant) was dismissed: in substance the Defendant would have had to retain a quantity surveyor to reach a final account regardless of any alleged earlier architect failing, and parts of the invoices related to expert/litigation work.

Practical consequences and next steps:

  • Judgment was entered for the Defendant against the Third Parties in respect of the Warehouse foundations and the haunching/capping defects conceded by the Third Parties. The parties were directed to confirm precise remedial cost figures post-judgment (the opinion records an expected underpinning cost in the order of €35,000–€40,000; the exact figures were to be finalised after judgment).
  • All other claims by the Defendant against the Third Parties were dismissed.
  • The court emphasised that the factual complexity (phased works, lack of a fully executed written building contract covering the expanded scope, the Defendant's rolling instructions and later conduct) materially affected available remedies and findings of liability.
  • No new general legal principle was established that expands the standard obligations of architects beyond the settled authorities cited; the judgment applies existing principles (notably McGlinn and East Ham) to the particular facts.

Postscript: Observations and Guidance from the Judgment

The judgment provides detailed guidance on several recurring contractual/practical themes in building disputes (as summarised directly from the opinion):

  • Where parties operate long-term building works on a rolling/informal basis, course-of-dealing can incorporate some standard-form contract provisions (e.g., procedures for certificates, retentions, insurance and defects liability), even without a signed document—courts will look to the conduct of the parties to determine which clauses were in effect.
  • An architect's duty in such contexts is controlled by the retainer and industry practice: periodic, tailored visual inspections are required, but continuous site supervision or a guarantee of workmanship is not.
  • Latent defects in workmanship (here, defective mixing) that only become visible with weathering are principally the contractor's responsibility; expert reports prepared years after works, when the works have been exposed to the elements, require careful caution against hindsight bias.
  • When a client unilaterally prevents completion, excludes a contractor and dismisses the architect, that conduct can materially limit or extinguish the client's remedies against the architect where it prevented the architect from carrying out contractual processes that would have addressed defects in the defects liability period.

If Further Particularisation Is Needed

The judgment notes that certain monetary figures in claims were adjusted during settlement of the principal proceedings and that exact quantification of the conceded remedial items (Warehouse underpinning; historic walls haunching) was to be finalised by the parties after judgment. The Court directed that those figures be supplied for assessment of the award where required.

This summary is strictly confined to the material and findings contained in the provided judgment and does not introduce facts or inferences beyond that text.

To access the original judgment, please Sign In or Subscribe.

Ashdrum Lodge Limited [Trading as Kiernan Homes] v. Barbouti

Contains public sector information licensed under the Open Justice Licence v1.0.

Use AI to get other relevant cases.

Comments

Ashdrum Lodge Limited [Trading as Kiernan Homes] v. Barbouti
(Aug 21, 2025)