TILBURY DOUGLAS CONSTRUCTION LTD AGAINST OVE ARUP & PARNTERS SCOTLAND LTD

Smart Summary

Factual and Procedural Background

This action concerns the development of a former railway yard near a major railway station in The City, adjacent to two railway tunnels. The development required lowering the ground level by removing up to 6 meters of soil, necessitating enabling works to protect the tunnels' structural integrity and allow piling nearby. The Plaintiff was contracted in November 2013 to carry out these enabling works, and the Defendant was appointed to provide related engineering services, including preparing a design approved by Network Rail.

The Plaintiff alleges that the Defendant breached contractual and delictual duties by adopting erroneous assumptions in the design for the north tunnel’s enabling works, specifically regarding the brickwork's strength and stiffness, failure to account for voids within and behind the tunnel lining, and failure to include necessary annular and interstitial grouting. This allegedly led to a need for design resubmission and costly amendments.

The case was initially before the court on a preliminary proof limited to the issue of prescription (limitation). The Plaintiff conceded loss occurred as of 27 November 2013, when it entered the enabling works contract relying on the Defendant’s design. The summons was not served until 30 July 2019, beyond the usual five-year prescriptive period, raising the question whether the limitation period should be postponed under relevant statutory provisions.

Evidence was heard from factual and expert witnesses from both parties, with some objections to evidence considered and ruled upon. The court also noted the Plaintiff’s failure to call certain key witnesses listed originally, though the decision did not turn on this point.

The development had a protracted history, with the Defendant involved in earlier stages and designs since 2007. The tunnels had been electrified between 2009 and 2012, with remedial works carried out by a third party. The Plaintiff’s contract and the Defendant’s appointment were formalized in November 2013. The Defendant’s design was based on limited information about the tunnel lining’s condition, with assumptions made about brickwork strength and the absence of significant voids, influencing the scope of grouting works specified.

A timeline of events from mid-2013 through 2015 detailed the design approvals, site works commencement, tactile surveys, discovery of brickwork defects, increased scope of repairs, delays, and eventual requirement for extensive grouting. The Plaintiff’s pleaded case specified multiple alleged breaches of duty relating to insufficient testing, erroneous assumptions, failure to account for voids, and reliance on data from the south tunnel for the north tunnel design.

Legal Issues Presented

  1. Whether the Plaintiff’s cause of action had prescribed under the five-year limitation period starting from the date of loss or whether the limitation period should be postponed under section 11(3) of the Prescription and Limitation (Scotland) Act 1973 due to lack of awareness of loss.
  2. Whether the limitation period should be postponed under section 6(4) of the 1973 Act due to error induced by words or conduct of the Defendant causing the Plaintiff to refrain from making a claim.
  3. Whether the Plaintiff’s introduction of a complaint regarding over-optimistic assumptions of lining stiffness, added to pleadings in 2021, was too late to interrupt prescription.

Arguments of the Parties

Plaintiff's Arguments

  • The Plaintiff accepted loss occurred as of November 2013 but argued it was not aware until November 2014 that the design was negligent and that the contract was less valuable.
  • The Plaintiff contended it was induced to refrain from making a claim by the Defendant’s assurances and ongoing representations that the design was competent and that only stitch grouting was needed until late 2014.
  • The Plaintiff argued that it could not, exercising reasonable diligence, have discovered the error before December 2014 when the Defendant advised full grouting was required.
  • The Plaintiff asserted that the complaint regarding lining stiffness was a development of existing grounds of fault, not a fundamentally new claim, and thus not time-barred.

Defendant's Arguments

  • The Defendant submitted loss did not occur until March/April 2014 when additional costs and delays were incurred.
  • The Defendant contended the Plaintiff failed to address section 11(3) in written submissions initially and that prescription started to run in August 2013 when the Plaintiff relied on the design.
  • The Defendant argued the Plaintiff’s claim concerning lining stiffness, introduced in 2021, was too late and barred by prescription.
  • The Defendant asserted that additional brick repair works and delays were not caused by breaches of duty but were risks inherent in the contractual arrangements and the development process.
  • The Defendant rejected the Plaintiff’s reliance on section 6(4), arguing that the Plaintiff could have discovered the error with reasonable diligence and that Network Rail’s role in design approvals limited the Defendant’s inducement of error.
  • The Defendant contended that mere denial of liability does not induce error and that the Plaintiff’s failure to call certain witnesses justified drawing adverse inferences.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Huntaven Properties Ltd v Hunter Construction (Aberdeen) Ltd [2017] CSOH 57 Requirement to take averments of breach and causation pro veritate in preliminary proof on prescription The court applied this principle to limit the scope of evidence considered on breach and causation to that pleaded by the Plaintiff.
O'Donnell v Murdoch McKenzie 1967 SC (HL) 63 Drawing adverse inferences from failure to call witnesses who might provide relevant evidence The court acknowledged the principle but did not base its decision on such inferences except where noted.
Royal Bank of Scotland v Carlyle 2010 CSOH 3 Similar to O'Donnell, supports drawing adverse inferences from failure to call relevant witnesses Referenced in support of the Defendant’s submission regarding missing witnesses.
David T Morrison & Co Ltd v ICL Plastics Ltd 2014 SC (UKSC) 222 For section 11(3) of the 1973 Act, the pursuer need not be aware that loss was caused by breach, only aware of the loss itself The court applied this principle to assess when the Plaintiff became aware of loss for prescription purposes.
Gordon's Trustees v Campbell Riddell Breeze Paterson LLP 2017 SLT 1287 Clarification on awareness of loss connected to cause of action under section 11(3) Used to determine the necessity of awareness of loss connected to the cause of action.
Midlothian Council v Raeburn Drilling and Geotechnical Ltd 2019 SLT 1327 Distinction between costs and loss for prescription purposes The court relied on this case to distinguish between costs incurred and losses caused by breach.
WPH Developments Ltd v Young and Gault LLP (in liquidation) [2021] CSIH 39 Awareness of loss for prescription requires connection to cause of action Referenced in assessing the Plaintiff’s awareness of loss.
Musselburgh and Fisherrow Co-operative Society Ltd v Mowlem Scotland Ltd 2004 SCLR 412 Need to identify particular respects in which a general duty is breached for prescription purposes The court preferred this approach to avoid conflating multiple breaches into a single cause of action.
Sinclair v MacDougall Estates Ltd 1994 SLT 76 Supports the need to distinguish discrete breaches for limitation Applied as part of the reasoning on breach identification.
Cole v Lonie 2001 SLT 608 Supports the principle of identifying discrete breaches for limitation Reinforced the approach to breach analysis.
Assuranceforeningen Skuld v International Oil Pollution Compensation Fund (No 2) 2000 SLT 1348 Test for whether a new ground of fault is a modification or a fundamentally different cause The court applied this test to reject the Defendant’s objection to the late addition of the stiffness complaint.
BP Exploration Operating Company Ltd v Chevron Transport (Scotland) 2002 SC (HL) No requirement for a conscious and deliberate decision to refrain from legal action to rely on section 6(4) The court used this to support the finding that the Plaintiff was induced to refrain from action by error.
Glasgow City Council and West Dunbartonshire Council v VFS Financial Services Limited [2022] CSIH 1 Reasonable diligence standard for discovery of error and loss Applied to differentiate between awareness of loss and discovery of error.
Heather Capital v Levy & McRae 2017 SLT 376 Error induced by defendant need not be sole cause; contributory error suffices Used to support that reliance on Defendant’s design contributed to the Plaintiff’s error.
Adams v Thorntons WS 2005 1 SC 30 Limits on relying on induced error as to scope of remedies The court rejected the Defendant’s submission based on this precedent.

Court's Reasoning and Analysis

The court began by identifying the date on which loss occurred for the purposes of section 11(1) of the 1973 Act, concluding it was when the Plaintiff relied on the Defendant’s defective design in August 2013, even if the Plaintiff was unaware at that time of the full extent of the loss. The court emphasized the necessity to distinguish particular respects in which the general duty of care was breached, rather than conflating all alleged breaches into a single cause of action, in line with established authority.

Regarding section 11(3), the court held that the prescriptive period is postponed until the Plaintiff either knew or could with reasonable diligence have known of the loss connected to the cause of action. The court found that the Plaintiff was aware or should have been aware by May/June 2014 of loss connected to insufficient test sampling and resulting delays caused by discovery of soft brickwork, thus prescription for those complaints had begun by then.

However, the court distinguished losses arising from additional brick repair works and variations that were not pleaded as breaches of duty and considered these as risks inherent in the contractual arrangements rather than losses caused by the Defendant’s breaches.

On section 6(4), the court accepted that the Plaintiff was induced to refrain from making a claim by the Defendant’s assurances and continued endorsement of the design’s validity until late 2014. The court found that the Plaintiff could not, even exercising reasonable diligence, have discovered the errors regarding the need for extensive redesign and full grouting before the Defendant’s admission in November 2014. Therefore, the court allowed postponement of the prescriptive period up to that date.

Finally, the court rejected the Defendant’s objection that the complaint regarding lining stiffness was introduced too late, reasoning that it was a development of existing grounds of fault rather than a new cause of action.

Holding and Implications

The court repelled the Defendant’s third plea in law, allowing a proof before answer on all averments other than those relating to prescription. This means the Plaintiff’s claim was not barred by prescription to the extent that the prescriptive period was postponed until November 2014 under section 6(4) of the 1973 Act.

The direct effect is that the Plaintiff may proceed to a full hearing on the merits of the alleged breaches other than prescription. No new precedent was established beyond the application of existing principles to the facts of this case. The court reserved the question of expenses for later determination.

To access the original judgment, please Sign In or Subscribe.

TILBURY DOUGLAS CONSTRUCTION LTD AGAINST OVE ARUP & PARNTERS SCOTLAND LTD

Contains public sector information licensed under the Open Justice Licence v1.0.