Factual and Procedural Background
On or about 16 March 2018, the parties entered into a sub-contract agreement under which the Plaintiff was to provide dredging services for a harbour expansion project, with the Defendant as the main contractor. On 6 March 2020, the Defendant terminated the sub-contract, giving rise to multiple disputes and seven adjudications, the present being the sixth. The Plaintiff claimed entitlement to an extension of time and prolongation costs in respect of four compensation events, notably two key events: delayed access to open quay work (CEN 048) and late delivery of remaining caissons (CEN 055). The adjudicator issued a decision on 14 September 2021, partially in favour of the Plaintiff, awarding an extension of time and costs for CEN 048 but not for CEN 055, and also awarding weather-related compensation and method-related charges.
The Plaintiff initially sought enforcement of the adjudicator's entire decision, while the Defendant resisted on grounds including breaches of natural justice and non-severability of the decision. Subsequently, both parties adjusted their positions, with the Plaintiff accepting that the weather compensation award could not be supported, and the Defendant accepting severability and that the remainder of the decision could stand if properly reached. The present dispute concerns whether the adjudicator's decision regarding CEN 048 is enforceable or must be reduced.
Legal Issues Presented
- Whether the adjudicator reached his decision on a basis not canvassed with the parties.
- If so, whether there was a material breach of the principles of natural justice such that the adjudicator’s decision cannot stand.
- Whether the adjudicator’s decision relating to CEN 048 is enforceable or requires to be reduced.
Arguments of the Parties
Defendant's Arguments
- The adjudicator was not entitled to adopt a baseline programme (from March 2019) that had been disavowed by both experts without first intimating this to the parties and allowing further submissions.
- The adjudicator selected a critical date for CEN 048 (31 July 2019) earlier than that contended by the Plaintiff, and this date was not canvassed with the parties.
- Had the Defendant been made aware of the adjudicator’s approach, it would have advanced a time bar argument under clause 61.3 of the subcontract, which bars claims notified more than seven weeks after the event.
- The failure to provide an opportunity to comment on these novel issues constituted a breach of natural justice, amounting to a “frolic” by the adjudicator.
- It is sufficient that the time bar argument was tenable; the Defendant need not prove it would have succeeded.
Plaintiff's Arguments
- The adjudicator was entitled to adopt an intermediate position between the parties’ cases, including using the March 2019 programme as baseline.
- The Defendant had been aware of the issue of delay and had in fact advanced a time bar argument during the adjudication process, albeit not precisely the one now asserted.
- The Defendant was aware that the Plaintiff contended delay occurred before 2 August 2019 and thus had the opportunity to argue time bar.
- The adjudicator gave the experts an opportunity to comment on the baseline programme during an adjudication meeting.
- The adjudicator’s selection of the critical date and baseline was within his leeway and did not require further submissions.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Carrillion Construction Ltd v Devonport Royal Dockyard Ltd [2005] EWCA Civ 1358 |
Courts generally enforce adjudicator decisions summarily; the need for a quick decision outweighs the need for the “right” answer; natural justice breaches succeed only in plain cases. |
Supported the principle that adjudicator decisions are enforced even if wrong, unless there is a clear breach of natural justice. |
| Gillies Ramsay Diamond v PJW Enterprises Limited 2004 SC 430 |
Enforcement will be refused where adjudicator acts contrary to natural justice. |
Confirmed that a breach of natural justice invalidates an adjudicator’s decision. |
| Costain Limited v Strathclyde Builders Limited 2004 SLT 102 |
Parties must have fair opportunity to present their case; adjudicator must canvas novel factual or legal propositions with parties before deciding. |
Outlined the interaction of natural justice with adjudication, guiding the court’s assessment of fairness in adjudicator’s approach. |
| Roe Brickwork Ltd v Wates Construction Ltd [2013] EWHC 3417 |
Adjudicator should not decide points on bases not argued; however, can decide on unargued bases if parties aware of material and issues fairly canvassed. |
Clarified limits on adjudicator’s discretion to adopt unargued positions; court applied this in assessing fairness. |
| Balfour Beatty Engineering Services (HY) Ltd v Shepherd Construction Ltd [2009] EWHC 2218 |
Material breach of natural justice occurs if parties not given opportunity to comment on decisive or important points. |
Used to assess whether the adjudicator’s failure to canvass the critical date and baseline programme was material. |
| Miller Construction (UK) Ltd v Building Design Partnership Ltd [2014] CSOH 80 |
Adjudicator has leeway to adopt intermediate positions not contended by parties without notice. |
Distinguished the present case from Miller, concluding the adjudicator here went beyond an intermediate position. |
| Barrs v British Wool Marketing Board 1957 SC 72 |
Natural justice test: whether opportunity was afforded for injustice to be done, not whether unjust result reached. |
Key to concluding that the adjudicator’s decision was vitiated by breach of natural justice due to lack of opportunity to comment. |
| Inland Revenue Commissioners v Barrs 1961 SC (HL) 22 |
Tribunal issuing decisions beyond parties’ submissions without opportunity to respond breaches natural justice. |
Analogous to present case where adjudicator issued decision on unargued critical date without opportunity for parties to respond. |
Court's Reasoning and Analysis
The court began by acknowledging the established legal principles governing adjudication and natural justice, emphasizing the court’s general reluctance to interfere with adjudicator decisions except in clear cases of unfairness. The court then examined the adjudicator’s approach, noting that he did not fully accept either expert’s baseline programme but instead adopted a March 2019 baseline rejected by both experts.
The critical issue was that the adjudicator selected a critical date for the compensation event (31 July 2019) earlier than that argued by the Plaintiff (2 August 2019) and without canvassing this with the parties. This was not a mere intermediate position but a novel factual determination that had significant consequences, including potential application of a contractual time bar.
The court found that the Defendant was deprived of the opportunity to address this new position and specifically to argue the time bar defence under clause 61.3. The adjudicator did not indicate whether he considered or rejected the time bar argument, leaving uncertainty as to his reasoning.
Applying the test from Barrs, the court held that an opportunity was afforded for injustice to be done, constituting a material breach of natural justice. The adjudicator’s decision was thus vitiated because he proceeded on a basis not fairly canvassed and denied the Defendant a chance to respond to a decisive issue.
The court distinguished this case from Miller Construction, where an intermediate position was taken within the scope of the dispute. Here, the adjudicator’s approach was outside the parties’ submissions and had significant legal consequences.
Holding and Implications
The court’s final ruling was to reduce the adjudicator's decision in its entirety and grant decree of absolvitor in favour of the Defendant, reserving questions of expenses.
The direct effect is that the adjudicator’s award relating to the disputed compensation event is unenforceable due to breach of natural justice. No broader precedent was established beyond the application of established principles to these facts.